Capital Projects Dashboard - Citywide Schedule History and Variance

This is the history all agency reported forecasts/actual project completion dates. Each row is the snapshot of data taken on each reporting period. The 'completion date type' column shows if the 'completion date' is either a forecast or actual date. Over time, a project would have one or more forecasted completion dates before it is actually completed. The 'variance' is the day difference between 'completion date' of each row and its prior reporting period. This dataset is part of the Capital Projects Dashboard.

City Government Mayor's Office of Operations (OPS) Dataset 95tx-snak 10 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4187
Reporting Period
202405
Managing Agency
DDC
Pid
4187
Agency Project Name
Park Ave - Ingersoll Houses Safety Improvements
Current Phase
Design
Completion Date
2028-06-23T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4187
Reporting Period
202409
Managing Agency
DDC
Pid
4187
Agency Project Name
Park Ave - Ingersoll Houses Safety Improvements
Current Phase
Design
Completion Date
2028-06-23T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4187
Reporting Period
202501
Managing Agency
DDC
Pid
4187
Agency Project Name
Park Ave - Ingersoll Houses Safety Improvements
Current Phase
Design
Completion Date
2030-06-05T00:00:00.000
Completion Date Type
Forecast
Variance Day
712
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO BUDGETARY CONSTRAINTS
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4187
Reporting Period
202505
Managing Agency
DDC
Pid
4187
Agency Project Name
Park Ave - Ingersoll Houses Safety Improvements
Current Phase
Design
Completion Date
2029-07-31T00:00:00.000
Completion Date Type
Forecast
Variance Day
-309
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4187
Reporting Period
202509
Managing Agency
DDC
Pid
4187
Agency Project Name
Park Ave - Ingersoll Houses Safety Improvements
Current Phase
Design
Completion Date
2029-07-31T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4187
Reporting Period
202601
Managing Agency
DDC
Pid
4187
Agency Project Name
Park Ave - Ingersoll Houses Safety Improvements
Current Phase
Design
Completion Date
2029-07-31T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4187
Reporting Period
202605
Managing Agency
DDC
Pid
4187
Agency Project Name
Park Ave - Ingersoll Houses Safety Improvements
Current Phase
Design
Completion Date
2029-07-31T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4188
Reporting Period
202305
Managing Agency
DDC
Pid
4188
Agency Project Name
Pedestrian Ramps Rehabilitation - Brooklyn
Current Phase
Close-out
Completion Date
2023-04-17T00:00:00.000
Completion Date Type
Actual
Data Date
2023-09-01T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4189
Reporting Period
202305
Managing Agency
DDC
Pid
4189
Agency Project Name
Pedestrian Ramp Rehabilitation - Brooklyn
Current Phase
Construction
Completion Date
2023-11-09T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4189
Reporting Period
202309
Managing Agency
DDC
Pid
4189
Agency Project Name
Pedestrian Ramp Rehabilitation - Brooklyn
Current Phase
Construction
Completion Date
2023-11-09T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2023-09-01T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4189
Reporting Period
202401
Managing Agency
DDC
Pid
4189
Agency Project Name
Pedestrian Ramp Rehabilitation - Brooklyn
Current Phase
Construction
Completion Date
2023-11-09T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2023-09-01T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4189
Reporting Period
202405
Managing Agency
DDC
Pid
4189
Agency Project Name
Pedestrian Ramp Rehabilitation - Brooklyn
Current Phase
Construction
Completion Date
2023-10-26T00:00:00.000
Completion Date Type
Actual
Variance Day
-14
Data Date
2024-07-18T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4190
Reporting Period
202305
Managing Agency
DDC
Pid
4190
Agency Project Name
Pedestrian Ramps Rehabilitation - Brooklyn
Current Phase
Construction
Completion Date
2025-04-15T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4190
Reporting Period
202309
Managing Agency
DDC
Pid
4190
Agency Project Name
Pedestrian Ramps Rehabilitation - Brooklyn
Current Phase
Construction
Completion Date
2025-04-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4190
Reporting Period
202401
Managing Agency
DDC
Pid
4190
Agency Project Name
Pedestrian Ramps Rehabilitation - Brooklyn
Current Phase
Construction
Completion Date
2025-04-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4190
Reporting Period
202405
Managing Agency
DDC
Pid
4190
Agency Project Name
Pedestrian Ramps Rehabilitation - Brooklyn
Current Phase
Construction
Completion Date
2025-04-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4190
Reporting Period
202409
Managing Agency
DDC
Pid
4190
Agency Project Name
Pedestrian Ramps Rehabilitation - Brooklyn
Current Phase
Construction
Completion Date
2024-05-31T00:00:00.000
Completion Date Type
Actual
Variance Day
-319
Data Date
2024-07-18T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4191
Reporting Period
202305
Managing Agency
DDC
Pid
4191
Agency Project Name
Pedestrian Ramp Upgrades at 81 non-standard locations in Manhattan.
Current Phase
Pre-Design
Completion Date
2028-06-28T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4191
Reporting Period
202309
Managing Agency
DDC
Pid
4191
Agency Project Name
Pedestrian Ramp Upgrades at 81 non-standard locations in Manhattan.
Current Phase
Pre-Design
Completion Date
2028-09-25T00:00:00.000
Completion Date Type
Forecast
Variance Day
89
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4191
Reporting Period
202401
Managing Agency
DDC
Pid
4191
Agency Project Name
Pedestrian Ramp Upgrades at 81 non-standard locations in Manhattan.
Current Phase
Pre-Design
Completion Date
2028-09-25T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4191
Reporting Period
202405
Managing Agency
DDC
Pid
4191
Agency Project Name
Pedestrian Ramp Upgrades at 81 non-standard locations in Manhattan.
Current Phase
Design
Completion Date
2028-09-25T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4191
Reporting Period
202409
Managing Agency
DDC
Pid
4191
Agency Project Name
Pedestrian Ramp Upgrades at 81 non-standard locations in Manhattan.
Current Phase
Design
Completion Date
2028-09-25T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4191
Reporting Period
202501
Managing Agency
DDC
Pid
4191
Agency Project Name
Pedestrian Ramp Upgrades at 81 non-standard locations in Manhattan.
Current Phase
Design
Completion Date
2028-09-25T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4191
Reporting Period
202505
Managing Agency
DDC
Pid
4191
Agency Project Name
Pedestrian Ramp Upgrades at 81 non-standard locations in Manhattan.
Current Phase
Design
Completion Date
2028-09-25T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4191
Reporting Period
202509
Managing Agency
DDC
Pid
4191
Agency Project Name
Pedestrian Ramp Upgrades at 81 non-standard locations in Manhattan.
Current Phase
Design
Completion Date
2029-04-18T00:00:00.000
Completion Date Type
Forecast
Variance Day
205
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4191
Reporting Period
202601
Managing Agency
DDC
Pid
4191
Agency Project Name
Pedestrian Ramp Upgrades at 81 non-standard locations in Manhattan.
Current Phase
Design
Completion Date
2029-04-18T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4191
Reporting Period
202605
Managing Agency
DDC
Pid
4191
Agency Project Name
Pedestrian Ramp Upgrades at 81 non-standard locations in Manhattan.
Current Phase
Design
Completion Date
2029-07-27T00:00:00.000
Completion Date Type
Forecast
Variance Day
100
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO BUDGETARY CONSTRAINTS
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4192
Reporting Period
202305
Managing Agency
DDC
Pid
4192
Agency Project Name
Pedestrian Ramp Upgrades at 91 non-standard locations in Brooklyn and Staten Island.
Current Phase
Pre-Design
Completion Date
2028-06-05T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4192
Reporting Period
202309
Managing Agency
DDC
Pid
4192
Agency Project Name
Pedestrian Ramp Upgrades at 91 non-standard locations in Brooklyn and Staten Island.
Current Phase
Pre-Design
Completion Date
2028-09-03T00:00:00.000
Completion Date Type
Forecast
Variance Day
90
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4192
Reporting Period
202401
Managing Agency
DDC
Pid
4192
Agency Project Name
Pedestrian Ramp Upgrades at 91 non-standard locations in Brooklyn and Staten Island.
Current Phase
Pre-Design
Completion Date
2028-09-03T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4192
Reporting Period
202405
Managing Agency
DDC
Pid
4192
Agency Project Name
Pedestrian Ramp Upgrades at 91 non-standard locations in Brooklyn and Staten Island.
Current Phase
Design
Completion Date
2028-09-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
10
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO BUDGETARY CONSTRAINTS
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4192
Reporting Period
202409
Managing Agency
DDC
Pid
4192
Agency Project Name
Pedestrian Ramp Upgrades at 91 non-standard locations in Brooklyn and Staten Island.
Current Phase
Design
Completion Date
2028-09-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4192
Reporting Period
202501
Managing Agency
DDC
Pid
4192
Agency Project Name
Pedestrian Ramp Upgrades at 91 non-standard locations in Brooklyn and Staten Island.
Current Phase
Design
Completion Date
2028-09-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4192
Reporting Period
202505
Managing Agency
DDC
Pid
4192
Agency Project Name
Pedestrian Ramp Upgrades at 91 non-standard locations in Brooklyn and Staten Island.
Current Phase
Design
Completion Date
2028-09-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4192
Reporting Period
202509
Managing Agency
DDC
Pid
4192
Agency Project Name
Pedestrian Ramp Upgrades at 91 non-standard locations in Brooklyn and Staten Island.
Current Phase
Design
Completion Date
2029-02-24T00:00:00.000
Completion Date Type
Forecast
Variance Day
164
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4192
Reporting Period
202601
Managing Agency
DDC
Pid
4192
Agency Project Name
Pedestrian Ramp Upgrades at 91 non-standard locations in Brooklyn and Staten Island.
Current Phase
Design
Completion Date
2029-02-24T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4192
Reporting Period
202605
Managing Agency
DDC
Pid
4192
Agency Project Name
Pedestrian Ramp Upgrades at 91 non-standard locations in Brooklyn and Staten Island.
Current Phase
Design
Completion Date
2029-10-26T00:00:00.000
Completion Date Type
Forecast
Variance Day
244
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4193
Reporting Period
202305
Managing Agency
DDC
Pid
4193
Agency Project Name
Simple Upgrades Ped Ramps- Brooklyn and Staten Island
Current Phase
Construction
Completion Date
2024-07-27T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4193
Reporting Period
202309
Managing Agency
DDC
Pid
4193
Agency Project Name
Simple Upgrades Ped Ramps- Brooklyn and Staten Island
Current Phase
Construction
Completion Date
2024-07-27T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4193
Reporting Period
202401
Managing Agency
DDC
Pid
4193
Agency Project Name
Simple Upgrades Ped Ramps- Brooklyn and Staten Island
Current Phase
Construction
Completion Date
2024-07-27T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4193
Reporting Period
202405
Managing Agency
DDC
Pid
4193
Agency Project Name
Simple Upgrades Ped Ramps- Brooklyn and Staten Island
Current Phase
Construction
Completion Date
2024-06-28T00:00:00.000
Completion Date Type
Actual
Variance Day
-29
Data Date
2024-07-18T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4194
Reporting Period
202305
Managing Agency
DDC
Pid
4194
Agency Project Name
MULTI-SITE PEDESTRIAN SAFETY PHASE 5
Current Phase
Construction
Completion Date
2024-06-01T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4194
Reporting Period
202309
Managing Agency
DDC
Pid
4194
Agency Project Name
MULTI-SITE PEDESTRIAN SAFETY PHASE 5
Current Phase
Construction
Completion Date
2024-06-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4194
Reporting Period
202401
Managing Agency
DDC
Pid
4194
Agency Project Name
MULTI-SITE PEDESTRIAN SAFETY PHASE 5
Current Phase
Construction
Completion Date
2024-06-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4194
Reporting Period
202405
Managing Agency
DDC
Pid
4194
Agency Project Name
MULTI-SITE PEDESTRIAN SAFETY PHASE 5
Current Phase
Construction
Completion Date
2025-01-07T00:00:00.000
Completion Date Type
Forecast
Variance Day
220
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO SCHEDULING OF UTILITY WORK
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4194
Reporting Period
202409
Managing Agency
DDC
Pid
4194
Agency Project Name
MULTI-SITE PEDESTRIAN SAFETY PHASE 5
Current Phase
Construction
Completion Date
2025-06-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
174
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4194
Reporting Period
202501
Managing Agency
DDC
Pid
4194
Agency Project Name
MULTI-SITE PEDESTRIAN SAFETY PHASE 5
Current Phase
Construction
Completion Date
2025-07-08T00:00:00.000
Completion Date Type
Forecast
Variance Day
8
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4194
Reporting Period
202505
Managing Agency
DDC
Pid
4194
Agency Project Name
MULTI-SITE PEDESTRIAN SAFETY PHASE 5
Current Phase
Construction
Completion Date
2025-07-08T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4194
Reporting Period
202509
Managing Agency
DDC
Pid
4194
Agency Project Name
MULTI-SITE PEDESTRIAN SAFETY PHASE 5
Current Phase
Construction
Completion Date
2025-12-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
160
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4194
Reporting Period
202601
Managing Agency
DDC
Pid
4194
Agency Project Name
MULTI-SITE PEDESTRIAN SAFETY PHASE 5
Current Phase
Close-out
Completion Date
2025-12-15T00:00:00.000
Completion Date Type
Actual
Variance Day
0
Data Date
2026-03-20T00:00:00.000