Capital Projects Dashboard - Citywide Schedule History and Variance

This is the history all agency reported forecasts/actual project completion dates. Each row is the snapshot of data taken on each reporting period. The 'completion date type' column shows if the 'completion date' is either a forecast or actual date. Over time, a project would have one or more forecasted completion dates before it is actually completed. The 'variance' is the day difference between 'completion date' of each row and its prior reporting period. This dataset is part of the Capital Projects Dashboard.

City Government Mayor's Office of Operations (OPS) Dataset 95tx-snak 10 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4233
Reporting Period
202509
Managing Agency
DDC
Pid
4233
Agency Project Name
RECONSTRUCTION OF ROADWAYS AT RANDALL'S ISLAND
Current Phase
Design
Completion Date
2030-06-16T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4233
Reporting Period
202601
Managing Agency
DDC
Pid
4233
Agency Project Name
RECONSTRUCTION OF ROADWAYS AT RANDALL'S ISLAND
Current Phase
Design
Completion Date
2030-06-16T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4233
Reporting Period
202605
Managing Agency
DDC
Pid
4233
Agency Project Name
RECONSTRUCTION OF ROADWAYS AT RANDALL'S ISLAND
Current Phase
Design
Completion Date
2030-06-16T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4234
Reporting Period
202305
Managing Agency
DDC
Pid
4234
Agency Project Name
Reconstruction of Schenck Avenue
Current Phase
Construction
Completion Date
2025-06-06T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4234
Reporting Period
202309
Managing Agency
DDC
Pid
4234
Agency Project Name
Reconstruction of Schenck Avenue
Current Phase
Construction
Completion Date
2025-06-06T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4234
Reporting Period
202401
Managing Agency
DDC
Pid
4234
Agency Project Name
Reconstruction of Schenck Avenue
Current Phase
Construction
Completion Date
2025-06-06T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4234
Reporting Period
202405
Managing Agency
DDC
Pid
4234
Agency Project Name
Reconstruction of Schenck Avenue
Current Phase
Construction
Completion Date
2025-06-06T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4234
Reporting Period
202409
Managing Agency
DDC
Pid
4234
Agency Project Name
Reconstruction of Schenck Avenue
Current Phase
Construction
Completion Date
2025-06-06T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4234
Reporting Period
202501
Managing Agency
DDC
Pid
4234
Agency Project Name
Reconstruction of Schenck Avenue
Current Phase
Construction
Completion Date
2025-06-06T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4234
Reporting Period
202505
Managing Agency
DDC
Pid
4234
Agency Project Name
Reconstruction of Schenck Avenue
Current Phase
Construction
Completion Date
2025-06-06T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4234
Reporting Period
202509
Managing Agency
DDC
Pid
4234
Agency Project Name
Reconstruction of Schenck Avenue
Current Phase
Close-out
Completion Date
2025-06-06T00:00:00.000
Completion Date Type
Actual
Variance Day
0
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4235
Reporting Period
202305
Managing Agency
DDC
Pid
4235
Agency Project Name
STM, SAN SEWERS & WM IN CONEY ISLAND AREA, PH3A,BK
Current Phase
Construction
Completion Date
2023-11-27T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4235
Reporting Period
202309
Managing Agency
DDC
Pid
4235
Agency Project Name
STM, SAN SEWERS & WM IN CONEY ISLAND AREA, PH3A,BK
Current Phase
Construction
Completion Date
2024-09-18T00:00:00.000
Completion Date Type
Forecast
Variance Day
296
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4235
Reporting Period
202401
Managing Agency
DDC
Pid
4235
Agency Project Name
STM, SAN SEWERS & WM IN CONEY ISLAND AREA, PH3A,BK
Current Phase
Construction
Completion Date
2024-09-18T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4235
Reporting Period
202405
Managing Agency
DDC
Pid
4235
Agency Project Name
STM, SAN SEWERS & WM IN CONEY ISLAND AREA, PH3A,BK
Current Phase
Construction
Completion Date
2024-09-18T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4235
Reporting Period
202409
Managing Agency
DDC
Pid
4235
Agency Project Name
STM, SAN SEWERS & WM IN CONEY ISLAND AREA, PH3A,BK
Current Phase
Construction
Completion Date
2025-06-11T00:00:00.000
Completion Date Type
Forecast
Variance Day
266
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO SCHEDULING OF UTILITY WORK
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4235
Reporting Period
202501
Managing Agency
DDC
Pid
4235
Agency Project Name
STM, SAN SEWERS & WM IN CONEY ISLAND AREA, PH3A,BK
Current Phase
Construction
Completion Date
2025-06-11T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4235
Reporting Period
202505
Managing Agency
DDC
Pid
4235
Agency Project Name
STM, SAN SEWERS & WM IN CONEY ISLAND AREA, PH3A,BK
Current Phase
Construction
Completion Date
2025-10-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
141
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4235
Reporting Period
202509
Managing Agency
DDC
Pid
4235
Agency Project Name
STM, SAN SEWERS & WM IN CONEY ISLAND AREA, PH3A,BK
Current Phase
Construction
Completion Date
2025-10-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4235
Reporting Period
202601
Managing Agency
DDC
Pid
4235
Agency Project Name
STM, SAN SEWERS & WM IN CONEY ISLAND AREA, PH3A,BK
Current Phase
Close-out
Completion Date
2026-01-30T00:00:00.000
Completion Date Type
Actual
Variance Day
92
Data Date
2026-03-20T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4236
Reporting Period
202305
Managing Agency
DDC
Pid
4236
Agency Project Name
RECONSTRUCTION OF ROSEDALE AREA, PHASE 2
Current Phase
Construction Procurement
Completion Date
2026-12-03T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4236
Reporting Period
202309
Managing Agency
DDC
Pid
4236
Agency Project Name
RECONSTRUCTION OF ROSEDALE AREA, PHASE 2
Current Phase
Construction
Completion Date
2026-12-02T00:00:00.000
Completion Date Type
Forecast
Variance Day
-1
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4236
Reporting Period
202401
Managing Agency
DDC
Pid
4236
Agency Project Name
RECONSTRUCTION OF ROSEDALE AREA, PHASE 2
Current Phase
Construction
Completion Date
2026-12-02T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4236
Reporting Period
202405
Managing Agency
DDC
Pid
4236
Agency Project Name
RECONSTRUCTION OF ROSEDALE AREA, PHASE 2
Current Phase
Construction
Completion Date
2026-12-02T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4236
Reporting Period
202409
Managing Agency
DDC
Pid
4236
Agency Project Name
RECONSTRUCTION OF ROSEDALE AREA, PHASE 2
Current Phase
Construction
Completion Date
2026-12-02T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4236
Reporting Period
202501
Managing Agency
DDC
Pid
4236
Agency Project Name
RECONSTRUCTION OF ROSEDALE AREA, PHASE 2
Current Phase
Construction
Completion Date
2026-12-02T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4236
Reporting Period
202505
Managing Agency
DDC
Pid
4236
Agency Project Name
RECONSTRUCTION OF ROSEDALE AREA, PHASE 2
Current Phase
Construction
Completion Date
2026-12-02T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4236
Reporting Period
202509
Managing Agency
DDC
Pid
4236
Agency Project Name
RECONSTRUCTION OF ROSEDALE AREA, PHASE 2
Current Phase
Construction
Completion Date
2026-12-02T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4236
Reporting Period
202601
Managing Agency
DDC
Pid
4236
Agency Project Name
RECONSTRUCTION OF ROSEDALE AREA, PHASE 2
Current Phase
Construction
Completion Date
2026-12-02T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4236
Reporting Period
202605
Managing Agency
DDC
Pid
4236
Agency Project Name
RECONSTRUCTION OF ROSEDALE AREA, PHASE 2
Current Phase
Construction
Completion Date
2026-12-02T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4237
Reporting Period
202305
Managing Agency
DDC
Pid
4237
Agency Project Name
SUNSET PARK NORTH BK WATERFRONT GREENWAY
Current Phase
Design
Completion Date
2027-09-30T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4237
Reporting Period
202309
Managing Agency
DDC
Pid
4237
Agency Project Name
SUNSET PARK NORTH BK WATERFRONT GREENWAY
Current Phase
Construction Procurement
Completion Date
2026-10-08T00:00:00.000
Completion Date Type
Forecast
Variance Day
-357
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4237
Reporting Period
202401
Managing Agency
DDC
Pid
4237
Agency Project Name
SUNSET PARK NORTH BK WATERFRONT GREENWAY
Current Phase
Construction Procurement
Completion Date
2026-10-08T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4237
Reporting Period
202405
Managing Agency
DDC
Pid
4237
Agency Project Name
SUNSET PARK NORTH BK WATERFRONT GREENWAY
Current Phase
Construction Procurement
Completion Date
2026-10-08T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4237
Reporting Period
202409
Managing Agency
DDC
Pid
4237
Agency Project Name
SUNSET PARK NORTH BK WATERFRONT GREENWAY
Current Phase
Construction Procurement
Completion Date
2027-01-08T00:00:00.000
Completion Date Type
Forecast
Variance Day
92
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4237
Reporting Period
202501
Managing Agency
DDC
Pid
4237
Agency Project Name
SUNSET PARK NORTH BK WATERFRONT GREENWAY
Current Phase
Construction Procurement
Completion Date
2027-06-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
144
Reason For Forecast Completion Change
PROJECT DELAYED PENDING APPROVAL OF NECESSARY PERMITS
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4237
Reporting Period
202505
Managing Agency
DDC
Pid
4237
Agency Project Name
SUNSET PARK NORTH BK WATERFRONT GREENWAY
Current Phase
Construction Procurement
Completion Date
2027-06-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4237
Reporting Period
202509
Managing Agency
DDC
Pid
4237
Agency Project Name
SUNSET PARK NORTH BK WATERFRONT GREENWAY
Current Phase
Construction
Completion Date
2027-06-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4237
Reporting Period
202601
Managing Agency
DDC
Pid
4237
Agency Project Name
SUNSET PARK NORTH BK WATERFRONT GREENWAY
Current Phase
Construction
Completion Date
2027-06-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4237
Reporting Period
202605
Managing Agency
DDC
Pid
4237
Agency Project Name
SUNSET PARK NORTH BK WATERFRONT GREENWAY
Current Phase
Construction
Completion Date
2027-06-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4238
Reporting Period
202305
Managing Agency
DDC
Pid
4238
Agency Project Name
170 East 121 Street - Harlem Courthouse Facade
Current Phase
Design
Completion Date
2027-07-07T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4238
Reporting Period
202309
Managing Agency
DDC
Pid
4238
Agency Project Name
170 East 121 Street - Harlem Courthouse Facade
Current Phase
Design
Completion Date
2027-01-22T00:00:00.000
Completion Date Type
Forecast
Variance Day
-166
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4238
Reporting Period
202401
Managing Agency
DDC
Pid
4238
Agency Project Name
170 East 121 Street - Harlem Courthouse Facade
Current Phase
Design
Completion Date
2027-01-22T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4238
Reporting Period
202405
Managing Agency
DDC
Pid
4238
Agency Project Name
170 East 121 Street - Harlem Courthouse Facade
Current Phase
Design
Completion Date
2027-01-22T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4238
Reporting Period
202409
Managing Agency
DDC
Pid
4238
Agency Project Name
170 East 121 Street - Harlem Courthouse Facade
Current Phase
Design
Completion Date
2027-01-22T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4238
Reporting Period
202501
Managing Agency
DDC
Pid
4238
Agency Project Name
170 East 121 Street - Harlem Courthouse Facade
Current Phase
Design
Completion Date
2027-09-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
251
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4238
Reporting Period
202505
Managing Agency
DDC
Pid
4238
Agency Project Name
170 East 121 Street - Harlem Courthouse Facade
Current Phase
Design
Completion Date
2028-01-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
122
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4238
Reporting Period
202509
Managing Agency
DDC
Pid
4238
Agency Project Name
170 East 121 Street - Harlem Courthouse Facade
Current Phase
Design
Completion Date
2028-04-28T00:00:00.000
Completion Date Type
Forecast
Variance Day
89
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4238
Reporting Period
202601
Managing Agency
DDC
Pid
4238
Agency Project Name
170 East 121 Street - Harlem Courthouse Facade
Current Phase
Construction Procurement
Completion Date
2028-05-31T00:00:00.000
Completion Date Type
Forecast
Variance Day
33
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4238
Reporting Period
202605
Managing Agency
DDC
Pid
4238
Agency Project Name
170 East 121 Street - Harlem Courthouse Facade
Current Phase
Construction Procurement
Completion Date
2028-09-04T00:00:00.000
Completion Date Type
Forecast
Variance Day
96
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
Data Date
2026-06-23T00:00:00.000