Capital Projects Dashboard - Citywide Schedule History and Variance

This is the history all agency reported forecasts/actual project completion dates. Each row is the snapshot of data taken on each reporting period. The 'completion date type' column shows if the 'completion date' is either a forecast or actual date. Over time, a project would have one or more forecasted completion dates before it is actually completed. The 'variance' is the day difference between 'completion date' of each row and its prior reporting period. This dataset is part of the Capital Projects Dashboard.

City Government Mayor's Office of Operations (OPS) Dataset 95tx-snak 10 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4244
Reporting Period
202305
Managing Agency
DDC
Pid
4244
Agency Project Name
RECON WYCKOFF AV-FLUSHING to COOPER AV/SE
Current Phase
Design
Completion Date
2027-08-29T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4244
Reporting Period
202309
Managing Agency
DDC
Pid
4244
Agency Project Name
RECON WYCKOFF AV-FLUSHING to COOPER AV/SE
Current Phase
Design
Completion Date
2028-09-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
397
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4244
Reporting Period
202401
Managing Agency
DDC
Pid
4244
Agency Project Name
RECON WYCKOFF AV-FLUSHING to COOPER AV/SE
Current Phase
Design
Completion Date
2028-09-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4244
Reporting Period
202405
Managing Agency
DDC
Pid
4244
Agency Project Name
RECON WYCKOFF AV-FLUSHING to COOPER AV/SE
Current Phase
Design
Completion Date
2028-09-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4244
Reporting Period
202409
Managing Agency
DDC
Pid
4244
Agency Project Name
RECON WYCKOFF AV-FLUSHING to COOPER AV/SE
Current Phase
Design
Completion Date
2028-12-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
75
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNFORESEEN HAZARDOUS CONDITION
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4244
Reporting Period
202501
Managing Agency
DDC
Pid
4244
Agency Project Name
RECON WYCKOFF AV-FLUSHING to COOPER AV/SE
Current Phase
Design
Completion Date
2029-05-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
139
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4244
Reporting Period
202505
Managing Agency
DDC
Pid
4244
Agency Project Name
RECON WYCKOFF AV-FLUSHING to COOPER AV/SE
Current Phase
Design
Completion Date
2029-05-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4244
Reporting Period
202509
Managing Agency
DDC
Pid
4244
Agency Project Name
RECON WYCKOFF AV-FLUSHING to COOPER AV/SE
Current Phase
Design
Completion Date
2029-09-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
137
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4244
Reporting Period
202601
Managing Agency
DDC
Pid
4244
Agency Project Name
RECON WYCKOFF AV-FLUSHING to COOPER AV/SE
Current Phase
Design
Completion Date
2030-02-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
152
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO SCHEDULING OF UTILITY WORK
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4244
Reporting Period
202605
Managing Agency
DDC
Pid
4244
Agency Project Name
RECON WYCKOFF AV-FLUSHING to COOPER AV/SE
Current Phase
Design
Completion Date
2030-06-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
120
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4245
Reporting Period
202305
Managing Agency
DDC
Pid
4245
Agency Project Name
4th Ave Safety Improvements - Phase B
Current Phase
Design
Completion Date
2029-01-29T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4245
Reporting Period
202309
Managing Agency
DDC
Pid
4245
Agency Project Name
4th Ave Safety Improvements - Phase B
Current Phase
Design
Completion Date
2029-08-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
213
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4245
Reporting Period
202401
Managing Agency
DDC
Pid
4245
Agency Project Name
4th Ave Safety Improvements - Phase B
Current Phase
Design
Completion Date
2029-08-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4245
Reporting Period
202405
Managing Agency
DDC
Pid
4245
Agency Project Name
4th Ave Safety Improvements - Phase B
Current Phase
Design
Completion Date
2030-08-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
365
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4245
Reporting Period
202409
Managing Agency
DDC
Pid
4245
Agency Project Name
4th Ave Safety Improvements - Phase B
Current Phase
Design
Completion Date
2030-05-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
-92
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4245
Reporting Period
202501
Managing Agency
DDC
Pid
4245
Agency Project Name
4th Ave Safety Improvements - Phase B
Current Phase
Design
Completion Date
2030-05-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4245
Reporting Period
202505
Managing Agency
DDC
Pid
4245
Agency Project Name
4th Ave Safety Improvements - Phase B
Current Phase
Design
Completion Date
2030-08-28T00:00:00.000
Completion Date Type
Forecast
Variance Day
90
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4245
Reporting Period
202509
Managing Agency
DDC
Pid
4245
Agency Project Name
4th Ave Safety Improvements - Phase B
Current Phase
Design
Completion Date
2030-10-25T00:00:00.000
Completion Date Type
Forecast
Variance Day
58
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4245
Reporting Period
202601
Managing Agency
DDC
Pid
4245
Agency Project Name
4th Ave Safety Improvements - Phase B
Current Phase
Design
Completion Date
2030-10-25T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4245
Reporting Period
202605
Managing Agency
DDC
Pid
4245
Agency Project Name
4th Ave Safety Improvements - Phase B
Current Phase
Design
Completion Date
2031-06-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
248
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4246
Reporting Period
202305
Managing Agency
DDC
Pid
4246
Agency Project Name
REGULAR CHAMBER ROOF REPLACEMENT
Current Phase
Construction
Completion Date
2024-08-26T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4246
Reporting Period
202309
Managing Agency
DDC
Pid
4246
Agency Project Name
REGULAR CHAMBER ROOF REPLACEMENT
Current Phase
Construction
Completion Date
2024-08-26T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4246
Reporting Period
202401
Managing Agency
DDC
Pid
4246
Agency Project Name
REGULAR CHAMBER ROOF REPLACEMENT
Current Phase
Construction
Completion Date
2024-08-26T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4246
Reporting Period
202405
Managing Agency
DDC
Pid
4246
Agency Project Name
REGULAR CHAMBER ROOF REPLACEMENT
Current Phase
Construction
Completion Date
2024-08-26T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4246
Reporting Period
202409
Managing Agency
DDC
Pid
4246
Agency Project Name
REGULAR CHAMBER ROOF REPLACEMENT
Current Phase
Construction
Completion Date
2024-08-23T00:00:00.000
Completion Date Type
Actual
Variance Day
-3
Data Date
2024-07-18T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4247
Reporting Period
202305
Managing Agency
DDC
Pid
4247
Agency Project Name
Simple Upgrades Ped Ramps - Brooklyn and Queens
Current Phase
Construction Procurement
Completion Date
2026-04-29T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4247
Reporting Period
202309
Managing Agency
DDC
Pid
4247
Agency Project Name
Simple Upgrades Ped Ramps - Brooklyn and Queens
Current Phase
Construction Procurement
Completion Date
2026-04-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4247
Reporting Period
202401
Managing Agency
DDC
Pid
4247
Agency Project Name
Simple Upgrades Ped Ramps - Brooklyn and Queens
Current Phase
Construction Procurement
Completion Date
2026-04-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4247
Reporting Period
202405
Managing Agency
DDC
Pid
4247
Agency Project Name
Simple Upgrades Ped Ramps - Brooklyn and Queens
Current Phase
Construction Procurement
Completion Date
2026-09-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
139
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO BUDGETARY CONSTRAINTS
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4247
Reporting Period
202409
Managing Agency
DDC
Pid
4247
Agency Project Name
Simple Upgrades Ped Ramps - Brooklyn and Queens
Current Phase
Construction
Completion Date
2026-09-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4247
Reporting Period
202501
Managing Agency
DDC
Pid
4247
Agency Project Name
Simple Upgrades Ped Ramps - Brooklyn and Queens
Current Phase
Construction
Completion Date
2026-09-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4247
Reporting Period
202505
Managing Agency
DDC
Pid
4247
Agency Project Name
Simple Upgrades Ped Ramps - Brooklyn and Queens
Current Phase
Construction
Completion Date
2026-09-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4247
Reporting Period
202509
Managing Agency
DDC
Pid
4247
Agency Project Name
Simple Upgrades Ped Ramps - Brooklyn and Queens
Current Phase
Construction
Completion Date
2026-09-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4247
Reporting Period
202601
Managing Agency
DDC
Pid
4247
Agency Project Name
Simple Upgrades Ped Ramps - Brooklyn and Queens
Current Phase
Construction
Completion Date
2026-09-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4247
Reporting Period
202605
Managing Agency
DDC
Pid
4247
Agency Project Name
Simple Upgrades Ped Ramps - Brooklyn and Queens
Current Phase
Construction
Completion Date
2026-09-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4248
Reporting Period
202305
Managing Agency
DDC
Pid
4248
Agency Project Name
Standard Ped Ramp Upgrades and Installs - Citywide
Current Phase
Construction Procurement
Completion Date
2025-09-10T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4248
Reporting Period
202309
Managing Agency
DDC
Pid
4248
Agency Project Name
Standard Ped Ramp Upgrades and Installs - Citywide
Current Phase
Construction
Completion Date
2025-09-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4248
Reporting Period
202401
Managing Agency
DDC
Pid
4248
Agency Project Name
Standard Ped Ramp Upgrades and Installs - Citywide
Current Phase
Construction
Completion Date
2025-09-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4248
Reporting Period
202405
Managing Agency
DDC
Pid
4248
Agency Project Name
Standard Ped Ramp Upgrades and Installs - Citywide
Current Phase
Construction
Completion Date
2025-09-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4248
Reporting Period
202409
Managing Agency
DDC
Pid
4248
Agency Project Name
Standard Ped Ramp Upgrades and Installs - Citywide
Current Phase
Construction
Completion Date
2025-09-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4248
Reporting Period
202501
Managing Agency
DDC
Pid
4248
Agency Project Name
Standard Ped Ramp Upgrades and Installs - Citywide
Current Phase
Construction
Completion Date
2025-09-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4248
Reporting Period
202505
Managing Agency
DDC
Pid
4248
Agency Project Name
Standard Ped Ramp Upgrades and Installs - Citywide
Current Phase
Construction
Completion Date
2025-09-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4248
Reporting Period
202509
Managing Agency
DDC
Pid
4248
Agency Project Name
Standard Ped Ramp Upgrades and Installs - Citywide
Current Phase
Close-out
Completion Date
2025-08-07T00:00:00.000
Completion Date Type
Actual
Variance Day
-34
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4249
Reporting Period
202305
Managing Agency
DDC
Pid
4249
Agency Project Name
Brkyln District 17/18 Garage: HVAC Replacement
Current Phase
Construction
Completion Date
2024-10-31T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4249
Reporting Period
202309
Managing Agency
DDC
Pid
4249
Agency Project Name
Brkyln District 17/18 Garage: HVAC Replacement
Current Phase
Construction
Completion Date
2024-10-23T00:00:00.000
Completion Date Type
Forecast
Variance Day
-8
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4249
Reporting Period
202401
Managing Agency
DDC
Pid
4249
Agency Project Name
Brkyln District 17/18 Garage: HVAC Replacement
Current Phase
Construction
Completion Date
2024-10-23T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4249
Reporting Period
202405
Managing Agency
DDC
Pid
4249
Agency Project Name
Brkyln District 17/18 Garage: HVAC Replacement
Current Phase
Construction
Completion Date
2025-11-28T00:00:00.000
Completion Date Type
Forecast
Variance Day
401
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO SCHEDULING OF UTILITY WORK
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4249
Reporting Period
202409
Managing Agency
DDC
Pid
4249
Agency Project Name
Brkyln District 17/18 Garage: HVAC Replacement
Current Phase
Construction
Completion Date
2025-11-28T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4249
Reporting Period
202501
Managing Agency
DDC
Pid
4249
Agency Project Name
Brkyln District 17/18 Garage: HVAC Replacement
Current Phase
Construction
Completion Date
2025-11-28T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4249
Reporting Period
202505
Managing Agency
DDC
Pid
4249
Agency Project Name
Brkyln District 17/18 Garage: HVAC Replacement
Current Phase
Construction
Completion Date
2025-11-28T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000