Capital Projects Dashboard - Citywide Schedule History and Variance

This is the history all agency reported forecasts/actual project completion dates. Each row is the snapshot of data taken on each reporting period. The 'completion date type' column shows if the 'completion date' is either a forecast or actual date. Over time, a project would have one or more forecasted completion dates before it is actually completed. The 'variance' is the day difference between 'completion date' of each row and its prior reporting period. This dataset is part of the Capital Projects Dashboard.

City Government Mayor's Office of Operations (OPS) Dataset 95tx-snak 10 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4249
Reporting Period
202509
Managing Agency
DDC
Pid
4249
Agency Project Name
Brkyln District 17/18 Garage: HVAC Replacement
Current Phase
Construction
Completion Date
2026-07-28T00:00:00.000
Completion Date Type
Forecast
Variance Day
242
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4249
Reporting Period
202601
Managing Agency
DDC
Pid
4249
Agency Project Name
Brkyln District 17/18 Garage: HVAC Replacement
Current Phase
Construction
Completion Date
2026-07-28T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4249
Reporting Period
202605
Managing Agency
DDC
Pid
4249
Agency Project Name
Brkyln District 17/18 Garage: HVAC Replacement
Current Phase
Construction
Completion Date
2026-07-28T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4250
Reporting Period
202305
Managing Agency
DDC
Pid
4250
Agency Project Name
East River Park
Current Phase
Construction
Completion Date
2024-09-28T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4250
Reporting Period
202309
Managing Agency
DDC
Pid
4250
Agency Project Name
East River Park
Current Phase
Construction
Completion Date
2024-09-28T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4250
Reporting Period
202401
Managing Agency
DDC
Pid
4250
Agency Project Name
East River Park
Current Phase
Construction
Completion Date
2024-09-28T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4250
Reporting Period
202405
Managing Agency
DDC
Pid
4250
Agency Project Name
East River Park
Current Phase
Construction
Completion Date
2024-09-28T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4250
Reporting Period
202409
Managing Agency
DDC
Pid
4250
Agency Project Name
East River Park
Current Phase
Construction
Completion Date
2025-09-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
367
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4250
Reporting Period
202501
Managing Agency
DDC
Pid
4250
Agency Project Name
East River Park
Current Phase
Construction
Completion Date
2025-09-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4250
Reporting Period
202505
Managing Agency
DDC
Pid
4250
Agency Project Name
East River Park
Current Phase
Construction
Completion Date
2025-09-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4250
Reporting Period
202509
Managing Agency
DDC
Pid
4250
Agency Project Name
East River Park
Current Phase
Construction
Completion Date
2027-03-25T00:00:00.000
Completion Date Type
Forecast
Variance Day
541
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4250
Reporting Period
202601
Managing Agency
DDC
Pid
4250
Agency Project Name
East River Park
Current Phase
Construction
Completion Date
2027-03-25T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4250
Reporting Period
202605
Managing Agency
DDC
Pid
4250
Agency Project Name
East River Park
Current Phase
Construction
Completion Date
2027-03-25T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4251
Reporting Period
202305
Managing Agency
DDC
Pid
4251
Agency Project Name
Simple Upgrades Ped Ramps- Brooklyn
Current Phase
Construction
Completion Date
2025-07-08T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4251
Reporting Period
202309
Managing Agency
DDC
Pid
4251
Agency Project Name
Simple Upgrades Ped Ramps- Brooklyn
Current Phase
Construction
Completion Date
2025-07-08T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4251
Reporting Period
202401
Managing Agency
DDC
Pid
4251
Agency Project Name
Simple Upgrades Ped Ramps- Brooklyn
Current Phase
Construction
Completion Date
2025-07-08T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4251
Reporting Period
202405
Managing Agency
DDC
Pid
4251
Agency Project Name
Simple Upgrades Ped Ramps- Brooklyn
Current Phase
Construction
Completion Date
2025-07-08T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4251
Reporting Period
202409
Managing Agency
DDC
Pid
4251
Agency Project Name
Simple Upgrades Ped Ramps- Brooklyn
Current Phase
Construction
Completion Date
2025-07-08T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4251
Reporting Period
202501
Managing Agency
DDC
Pid
4251
Agency Project Name
Simple Upgrades Ped Ramps- Brooklyn
Current Phase
Construction
Completion Date
2025-07-08T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4251
Reporting Period
202505
Managing Agency
DDC
Pid
4251
Agency Project Name
Simple Upgrades Ped Ramps- Brooklyn
Current Phase
Construction
Completion Date
2025-07-08T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4251
Reporting Period
202509
Managing Agency
DDC
Pid
4251
Agency Project Name
Simple Upgrades Ped Ramps- Brooklyn
Current Phase
Close-out
Completion Date
2025-03-03T00:00:00.000
Completion Date Type
Actual
Variance Day
-127
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4252
Reporting Period
202305
Managing Agency
DDC
Pid
4252
Agency Project Name
Simple Upgrades Ped Ramps - Brooklyn
Current Phase
Construction Procurement
Completion Date
2026-06-17T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4252
Reporting Period
202309
Managing Agency
DDC
Pid
4252
Agency Project Name
Simple Upgrades Ped Ramps - Brooklyn
Current Phase
Construction Procurement
Completion Date
2027-06-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
378
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4252
Reporting Period
202401
Managing Agency
DDC
Pid
4252
Agency Project Name
Simple Upgrades Ped Ramps - Brooklyn
Current Phase
Construction Procurement
Completion Date
2027-06-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4252
Reporting Period
202405
Managing Agency
DDC
Pid
4252
Agency Project Name
Simple Upgrades Ped Ramps - Brooklyn
Current Phase
Construction Procurement
Completion Date
2026-09-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
-288
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4252
Reporting Period
202409
Managing Agency
DDC
Pid
4252
Agency Project Name
Simple Upgrades Ped Ramps - Brooklyn
Current Phase
Construction
Completion Date
2026-09-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4252
Reporting Period
202501
Managing Agency
DDC
Pid
4252
Agency Project Name
Simple Upgrades Ped Ramps - Brooklyn
Current Phase
Construction
Completion Date
2026-09-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4252
Reporting Period
202505
Managing Agency
DDC
Pid
4252
Agency Project Name
Simple Upgrades Ped Ramps - Brooklyn
Current Phase
Construction
Completion Date
2026-09-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4252
Reporting Period
202509
Managing Agency
DDC
Pid
4252
Agency Project Name
Simple Upgrades Ped Ramps - Brooklyn
Current Phase
Construction
Completion Date
2026-09-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4252
Reporting Period
202601
Managing Agency
DDC
Pid
4252
Agency Project Name
Simple Upgrades Ped Ramps - Brooklyn
Current Phase
Construction
Completion Date
2026-09-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4252
Reporting Period
202605
Managing Agency
DDC
Pid
4252
Agency Project Name
Simple Upgrades Ped Ramps - Brooklyn
Current Phase
Construction
Completion Date
2026-09-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4253
Reporting Period
202305
Managing Agency
DDC
Pid
4253
Agency Project Name
Simple Upgrades Ped Ramps- Manhattan and Queens
Current Phase
Construction
Completion Date
2024-08-06T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4253
Reporting Period
202309
Managing Agency
DDC
Pid
4253
Agency Project Name
Simple Upgrades Ped Ramps- Manhattan and Queens
Current Phase
Construction
Completion Date
2024-08-06T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4253
Reporting Period
202401
Managing Agency
DDC
Pid
4253
Agency Project Name
Simple Upgrades Ped Ramps- Manhattan and Queens
Current Phase
Construction
Completion Date
2024-08-06T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4253
Reporting Period
202405
Managing Agency
DDC
Pid
4253
Agency Project Name
Simple Upgrades Ped Ramps- Manhattan and Queens
Current Phase
Construction
Completion Date
2024-08-06T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4253
Reporting Period
202409
Managing Agency
DDC
Pid
4253
Agency Project Name
Simple Upgrades Ped Ramps- Manhattan and Queens
Current Phase
Construction
Completion Date
2024-08-06T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4253
Reporting Period
202501
Managing Agency
DDC
Pid
4253
Agency Project Name
Simple Upgrades Ped Ramps- Manhattan and Queens
Current Phase
Close-out
Completion Date
2024-08-06T00:00:00.000
Completion Date Type
Actual
Variance Day
0
Data Date
2025-03-03T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4254
Reporting Period
202305
Managing Agency
DDC
Pid
4254
Agency Project Name
Simple Upgrades Ped Ramps- Brooklyn
Current Phase
Construction
Completion Date
2024-08-06T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4254
Reporting Period
202309
Managing Agency
DDC
Pid
4254
Agency Project Name
Simple Upgrades Ped Ramps- Brooklyn
Current Phase
Construction
Completion Date
2024-08-06T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4254
Reporting Period
202401
Managing Agency
DDC
Pid
4254
Agency Project Name
Simple Upgrades Ped Ramps- Brooklyn
Current Phase
Construction
Completion Date
2024-08-06T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4254
Reporting Period
202405
Managing Agency
DDC
Pid
4254
Agency Project Name
Simple Upgrades Ped Ramps- Brooklyn
Current Phase
Construction
Completion Date
2024-08-06T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4254
Reporting Period
202409
Managing Agency
DDC
Pid
4254
Agency Project Name
Simple Upgrades Ped Ramps- Brooklyn
Current Phase
Construction
Completion Date
2024-08-06T00:00:00.000
Completion Date Type
Actual
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4255
Reporting Period
202305
Managing Agency
DDC
Pid
4255
Agency Project Name
Simple Upgrades Ped Ramps- Manhattan and Queens
Current Phase
Construction
Completion Date
2025-07-08T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4255
Reporting Period
202309
Managing Agency
DDC
Pid
4255
Agency Project Name
Simple Upgrades Ped Ramps- Manhattan and Queens
Current Phase
Construction
Completion Date
2025-07-08T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4255
Reporting Period
202401
Managing Agency
DDC
Pid
4255
Agency Project Name
Simple Upgrades Ped Ramps- Manhattan and Queens
Current Phase
Construction
Completion Date
2025-07-08T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4255
Reporting Period
202405
Managing Agency
DDC
Pid
4255
Agency Project Name
Simple Upgrades Ped Ramps- Manhattan and Queens
Current Phase
Construction
Completion Date
2025-07-08T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4255
Reporting Period
202409
Managing Agency
DDC
Pid
4255
Agency Project Name
Simple Upgrades Ped Ramps- Manhattan and Queens
Current Phase
Construction
Completion Date
2025-07-08T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4255
Reporting Period
202501
Managing Agency
DDC
Pid
4255
Agency Project Name
Simple Upgrades Ped Ramps- Manhattan and Queens
Current Phase
Construction
Completion Date
2025-07-08T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4255
Reporting Period
202505
Managing Agency
DDC
Pid
4255
Agency Project Name
Simple Upgrades Ped Ramps- Manhattan and Queens
Current Phase
Construction
Completion Date
2025-07-08T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4255
Reporting Period
202509
Managing Agency
DDC
Pid
4255
Agency Project Name
Simple Upgrades Ped Ramps- Manhattan and Queens
Current Phase
Construction
Completion Date
2025-10-31T00:00:00.000
Completion Date Type
Forecast
Variance Day
115
Data Date
2025-10-23T00:00:00.000