Capital Projects Dashboard - Citywide Schedule History and Variance

This is the history all agency reported forecasts/actual project completion dates. Each row is the snapshot of data taken on each reporting period. The 'completion date type' column shows if the 'completion date' is either a forecast or actual date. Over time, a project would have one or more forecasted completion dates before it is actually completed. The 'variance' is the day difference between 'completion date' of each row and its prior reporting period. This dataset is part of the Capital Projects Dashboard.

City Government Mayor's Office of Operations (OPS) Dataset 95tx-snak 10 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
202501
Reporting Period: 202501 • Managing Agency: DCAS • Pid: 3351
Reporting Period
202501
Managing Agency
DCAS
Pid
3351
Agency Project Name
NYPD - 9 NYPD SITES COMBINED
Current Phase
Construction
Completion Date
2026-06-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-03-04T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DCAS • Pid: 3351
Reporting Period
202505
Managing Agency
DCAS
Pid
3351
Agency Project Name
NYPD - 9 NYPD SITES COMBINED
Current Phase
Close-out
Completion Date
2025-05-22T00:00:00.000
Completion Date Type
Actual
Variance Day
-404
Data Date
2025-06-18T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DCAS • Pid: 3352
Reporting Period
202305
Managing Agency
DCAS
Pid
3352
Agency Project Name
NYPD - 63rd Precinct
Current Phase
Construction Procurement
Completion Date
2024-02-27T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-06-28T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DCAS • Pid: 3352
Reporting Period
202309
Managing Agency
DCAS
Pid
3352
Agency Project Name
NYPD - 63rd Precinct
Current Phase
Construction Procurement
Completion Date
2024-02-27T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-01-04T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DCAS • Pid: 3352
Reporting Period
202401
Managing Agency
DCAS
Pid
3352
Agency Project Name
NYPD - 63rd Precinct
Current Phase
Construction
Completion Date
2024-05-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
92
Data Date
2024-05-02T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DCAS • Pid: 3352
Reporting Period
202405
Managing Agency
DCAS
Pid
3352
Agency Project Name
NYPD - 63rd Precinct
Current Phase
Construction
Completion Date
2024-05-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-11T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DCAS • Pid: 3352
Reporting Period
202409
Managing Agency
DCAS
Pid
3352
Agency Project Name
NYPD - 63rd Precinct
Current Phase
Construction
Completion Date
2024-06-26T00:00:00.000
Completion Date Type
Actual
Variance Day
28
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNAVAILABILITY OF PRODUCT
Data Date
2024-11-01T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DCAS • Pid: 3353
Reporting Period
202305
Managing Agency
DCAS
Pid
3353
Agency Project Name
NYPD - 66th Precinct
Current Phase
Construction Procurement
Completion Date
2024-02-27T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-06-28T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DCAS • Pid: 3353
Reporting Period
202309
Managing Agency
DCAS
Pid
3353
Agency Project Name
NYPD - 66th Precinct
Current Phase
Construction Procurement
Completion Date
2024-02-27T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-01-04T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DCAS • Pid: 3353
Reporting Period
202401
Managing Agency
DCAS
Pid
3353
Agency Project Name
NYPD - 66th Precinct
Current Phase
Construction
Completion Date
2024-06-24T00:00:00.000
Completion Date Type
Forecast
Variance Day
118
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNAVAILABILITY OF PRODUCT
Data Date
2024-05-02T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DCAS • Pid: 3353
Reporting Period
202405
Managing Agency
DCAS
Pid
3353
Agency Project Name
NYPD - 66th Precinct
Current Phase
Construction
Completion Date
2024-06-24T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-11T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DCAS • Pid: 3353
Reporting Period
202409
Managing Agency
DCAS
Pid
3353
Agency Project Name
NYPD - 66th Precinct
Current Phase
Construction
Completion Date
2024-06-26T00:00:00.000
Completion Date Type
Actual
Variance Day
2
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNAVAILABILITY OF PRODUCT
Data Date
2024-11-01T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DCAS • Pid: 3354
Reporting Period
202305
Managing Agency
DCAS
Pid
3354
Agency Project Name
NYPD - 88th Precinct
Current Phase
Construction Procurement
Completion Date
2024-03-15T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-06-28T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DCAS • Pid: 3354
Reporting Period
202309
Managing Agency
DCAS
Pid
3354
Agency Project Name
NYPD - 88th Precinct
Current Phase
Construction Procurement
Completion Date
2024-03-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-01-04T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DCAS • Pid: 3354
Reporting Period
202401
Managing Agency
DCAS
Pid
3354
Agency Project Name
NYPD - 88th Precinct
Current Phase
Construction
Completion Date
2024-06-28T00:00:00.000
Completion Date Type
Forecast
Variance Day
105
Data Date
2024-05-02T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DCAS • Pid: 3354
Reporting Period
202405
Managing Agency
DCAS
Pid
3354
Agency Project Name
NYPD - 88th Precinct
Current Phase
Construction
Completion Date
2024-06-28T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-11T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DCAS • Pid: 3354
Reporting Period
202409
Managing Agency
DCAS
Pid
3354
Agency Project Name
NYPD - 88th Precinct
Current Phase
Close-out
Completion Date
2024-10-22T00:00:00.000
Completion Date Type
Actual
Variance Day
116
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNAVAILABILITY OF PRODUCT
Data Date
2024-11-01T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DCAS • Pid: 3355
Reporting Period
202305
Managing Agency
DCAS
Pid
3355
Agency Project Name
NYPD - 52nd Precinct
Current Phase
Construction Procurement
Completion Date
2024-05-31T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-06-28T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DCAS • Pid: 3355
Reporting Period
202309
Managing Agency
DCAS
Pid
3355
Agency Project Name
NYPD - 52nd Precinct
Current Phase
Construction Procurement
Completion Date
2024-05-31T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-01-04T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DCAS • Pid: 3355
Reporting Period
202401
Managing Agency
DCAS
Pid
3355
Agency Project Name
NYPD - 52nd Precinct
Current Phase
Construction
Completion Date
2024-07-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
59
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNAVAILABILITY OF PRODUCT
Data Date
2024-05-02T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DCAS • Pid: 3355
Reporting Period
202405
Managing Agency
DCAS
Pid
3355
Agency Project Name
NYPD - 52nd Precinct
Current Phase
Construction
Completion Date
2024-07-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-11T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DCAS • Pid: 3355
Reporting Period
202409
Managing Agency
DCAS
Pid
3355
Agency Project Name
NYPD - 52nd Precinct
Current Phase
Construction
Completion Date
2026-04-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
640
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNAVAILABILITY OF PRODUCT
Data Date
2024-11-01T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DCAS • Pid: 3355
Reporting Period
202501
Managing Agency
DCAS
Pid
3355
Agency Project Name
NYPD - 52nd Precinct
Current Phase
Construction
Completion Date
2026-04-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-03-04T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DCAS • Pid: 3355
Reporting Period
202505
Managing Agency
DCAS
Pid
3355
Agency Project Name
NYPD - 52nd Precinct
Current Phase
Close-out
Completion Date
2025-01-16T00:00:00.000
Completion Date Type
Actual
Variance Day
-469
Data Date
2025-06-18T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DCAS • Pid: 3356
Reporting Period
202305
Managing Agency
DCAS
Pid
3356
Agency Project Name
NYPD - 10th Precinct
Current Phase
Construction
Completion Date
2024-02-15T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-06-28T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DCAS • Pid: 3356
Reporting Period
202309
Managing Agency
DCAS
Pid
3356
Agency Project Name
NYPD - 10th Precinct
Current Phase
Construction
Completion Date
2024-02-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-01-04T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DCAS • Pid: 3356
Reporting Period
202401
Managing Agency
DCAS
Pid
3356
Agency Project Name
NYPD - 10th Precinct
Current Phase
Close-out
Completion Date
2023-12-21T00:00:00.000
Completion Date Type
Actual
Variance Day
-56
Data Date
2024-05-02T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DCAS • Pid: 3357
Reporting Period
202305
Managing Agency
DCAS
Pid
3357
Agency Project Name
NYPD -Engine Co. 39, Ladder Co. 16 and 19th Precinct Campus
Current Phase
Construction Procurement
Completion Date
2023-12-29T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-06-28T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DCAS • Pid: 3357
Reporting Period
202309
Managing Agency
DCAS
Pid
3357
Agency Project Name
NYPD -Engine Co. 39, Ladder Co. 16 and 19th Precinct Campus
Current Phase
Construction Procurement
Completion Date
2023-12-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-01-04T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DCAS • Pid: 3357
Reporting Period
202401
Managing Agency
DCAS
Pid
3357
Agency Project Name
NYPD -Engine Co. 39, Ladder Co. 16 and 19th Precinct Campus
Current Phase
Construction
Completion Date
2024-07-31T00:00:00.000
Completion Date Type
Forecast
Variance Day
215
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNAVAILABILITY OF PRODUCT
Data Date
2024-05-02T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DCAS • Pid: 3357
Reporting Period
202405
Managing Agency
DCAS
Pid
3357
Agency Project Name
NYPD -Engine Co. 39, Ladder Co. 16 and 19th Precinct Campus
Current Phase
Construction
Completion Date
2024-07-31T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-11T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DCAS • Pid: 3357
Reporting Period
202409
Managing Agency
DCAS
Pid
3357
Agency Project Name
NYPD -Engine Co. 39, Ladder Co. 16 and 19th Precinct Campus
Current Phase
Construction
Completion Date
2026-04-19T00:00:00.000
Completion Date Type
Forecast
Variance Day
627
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNAVAILABILITY OF PRODUCT
Data Date
2024-11-01T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DCAS • Pid: 3357
Reporting Period
202501
Managing Agency
DCAS
Pid
3357
Agency Project Name
NYPD -Engine Co. 39, Ladder Co. 16 and 19th Precinct Campus
Current Phase
Construction
Completion Date
2026-04-19T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-03-04T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DCAS • Pid: 3357
Reporting Period
202505
Managing Agency
DCAS
Pid
3357
Agency Project Name
NYPD -Engine Co. 39, Ladder Co. 16 and 19th Precinct Campus
Current Phase
Close-out
Completion Date
2025-02-24T00:00:00.000
Completion Date Type
Actual
Variance Day
-419
Data Date
2025-06-18T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DCAS • Pid: 3358
Reporting Period
202305
Managing Agency
DCAS
Pid
3358
Agency Project Name
NYPD - 30th Precinct
Current Phase
Construction
Completion Date
2024-03-15T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-06-28T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DCAS • Pid: 3358
Reporting Period
202309
Managing Agency
DCAS
Pid
3358
Agency Project Name
NYPD - 30th Precinct
Current Phase
Construction
Completion Date
2024-03-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-01-04T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DCAS • Pid: 3358
Reporting Period
202401
Managing Agency
DCAS
Pid
3358
Agency Project Name
NYPD - 30th Precinct
Current Phase
Close-out
Completion Date
2023-09-28T00:00:00.000
Completion Date Type
Actual
Variance Day
-169
Data Date
2024-05-02T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DCAS • Pid: 3359
Reporting Period
202305
Managing Agency
DCAS
Pid
3359
Agency Project Name
NYPD - 32nd Precinct
Current Phase
Construction
Completion Date
2024-03-15T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-06-28T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DCAS • Pid: 3359
Reporting Period
202309
Managing Agency
DCAS
Pid
3359
Agency Project Name
NYPD - 32nd Precinct
Current Phase
Construction
Completion Date
2024-03-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-01-04T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DCAS • Pid: 3359
Reporting Period
202401
Managing Agency
DCAS
Pid
3359
Agency Project Name
NYPD - 32nd Precinct
Current Phase
Close-out
Completion Date
2024-01-18T00:00:00.000
Completion Date Type
Actual
Variance Day
-57
Data Date
2024-05-02T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DCAS • Pid: 3360
Reporting Period
202305
Managing Agency
DCAS
Pid
3360
Agency Project Name
NYPD - HARBOR UNIT CHARLIE
Current Phase
Construction Procurement
Completion Date
2024-02-29T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-06-28T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DCAS • Pid: 3360
Reporting Period
202309
Managing Agency
DCAS
Pid
3360
Agency Project Name
NYPD - HARBOR UNIT CHARLIE
Current Phase
Construction Procurement
Completion Date
2024-02-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-01-04T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DCAS • Pid: 3360
Reporting Period
202401
Managing Agency
DCAS
Pid
3360
Agency Project Name
NYPD - HARBOR UNIT CHARLIE
Current Phase
Construction Procurement
Completion Date
2024-12-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
305
Data Date
2024-05-02T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DCAS • Pid: 3360
Reporting Period
202405
Managing Agency
DCAS
Pid
3360
Agency Project Name
NYPD - HARBOR UNIT CHARLIE
Current Phase
Construction Procurement
Completion Date
2024-12-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-11T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DCAS • Pid: 3360
Reporting Period
202409
Managing Agency
DCAS
Pid
3360
Agency Project Name
NYPD - HARBOR UNIT CHARLIE
Current Phase
Construction
Completion Date
2024-12-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-01T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DCAS • Pid: 3360
Reporting Period
202501
Managing Agency
DCAS
Pid
3360
Agency Project Name
NYPD - HARBOR UNIT CHARLIE
Current Phase
Construction
Completion Date
2024-12-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-03-04T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DCAS • Pid: 3360
Reporting Period
202505
Managing Agency
DCAS
Pid
3360
Agency Project Name
NYPD - HARBOR UNIT CHARLIE
Current Phase
Construction
Completion Date
2025-06-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
182
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNAVAILABILITY OF PRODUCT
Data Date
2025-06-18T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DCAS • Pid: 3360
Reporting Period
202509
Managing Agency
DCAS
Pid
3360
Agency Project Name
NYPD - HARBOR UNIT CHARLIE
Current Phase
Close-out
Completion Date
2025-06-23T00:00:00.000
Completion Date Type
Actual
Variance Day
-7
Data Date
2025-11-17T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DCAS • Pid: 3361
Reporting Period
202305
Managing Agency
DCAS
Pid
3361
Agency Project Name
NYPD - 44TH PRECINCT
Current Phase
Construction Procurement
Completion Date
2024-03-11T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-06-28T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DCAS • Pid: 3361
Reporting Period
202309
Managing Agency
DCAS
Pid
3361
Agency Project Name
NYPD - 44TH PRECINCT
Current Phase
Construction Procurement
Completion Date
2024-03-11T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-01-04T00:00:00.000