Capital Projects Dashboard - Citywide Schedule History and Variance

This is the history all agency reported forecasts/actual project completion dates. Each row is the snapshot of data taken on each reporting period. The 'completion date type' column shows if the 'completion date' is either a forecast or actual date. Over time, a project would have one or more forecasted completion dates before it is actually completed. The 'variance' is the day difference between 'completion date' of each row and its prior reporting period. This dataset is part of the Capital Projects Dashboard.

City Government Mayor's Office of Operations (OPS) Dataset 95tx-snak 10 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4262
Reporting Period
202401
Managing Agency
DDC
Pid
4262
Agency Project Name
Court Square BLDG: 2 Lafayette St. Renovation Faca
Current Phase
Design
Completion Date
2028-07-17T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4262
Reporting Period
202405
Managing Agency
DDC
Pid
4262
Agency Project Name
Court Square BLDG: 2 Lafayette St. Renovation Faca
Current Phase
Design
Completion Date
2027-04-21T00:00:00.000
Completion Date Type
Forecast
Variance Day
-453
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4262
Reporting Period
202409
Managing Agency
DDC
Pid
4262
Agency Project Name
Court Square BLDG: 2 Lafayette St. Renovation Faca
Current Phase
Design
Completion Date
2027-06-24T00:00:00.000
Completion Date Type
Forecast
Variance Day
64
Reason For Forecast Completion Change
PROJECT DELAYED PENDING APPROVAL OF NECESSARY PERMITS
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4262
Reporting Period
202501
Managing Agency
DDC
Pid
4262
Agency Project Name
Court Square BLDG: 2 Lafayette St. Renovation Faca
Current Phase
Design
Completion Date
2027-06-24T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4262
Reporting Period
202505
Managing Agency
DDC
Pid
4262
Agency Project Name
Court Square BLDG: 2 Lafayette St. Renovation Faca
Current Phase
Design
Completion Date
2029-05-11T00:00:00.000
Completion Date Type
Forecast
Variance Day
687
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4262
Reporting Period
202509
Managing Agency
DDC
Pid
4262
Agency Project Name
Court Square BLDG: 2 Lafayette St. Renovation Faca
Current Phase
Design
Completion Date
2029-06-24T00:00:00.000
Completion Date Type
Forecast
Variance Day
44
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4262
Reporting Period
202601
Managing Agency
DDC
Pid
4262
Agency Project Name
Court Square BLDG: 2 Lafayette St. Renovation Faca
Current Phase
Design
Completion Date
2029-12-09T00:00:00.000
Completion Date Type
Forecast
Variance Day
168
Reason For Forecast Completion Change
PROJECT DELAYED PENDING APPROVAL OF NECESSARY PERMITS
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4262
Reporting Period
202605
Managing Agency
DDC
Pid
4262
Agency Project Name
Court Square BLDG: 2 Lafayette St. Renovation Faca
Current Phase
Design
Completion Date
2030-02-11T00:00:00.000
Completion Date Type
Forecast
Variance Day
64
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4263
Reporting Period
202305
Managing Agency
DDC
Pid
4263
Agency Project Name
CSV - Clemente Soto Velez - Interior Code Complian
Current Phase
Construction Procurement
Completion Date
2025-04-30T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4263
Reporting Period
202309
Managing Agency
DDC
Pid
4263
Agency Project Name
CSV - Clemente Soto Velez - Interior Code Complian
Current Phase
Construction Procurement
Completion Date
2025-06-09T00:00:00.000
Completion Date Type
Forecast
Variance Day
40
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4263
Reporting Period
202401
Managing Agency
DDC
Pid
4263
Agency Project Name
CSV - Clemente Soto Velez - Interior Code Complian
Current Phase
Construction Procurement
Completion Date
2025-06-09T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4263
Reporting Period
202405
Managing Agency
DDC
Pid
4263
Agency Project Name
CSV - Clemente Soto Velez - Interior Code Complian
Current Phase
Construction
Completion Date
2025-06-09T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4263
Reporting Period
202409
Managing Agency
DDC
Pid
4263
Agency Project Name
CSV - Clemente Soto Velez - Interior Code Complian
Current Phase
Construction
Completion Date
2025-11-16T00:00:00.000
Completion Date Type
Forecast
Variance Day
160
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4263
Reporting Period
202501
Managing Agency
DDC
Pid
4263
Agency Project Name
CSV - Clemente Soto Velez - Interior Code Complian
Current Phase
Construction
Completion Date
2026-01-26T00:00:00.000
Completion Date Type
Forecast
Variance Day
71
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4263
Reporting Period
202505
Managing Agency
DDC
Pid
4263
Agency Project Name
CSV - Clemente Soto Velez - Interior Code Complian
Current Phase
Construction
Completion Date
2026-01-26T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4263
Reporting Period
202509
Managing Agency
DDC
Pid
4263
Agency Project Name
CSV - Clemente Soto Velez - Interior Code Complian
Current Phase
Construction
Completion Date
2026-01-26T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4263
Reporting Period
202601
Managing Agency
DDC
Pid
4263
Agency Project Name
CSV - Clemente Soto Velez - Interior Code Complian
Current Phase
Construction
Completion Date
2026-07-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
165
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4263
Reporting Period
202605
Managing Agency
DDC
Pid
4263
Agency Project Name
CSV - Clemente Soto Velez - Interior Code Complian
Current Phase
Construction
Completion Date
2026-09-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
62
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4264
Reporting Period
202305
Managing Agency
DDC
Pid
4264
Agency Project Name
REPAIRS & REHAB OF INTERCEPTING SEWERS, MN & BX
Current Phase
Construction
Completion Date
2025-06-10T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4264
Reporting Period
202309
Managing Agency
DDC
Pid
4264
Agency Project Name
REPAIRS & REHAB OF INTERCEPTING SEWERS, MN & BX
Current Phase
Construction
Completion Date
2025-06-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4264
Reporting Period
202401
Managing Agency
DDC
Pid
4264
Agency Project Name
REPAIRS & REHAB OF INTERCEPTING SEWERS, MN & BX
Current Phase
Construction
Completion Date
2025-06-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4264
Reporting Period
202405
Managing Agency
DDC
Pid
4264
Agency Project Name
REPAIRS & REHAB OF INTERCEPTING SEWERS, MN & BX
Current Phase
Construction
Completion Date
2025-06-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4264
Reporting Period
202409
Managing Agency
DDC
Pid
4264
Agency Project Name
REPAIRS & REHAB OF INTERCEPTING SEWERS, MN & BX
Current Phase
Construction
Completion Date
2025-09-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
112
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4264
Reporting Period
202501
Managing Agency
DDC
Pid
4264
Agency Project Name
REPAIRS & REHAB OF INTERCEPTING SEWERS, MN & BX
Current Phase
Construction
Completion Date
2025-09-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4264
Reporting Period
202505
Managing Agency
DDC
Pid
4264
Agency Project Name
REPAIRS & REHAB OF INTERCEPTING SEWERS, MN & BX
Current Phase
Construction
Completion Date
2025-09-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4264
Reporting Period
202509
Managing Agency
DDC
Pid
4264
Agency Project Name
REPAIRS & REHAB OF INTERCEPTING SEWERS, MN & BX
Current Phase
Construction
Completion Date
2025-11-16T00:00:00.000
Completion Date Type
Forecast
Variance Day
47
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4264
Reporting Period
202601
Managing Agency
DDC
Pid
4264
Agency Project Name
REPAIRS & REHAB OF INTERCEPTING SEWERS, MN & BX
Current Phase
Construction
Completion Date
2026-03-16T00:00:00.000
Completion Date Type
Forecast
Variance Day
120
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4264
Reporting Period
202605
Managing Agency
DDC
Pid
4264
Agency Project Name
REPAIRS & REHAB OF INTERCEPTING SEWERS, MN & BX
Current Phase
Construction
Completion Date
2026-03-16T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4265
Reporting Period
202305
Managing Agency
DDC
Pid
4265
Agency Project Name
TLC - NEW OFFICE FACILITY - 24-55 BQE WEST
Current Phase
Construction
Completion Date
2026-05-01T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4265
Reporting Period
202309
Managing Agency
DDC
Pid
4265
Agency Project Name
TLC - NEW OFFICE FACILITY - 24-55 BQE WEST
Current Phase
Construction
Completion Date
2026-05-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4265
Reporting Period
202401
Managing Agency
DDC
Pid
4265
Agency Project Name
TLC - NEW OFFICE FACILITY - 24-55 BQE WEST
Current Phase
Construction
Completion Date
2026-05-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4265
Reporting Period
202405
Managing Agency
DDC
Pid
4265
Agency Project Name
TLC - NEW OFFICE FACILITY - 24-55 BQE WEST
Current Phase
Construction
Completion Date
2026-05-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4265
Reporting Period
202409
Managing Agency
DDC
Pid
4265
Agency Project Name
TLC - NEW OFFICE FACILITY - 24-55 BQE WEST
Current Phase
Construction
Completion Date
2026-05-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4265
Reporting Period
202501
Managing Agency
DDC
Pid
4265
Agency Project Name
TLC - NEW OFFICE FACILITY - 24-55 BQE WEST
Current Phase
Construction
Completion Date
2026-05-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4265
Reporting Period
202505
Managing Agency
DDC
Pid
4265
Agency Project Name
TLC - NEW OFFICE FACILITY - 24-55 BQE WEST
Current Phase
Construction
Completion Date
2026-05-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4265
Reporting Period
202509
Managing Agency
DDC
Pid
4265
Agency Project Name
TLC - NEW OFFICE FACILITY - 24-55 BQE WEST
Current Phase
Construction
Completion Date
2027-05-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
365
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4265
Reporting Period
202601
Managing Agency
DDC
Pid
4265
Agency Project Name
TLC - NEW OFFICE FACILITY - 24-55 BQE WEST
Current Phase
Construction
Completion Date
2027-05-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4265
Reporting Period
202605
Managing Agency
DDC
Pid
4265
Agency Project Name
TLC - NEW OFFICE FACILITY - 24-55 BQE WEST
Current Phase
Construction
Completion Date
2027-07-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
61
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4266
Reporting Period
202305
Managing Agency
DDC
Pid
4266
Agency Project Name
Muhlenberg Elevator Upgrade
Current Phase
Construction
Completion Date
2024-02-14T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4266
Reporting Period
202309
Managing Agency
DDC
Pid
4266
Agency Project Name
Muhlenberg Elevator Upgrade
Current Phase
Construction
Completion Date
2024-03-06T00:00:00.000
Completion Date Type
Forecast
Variance Day
21
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4266
Reporting Period
202401
Managing Agency
DDC
Pid
4266
Agency Project Name
Muhlenberg Elevator Upgrade
Current Phase
Construction
Completion Date
2024-03-06T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4266
Reporting Period
202405
Managing Agency
DDC
Pid
4266
Agency Project Name
Muhlenberg Elevator Upgrade
Current Phase
Construction
Completion Date
2024-05-01T00:00:00.000
Completion Date Type
Actual
Variance Day
56
Data Date
2024-07-18T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4267
Reporting Period
202305
Managing Agency
DDC
Pid
4267
Agency Project Name
1400 Williamsbridge Rd, BX.HVAC Replacement
Current Phase
Construction
Completion Date
2024-08-19T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4267
Reporting Period
202309
Managing Agency
DDC
Pid
4267
Agency Project Name
1400 Williamsbridge Rd, BX.HVAC Replacement
Current Phase
Construction
Completion Date
2024-08-19T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4267
Reporting Period
202401
Managing Agency
DDC
Pid
4267
Agency Project Name
1400 Williamsbridge Rd, BX.HVAC Replacement
Current Phase
Construction
Completion Date
2024-08-19T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4267
Reporting Period
202405
Managing Agency
DDC
Pid
4267
Agency Project Name
1400 Williamsbridge Rd, BX.HVAC Replacement
Current Phase
Construction
Completion Date
2024-08-19T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4267
Reporting Period
202409
Managing Agency
DDC
Pid
4267
Agency Project Name
1400 Williamsbridge Rd, BX.HVAC Replacement
Current Phase
Construction
Completion Date
2024-11-22T00:00:00.000
Completion Date Type
Forecast
Variance Day
95
Reason For Forecast Completion Change
PROJECT DELAYED PENDING APPROVAL OF NECESSARY PERMITS
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4267
Reporting Period
202501
Managing Agency
DDC
Pid
4267
Agency Project Name
1400 Williamsbridge Rd, BX.HVAC Replacement
Current Phase
Construction
Completion Date
2025-05-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
174
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4267
Reporting Period
202505
Managing Agency
DDC
Pid
4267
Agency Project Name
1400 Williamsbridge Rd, BX.HVAC Replacement
Current Phase
Construction
Completion Date
2025-09-12T00:00:00.000
Completion Date Type
Forecast
Variance Day
120
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4267
Reporting Period
202509
Managing Agency
DDC
Pid
4267
Agency Project Name
1400 Williamsbridge Rd, BX.HVAC Replacement
Current Phase
Construction
Completion Date
2025-12-31T00:00:00.000
Completion Date Type
Forecast
Variance Day
110
Data Date
2025-10-23T00:00:00.000