Capital Projects Dashboard - Citywide Schedule History and Variance

This is the history all agency reported forecasts/actual project completion dates. Each row is the snapshot of data taken on each reporting period. The 'completion date type' column shows if the 'completion date' is either a forecast or actual date. Over time, a project would have one or more forecasted completion dates before it is actually completed. The 'variance' is the day difference between 'completion date' of each row and its prior reporting period. This dataset is part of the Capital Projects Dashboard.

City Government Mayor's Office of Operations (OPS) Dataset 95tx-snak 10 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
202305
Reporting Period: 202305 • Managing Agency: CUNY • Pid: 72
Reporting Period
202305
Managing Agency
CUNY
Pid
72
Agency Project Name
BKLYNC-Performing Arts Center
Current Phase
Close-out
Completion Date
2018-07-03T00:00:00.000
Completion Date Type
Actual
Data Date
2023-04-26T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Pid: 73
Reporting Period
202305
Managing Agency
CUNY
Pid
73
Agency Project Name
BARUCH-17 Lexington Avenue
Current Phase
Close-out
Completion Date
2016-06-01T00:00:00.000
Completion Date Type
Actual
Data Date
2023-04-26T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Pid: 74
Reporting Period
202305
Managing Agency
CUNY
Pid
74
Agency Project Name
HTSCC-ADA Work
Current Phase
Close-out
Completion Date
2010-12-20T00:00:00.000
Completion Date Type
Actual
Data Date
2023-04-26T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Pid: 75
Reporting Period
202305
Managing Agency
CUNY
Pid
75
Agency Project Name
HTSCC-HVAC Work
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2023-04-26T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: CUNY • Pid: 75
Reporting Period
202309
Managing Agency
CUNY
Pid
75
Agency Project Name
HTSCC-HVAC Work
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2024-02-02T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: CUNY • Pid: 75
Reporting Period
202401
Managing Agency
CUNY
Pid
75
Agency Project Name
HTSCC-HVAC Work
Current Phase
Design
Completion Date
2025-05-12T00:00:00.000
Completion Date Type
Forecast
Data Date
2024-05-03T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: CUNY • Pid: 75
Reporting Period
202405
Managing Agency
CUNY
Pid
75
Agency Project Name
HTSCC-HVAC Work
Current Phase
Design
Completion Date
2025-05-12T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-05-03T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: CUNY • Pid: 75
Reporting Period
202409
Managing Agency
CUNY
Pid
75
Agency Project Name
HTSCC-HVAC Work
Current Phase
Construction
Completion Date
2025-05-12T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-15T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: CUNY • Pid: 75
Reporting Period
202501
Managing Agency
CUNY
Pid
75
Agency Project Name
HTSCC-HVAC Work
Current Phase
Construction
Completion Date
2025-05-12T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-03-20T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: CUNY • Pid: 75
Reporting Period
202505
Managing Agency
CUNY
Pid
75
Agency Project Name
HTSCC-HVAC Work
Current Phase
Close-out
Completion Date
2024-06-06T00:00:00.000
Completion Date Type
Actual
Variance Day
-340
Data Date
2025-06-25T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Pid: 76
Reporting Period
202305
Managing Agency
CUNY
Pid
76
Agency Project Name
BKLYNC-ADA Upgrade
Completion Date
2020-06-01T00:00:00.000
Completion Date Type
Actual
Data Date
2023-04-26T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Pid: 77
Reporting Period
202305
Managing Agency
CUNY
Pid
77
Agency Project Name
Central Office - Data Center
Current Phase
Construction
Completion Date
2023-06-01T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-04-26T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: CUNY • Pid: 77
Reporting Period
202309
Managing Agency
CUNY
Pid
77
Agency Project Name
Central Office - Data Center
Current Phase
Construction
Completion Date
2024-09-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
487
Data Date
2024-02-02T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: CUNY • Pid: 77
Reporting Period
202401
Managing Agency
CUNY
Pid
77
Agency Project Name
Central Office - Data Center
Current Phase
Construction
Completion Date
2024-10-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
30
Data Date
2024-05-03T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: CUNY • Pid: 77
Reporting Period
202405
Managing Agency
CUNY
Pid
77
Agency Project Name
Central Office - Data Center
Current Phase
Construction
Completion Date
2024-10-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-05-03T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: CUNY • Pid: 77
Reporting Period
202409
Managing Agency
CUNY
Pid
77
Agency Project Name
Central Office - Data Center
Current Phase
Close-out
Completion Date
2024-10-10T00:00:00.000
Completion Date Type
Actual
Variance Day
-20
Data Date
2024-11-15T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Pid: 78
Reporting Period
202305
Managing Agency
CUNY
Pid
78
Agency Project Name
BMCC - Upgrades to Theatres
Current Phase
Design
Completion Date
2024-12-01T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-04-26T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: CUNY • Pid: 78
Reporting Period
202309
Managing Agency
CUNY
Pid
78
Agency Project Name
BMCC - Upgrades to Theatres
Current Phase
Design
Completion Date
2024-12-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-02T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: CUNY • Pid: 78
Reporting Period
202401
Managing Agency
CUNY
Pid
78
Agency Project Name
BMCC - Upgrades to Theatres
Current Phase
Design
Completion Date
2025-07-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
212
Data Date
2024-05-03T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: CUNY • Pid: 78
Reporting Period
202405
Managing Agency
CUNY
Pid
78
Agency Project Name
BMCC - Upgrades to Theatres
Current Phase
Design
Completion Date
2025-07-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-05-03T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: CUNY • Pid: 78
Reporting Period
202409
Managing Agency
CUNY
Pid
78
Agency Project Name
BMCC - Upgrades to Theatres
Current Phase
Design
Completion Date
2027-07-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
730
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO BUDGETARY CONSTRAINTS
Data Date
2024-11-15T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: CUNY • Pid: 78
Reporting Period
202501
Managing Agency
CUNY
Pid
78
Agency Project Name
BMCC - Upgrades to Theatres
Current Phase
Design
Completion Date
2027-07-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-03-20T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: CUNY • Pid: 78
Reporting Period
202505
Managing Agency
CUNY
Pid
78
Agency Project Name
BMCC - Upgrades to Theatres
Current Phase
Design
Completion Date
2027-07-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-06-25T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: CUNY • Pid: 78
Reporting Period
202509
Managing Agency
CUNY
Pid
78
Agency Project Name
BMCC - Upgrades to Theatres
Current Phase
Design
Completion Date
2027-07-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-11-17T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: CUNY • Pid: 78
Reporting Period
202601
Managing Agency
CUNY
Pid
78
Agency Project Name
BMCC - Upgrades to Theatres
Current Phase
Design
Completion Date
2027-07-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-04-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: CUNY • Pid: 78
Reporting Period
202605
Managing Agency
CUNY
Pid
78
Agency Project Name
BMCC - Upgrades to Theatres
Current Phase
Design
Completion Date
2027-07-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-05-28T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Pid: 79
Reporting Period
202305
Managing Agency
CUNY
Pid
79
Agency Project Name
HTSCC 450 GC FA Upgrade
Current Phase
Construction
Completion Date
2023-10-31T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-04-26T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: CUNY • Pid: 79
Reporting Period
202309
Managing Agency
CUNY
Pid
79
Agency Project Name
HTSCC 450 GC FA Upgrade
Current Phase
Construction
Completion Date
2023-12-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
59
Data Date
2024-02-02T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: CUNY • Pid: 79
Reporting Period
202401
Managing Agency
CUNY
Pid
79
Agency Project Name
HTSCC 450 GC FA Upgrade
Current Phase
Construction
Completion Date
2026-04-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
824
Data Date
2024-05-03T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: CUNY • Pid: 79
Reporting Period
202405
Managing Agency
CUNY
Pid
79
Agency Project Name
HTSCC 450 GC FA Upgrade
Current Phase
Construction
Completion Date
2026-04-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-05-03T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: CUNY • Pid: 79
Reporting Period
202409
Managing Agency
CUNY
Pid
79
Agency Project Name
HTSCC 450 GC FA Upgrade
Current Phase
Construction
Completion Date
2026-04-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-15T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: CUNY • Pid: 79
Reporting Period
202501
Managing Agency
CUNY
Pid
79
Agency Project Name
HTSCC 450 GC FA Upgrade
Current Phase
Construction
Completion Date
2026-04-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-03-20T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: CUNY • Pid: 79
Reporting Period
202505
Managing Agency
CUNY
Pid
79
Agency Project Name
HTSCC 450 GC FA Upgrade
Current Phase
Construction
Completion Date
2026-04-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-06-25T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: CUNY • Pid: 79
Reporting Period
202509
Managing Agency
CUNY
Pid
79
Agency Project Name
HTSCC 450 GC FA Upgrade
Current Phase
Construction
Completion Date
2025-01-31T00:00:00.000
Completion Date Type
Actual
Variance Day
-425
Data Date
2025-11-17T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Pid: 80
Reporting Period
202305
Managing Agency
CUNY
Pid
80
Agency Project Name
BRXCC - Campus Wide Fire Alarm
Current Phase
Construction
Completion Date
2024-06-01T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-04-26T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: CUNY • Pid: 80
Reporting Period
202309
Managing Agency
CUNY
Pid
80
Agency Project Name
BRXCC - Campus Wide Fire Alarm
Current Phase
Construction
Completion Date
2024-12-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
212
Data Date
2024-02-02T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: CUNY • Pid: 80
Reporting Period
202401
Managing Agency
CUNY
Pid
80
Agency Project Name
BRXCC - Campus Wide Fire Alarm
Current Phase
Construction
Completion Date
2024-12-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-05-03T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: CUNY • Pid: 80
Reporting Period
202405
Managing Agency
CUNY
Pid
80
Agency Project Name
BRXCC - Campus Wide Fire Alarm
Current Phase
Construction
Completion Date
2024-12-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-05-03T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: CUNY • Pid: 80
Reporting Period
202409
Managing Agency
CUNY
Pid
80
Agency Project Name
BRXCC - Campus Wide Fire Alarm
Current Phase
Construction
Completion Date
2024-12-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-15T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: CUNY • Pid: 80
Reporting Period
202501
Managing Agency
CUNY
Pid
80
Agency Project Name
BRXCC - Campus Wide Fire Alarm
Current Phase
Construction
Completion Date
2025-12-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
365
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION
Data Date
2025-03-20T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: CUNY • Pid: 80
Reporting Period
202505
Managing Agency
CUNY
Pid
80
Agency Project Name
BRXCC - Campus Wide Fire Alarm
Current Phase
Construction
Completion Date
2025-12-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-06-25T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: CUNY • Pid: 80
Reporting Period
202509
Managing Agency
CUNY
Pid
80
Agency Project Name
BRXCC - Campus Wide Fire Alarm
Current Phase
Construction
Completion Date
2026-07-24T00:00:00.000
Completion Date Type
Actual
Variance Day
206
Data Date
2025-11-17T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Pid: 82
Reporting Period
202305
Managing Agency
CUNY
Pid
82
Agency Project Name
CUNY School of Law 2 Court
Current Phase
Close-out
Completion Date
2022-11-30T00:00:00.000
Completion Date Type
Actual
Data Date
2023-04-26T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Pid: 83
Reporting Period
202305
Managing Agency
CUNY
Pid
83
Agency Project Name
LGCC - Schenker M Bldg
Current Phase
Design
Completion Date Type
Forecast
Data Date
2023-04-26T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: CUNY • Pid: 83
Reporting Period
202309
Managing Agency
CUNY
Pid
83
Agency Project Name
LGCC - Schenker M Bldg
Current Phase
Design
Completion Date Type
Forecast
Data Date
2024-02-02T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: CUNY • Pid: 83
Reporting Period
202401
Managing Agency
CUNY
Pid
83
Agency Project Name
LGCC - Schenker M Bldg
Current Phase
Design
Completion Date
2025-12-12T00:00:00.000
Completion Date Type
Forecast
Data Date
2024-05-03T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: CUNY • Pid: 83
Reporting Period
202405
Managing Agency
CUNY
Pid
83
Agency Project Name
LGCC - Schenker M Bldg
Current Phase
Design
Completion Date
2025-12-12T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-05-03T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: CUNY • Pid: 83
Reporting Period
202409
Managing Agency
CUNY
Pid
83
Agency Project Name
LGCC - Schenker M Bldg
Current Phase
Construction
Completion Date
2025-12-12T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-15T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: CUNY • Pid: 83
Reporting Period
202501
Managing Agency
CUNY
Pid
83
Agency Project Name
LGCC - Schenker M Bldg
Current Phase
Construction
Completion Date
2025-12-12T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-03-20T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: CUNY • Pid: 83
Reporting Period
202505
Managing Agency
CUNY
Pid
83
Agency Project Name
LGCC - Schenker M Bldg
Current Phase
Construction
Completion Date
2026-01-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
20
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO BUDGETARY CONSTRAINTS
Data Date
2025-06-25T00:00:00.000