This data is a spatial representation of street construction projects. Street and Highway capital projects are major street reconstruction projects, ranging from general street resurfacing projects to full reconstruction of the roadbed, sidewalks, sewer and water pipes and other utilities. Capital projects are essential to keep the City's infrastructure in a state of good repair.

Transportation Department of Transportation (DOT) Dataset 97nd-ff3i 30 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
1280
Projectid: 1280 • Projtitle: Reconstruction of 99th Avenue and 110th Avenue • Fmsid: HWQ1161
The Geom
{"type":"MultiPoint","coordinates":[[-73.76498520645238,40.71103921128313],[-73.76513207166981,40.71094091373925]]}
Projectid
1280
Projtitle
Reconstruction of 99th Avenue and 110th Avenue
Fmsid
HWQ1161
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
Total reconstruction of sections of 110 Avenue, 173 Street, 104 Avenue, 189 Street, 99 Avenue etc.. These streets will be reconstructed following installation a 48 inch Trunk Water Main. Liberty Avenue in this area will be restored with concrete base whe
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2006
Currentfun
11826044.0
Projectcos
11826044.0
Overallsco
General Roadway,Sidewalk (Standalone)
Onstreetna
195 STREET
Fromstreet
SAGAMORE AVENUE
Boroughnam
QUEENS
Oftcode
425690461185000000
Designfy
2002
Latitude
40.7109900625112
Longitude
-73.7650586390611
X
1049383.91794831
Y
198396.695119895
VIEW LOCATION
1280
Projectid: 1280 • Projtitle: Reconstruction of 99th Avenue and 110th Avenue • Fmsid: HWQ1161
The Geom
{"type":"MultiPoint","coordinates":[[-73.76881217338108,40.709808122574046]]}
Projectid
1280
Projtitle
Reconstruction of 99th Avenue and 110th Avenue
Fmsid
HWQ1161
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
Total reconstruction of sections of 110 Avenue, 173 Street, 104 Avenue, 189 Street, 99 Avenue etc.. These streets will be reconstructed following installation a 48 inch Trunk Water Main. Liberty Avenue in this area will be restored with concrete base whe
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2006
Currentfun
11826044.0
Projectcos
11826044.0
Overallsco
General Roadway,Sidewalk (Standalone)
Onstreetna
190 STREET
Fromstreet
HOLLIS AVENUE
Boroughnam
QUEENS
Oftcode
425340449990000000
Designfy
2002
Latitude
40.7098081234745
Longitude
-73.768812173378
X
1048344.44660206
Y
197963.311472222
VIEW LOCATION
1280
Projectid: 1280 • Projtitle: Reconstruction of 99th Avenue and 110th Avenue • Fmsid: HWQ1161
The Geom
{"type":"MultiPoint","coordinates":[[-73.76750704312609,40.70372448191735]]}
Projectid
1280
Projtitle
Reconstruction of 99th Avenue and 110th Avenue
Fmsid
HWQ1161
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
Total reconstruction of sections of 110 Avenue, 173 Street, 104 Avenue, 189 Street, 99 Avenue etc.. These streets will be reconstructed following installation a 48 inch Trunk Water Main. Liberty Avenue in this area will be restored with concrete base whe
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2006
Currentfun
11826044.0
Projectcos
11826044.0
Overallsco
General Roadway,Sidewalk (Standalone)
Onstreetna
189 STREET
Fromstreet
BRINKERHOFF AVENUE
Boroughnam
QUEENS
Oftcode
425270436990000000
Designfy
2002
Latitude
40.7037244819173
Longitude
-73.7675070431261
X
1048712.16240205
Y
195747.823777229
VIEW LOCATION
1280
Projectid: 1280 • Projtitle: Reconstruction of 99th Avenue and 110th Avenue • Fmsid: HWQ1161
The Geom
{"type":"MultiPoint","coordinates":[[-73.78034491117442,40.70541241634212]]}
Projectid
1280
Projtitle
Reconstruction of 99th Avenue and 110th Avenue
Fmsid
HWQ1161
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
Total reconstruction of sections of 110 Avenue, 173 Street, 104 Avenue, 189 Street, 99 Avenue etc.. These streets will be reconstructed following installation a 48 inch Trunk Water Main. Liberty Avenue in this area will be restored with concrete base whe
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2006
Currentfun
11826044.0
Projectcos
11826044.0
Overallsco
General Roadway,Sidewalk (Standalone)
Onstreetna
180 STREET
Fromstreet
LIBERTY AVENUE
Boroughnam
QUEENS
Oftcode
425050453790000000
Designfy
2002
Latitude
40.7054124163421
Longitude
-73.7803449111744
X
1045151.13638763
Y
196353.600452811
VIEW LOCATION
1280
Projectid: 1280 • Projtitle: Reconstruction of 99th Avenue and 110th Avenue • Fmsid: HWQ1161
The Geom
{"type":"MultiPoint","coordinates":[[-73.76537468823511,40.711490983177775]]}
Projectid
1280
Projtitle
Reconstruction of 99th Avenue and 110th Avenue
Fmsid
HWQ1161
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
Total reconstruction of sections of 110 Avenue, 173 Street, 104 Avenue, 189 Street, 99 Avenue etc.. These streets will be reconstructed following installation a 48 inch Trunk Water Main. Liberty Avenue in this area will be restored with concrete base whe
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2006
Currentfun
11826044.0
Projectcos
11826044.0
Overallsco
General Roadway,Sidewalk (Standalone)
Onstreetna
195 STREET
Fromstreet
WOODHULL AVENUE
Boroughnam
QUEENS
Oftcode
425690468190000000
Designfy
2002
Latitude
40.7114909831777
Longitude
-73.7653746882351
X
1049295.80952872
Y
198578.960175306
VIEW LOCATION
1280
Projectid: 1280 • Projtitle: Reconstruction of 99th Avenue and 110th Avenue • Fmsid: HWQ1161
The Geom
{"type":"MultiPoint","coordinates":[[-73.7848487631648,40.704585570715615]]}
Projectid
1280
Projtitle
Reconstruction of 99th Avenue and 110th Avenue
Fmsid
HWQ1161
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
Total reconstruction of sections of 110 Avenue, 173 Street, 104 Avenue, 189 Street, 99 Avenue etc.. These streets will be reconstructed following installation a 48 inch Trunk Water Main. Liberty Avenue in this area will be restored with concrete base whe
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2006
Currentfun
11826044.0
Projectcos
11826044.0
Overallsco
General Roadway,Sidewalk (Standalone)
Onstreetna
173 STREET
Fromstreet
LIBERTY AVENUE
Boroughnam
QUEENS
Oftcode
424790453790000000
Designfy
2002
Latitude
40.7045855707156
Longitude
-73.7848487631648
X
1043903.14971039
Y
196049.257557556
VIEW LOCATION
1280
Projectid: 1280 • Projtitle: Reconstruction of 99th Avenue and 110th Avenue • Fmsid: HWQ1161
The Geom
{"type":"MultiPoint","coordinates":[[-73.77582076077265,40.7053739050828]]}
Projectid
1280
Projtitle
Reconstruction of 99th Avenue and 110th Avenue
Fmsid
HWQ1161
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
Total reconstruction of sections of 110 Avenue, 173 Street, 104 Avenue, 189 Street, 99 Avenue etc.. These streets will be reconstructed following installation a 48 inch Trunk Water Main. Liberty Avenue in this area will be restored with concrete base whe
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2006
Currentfun
11826044.0
Projectcos
11826044.0
Overallsco
General Roadway,Sidewalk (Standalone)
Onstreetna
183 STREET
Fromstreet
LIBERTY AVENUE
Boroughnam
QUEENS
Oftcode
425140453790000000
Designfy
2002
Latitude
40.7053739050827
Longitude
-73.7758207607726
X
1046405.52659538
Y
196342.747456148
VIEW LOCATION
1280
Projectid: 1280 • Projtitle: Reconstruction of 99th Avenue and 110th Avenue • Fmsid: HWQ1161
The Geom
{"type":"MultiPoint","coordinates":[[-73.76780765965322,40.703574298420904]]}
Projectid
1280
Projtitle
Reconstruction of 99th Avenue and 110th Avenue
Fmsid
HWQ1161
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
Total reconstruction of sections of 110 Avenue, 173 Street, 104 Avenue, 189 Street, 99 Avenue etc.. These streets will be reconstructed following installation a 48 inch Trunk Water Main. Liberty Avenue in this area will be restored with concrete base whe
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2006
Currentfun
11826044.0
Projectcos
11826044.0
Overallsco
General Roadway,Sidewalk (Standalone)
Onstreetna
BRINKERHOFF AVENUE
Fromstreet
LIBERTY AVENUE
Boroughnam
QUEENS
Oftcode
436990453790000000
Designfy
2002
Latitude
40.7035742984209
Longitude
-73.7678076596532
X
1048628.95718789
Y
195692.886551142
VIEW LOCATION
1280
Projectid: 1280 • Projtitle: Reconstruction of 99th Avenue and 110th Avenue • Fmsid: HWQ1161
The Geom
{"type":"MultiPoint","coordinates":[[-73.77981828017346,40.704927897020525]]}
Projectid
1280
Projtitle
Reconstruction of 99th Avenue and 110th Avenue
Fmsid
HWQ1161
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
Total reconstruction of sections of 110 Avenue, 173 Street, 104 Avenue, 189 Street, 99 Avenue etc.. These streets will be reconstructed following installation a 48 inch Trunk Water Main. Liberty Avenue in this area will be restored with concrete base whe
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2006
Currentfun
11826044.0
Projectcos
11826044.0
Overallsco
General Roadway,Sidewalk (Standalone)
Onstreetna
104 AVENUE
Fromstreet
180 STREET
Boroughnam
QUEENS
Oftcode
419720425050000000
Designfy
2002
Latitude
40.7049278970205
Longitude
-73.7798182801735
X
1045297.59245956
Y
196177.442668647
VIEW LOCATION
1280
Projectid: 1280 • Projtitle: Reconstruction of 99th Avenue and 110th Avenue • Fmsid: HWQ1161
The Geom
{"type":"MultiPoint","coordinates":[[-73.76789085836221,40.70840640216892]]}
Projectid
1280
Projtitle
Reconstruction of 99th Avenue and 110th Avenue
Fmsid
HWQ1161
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
Total reconstruction of sections of 110 Avenue, 173 Street, 104 Avenue, 189 Street, 99 Avenue etc.. These streets will be reconstructed following installation a 48 inch Trunk Water Main. Liberty Avenue in this area will be restored with concrete base whe
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2006
Currentfun
11826044.0
Projectcos
11826044.0
Overallsco
General Roadway,Sidewalk (Standalone)
Onstreetna
FARMERS BOULEVARD
Fromstreet
HENDERSON AVENUE
Boroughnam
QUEENS
Oftcode
444690449210000000
Designfy
2002
Latitude
40.7084064021689
Longitude
-73.7678908583622
X
1048601.22430372
Y
197453.299696982
VIEW LOCATION
1280
Projectid: 1280 • Projtitle: Reconstruction of 99th Avenue and 110th Avenue • Fmsid: HWQ1161
The Geom
{"type":"MultiPoint","coordinates":[[-73.78105798100744,40.698800837402615]]}
Projectid
1280
Projtitle
Reconstruction of 99th Avenue and 110th Avenue
Fmsid
HWQ1161
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
Total reconstruction of sections of 110 Avenue, 173 Street, 104 Avenue, 189 Street, 99 Avenue etc.. These streets will be reconstructed following installation a 48 inch Trunk Water Main. Liberty Avenue in this area will be restored with concrete base whe
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2006
Currentfun
11826044.0
Projectcos
11826044.0
Overallsco
General Roadway,Sidewalk (Standalone)
Onstreetna
109 AVENUE
Fromstreet
174 STREET
Boroughnam
QUEENS
Oftcode
420240424810000000
Designfy
2002
Latitude
40.6988008374026
Longitude
-73.7810579810074
X
1044959.45304397
Y
193944.317541733
VIEW LOCATION
1280
Projectid: 1280 • Projtitle: Reconstruction of 99th Avenue and 110th Avenue • Fmsid: HWQ1161
The Geom
{"type":"MultiPoint","coordinates":[[-73.7967669446506,40.689967102154924],[-73.7966471986688,40.68984984159267]]}
Projectid
1280
Projtitle
Reconstruction of 99th Avenue and 110th Avenue
Fmsid
HWQ1161
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
Total reconstruction of sections of 110 Avenue, 173 Street, 104 Avenue, 189 Street, 99 Avenue etc.. These streets will be reconstructed following installation a 48 inch Trunk Water Main. Liberty Avenue in this area will be restored with concrete base whe
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2006
Currentfun
11826044.0
Projectcos
11826044.0
Overallsco
General Roadway,Sidewalk (Standalone)
Onstreetna
110 AVENUE
Fromstreet
SUTPHIN BOULEVARD
Boroughnam
QUEENS
Oftcode
400291464790000000
Designfy
2002
Latitude
40.6899084718738
Longitude
-73.7967070716597
X
1040627.71351193
Y
190694.117349222
VIEW LOCATION
1280
Projectid: 1280 • Projtitle: Reconstruction of 99th Avenue and 110th Avenue • Fmsid: HWQ1161
The Geom
{"type":"MultiPoint","coordinates":[[-73.7852210165492,40.6942105877248]]}
Projectid
1280
Projtitle
Reconstruction of 99th Avenue and 110th Avenue
Fmsid
HWQ1161
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
Total reconstruction of sections of 110 Avenue, 173 Street, 104 Avenue, 189 Street, 99 Avenue etc.. These streets will be reconstructed following installation a 48 inch Trunk Water Main. Liberty Avenue in this area will be restored with concrete base whe
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2006
Currentfun
11826044.0
Projectcos
11826044.0
Overallsco
General Roadway,Sidewalk (Standalone)
Onstreetna
110 ROAD
Fromstreet
167 STREET
Boroughnam
QUEENS
Oftcode
420385424390000000
Designfy
2002
Latitude
40.6942105877248
Longitude
-73.7852210165492
X
1043809.20632872
Y
192269.101075888
VIEW LOCATION
1280
Projectid: 1280 • Projtitle: Reconstruction of 99th Avenue and 110th Avenue • Fmsid: HWQ1161
The Geom
{"type":"MultiPoint","coordinates":[[-73.75360661815493,40.71307112194851]]}
Projectid
1280
Projtitle
Reconstruction of 99th Avenue and 110th Avenue
Fmsid
HWQ1161
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
Total reconstruction of sections of 110 Avenue, 173 Street, 104 Avenue, 189 Street, 99 Avenue etc.. These streets will be reconstructed following installation a 48 inch Trunk Water Main. Liberty Avenue in this area will be restored with concrete base whe
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2006
Currentfun
11826044.0
Projectcos
11826044.0
Overallsco
General Roadway,Sidewalk (Standalone)
Onstreetna
99 AVENUE
Fromstreet
FRANCIS LEWIS BOULEVARD
Boroughnam
QUEENS
Oftcode
419140445890000000
Designfy
2002
Latitude
40.7130711219485
Longitude
-73.7536066181549
X
1052556.67571039
Y
199163.607956141
VIEW LOCATION
1280
Projectid: 1280 • Projtitle: Reconstruction of 99th Avenue and 110th Avenue • Fmsid: HWQ1161
The Geom
{"type":"MultiPoint","coordinates":[[-73.76790400369293,40.70512381033337]]}
Projectid
1280
Projtitle
Reconstruction of 99th Avenue and 110th Avenue
Fmsid
HWQ1161
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
Total reconstruction of sections of 110 Avenue, 173 Street, 104 Avenue, 189 Street, 99 Avenue etc.. These streets will be reconstructed following installation a 48 inch Trunk Water Main. Liberty Avenue in this area will be restored with concrete base whe
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2006
Currentfun
11826044.0
Projectcos
11826044.0
Overallsco
General Roadway,Sidewalk (Standalone)
Onstreetna
189 STREET
Fromstreet
LUDLUM AVENUE
Boroughnam
QUEENS
Oftcode
425270454330000000
Designfy
2002
Latitude
40.7051238103333
Longitude
-73.7679040036929
X
1048600.74858288
Y
196257.34736447
VIEW LOCATION
1280
Projectid: 1280 • Projtitle: Reconstruction of 99th Avenue and 110th Avenue • Fmsid: HWQ1161
The Geom
{"type":"MultiPoint","coordinates":[[-73.74984240835713,40.713966705776464],[-73.74925961358524,40.71380781189764],[-73.76825969090255,40.709526367356766]]}
Projectid
1280
Projtitle
Reconstruction of 99th Avenue and 110th Avenue
Fmsid
HWQ1161
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
Total reconstruction of sections of 110 Avenue, 173 Street, 104 Avenue, 189 Street, 99 Avenue etc.. These streets will be reconstructed following installation a 48 inch Trunk Water Main. Liberty Avenue in this area will be restored with concrete base whe
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2006
Currentfun
11826044.0
Projectcos
11826044.0
Overallsco
General Roadway,Sidewalk (Standalone)
Onstreetna
99 AVENUE
Fromstreet
BEND
Boroughnam
QUEENS
Oftcode
419140435780000000
Designfy
2002
Latitude
40.7124336283436
Longitude
-73.755787237615
X
1051952.72449047
Y
198929.780777256
VIEW LOCATION
1280
Projectid: 1280 • Projtitle: Reconstruction of 99th Avenue and 110th Avenue • Fmsid: HWQ1161
The Geom
{"type":"MultiPoint","coordinates":[[-73.77088280708217,40.70440274768131]]}
Projectid
1280
Projtitle
Reconstruction of 99th Avenue and 110th Avenue
Fmsid
HWQ1161
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
Total reconstruction of sections of 110 Avenue, 173 Street, 104 Avenue, 189 Street, 99 Avenue etc.. These streets will be reconstructed following installation a 48 inch Trunk Water Main. Liberty Avenue in this area will be restored with concrete base whe
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2006
Currentfun
11826044.0
Projectcos
11826044.0
Overallsco
General Roadway,Sidewalk (Standalone)
Onstreetna
186 STREET
Fromstreet
CAMDEN AVENUE
Boroughnam
QUEENS
Oftcode
425200438335000000
Designfy
2002
Latitude
40.7044027476813
Longitude
-73.7708828070822
X
1047775.53697872
Y
195992.469285309
VIEW LOCATION
1284
Projectid: 1284 • Projtitle: Broad Channel Roadways and Bulkheads • Fmsid: HWQ1182A
The Geom
{"type":"MultiPoint","coordinates":[[-73.82280627795863,40.603975179232975]]}
Projectid
1284
Projtitle
Broad Channel Roadways and Bulkheads
Fmsid
HWQ1182A
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
This project will address flooding on W11th, 12th, and 13th Roads in Broad Channel by reconstructing streets at a higher elevation. New bulkheads will be constructed.
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Substantial Completion
Constructi
2014
Designstar
2010/04/30 00:00:00
Construc 2
2023/05/03 00:00:00
Currentfun
14810009.0
Projectcos
15773209.0
Overallsco
General Roadway,Limited-Access Roadway
Safetyscop
Shared Street
Otherscope
Green Opportunities,Localized Flooding,New or Expanded Road
Projectjus
Due to regular and sometimes severe flooding, West 11th, 12th, and 13th Roads from Cross Bay Boulevard in Broad Channel, Queens, will be reconstructed at a higher elevation. In addition, new bulkheads will be constructed at the bay end of each street. Th
Onstreetna
WEST 13 ROAD
Fromstreet
DEAD END
Boroughnam
QUEENS
Oftcode
405850441700000000
Designfy
2011
Latitude
40.6039751792329
Longitude
-73.8228062779586
X
1033453.15584664
Y
159370.604865149
VIEW LOCATION
1284
Projectid: 1284 • Projtitle: Broad Channel Roadways and Bulkheads • Fmsid: HWQ1182A
The Geom
{"type":"MultiPoint","coordinates":[[-73.82255472609981,40.60536206500494]]}
Projectid
1284
Projtitle
Broad Channel Roadways and Bulkheads
Fmsid
HWQ1182A
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
This project will address flooding on W11th, 12th, and 13th Roads in Broad Channel by reconstructing streets at a higher elevation. New bulkheads will be constructed.
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Substantial Completion
Constructi
2014
Designstar
2010/04/30 00:00:00
Construc 2
2023/05/03 00:00:00
Currentfun
14810009.0
Projectcos
15773209.0
Overallsco
General Roadway,Limited-Access Roadway
Safetyscop
Shared Street
Otherscope
Green Opportunities,Localized Flooding,New or Expanded Road
Projectjus
Due to regular and sometimes severe flooding, West 11th, 12th, and 13th Roads from Cross Bay Boulevard in Broad Channel, Queens, will be reconstructed at a higher elevation. In addition, new bulkheads will be constructed at the bay end of each street. Th
Onstreetna
WEST 11 ROAD
Fromstreet
DEAD END
Boroughnam
QUEENS
Oftcode
405695441700000000
Designfy
2011
Latitude
40.6053620650049
Longitude
-73.8225547260998
X
1033521.9831368
Y
159876.023473725
VIEW LOCATION
1284
Projectid: 1284 • Projtitle: Broad Channel Roadways and Bulkheads • Fmsid: HWQ1182A
The Geom
{"type":"MultiPoint","coordinates":[[-73.81980601497982,40.60512352704889],[-73.81972781750807,40.60511643436861]]}
Projectid
1284
Projtitle
Broad Channel Roadways and Bulkheads
Fmsid
HWQ1182A
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
This project will address flooding on W11th, 12th, and 13th Roads in Broad Channel by reconstructing streets at a higher elevation. New bulkheads will be constructed.
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Substantial Completion
Constructi
2014
Designstar
2010/04/30 00:00:00
Construc 2
2023/05/03 00:00:00
Currentfun
14810009.0
Projectcos
15773209.0
Overallsco
General Roadway,Limited-Access Roadway
Safetyscop
Shared Street
Otherscope
Green Opportunities,Localized Flooding,New or Expanded Road
Projectjus
Due to regular and sometimes severe flooding, West 11th, 12th, and 13th Roads from Cross Bay Boulevard in Broad Channel, Queens, will be reconstructed at a higher elevation. In addition, new bulkheads will be constructed at the bay end of each street. Th
Onstreetna
WEST 11 ROAD
Fromstreet
CROSS BAY BOULEVARD
Boroughnam
QUEENS
Oftcode
405695440890000000
Designfy
2011
Latitude
40.6051199807087
Longitude
-73.8197669162439
X
1034296.26652918
Y
159789.406520978
VIEW LOCATION
1284
Projectid: 1284 • Projtitle: Broad Channel Roadways and Bulkheads • Fmsid: HWQ1182A
The Geom
{"type":"MultiPoint","coordinates":[[-73.82290282958193,40.60468726770143]]}
Projectid
1284
Projtitle
Broad Channel Roadways and Bulkheads
Fmsid
HWQ1182A
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
This project will address flooding on W11th, 12th, and 13th Roads in Broad Channel by reconstructing streets at a higher elevation. New bulkheads will be constructed.
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Substantial Completion
Constructi
2014
Designstar
2010/04/30 00:00:00
Construc 2
2023/05/03 00:00:00
Currentfun
14810009.0
Projectcos
15773209.0
Overallsco
General Roadway,Limited-Access Roadway
Safetyscop
Shared Street
Otherscope
Green Opportunities,Localized Flooding,New or Expanded Road
Projectjus
Due to regular and sometimes severe flooding, West 11th, 12th, and 13th Roads from Cross Bay Boulevard in Broad Channel, Queens, will be reconstructed at a higher elevation. In addition, new bulkheads will be constructed at the bay end of each street. Th
Onstreetna
12 ROAD
Fromstreet
DEAD END
Boroughnam
QUEENS
Oftcode
405760441700000000
Designfy
2011
Latitude
40.6046872677014
Longitude
-73.8229028295819
X
1033425.82092756
Y
159629.982299149
VIEW LOCATION
1284
Projectid: 1284 • Projtitle: Broad Channel Roadways and Bulkheads • Fmsid: HWQ1182A
The Geom
{"type":"MultiPoint","coordinates":[[-73.81991906878818,40.60443027393861],[-73.81983479788045,40.60442274856681]]}
Projectid
1284
Projtitle
Broad Channel Roadways and Bulkheads
Fmsid
HWQ1182A
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
This project will address flooding on W11th, 12th, and 13th Roads in Broad Channel by reconstructing streets at a higher elevation. New bulkheads will be constructed.
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Substantial Completion
Constructi
2014
Designstar
2010/04/30 00:00:00
Construc 2
2023/05/03 00:00:00
Currentfun
14810009.0
Projectcos
15773209.0
Overallsco
General Roadway,Limited-Access Roadway
Safetyscop
Shared Street
Otherscope
Green Opportunities,Localized Flooding,New or Expanded Road
Projectjus
Due to regular and sometimes severe flooding, West 11th, 12th, and 13th Roads from Cross Bay Boulevard in Broad Channel, Queens, will be reconstructed at a higher elevation. In addition, new bulkheads will be constructed at the bay end of each street. Th
Onstreetna
WEST 12 ROAD
Fromstreet
CROSS BAY BOULEVARD
Boroughnam
QUEENS
Oftcode
405795440890000000
Designfy
2011
Latitude
40.6044265117029
Longitude
-73.8198769333331
X
1034266.23706168
Y
159536.695412226
VIEW LOCATION
1285
Projectid: 1285 • Projtitle: Broad Channel Bulkheads - Phase II • Fmsid: HWQ1182B
The Geom
{"type":"MultiPoint","coordinates":[[-73.82294484747898,40.60258290920288]]}
Projectid
1285
Projtitle
Broad Channel Bulkheads - Phase II
Fmsid
HWQ1182B
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
This multi-phase project will address flooding from W14th to W17th by raising the roadway grade, reconstructing the bulkhead, and constructing a storm sewer system.
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Substantial Completion
Constructi
2020
Designstar
2014/01/07 00:00:00
Construc 2
2024/11/04 00:00:00
Currentfun
34671895.0
Projectcos
32951662.0
Overallsco
General Roadway,Limited-Access Roadway
Safetyscop
Shared Street,New Sidewalks
Otherscope
Green Opportunities,Localized Flooding,New or Expanded Road
Projectjus
This is multi-phase project is to address the flooding conditions on West 14 through West 17 Roads through a combination of raising the roadway grades, reconstructing the bulkheads, and constructing a storm sewer drainage system.
Onstreetna
15 ROAD
Fromstreet
BODY OF WATER
Boroughnam
QUEENS
Oftcode
406150462250000000
Designfy
2015
Latitude
40.6025829092028
Longitude
-73.822944847479
X
1033415.70316564
Y
158863.288294479
VIEW LOCATION
1285
Projectid: 1285 • Projtitle: Broad Channel Bulkheads - Phase II • Fmsid: HWQ1182B
The Geom
{"type":"MultiPoint","coordinates":[[-73.82287967343274,40.60328278236758]]}
Projectid
1285
Projtitle
Broad Channel Bulkheads - Phase II
Fmsid
HWQ1182B
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
This multi-phase project will address flooding from W14th to W17th by raising the roadway grade, reconstructing the bulkhead, and constructing a storm sewer system.
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Substantial Completion
Constructi
2020
Designstar
2014/01/07 00:00:00
Construc 2
2024/11/04 00:00:00
Currentfun
34671895.0
Projectcos
32951662.0
Overallsco
General Roadway,Limited-Access Roadway
Safetyscop
Shared Street,New Sidewalks
Otherscope
Green Opportunities,Localized Flooding,New or Expanded Road
Projectjus
This is multi-phase project is to address the flooding conditions on West 14 through West 17 Roads through a combination of raising the roadway grades, reconstructing the bulkheads, and constructing a storm sewer drainage system.
Onstreetna
14 ROAD
Fromstreet
DEAD END
Boroughnam
QUEENS
Oftcode
406040441700000000
Designfy
2015
Latitude
40.6032827823676
Longitude
-73.8228796734327
X
1033433.28547956
Y
159118.306157142
VIEW LOCATION
1285
Projectid: 1285 • Projtitle: Broad Channel Bulkheads - Phase II • Fmsid: HWQ1182B
The Geom
{"type":"MultiPoint","coordinates":[[-73.8235849834935,40.601940033419325]]}
Projectid
1285
Projtitle
Broad Channel Bulkheads - Phase II
Fmsid
HWQ1182B
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
This multi-phase project will address flooding from W14th to W17th by raising the roadway grade, reconstructing the bulkhead, and constructing a storm sewer system.
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Substantial Completion
Constructi
2020
Designstar
2014/01/07 00:00:00
Construc 2
2024/11/04 00:00:00
Currentfun
34671895.0
Projectcos
32951662.0
Overallsco
General Roadway,Limited-Access Roadway
Safetyscop
Shared Street,New Sidewalks
Otherscope
Green Opportunities,Localized Flooding,New or Expanded Road
Projectjus
This is multi-phase project is to address the flooding conditions on West 14 through West 17 Roads through a combination of raising the roadway grades, reconstructing the bulkheads, and constructing a storm sewer drainage system.
Onstreetna
16 ROAD
Fromstreet
BODY OF WATER
Boroughnam
QUEENS
Oftcode
406170462250000000
Designfy
2015
Latitude
40.6019400325187
Longitude
-73.8235849834959
X
1033238.41841522
Y
158628.713960484
VIEW LOCATION
1290
Projectid: 1290 • Projtitle: James Court Bulkhead • Fmsid: HWQ1184A
The Geom
{"type":"MultiPoint","coordinates":[[-73.82772384540503,40.652761240166974]]}
Projectid
1290
Projtitle
James Court Bulkhead
Fmsid
HWQ1184A
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
This project will reconstruct the bulkhead on James Ct. at Hawtree Basin
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2019
Designstar
2010/11/08 00:00:00
Construc 2
2022/08/26 00:00:00
Currentfun
4989535.0
Projectcos
4989535.0
Overallsco
General Roadway
Projectjus
This project will reconstruct the missing bulkhead on James Court at Hawtree Basin. In addition it includes the resurfacing of James Court from 104th Street to the new Bulkhead at Hawtree Basin to enhance its ride ability.
Onstreetna
163 DRIVE
Fromstreet
104 STREET
Boroughnam
QUEENS
Oftcode
400337419740000000
Designfy
2012
Latitude
40.6527612401669
Longitude
-73.827723845405
X
1032052.69145598
Y
177141.910529807
VIEW LOCATION
1296
Projectid: 1296 • Projtitle: Rockaway Beach Bulkhead • Fmsid: HWQ1186
The Geom
{"type":"MultiPoint","coordinates":[[-73.86052610079156,40.57719031631696]]}
Projectid
1296
Projtitle
Rockaway Beach Bulkhead
Fmsid
HWQ1186
Fmsagencyi
801
Leadagency
EDC
Managingag
31
Projectdes
The project will reconstruct the bulkhead that supports Beach Channel Drive between Beach 116th and Beach 145th Streets.
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2013
Designstar
2012/06/29 00:00:00
Construc 2
2016/04/06 00:00:00
Currentfun
21424334.0
Projectcos
21424334.0
Projectjus
The project is located on Beach Channel Drive between Beach 116th and Beach 145th Streets in Rockaway, Queens. A condition assessment of the Beach Channel Drive bulkhead was performed in summer of 2011 and identified the general areas that require priori
Onstreetna
BEACH 141 STREET
Fromstreet
BEACH CHANNEL DRIVE
Boroughnam
QUEENS
Oftcode
435095435290000000
Designfy
0
Latitude
40.5771903163169
Longitude
-73.8605261007915
X
1022994.66232798
Y
149593.282228231
VIEW LOCATION
1296
Projectid: 1296 • Projtitle: Rockaway Beach Bulkhead • Fmsid: HWQ1186
The Geom
{"type":"MultiPoint","coordinates":[[-73.85122514459994,40.58161592359949]]}
Projectid
1296
Projtitle
Rockaway Beach Bulkhead
Fmsid
HWQ1186
Fmsagencyi
801
Leadagency
EDC
Managingag
31
Projectdes
The project will reconstruct the bulkhead that supports Beach Channel Drive between Beach 116th and Beach 145th Streets.
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2013
Designstar
2012/06/29 00:00:00
Construc 2
2016/04/06 00:00:00
Currentfun
21424334.0
Projectcos
21424334.0
Projectjus
The project is located on Beach Channel Drive between Beach 116th and Beach 145th Streets in Rockaway, Queens. A condition assessment of the Beach Channel Drive bulkhead was performed in summer of 2011 and identified the general areas that require priori
Onstreetna
BEACH 129 STREET
Fromstreet
BEACH CHANNEL DRIVE
Boroughnam
QUEENS
Oftcode
434640435290000000
Designfy
0
Latitude
40.5816159245
Longitude
-73.8512251445979
X
1025575.64797963
Y
151209.889887393
VIEW LOCATION
1296
Projectid: 1296 • Projtitle: Rockaway Beach Bulkhead • Fmsid: HWQ1186
The Geom
{"type":"MultiPoint","coordinates":[[-73.83829751555618,40.58176615195211]]}
Projectid
1296
Projtitle
Rockaway Beach Bulkhead
Fmsid
HWQ1186
Fmsagencyi
801
Leadagency
EDC
Managingag
31
Projectdes
The project will reconstruct the bulkhead that supports Beach Channel Drive between Beach 116th and Beach 145th Streets.
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2013
Designstar
2012/06/29 00:00:00
Construc 2
2016/04/06 00:00:00
Currentfun
21424334.0
Projectcos
21424334.0
Projectjus
The project is located on Beach Channel Drive between Beach 116th and Beach 145th Streets in Rockaway, Queens. A condition assessment of the Beach Channel Drive bulkhead was performed in summer of 2011 and identified the general areas that require priori
Onstreetna
BEACH 116 STREET
Fromstreet
BEACH CHANNEL DRIVE
Boroughnam
QUEENS
Oftcode
433990435290000000
Designfy
0
Latitude
40.5817661519521
Longitude
-73.8382975155562
X
1029166.49020739
Y
151270.985565722
VIEW LOCATION
1297
Projectid: 1297 • Projtitle: BEACH CHANNEL DRIVE BTWN 131st - 141st • Fmsid: HWQ1186A
The Geom
{"type":"MultiPoint","coordinates":[[-73.85298902653876,40.58116181700232]]}
Projectid
1297
Projtitle
BEACH CHANNEL DRIVE BTWN 131st - 141st
Fmsid
HWQ1186A
Fmsagencyi
801
Leadagency
EDC
Managingag
0
Projectdes
Emergency contract to reconstruct/repair Jamaica Bay Rockway Seawall between Beach 130 to Beach 141 Streets that is adjacent to Beach Channe
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2011
Currentfun
2969979.0
Projectcos
2969979.0
Overallsco
General Roadway
Onstreetna
BEACH 131 STREET
Fromstreet
BEACH CHANNEL DRIVE
Boroughnam
QUEENS
Oftcode
434740435290000000
Designfy
0
Latitude
40.5811618170023
Longitude
-73.8529890265388
X
1025085.96720047
Y
151043.620534897
VIEW LOCATION
1297
Projectid: 1297 • Projtitle: BEACH CHANNEL DRIVE BTWN 131st - 141st • Fmsid: HWQ1186A
The Geom
{"type":"MultiPoint","coordinates":[[-73.86052610079156,40.57719031631696]]}
Projectid
1297
Projtitle
BEACH CHANNEL DRIVE BTWN 131st - 141st
Fmsid
HWQ1186A
Fmsagencyi
801
Leadagency
EDC
Managingag
0
Projectdes
Emergency contract to reconstruct/repair Jamaica Bay Rockway Seawall between Beach 130 to Beach 141 Streets that is adjacent to Beach Channe
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2011
Currentfun
2969979.0
Projectcos
2969979.0
Overallsco
General Roadway
Onstreetna
BEACH 141 STREET
Fromstreet
BEACH CHANNEL DRIVE
Boroughnam
QUEENS
Oftcode
435095435290000000
Designfy
0
Latitude
40.5771903163169
Longitude
-73.8605261007915
X
1022994.66232798
Y
149593.282228231
VIEW LOCATION
1313
Projectid: 1313 • Projtitle: RECONSTRUCTION OF SOUTH JAMAICA AREA • Fmsid: HWQ121B4
The Geom
{"type":"MultiPoint","coordinates":[[-73.78477483317404,40.68218318093545]]}
Projectid
1313
Projtitle
RECONSTRUCTION OF SOUTH JAMAICA AREA
Fmsid
HWQ121B4
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
Lakeview Blvd East from 118 Ave to 122 Ave, 122 Ave to Lakeview Lane and Lakeview Lane to Baisley Blvd, total Reconstruction. DOT project to accompany DEP project. DOT construction funds were restored in January 2012 Plan
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2016
Designstar
2006/10/27 00:00:00
Construc 2
2018/05/31 00:00:00
Currentfun
3697546.0
Projectcos
3697546.0
Overallsco
General Roadway,Sidewalk (Standalone)
Safetyscop
Lane Removal or Road Narrowing
Onstreetna
118 ROAD
Fromstreet
LAKEVIEW BOULEVARD EAST
Boroughnam
QUEENS
Oftcode
421090452560000000
Designfy
2012
Latitude
40.6821831809354
Longitude
-73.784774833174
X
1043943.70113847
Y
187887.48254256
VIEW LOCATION
1313
Projectid: 1313 • Projtitle: RECONSTRUCTION OF SOUTH JAMAICA AREA • Fmsid: HWQ121B4
The Geom
{"type":"MultiPoint","coordinates":[[-73.78433679448902,40.67932610099164]]}
Projectid
1313
Projtitle
RECONSTRUCTION OF SOUTH JAMAICA AREA
Fmsid
HWQ121B4
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
Lakeview Blvd East from 118 Ave to 122 Ave, 122 Ave to Lakeview Lane and Lakeview Lane to Baisley Blvd, total Reconstruction. DOT project to accompany DEP project. DOT construction funds were restored in January 2012 Plan
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2016
Designstar
2006/10/27 00:00:00
Construc 2
2018/05/31 00:00:00
Currentfun
3697546.0
Projectcos
3697546.0
Overallsco
General Roadway,Sidewalk (Standalone)
Safetyscop
Lane Removal or Road Narrowing
Onstreetna
120 AVENUE
Fromstreet
LAKEVIEW BOULEVARD EAST
Boroughnam
QUEENS
Oftcode
421290452560000000
Designfy
2012
Latitude
40.6793261009916
Longitude
-73.784336794489
X
1044067.75568038
Y
186846.867825896
VIEW LOCATION
1313
Projectid: 1313 • Projtitle: RECONSTRUCTION OF SOUTH JAMAICA AREA • Fmsid: HWQ121B4
The Geom
{"type":"MultiPoint","coordinates":[[-73.78422986747735,40.678615950785215]]}
Projectid
1313
Projtitle
RECONSTRUCTION OF SOUTH JAMAICA AREA
Fmsid
HWQ121B4
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
Lakeview Blvd East from 118 Ave to 122 Ave, 122 Ave to Lakeview Lane and Lakeview Lane to Baisley Blvd, total Reconstruction. DOT project to accompany DEP project. DOT construction funds were restored in January 2012 Plan
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2016
Designstar
2006/10/27 00:00:00
Construc 2
2018/05/31 00:00:00
Currentfun
3697546.0
Projectcos
3697546.0
Overallsco
General Roadway,Sidewalk (Standalone)
Safetyscop
Lane Removal or Road Narrowing
Onstreetna
121 AVENUE
Fromstreet
LAKEVIEW BOULEVARD EAST
Boroughnam
QUEENS
Oftcode
421370452560000000
Designfy
2012
Latitude
40.6786159507852
Longitude
-73.7842298674774
X
1044098.05089539
Y
186588.213487566
VIEW LOCATION
1313
Projectid: 1313 • Projtitle: RECONSTRUCTION OF SOUTH JAMAICA AREA • Fmsid: HWQ121B4
The Geom
{"type":"MultiPoint","coordinates":[[-73.78444725306757,40.68004185886497]]}
Projectid
1313
Projtitle
RECONSTRUCTION OF SOUTH JAMAICA AREA
Fmsid
HWQ121B4
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
Lakeview Blvd East from 118 Ave to 122 Ave, 122 Ave to Lakeview Lane and Lakeview Lane to Baisley Blvd, total Reconstruction. DOT project to accompany DEP project. DOT construction funds were restored in January 2012 Plan
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2016
Designstar
2006/10/27 00:00:00
Construc 2
2018/05/31 00:00:00
Currentfun
3697546.0
Projectcos
3697546.0
Overallsco
General Roadway,Sidewalk (Standalone)
Safetyscop
Lane Removal or Road Narrowing
Onstreetna
119 DRIVE
Fromstreet
LAKEVIEW BOULEVARD EAST
Boroughnam
QUEENS
Oftcode
421200452560000000
Designfy
2012
Latitude
40.6800418588649
Longitude
-73.7844472530676
X
1044036.47654347
Y
187107.562842563
VIEW LOCATION
1313
Projectid: 1313 • Projtitle: RECONSTRUCTION OF SOUTH JAMAICA AREA • Fmsid: HWQ121B4
The Geom
{"type":"MultiPoint","coordinates":[[-73.78487480218396,40.682886661576276]]}
Projectid
1313
Projtitle
RECONSTRUCTION OF SOUTH JAMAICA AREA
Fmsid
HWQ121B4
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
Lakeview Blvd East from 118 Ave to 122 Ave, 122 Ave to Lakeview Lane and Lakeview Lane to Baisley Blvd, total Reconstruction. DOT project to accompany DEP project. DOT construction funds were restored in January 2012 Plan
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2016
Designstar
2006/10/27 00:00:00
Construc 2
2018/05/31 00:00:00
Currentfun
3697546.0
Projectcos
3697546.0
Overallsco
General Roadway,Sidewalk (Standalone)
Safetyscop
Lane Removal or Road Narrowing
Onstreetna
118 AVENUE
Fromstreet
LAKEVIEW BOULEVARD EAST
Boroughnam
QUEENS
Oftcode
421070452560000000
Designfy
2012
Latitude
40.6828866624768
Longitude
-73.7848748021811
X
1043915.34489597
Y
188143.71201697
VIEW LOCATION
1313
Projectid: 1313 • Projtitle: RECONSTRUCTION OF SOUTH JAMAICA AREA • Fmsid: HWQ121B4
The Geom
{"type":"MultiPoint","coordinates":[[-73.78244525323166,40.67846091615775],[-73.78405958899127,40.67794606973515]]}
Projectid
1313
Projtitle
RECONSTRUCTION OF SOUTH JAMAICA AREA
Fmsid
HWQ121B4
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
Lakeview Blvd East from 118 Ave to 122 Ave, 122 Ave to Lakeview Lane and Lakeview Lane to Baisley Blvd, total Reconstruction. DOT project to accompany DEP project. DOT construction funds were restored in January 2012 Plan
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2016
Designstar
2006/10/27 00:00:00
Construc 2
2018/05/31 00:00:00
Currentfun
3697546.0
Projectcos
3697546.0
Overallsco
General Roadway,Sidewalk (Standalone)
Safetyscop
Lane Removal or Road Narrowing
Onstreetna
122 AVENUE
Fromstreet
LAKEVIEW BOULEVARD EAST
Boroughnam
QUEENS
Oftcode
421420452560000000
Designfy
2012
Latitude
40.6782034929464
Longitude
-73.7832524211115
X
1044369.53509651
Y
186438.614049226
VIEW LOCATION
1313
Projectid: 1313 • Projtitle: RECONSTRUCTION OF SOUTH JAMAICA AREA • Fmsid: HWQ121B4
The Geom
{"type":"MultiPoint","coordinates":[[-73.78466584046197,40.6814728474325]]}
Projectid
1313
Projtitle
RECONSTRUCTION OF SOUTH JAMAICA AREA
Fmsid
HWQ121B4
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
Lakeview Blvd East from 118 Ave to 122 Ave, 122 Ave to Lakeview Lane and Lakeview Lane to Baisley Blvd, total Reconstruction. DOT project to accompany DEP project. DOT construction funds were restored in January 2012 Plan
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2016
Designstar
2006/10/27 00:00:00
Construc 2
2018/05/31 00:00:00
Currentfun
3697546.0
Projectcos
3697546.0
Overallsco
General Roadway,Sidewalk (Standalone)
Safetyscop
Lane Removal or Road Narrowing
Onstreetna
119 AVENUE
Fromstreet
LAKEVIEW BOULEVARD EAST
Boroughnam
QUEENS
Oftcode
421190452560000000
Designfy
2012
Latitude
40.6814728474325
Longitude
-73.784665840462
X
1043974.56689039
Y
187628.762587562
VIEW LOCATION
1313
Projectid: 1313 • Projtitle: RECONSTRUCTION OF SOUTH JAMAICA AREA • Fmsid: HWQ121B4
The Geom
{"type":"MultiPoint","coordinates":[[-73.78456178392302,40.68075810056343]]}
Projectid
1313
Projtitle
RECONSTRUCTION OF SOUTH JAMAICA AREA
Fmsid
HWQ121B4
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
Lakeview Blvd East from 118 Ave to 122 Ave, 122 Ave to Lakeview Lane and Lakeview Lane to Baisley Blvd, total Reconstruction. DOT project to accompany DEP project. DOT construction funds were restored in January 2012 Plan
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2016
Designstar
2006/10/27 00:00:00
Construc 2
2018/05/31 00:00:00
Currentfun
3697546.0
Projectcos
3697546.0
Overallsco
General Roadway,Sidewalk (Standalone)
Safetyscop
Lane Removal or Road Narrowing
Onstreetna
119 ROAD
Fromstreet
LAKEVIEW BOULEVARD EAST
Boroughnam
QUEENS
Oftcode
421210452560000000
Designfy
2012
Latitude
40.6807581014639
Longitude
-73.7845617839201
X
1044004.06814373
Y
187368.431415305
VIEW LOCATION
1313
Projectid: 1313 • Projtitle: RECONSTRUCTION OF SOUTH JAMAICA AREA • Fmsid: HWQ121B4
The Geom
{"type":"MultiPoint","coordinates":[[-73.7811508587969,40.68286272837521]]}
Projectid
1313
Projtitle
RECONSTRUCTION OF SOUTH JAMAICA AREA
Fmsid
HWQ121B4
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
Lakeview Blvd East from 118 Ave to 122 Ave, 122 Ave to Lakeview Lane and Lakeview Lane to Baisley Blvd, total Reconstruction. DOT project to accompany DEP project. DOT construction funds were restored in January 2012 Plan
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2016
Designstar
2006/10/27 00:00:00
Construc 2
2018/05/31 00:00:00
Currentfun
3697546.0
Projectcos
3697546.0
Overallsco
General Roadway,Sidewalk (Standalone)
Safetyscop
Lane Removal or Road Narrowing
Onstreetna
119 AVENUE
Fromstreet
164 STREET
Boroughnam
QUEENS
Oftcode
421190424240000000
Designfy
2012
Latitude
40.6828627283752
Longitude
-73.7811508587969
X
1044948.20667538
Y
188137.550940067
VIEW LOCATION
1316
Projectid: 1316 • Projtitle: RECONSTRUCTION OF COLLEGE POINT BLVD • Fmsid: HWQ1675
The Geom
{"type":"MultiPoint","coordinates":[[-73.83452851718795,40.75899259318515]]}
Projectid
1316
Projtitle
RECONSTRUCTION OF COLLEGE POINT BLVD
Fmsid
HWQ1675
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
The project reconstructed College Point Blvd from Fowler Ave to the southbound Whitestone Expressway Service Rd to restore to a state of good repair.
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2010
Designstar
2006/10/31 00:00:00
Construc 2
2016/08/29 00:00:00
Currentfun
13345830.0
Projectcos
13345830.0
Overallsco
General Roadway,Sidewalk (Standalone)
Safetyscop
New Median / Ped Refuge,Median Improvement (Raised or Widened)
Projectjus
Construction was completed in Summer 2014. SOGR street reconstruction project from College Point Boulevard from Fowler Avenue to the southbound Whitestone Expressway Service Road to restore the roadway to a state of good repair.
Onstreetna
39 AVENUE
Fromstreet
COLLEGE POINT BOULEVARD
Boroughnam
QUEENS
Oftcode
409140439595000000
Designfy
0
Latitude
40.7589925931851
Longitude
-73.8345285171879
X
1030091.44242573
Y
215841.477487475
VIEW LOCATION
1316
Projectid: 1316 • Projtitle: RECONSTRUCTION OF COLLEGE POINT BLVD • Fmsid: HWQ1675
The Geom
{"type":"MultiPoint","coordinates":[[-73.83528642689855,40.76138604523342]]}
Projectid
1316
Projtitle
RECONSTRUCTION OF COLLEGE POINT BLVD
Fmsid
HWQ1675
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
The project reconstructed College Point Blvd from Fowler Ave to the southbound Whitestone Expressway Service Rd to restore to a state of good repair.
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2010
Designstar
2006/10/31 00:00:00
Construc 2
2016/08/29 00:00:00
Currentfun
13345830.0
Projectcos
13345830.0
Overallsco
General Roadway,Sidewalk (Standalone)
Safetyscop
New Median / Ped Refuge,Median Improvement (Raised or Widened)
Projectjus
Construction was completed in Summer 2014. SOGR street reconstruction project from College Point Boulevard from Fowler Avenue to the southbound Whitestone Expressway Service Road to restore the roadway to a state of good repair.
Onstreetna
COLLEGE POINT BOULEVARD
Fromstreet
KING ROAD
Boroughnam
QUEENS
Oftcode
439595452230000000
Designfy
0
Latitude
40.7613860452334
Longitude
-73.8352864268985
X
1029879.83523738
Y
216713.093198314
VIEW LOCATION
1316
Projectid: 1316 • Projtitle: RECONSTRUCTION OF COLLEGE POINT BLVD • Fmsid: HWQ1675
The Geom
{"type":"MultiPoint","coordinates":[[-73.83492178745541,40.76025453260997]]}
Projectid
1316
Projtitle
RECONSTRUCTION OF COLLEGE POINT BLVD
Fmsid
HWQ1675
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
The project reconstructed College Point Blvd from Fowler Ave to the southbound Whitestone Expressway Service Rd to restore to a state of good repair.
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2010
Designstar
2006/10/31 00:00:00
Construc 2
2016/08/29 00:00:00
Currentfun
13345830.0
Projectcos
13345830.0
Overallsco
General Roadway,Sidewalk (Standalone)
Safetyscop
New Median / Ped Refuge,Median Improvement (Raised or Widened)
Projectjus
Construction was completed in Summer 2014. SOGR street reconstruction project from College Point Boulevard from Fowler Avenue to the southbound Whitestone Expressway Service Road to restore the roadway to a state of good repair.
Onstreetna
37 AVENUE
Fromstreet
COLLEGE POINT BOULEVARD
Boroughnam
QUEENS
Oftcode
408790439595000000
Designfy
0
Latitude
40.7602545326099
Longitude
-73.8349217874554
X
1029981.62637238
Y
216301.036935806
VIEW LOCATION
1316
Projectid: 1316 • Projtitle: RECONSTRUCTION OF COLLEGE POINT BLVD • Fmsid: HWQ1675
The Geom
{"type":"MultiPoint","coordinates":[[-73.83310291312601,40.75466142266581]]}
Projectid
1316
Projtitle
RECONSTRUCTION OF COLLEGE POINT BLVD
Fmsid
HWQ1675
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
The project reconstructed College Point Blvd from Fowler Ave to the southbound Whitestone Expressway Service Rd to restore to a state of good repair.
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2010
Designstar
2006/10/31 00:00:00
Construc 2
2016/08/29 00:00:00
Currentfun
13345830.0
Projectcos
13345830.0
Overallsco
General Roadway,Sidewalk (Standalone)
Safetyscop
New Median / Ped Refuge,Median Improvement (Raised or Widened)
Projectjus
Construction was completed in Summer 2014. SOGR street reconstruction project from College Point Boulevard from Fowler Avenue to the southbound Whitestone Expressway Service Road to restore the roadway to a state of good repair.
Onstreetna
COLLEGE POINT BOULEVARD
Fromstreet
SANFORD AVENUE
Boroughnam
QUEENS
Oftcode
439595461390000000
Designfy
0
Latitude
40.7546614226658
Longitude
-73.833102913126
X
1030489.39110489
Y
214264.243109137
VIEW LOCATION
1316
Projectid: 1316 • Projtitle: RECONSTRUCTION OF COLLEGE POINT BLVD • Fmsid: HWQ1675
The Geom
{"type":"MultiPoint","coordinates":[[-73.83229535720528,40.751941789695394]]}
Projectid
1316
Projtitle
RECONSTRUCTION OF COLLEGE POINT BLVD
Fmsid
HWQ1675
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
The project reconstructed College Point Blvd from Fowler Ave to the southbound Whitestone Expressway Service Rd to restore to a state of good repair.
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2010
Designstar
2006/10/31 00:00:00
Construc 2
2016/08/29 00:00:00
Currentfun
13345830.0
Projectcos
13345830.0
Overallsco
General Roadway,Sidewalk (Standalone)
Safetyscop
New Median / Ped Refuge,Median Improvement (Raised or Widened)
Projectjus
Construction was completed in Summer 2014. SOGR street reconstruction project from College Point Boulevard from Fowler Avenue to the southbound Whitestone Expressway Service Road to restore the roadway to a state of good repair.
Onstreetna
COLLEGE POINT BOULEVARD
Fromstreet
FOWLER AVENUE
Boroughnam
QUEENS
Oftcode
439595445720000000
Designfy
0
Latitude
40.7519417896953
Longitude
-73.8322953572053
X
1030715.02385572
Y
213273.82186164
VIEW LOCATION
1316
Projectid: 1316 • Projtitle: RECONSTRUCTION OF COLLEGE POINT BLVD • Fmsid: HWQ1675
The Geom
{"type":"MultiPoint","coordinates":[[-73.83542617735836,40.76210421840718]]}
Projectid
1316
Projtitle
RECONSTRUCTION OF COLLEGE POINT BLVD
Fmsid
HWQ1675
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
The project reconstructed College Point Blvd from Fowler Ave to the southbound Whitestone Expressway Service Rd to restore to a state of good repair.
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2010
Designstar
2006/10/31 00:00:00
Construc 2
2016/08/29 00:00:00
Currentfun
13345830.0
Projectcos
13345830.0
Overallsco
General Roadway,Sidewalk (Standalone)
Safetyscop
New Median / Ped Refuge,Median Improvement (Raised or Widened)
Projectjus
Construction was completed in Summer 2014. SOGR street reconstruction project from College Point Boulevard from Fowler Avenue to the southbound Whitestone Expressway Service Road to restore the roadway to a state of good repair.
Onstreetna
36 AVENUE
Fromstreet
COLLEGE POINT BOULEVARD
Boroughnam
QUEENS
Oftcode
408690439595000000
Designfy
0
Latitude
40.7621042184071
Longitude
-73.8354261773584
X
1029840.62927905
Y
216974.674039975
VIEW LOCATION
1316
Projectid: 1316 • Projtitle: RECONSTRUCTION OF COLLEGE POINT BLVD • Fmsid: HWQ1675
The Geom
{"type":"MultiPoint","coordinates":[[-73.83602374184183,40.763589500376895]]}
Projectid
1316
Projtitle
RECONSTRUCTION OF COLLEGE POINT BLVD
Fmsid
HWQ1675
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
The project reconstructed College Point Blvd from Fowler Ave to the southbound Whitestone Expressway Service Rd to restore to a state of good repair.
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2010
Designstar
2006/10/31 00:00:00
Construc 2
2016/08/29 00:00:00
Currentfun
13345830.0
Projectcos
13345830.0
Overallsco
General Roadway,Sidewalk (Standalone)
Safetyscop
New Median / Ped Refuge,Median Improvement (Raised or Widened)
Projectjus
Construction was completed in Summer 2014. SOGR street reconstruction project from College Point Boulevard from Fowler Avenue to the southbound Whitestone Expressway Service Road to restore the roadway to a state of good repair.
Onstreetna
35 AVENUE
Fromstreet
COLLEGE POINT BOULEVARD
Boroughnam
QUEENS
Oftcode
408590439595000000
Designfy
0
Latitude
40.7635895003769
Longitude
-73.8360237418418
X
1029674.07777488
Y
217515.499729976
VIEW LOCATION
1316
Projectid: 1316 • Projtitle: RECONSTRUCTION OF COLLEGE POINT BLVD • Fmsid: HWQ1675
The Geom
{"type":"MultiPoint","coordinates":[[-73.83547161299927,40.76692535642954]]}
Projectid
1316
Projtitle
RECONSTRUCTION OF COLLEGE POINT BLVD
Fmsid
HWQ1675
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
The project reconstructed College Point Blvd from Fowler Ave to the southbound Whitestone Expressway Service Rd to restore to a state of good repair.
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2010
Designstar
2006/10/31 00:00:00
Construc 2
2016/08/29 00:00:00
Currentfun
13345830.0
Projectcos
13345830.0
Overallsco
General Roadway,Sidewalk (Standalone)
Safetyscop
New Median / Ped Refuge,Median Improvement (Raised or Widened)
Projectjus
Construction was completed in Summer 2014. SOGR street reconstruction project from College Point Boulevard from Fowler Avenue to the southbound Whitestone Expressway Service Road to restore the roadway to a state of good repair.
Onstreetna
32 AVENUE
Fromstreet
DOWNING STREET
Boroughnam
QUEENS
Oftcode
408190442800000000
Designfy
0
Latitude
40.7669253564295
Longitude
-73.8354716129993
X
1029824.74348405
Y
218731.146904975
VIEW LOCATION
1316
Projectid: 1316 • Projtitle: RECONSTRUCTION OF COLLEGE POINT BLVD • Fmsid: HWQ1675
The Geom
{"type":"MultiPoint","coordinates":[[-73.83766223090227,40.766436076558094],[-73.83802905457209,40.76633726799704]]}
Projectid
1316
Projtitle
RECONSTRUCTION OF COLLEGE POINT BLVD
Fmsid
HWQ1675
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
The project reconstructed College Point Blvd from Fowler Ave to the southbound Whitestone Expressway Service Rd to restore to a state of good repair.
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2010
Designstar
2006/10/31 00:00:00
Construc 2
2016/08/29 00:00:00
Currentfun
13345830.0
Projectcos
13345830.0
Overallsco
General Roadway,Sidewalk (Standalone)
Safetyscop
New Median / Ped Refuge,Median Improvement (Raised or Widened)
Projectjus
Construction was completed in Summer 2014. SOGR street reconstruction project from College Point Boulevard from Fowler Avenue to the southbound Whitestone Expressway Service Road to restore the roadway to a state of good repair.
Onstreetna
32 AVENUE
Fromstreet
COLLEGE POINT BOULEVARD
Boroughnam
QUEENS
Oftcode
408190439595000000
Designfy
0
Latitude
40.7663866727278
Longitude
-73.8378456427361
X
1029167.49578281
Y
218533.660587355
VIEW LOCATION
1316
Projectid: 1316 • Projtitle: RECONSTRUCTION OF COLLEGE POINT BLVD • Fmsid: HWQ1675
The Geom
{"type":"MultiPoint","coordinates":[[-73.83282012096575,40.75372125332829]]}
Projectid
1316
Projtitle
RECONSTRUCTION OF COLLEGE POINT BLVD
Fmsid
HWQ1675
Fmsagencyi
841
Leadagency
DOT
Managingag
3
Projectdes
The project reconstructed College Point Blvd from Fowler Ave to the southbound Whitestone Expressway Service Rd to restore to a state of good repair.
Projecttyp
REC
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Constructi
2010
Designstar
2006/10/31 00:00:00
Construc 2
2016/08/29 00:00:00
Currentfun
13345830.0
Projectcos
13345830.0
Overallsco
General Roadway,Sidewalk (Standalone)
Safetyscop
New Median / Ped Refuge,Median Improvement (Raised or Widened)
Projectjus
Construction was completed in Summer 2014. SOGR street reconstruction project from College Point Boulevard from Fowler Avenue to the southbound Whitestone Expressway Service Road to restore the roadway to a state of good repair.
Onstreetna
COLLEGE POINT BOULEVARD
Fromstreet
MAPLE AVENUE
Boroughnam
QUEENS
Oftcode
439595454790000000
Designfy
0
Latitude
40.7537212533283
Longitude
-73.8328201209657
X
1030568.39324348
Y
213921.85895139