Capital Projects Dashboard - Citywide Budget and Schedule

All major capital infrastructure projects with a committed budget. Financial information and agency schedule details for each project are joined via FMS ID. Only projects in the design phase or later have project schedules displayed. This dataset is part of the Capital Projects Dashboard.

Note: Each row is uniquely identified by its Financial Management Service (FMS) ID. FMS ID is the unique ID that OMB uses for the FMS (Financial Information System). This ID can be universally joined with any OMB dataset that has the same field. The Capital Projects Dashboard is the result of joining OMB’s fiscal data with the agency’s schedule data. FMS IDs and agency projects don't always have a one-to-one relationship (i.e., one project schedule may correlate to multiple FMS IDs, and one FMS may correct to multiple projects with different schedules).

City Government Mayor's Office of Operations (OPS) Dataset fb86-vt7u 27 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DCLA
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DCLA
Pid
4371
Fms Id
PV502-SDW
Total Budget
2337000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
JCAL - JPAC Outdoor Performance Space & Sidewals
Agency Project Name
JCAL JPAC Outdoor Space
Agency Project Description
This project seeks to re-imagine the entire outdoor space at the Jamaica Performing Arts Center (JPAC) to annihilate and minimize further hazardous issues as we respond to the needs of artists and the community.
Current Phase
Design
Current Phase Start
2023-09-13T00:00:00.000
Forecast Current Phase End
2024-11-14T00:00:00.000
Forecast Completion
2026-09-11T00:00:00.000
Actual Design Start
2023-09-13T00:00:00.000
Borough
Queens
Community Board
Queens 12
Budget Line
PV-0467, PV-0502, PV-D502, PV-Q502
Ten Year Plan Category
ESSENTIAL RECONSTRUCTION OF FACILITIES
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DEP
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DEP
Pid
4372
Fms Id
HED593
Total Budget
14981000.00
Spend To Date
13280.40
Spend To Date 1
0.0008
Fms Project Name
Dist WM installation at E 142 St & Southern Blvd, the BX
Agency Project Name
This project calls for combined sewer replacement and extension and water main replacement in East 142nd Street and Southern Boulevard (see design scope).
Agency Project Description
This project will install approximately 1,800 linear feet of distribution water main, 500 linear feetof trunk water main, and 1,165 linear feet of combined sewer in East 142nd Street and SouthernBlvd (see design scope). All distribution water main installation will be paid for by DEP and allsewer and trunk water main installation will be paid for by DOC
Current Phase
Pre-Design
Borough
Bronx
Community Board
Bronx 01
Budget Line
C-0114, WM-0001
Ten Year Plan Category
New Jail Facilities
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4373
Fms Id
HWQ788CS
Total Budget
18094851.00
Spend To Date
843859.56
Spend To Date 1
0.0466
Fms Project Name
Court Square Pedestrian Improvements
Agency Project Name
Court Square Pedestrian Improvements
Agency Project Description
This project will modernize the local street network in this dynamic outer-borough growth center to better meet the needs of its expanding residential population and workforce. The project scope is distributed across the following four sites in the vicinity of Court Square:A. Court Square West from Jackson Avenue to midblock (Construction of a shared street) B. Thomson Avenue from 44th Drive to Jackson Avenue (Full reconstruction, including additional public space on both the east and west sidewalks, and a raised crosswalk at the intersection with Court Square East)C. Pearson Street at Jackson Avenue (New pedestrian crossing and new curb extension for receiving ramp)D. Jackson Avenue from Court Square West to Thomson Avenue (Sidewalk reconstruction using standard materials, to eliminate the distinctive pavers along north side of Court Square Park).
Current Phase
Design
Current Phase Start
2022-08-08T00:00:00.000
Forecast Current Phase End
2024-08-22T00:00:00.000
Forecast Completion
2028-04-19T00:00:00.000
Actual Design Start
2022-08-08T00:00:00.000
Borough
Queens
Community Board
Queens
Budget Line
HW-0001Q
Ten Year Plan Category
PRIMARY STREET RECONSTRUCTION
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DEP
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DEP
Pid
4374
Fms Id
QED-1056
Total Budget
19458000.00
Spend To Date
482128.43
Spend To Date 1
0.0247
Fms Project Name
Dist WM work in 43rd Ave btwn National St & 104 St, QNS
Agency Project Name
Distribution Water Main replacement work in 43rd Avenue between National Street and 104th Street, as well as other locations listed in Page 3 of the attached CPI. Borough of Queens.
Agency Project Description
This project will replace a total of 14,350 linear feet of distribution water main in various locations listed in Page 3. Borough of Queens.
Current Phase
Construction Procurement
Current Phase Start
2023-08-17T00:00:00.000
Forecast Current Phase End
2024-07-16T00:00:00.000
Forecast Completion
2026-07-15T00:00:00.000
Actual Design Start
2021-10-18T00:00:00.000
Actual Design End
2023-08-17T00:00:00.000
Actual Construction
2023-08-17T00:00:00.000
Borough
Queens
Community Board
Queens
Budget Line
WM-0001
Ten Year Plan Category
AUGMENTATION OF WATER SUPPLY SYSTEMS
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DEP
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DEP
Pid
4375
Fms Id
QED-1055
Total Budget
15604375.05
Spend To Date
943944.21
Spend To Date 1
0.0604
Fms Project Name
Dist. WM work in Jay Ave btwn Borden Ave & 66th St, QNS
Agency Project Name
Distribution Water Main work in Jay Avenue between Borden Avenue and 66th Street, as well as other locations listed in Page 3 of the attached CPI. Borough of Queens.
Agency Project Description
This project will replace a total of 8,850 linear feet of distrubution water main in various locations listed in Page 3. Borough of Queens.No sewer work is included under this project.
Current Phase
Construction
Current Phase Start
2023-03-20T00:00:00.000
Forecast Current Phase End
2024-09-14T00:00:00.000
Forecast Completion
2024-09-14T00:00:00.000
Actual Design Start
2021-03-12T00:00:00.000
Actual Design End
2022-09-07T00:00:00.000
Actual Construction
2022-09-07T00:00:00.000
Actual Construction 1
2023-03-20T00:00:00.000
Actual Construction Start
2023-03-20T00:00:00.000
Borough
Queens
Community Board
Queens
Budget Line
WM-0001
Ten Year Plan Category
AUGMENTATION OF WATER SUPPLY SYSTEMS
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4376
Fms Id
HWX404
Total Budget
8651751.00
Spend To Date
807884.81
Spend To Date 1
0.0933
Fms Project Name
Southern Bronx Multi-Site Safety Improvements
Agency Project Name
Southern Bronx Multi-Site Safety Improvements
Agency Project Description
This Vision Zero capital project will construct pedestrian safety-focused geometric improvements at threeintersections in the southern Bronx. The project scope includes two bus bulbs on Westchester Avenue below the Prospect Avenue 2/5 subway station, four additional curb extensions, and streetscape improvements. All three locations in this capital project have received successful operational treatments introduced via StreetImprovement Projects (SIPs). Capital construction will permanently improve safety conditions at theseintersections for all street users by shortening crossing distances, calming traffic, increasing pedestrian visibility, and controlling vehicle turning movements.
Current Phase
Design
Current Phase Start
2021-10-06T00:00:00.000
Forecast Current Phase End
2024-11-05T00:00:00.000
Forecast Completion
2026-11-29T00:00:00.000
Actual Design Start
2021-10-06T00:00:00.000
Borough
Bronx
Community Board
Bronx
Budget Line
HW-0001X, HW-D105
Ten Year Plan Category
PRIMARY STREET RECONSTRUCTION
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4377
Fms Id
HWX406
Total Budget
12567779.00
Spend To Date
627501.20
Spend To Date 1
0.0499
Fms Project Name
Northwest Bronx School Safety Improvements, SEX002274
Agency Project Name
Northwest Bronx School Safety Improvements
Agency Project Description
This Vision Zero capital project will improve pedestrian safety and accessibility near two schools in the northwest Bronx. In Riverdale, adjacent to the Salanter Akiba Riverdale (SAR) Academy, and in the vicinity of the Judith K. Weiss Woodlawn School (P.S. 19)
Current Phase
Design
Current Phase Start
2021-09-29T00:00:00.000
Forecast Current Phase End
2024-10-01T00:00:00.000
Forecast Completion
2027-09-14T00:00:00.000
Actual Design Start
2021-09-29T00:00:00.000
Borough
Bronx
Community Board
Bronx
Budget Line
HW-0061, HW-0988, HW-D105
Ten Year Plan Category
PRIMARY STREET RECONSTRUCTION
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4377
Fms Id
SEX002274
Total Budget
2225000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
Recon W254 St btwn Railroad Terrace& Riverdale Av, BX HWX406
Agency Project Name
Northwest Bronx School Safety Improvements
Agency Project Description
This Vision Zero capital project will improve pedestrian safety and accessibility near two schools in the northwest Bronx. In Riverdale, adjacent to the Salanter Akiba Riverdale (SAR) Academy, and in the vicinity of the Judith K. Weiss Woodlawn School (P.S. 19)
Current Phase
Design
Current Phase Start
2021-09-29T00:00:00.000
Forecast Current Phase End
2024-10-01T00:00:00.000
Forecast Completion
2027-09-14T00:00:00.000
Actual Design Start
2021-09-29T00:00:00.000
Borough
Bronx
Community Board
Bronx 08
Budget Line
SE-0002X, WM-0001
Ten Year Plan Category
REPLACEMENT OR AUGMENTATION OF EXISTING SYSTEMS
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DCLA
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DCLA
Pid
4378
Fms Id
PV411ITC2
Total Budget
4297756.75
Spend To Date
2750291.22
Spend To Date 1
0.6399
Fms Project Name
FAB - ITC 64 E. Fourth Street Buillding Renovation Phase 2
Agency Project Name
64 E. Fourth Street Buillding Renovation
Agency Project Description
To construct a new façade and renovate the lobby of the Choicirciati Cultural Center to maximize openness and circulation.
Current Phase
Construction
Current Phase Start
2022-03-01T00:00:00.000
Forecast Current Phase End
2024-02-29T00:00:00.000
Forecast Completion
2024-02-29T00:00:00.000
Actual Design Start
2015-04-24T00:00:00.000
Actual Design End
2019-06-03T00:00:00.000
Actual Construction
2019-06-03T00:00:00.000
Actual Construction 1
2022-03-01T00:00:00.000
Actual Construction Start
2022-03-01T00:00:00.000
Borough
Manhattan
Community Board
Manhattan 03
Budget Line
PV-0467, PV-0N411
Ten Year Plan Category
ESSENTIAL RECONSTRUCTION OF FACILITIES
Agency Data Date
2024-01-04T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: NYPD
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
NYPD
Pid
4379
Fms Id
PO79FDBNX
Total Budget
2873501.00
Spend To Date
2169803.41
Spend To Date 1
0.7551
Fms Project Name
BRONX FRONT DESK REPLACEMENT 42ND, 44TH, 46TH, 108TH
Agency Project Name
NYPD: REPLACEMENT OF FRONT DESKS/ BRONX PRECINCTS
Agency Project Description
TO PROVIDE FOR THE FRONT DESK REPLACEMENT AT THE 42ND, 44TH, 46TH AND 108TH PCT IN THE BRONX AND QUEENS.
Current Phase
Construction
Current Phase Start
2021-08-16T00:00:00.000
Forecast Current Phase End
2024-02-29T00:00:00.000
Forecast Completion
2024-02-29T00:00:00.000
Actual Design Start
2016-10-06T00:00:00.000
Actual Design End
2019-06-25T00:00:00.000
Actual Construction
2019-06-25T00:00:00.000
Actual Construction 1
2021-08-16T00:00:00.000
Actual Construction Start
2021-08-16T00:00:00.000
Borough
Bronx
Community Board
Bronx
Budget Line
PO-0079
Ten Year Plan Category
POLICE FACILITIES
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: NYPD
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
NYPD
Pid
4380
Fms Id
PO79SHOPR
Total Budget
9163300.00
Spend To Date
782144.66
Spend To Date 1
0.0853
Fms Project Name
SERVICE SHOP #6 ROOF RENOVATION
Agency Project Name
Service Shop #6/72 PCT151 30th Street. Brooklyn NY
Agency Project Description
TO PROVIDE LABOR AND MATERIALS FOR THE SERVICE SHOP #6 ROOF RENOVATION AND FACADE REHABILITATION, LOCATED 151 30TH STREET BROOKLYN NY
Current Phase
Design
Current Phase Start
2018-01-03T00:00:00.000
Forecast Current Phase End
2024-03-30T00:00:00.000
Forecast Completion
2026-07-15T00:00:00.000
Actual Design Start
2018-01-03T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn
Budget Line
PO-0079
Ten Year Plan Category
POLICE FACILITIES
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DCLA
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DCLA
Pid
4381
Fms Id
PV467POPP
Total Budget
8786685.27
Spend To Date
1619651.24
Spend To Date 1
0.1843
Fms Project Name
POP - Poppenhusen Institute Window Restoration/Archive Stor.
Agency Project Name
Poppenhusen Institute Window/Façade Restoration
Agency Project Description
To restore the exterior façade of the Poppenhusen Institute as well as replacing all the windows on all sides of the façade.
Current Phase
Construction
Current Phase Start
2023-03-29T00:00:00.000
Forecast Current Phase End
2024-09-18T00:00:00.000
Forecast Completion
2024-09-18T00:00:00.000
Actual Design Start
2011-09-26T00:00:00.000
Actual Design End
2021-12-10T00:00:00.000
Actual Construction
2021-12-10T00:00:00.000
Actual Construction 1
2023-03-29T00:00:00.000
Actual Construction Start
2023-03-29T00:00:00.000
Borough
Queens
Community Board
Queens
Budget Line
PV-0467, PV-0N332, PV-DN332, PV-QN332
Ten Year Plan Category
ESSENTIAL RECONSTRUCTION OF FACILITIES
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4382
Fms Id
HWQ121B3
Total Budget
39530806.94
Spend To Date
3563336.83
Spend To Date 1
0.0901
Fms Project Name
RECONSTRUCTION OF SOUTH JAMAICA AREA (SEQ200562)
Agency Project Name
RECONSTRUCTION OF SOUTH JAMAICA AREA (SEQ200562)
Agency Project Description
Total reconstruction of two street grids in South Jamaica approximately bounded by Sutphin Boulevard, 109th Avenue, 155th Street and Linden Boulevard, and by 157th Street, 111th Avenue, Beddell Street and 116th Avenue.
Current Phase
Design
Current Phase Start
2014-02-04T00:00:00.000
Forecast Current Phase End
2024-10-31T00:00:00.000
Forecast Completion
2027-06-24T00:00:00.000
Actual Design Start
2014-02-04T00:00:00.000
Borough
Queens
Community Board
Queens 12
Budget Line
HW-0001Q, HW-0061, HW-0121, HW-0200, HW-0200, HW-0944, TF-0002, TF-0502
Ten Year Plan Category
SIDEWALK RECONSTRUCTION
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4382
Fms Id
SEQ200562
Total Budget
17865265.00
Spend To Date
362464.54
Spend To Date 1
0.0202
Fms Project Name
SEQ - Storm Sewer & WM Work in 158th Street (HWQ121B3)
Agency Project Name
RECONSTRUCTION OF SOUTH JAMAICA AREA (SEQ200562)
Agency Project Description
Total reconstruction of two street grids in South Jamaica approximately bounded by Sutphin Boulevard, 109th Avenue, 155th Street and Linden Boulevard, and by 157th Street, 111th Avenue, Beddell Street and 116th Avenue.
Current Phase
Design
Current Phase Start
2014-02-04T00:00:00.000
Forecast Current Phase End
2024-10-31T00:00:00.000
Forecast Completion
2027-06-24T00:00:00.000
Actual Design Start
2014-02-04T00:00:00.000
Borough
Queens
Community Board
Queens 12
Budget Line
EP-0007, SE-0002Q, SE-0200Q, SE-1000, WM-0001
Ten Year Plan Category
UTILITY RELOCATION FOR SE AND WM PROJECTS
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4383
Fms Id
HWR00511
Total Budget
41528351.52
Spend To Date
1784740.65
Spend To Date 1
0.0429
Fms Project Name
Travis Avenue Widening, SER200322
Agency Project Name
TRAVIS AVENUE WIDENING
Agency Project Description
TRAVIS AVENUE WIDENING
Current Phase
Design
Current Phase Start
2015-01-15T00:00:00.000
Forecast Current Phase End
2025-07-11T00:00:00.000
Forecast Completion
2029-12-28T00:00:00.000
Actual Design Start
2015-01-15T00:00:00.000
Borough
Staten Island
Community Board
Staten Island, Staten Island 02
Budget Line
HW-0001R, HW-D104, HW-R005
Ten Year Plan Category
PRIMARY STREET RECONSTRUCTION
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4383
Fms Id
RED-372
Total Budget
150000.00
Spend To Date
150000.00
Spend To Date 1
1.00
Fms Project Name
WM, PART OF RECON TRAVIS AVE FORM PARK DR N TO DRAPER PL
Agency Project Name
TRAVIS AVENUE WIDENING
Agency Project Description
TRAVIS AVENUE WIDENING
Current Phase
Design
Current Phase Start
2015-01-15T00:00:00.000
Forecast Current Phase End
2025-07-11T00:00:00.000
Forecast Completion
2029-12-28T00:00:00.000
Actual Design Start
2015-01-15T00:00:00.000
Borough
Staten Island
Community Board
Staten Island 01
Budget Line
SE-0002R, WM-0001
Ten Year Plan Category
REPLACEMENT OR AUGMENTATION OF EXISTING SYSTEMS
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4383
Fms Id
SER200322
Total Budget
86273000.00
Spend To Date
62882.77
Spend To Date 1
0.0007
Fms Project Name
New Storm Sewers in Saxon Ave & Draper Pl, SI, HWR00511
Agency Project Name
TRAVIS AVENUE WIDENING
Agency Project Description
TRAVIS AVENUE WIDENING
Current Phase
Design
Current Phase Start
2015-01-15T00:00:00.000
Forecast Current Phase End
2025-07-11T00:00:00.000
Forecast Completion
2029-12-28T00:00:00.000
Actual Design Start
2015-01-15T00:00:00.000
Borough
Staten Island
Community Board
Staten Island 02
Budget Line
SE-0002R, SE-0200R, WM-0001, WM-0006
Ten Year Plan Category
TRUNK AND DISTRIBUTION MAIN REPLACEMENT
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4384
Fms Id
HWTRK1
Total Budget
26931831.45
Spend To Date
2730136.67
Spend To Date 1
0.1013
Fms Project Name
Trench Restoration - Brooklyn
Agency Project Name
TRENCH RESTORATION BROOKLYN
Agency Project Description
Trench Restoration in The Borough Of Brooklyn including Full Street Reconstruction
Current Phase
Design
Current Phase Start
2018-06-05T00:00:00.000
Forecast Current Phase End
2024-12-31T00:00:00.000
Forecast Completion
2027-09-29T00:00:00.000
Actual Design Start
2018-06-05T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn
Budget Line
HW-0001K, HW-D101, HW-K005, TF-0002
Ten Year Plan Category
TRAFFIC WORK IN CONJUNCTION WITH HIGHWAY RECONSTRUCTION
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4384
Fms Id
SEK20076
Total Budget
4987000.00
Spend To Date
47867.02
Spend To Date 1
0.0095
Fms Project Name
Replace deficient combined sewers and WM in East 80 St
Agency Project Name
TRENCH RESTORATION BROOKLYN
Agency Project Description
Trench Restoration in The Borough Of Brooklyn including Full Street Reconstruction
Current Phase
Design
Current Phase Start
2018-06-05T00:00:00.000
Forecast Current Phase End
2024-12-31T00:00:00.000
Forecast Completion
2027-09-29T00:00:00.000
Actual Design Start
2018-06-05T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn
Budget Line
SE-0002K, WM-0001
Ten Year Plan Category
REPLACEMENT OR AUGMENTATION OF EXISTING SYSTEMS
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4385
Fms Id
HWTRQX1
Total Budget
17273299.75
Spend To Date
4373101.71
Spend To Date 1
0.2531
Fms Project Name
Trench Restoration - Queens and Bronx (SEX002271)
Agency Project Name
TRENCH RESTORATION QUEENS & THE BRONX
Agency Project Description
TRENCH RESTORATION, QUEENS & THE BRONX. INCLUDES RESTORATION OF TRENCHES, ROADWAY RECONSTRUCTION, REPLACE CURBS AND ADJACENT SIDEWALK FLAGS WHERE CONDITION IS POOR, INSTALL ACCESSIBLE PEDESTRIAN SYSTEMS AT SIGNALIZED INTERSECTIONS, ETC.
Current Phase
Construction
Current Phase Start
2022-10-17T00:00:00.000
Forecast Current Phase End
2024-10-15T00:00:00.000
Forecast Completion
2024-10-15T00:00:00.000
Actual Design Start
2018-04-23T00:00:00.000
Actual Design End
2022-01-26T00:00:00.000
Actual Construction
2022-01-26T00:00:00.000
Actual Construction 1
2022-10-17T00:00:00.000
Actual Construction Start
2022-10-17T00:00:00.000
Borough
Citywide
Community Board
Citywide
Budget Line
HW-0001, HW-0200, HW-0944, TF-0002, TF-0502
Ten Year Plan Category
SIDEWALK RECONSTRUCTION
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4385
Fms Id
SEX002271
Total Budget
3710404.69
Spend To Date
242686.41
Spend To Date 1
0.0654
Fms Project Name
Upgrade combined sewer Franklin ave- other Locs HWTRQX1
Agency Project Name
TRENCH RESTORATION QUEENS & THE BRONX
Agency Project Description
TRENCH RESTORATION, QUEENS & THE BRONX. INCLUDES RESTORATION OF TRENCHES, ROADWAY RECONSTRUCTION, REPLACE CURBS AND ADJACENT SIDEWALK FLAGS WHERE CONDITION IS POOR, INSTALL ACCESSIBLE PEDESTRIAN SYSTEMS AT SIGNALIZED INTERSECTIONS, ETC.
Current Phase
Construction
Current Phase Start
2022-10-17T00:00:00.000
Forecast Current Phase End
2024-10-15T00:00:00.000
Forecast Completion
2024-10-15T00:00:00.000
Actual Design Start
2018-04-23T00:00:00.000
Actual Design End
2022-01-26T00:00:00.000
Actual Construction
2022-01-26T00:00:00.000
Actual Construction 1
2022-10-17T00:00:00.000
Actual Construction Start
2022-10-17T00:00:00.000
Borough
Citywide
Community Board
Citywide
Budget Line
SE-0002Q, SE-0002X
Ten Year Plan Category
REPLACEMENT OR AUGMENTATION OF EXISTING SYSTEMS
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DEP
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DEP
Pid
4386
Fms Id
MED-607
Total Budget
53107576.62
Spend To Date
31208153.28
Spend To Date 1
0.5876
Fms Project Name
TRUNK MAIN CONN TO SHAFT 32B IN 2ND AVE. INTER. OF E. 35ST.
Agency Project Name
TRUNK WATER MAIN in 2nd Ave. ( SHAFT 32B)
Agency Project Description
Trunk and Distribution Main Connection to shaft 32B in 2nd Ave., etc., together with all work incidental thereto, Borough of Manhattan.2nd Avenue from East 33rd Street to East 37th Street
Current Phase
Construction
Current Phase Start
2018-06-04T00:00:00.000
Forecast Current Phase End
2025-01-23T00:00:00.000
Forecast Completion
2025-01-23T00:00:00.000
Actual Design Start
2013-09-30T00:00:00.000
Actual Design End
2015-08-27T00:00:00.000
Actual Construction
2015-08-27T00:00:00.000
Actual Construction 1
2018-06-04T00:00:00.000
Actual Construction Start
2018-06-04T00:00:00.000
Borough
Manhattan
Community Board
Manhattan 06
Budget Line
SE-0002M, TF-0002, TF-0502, WM-0001, WM-0006
Ten Year Plan Category
TRUNK AND DISTRIBUTION MAIN REPLACEMENT
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DEP
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DEP
Pid
4387
Fms Id
BED-778A
Total Budget
17101611.91
Spend To Date
11094659.55
Spend To Date 1
0.6487
Fms Project Name
Trunk & Dist WM Rep in Atlantic Ave b/t Carlton & Portland
Agency Project Name
REPLACEMENT OF TRUNK WATER MAINS IN ATLANTIC AVE
Agency Project Description
Trunk and Distribution Water Mains Replacement in Atlantic Avenue between Carlton Avenue and Portland Avenue in the Borough of Brooklyn.Water Main (WM-6) in:1. Atlantic Avenue from Carlton Avenue to South Portland Avenue.2. Intersection of Atlantic Avenue and Carlton Avenue.Water Main(WM -1) in:1. Atlantic Avenue(SS) from Carlton Avenue to South Portland Avenue2. Intersection of Atlantic Avenue and Carlton Avenue3. Intersection of Atlantic Avenue and Cumberland Street.
Current Phase
(Completed)
Actual Design Start
2013-02-19T00:00:00.000
Actual Design End
2019-02-06T00:00:00.000
Actual Construction
2019-02-06T00:00:00.000
Actual Construction 1
2020-03-30T00:00:00.000
Actual Construction Start
2020-03-30T00:00:00.000
Actual Construction End
2023-05-31T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn 02
Budget Line
WM-0001, WM-0006
Ten Year Plan Category
TRUNK AND DISTRIBUTION MAIN REPLACEMENT
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DEP
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DEP
Pid
4388
Fms Id
BED-776
Total Budget
91097074.19
Spend To Date
32905802.29
Spend To Date 1
0.3612
Fms Project Name
WM REPLMT EAST NEW YORK AVE B/T HOWARD AV & PACIFIC ST, ETC
Agency Project Name
WM REPLMT EAST NEW YORK AVE
Agency Project Description
Trunk Water Main replacement in East New York Avenue between Howard Avenue and Pacific Street; Jamaica Avenue between Herkimer Street and Vermont Street; and Atlantic Avenue between Van Sinderen Avenue and Pennsylvania Avenue.
Current Phase
Construction
Current Phase Start
2021-03-15T00:00:00.000
Forecast Current Phase End
2024-09-09T00:00:00.000
Forecast Completion
2024-09-09T00:00:00.000
Actual Design Start
2015-02-16T00:00:00.000
Actual Design End
2019-12-06T00:00:00.000
Actual Construction
2019-12-06T00:00:00.000
Actual Construction 1
2021-03-15T00:00:00.000
Actual Construction Start
2021-03-15T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn 05, Brooklyn 16
Budget Line
SE-0002K, WM-0001, WM-0006
Ten Year Plan Category
TRUNK AND DISTRIBUTION MAIN REPLACEMENT
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DEP
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DEP
Pid
4389
Fms Id
SEK002380
Total Budget
14586024.18
Spend To Date
5141859.57
Spend To Date 1
0.3525
Fms Project Name
Combined relief sewer & WM replac. at 7ST B/T 3 & 4 AV, BKL
Agency Project Name
COMBINED SEWER AND CHAMBERS IN 7TH STREET, BK
Agency Project Description
Trunk Water Main replacement in: 1. East New York Avenue between Howard Avenue and Pacific Street.2. Jamaica Avenue between Herkimer Street and Vermont Street.3. Atlantic Avenue between Van Sinderen Avenue and Pennsylvania Avenue.
Current Phase
Construction
Current Phase Start
2021-04-12T00:00:00.000
Forecast Current Phase End
2024-05-10T00:00:00.000
Forecast Completion
2024-05-10T00:00:00.000
Actual Design Start
2015-09-30T00:00:00.000
Actual Design End
2019-06-26T00:00:00.000
Actual Construction
2019-06-26T00:00:00.000
Actual Construction 1
2021-04-12T00:00:00.000
Actual Construction Start
2021-04-12T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn 06
Budget Line
SE-0200K, WM-0001
Ten Year Plan Category
REPLACEMENT OR AUGMENTATION OF EXISTING SYSTEMS
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4390
Fms Id
HWQ1193
Total Budget
11286604.99
Spend To Date
3041683.15
Spend To Date 1
0.2694
Fms Project Name
Union Turnpike Curb Repair
Agency Project Name
UNION TURNPIKE CENTER MEDIAN REPLACEMENT
Agency Project Description
Union Turnpike Center Median Replacement from Hollis Court Blvd to 226th Street, Borough of Queens
Current Phase
Construction
Current Phase Start
2022-08-22T00:00:00.000
Forecast Current Phase End
2024-08-20T00:00:00.000
Forecast Completion
2024-08-20T00:00:00.000
Actual Design Start
2019-05-23T00:00:00.000
Actual Design End
2021-11-08T00:00:00.000
Actual Construction
2021-11-08T00:00:00.000
Actual Construction 1
2022-08-22T00:00:00.000
Actual Construction Start
2022-08-22T00:00:00.000
Borough
Queens
Community Board
Queens
Budget Line
HW-0001Q
Ten Year Plan Category
PRIMARY STREET RECONSTRUCTION
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DOHMH
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DOHMH
Pid
4391
Fms Id
HL82MANAT
Total Budget
9071270.31
Spend To Date
7368973.85
Spend To Date 1
0.8123
Fms Project Name
Manhattan Animal Care Center Upgrade
Agency Project Name
Manhattan Pet Adoption Center
Agency Project Description
Upgrade existing garage to an Animal Adoption Center. The Scope of work consists of interior and exterior renovation, including exterior metal cladding, masonry restoration, storefront system, HVAC, fire protection, BMS, electric/plumbing, skylights, roof, windows, doors, lighting, interior partitions, finishes, sidewalk replacement, and egress path at rear yard.
Current Phase
Construction
Current Phase Start
2021-04-12T00:00:00.000
Forecast Current Phase End
2024-02-07T00:00:00.000
Forecast Completion
2024-02-07T00:00:00.000
Actual Design Start
2016-10-27T00:00:00.000
Actual Design End
2019-12-17T00:00:00.000
Actual Construction
2019-12-17T00:00:00.000
Actual Construction 1
2021-04-12T00:00:00.000
Actual Construction Start
2021-04-12T00:00:00.000
Borough
Manhattan
Community Board
Manhattan
Budget Line
HL-0082
Ten Year Plan Category
ANIMAL CARE
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4392
Fms Id
HWPR20KC
Total Budget
9039000.00
Spend To Date
920000.00
Spend To Date 1
0.1017
Fms Project Name
Non-Standard Upgrades Ped Ramp - Brooklyn
Agency Project Name
Complex Upgrades Ped Ramps - Brooklyn
Agency Project Description
Upgrade of Complex pedestrian ramps in the Borough of Brooklyn.
Current Phase
Design
Current Phase Start
2020-01-28T00:00:00.000
Forecast Current Phase End
2024-05-03T00:00:00.000
Forecast Completion
2027-02-04T00:00:00.000
Actual Design Start
2020-01-28T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn
Budget Line
HW-0200, HW-0944, TF-0001, TF-0002
Ten Year Plan Category
TRAFFIC WORK IN CONJUNCTION WITH HIGHWAY RECONSTRUCTION
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4393
Fms Id
HWPR20MKL
Total Budget
8698000.00
Spend To Date
1355000.00
Spend To Date 1
0.1557
Fms Project Name
Non-Standard Upgrades Ped Ramp - Manhattan & Brooklyn
Agency Project Name
COMPLEX UPGRADES PED RAMPS - LANDMARK IN MANHATTAN AND BROOKLYN
Agency Project Description
Upgrade of pedestrian ramps at 41 complex corners in the boroughs of Manhattan and Brooklyn.
Current Phase
Design
Current Phase Start
2020-01-28T00:00:00.000
Forecast Current Phase End
2024-02-29T00:00:00.000
Forecast Completion
2026-09-27T00:00:00.000
Actual Design Start
2020-01-28T00:00:00.000
Borough
Citywide
Community Board
Citywide
Budget Line
HW-0200, HW-0944, TF-0001, TF-0002
Ten Year Plan Category
TRAFFIC WORK IN CONJUNCTION WITH HIGHWAY RECONSTRUCTION
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4394
Fms Id
HWPR20KMC
Total Budget
10039000.00
Spend To Date
1281645.05
Spend To Date 1
0.1276
Fms Project Name
Non-Standard Upgrades Ped Ramp - Manhattan & Brooklyn
Agency Project Name
COMPLEX UPGRADES PED RAMPS - BROOKLYN AND MANHATTAN
Agency Project Description
Upgrade of pedestrian ramps at 50 complex corners in the boroughs of Manhattan and Brooklyn.
Current Phase
Design
Current Phase Start
2020-01-28T00:00:00.000
Forecast Current Phase End
2024-02-15T00:00:00.000
Forecast Completion
2026-03-31T00:00:00.000
Actual Design Start
2020-01-28T00:00:00.000
Borough
Citywide
Community Board
Citywide
Budget Line
HW-0200, HW-0944, TF-0001, TF-0002
Ten Year Plan Category
TRAFFIC WORK IN CONJUNCTION WITH HIGHWAY RECONSTRUCTION
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4395
Fms Id
HWPR21XC
Total Budget
9136984.00
Spend To Date
301918.80
Spend To Date 1
0.033
Fms Project Name
FY23 Non-Standard Pedestrian Ramp Upgrades
Agency Project Name
Upgrades of pedestrian ramps at 51 non-standard locations in the Bronx.
Agency Project Description
Upgrades of pedestrian ramps at 51 non-standard locations in the Bronx.
Current Phase
Design
Current Phase Start
2022-09-07T00:00:00.000
Forecast Current Phase End
2024-08-26T00:00:00.000
Forecast Completion
2027-03-23T00:00:00.000
Actual Design Start
2022-09-07T00:00:00.000
Borough
Citywide
Community Board
Citywide
Budget Line
HW-0200
Ten Year Plan Category
PEDESTRIAN RAMP CONSTRUCTION
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4396
Fms Id
HWPR21KRC
Total Budget
8914942.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
FY23 Non-Standard Pedestrian Ramp Upgrades
Agency Project Name
Upgrading of pedestrian ramps at 51 non standard locations in Brooklyn and Staten Island.
Agency Project Description
Upgrading non-standard pedestrian ramps - Brooklyn and Staten Island
Current Phase
Design
Current Phase Start
2023-03-29T00:00:00.000
Forecast Current Phase End
2025-03-17T00:00:00.000
Forecast Completion
2026-10-12T00:00:00.000
Actual Design Start
2023-03-29T00:00:00.000
Borough
Citywide
Community Board
Citywide
Budget Line
HW-0200, HW-0944
Ten Year Plan Category
PRIMARY STREET RECONSTRUCTION
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4397
Fms Id
HWPR21QC
Total Budget
8841916.00
Spend To Date
84699.10
Spend To Date 1
0.0095
Fms Project Name
FY23 Non-Standard Pedestrian Ramp Upgrades
Agency Project Name
Upgrading of pedestrian ramps at 51 non-standard locations in Queens.
Agency Project Description
Upgrading of 51 pedestrian ramps in Queens.
Current Phase
Design
Current Phase Start
2023-03-16T00:00:00.000
Forecast Current Phase End
2025-03-04T00:00:00.000
Forecast Completion
2027-09-14T00:00:00.000
Actual Design Start
2023-03-16T00:00:00.000
Borough
Citywide
Community Board
Citywide
Budget Line
HW-0200, HW-0944
Ten Year Plan Category
PRIMARY STREET RECONSTRUCTION
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4398
Fms Id
HWPR21LMT
Total Budget
9515410.00
Spend To Date
193716.44
Spend To Date 1
0.0203
Fms Project Name
FY23 Non-Standard Pedestrian Ramp Upgrades
Agency Project Name
Upgrading pedestrian ramps at 52 non-standard landmarked locations in Manhattan.
Agency Project Description
Upgrading pedestrian ramps at 52 non-standard landmarked locations in Manhattan
Current Phase
Design
Current Phase Start
2022-12-05T00:00:00.000
Forecast Current Phase End
2024-10-05T00:00:00.000
Forecast Completion
2027-05-31T00:00:00.000
Actual Design Start
2022-12-05T00:00:00.000
Borough
Citywide
Community Board
Citywide
Budget Line
HW-0200, HW-0944
Ten Year Plan Category
PRIMARY STREET RECONSTRUCTION
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4399
Fms Id
HWPR21MTA
Total Budget
10904186.00
Spend To Date
132258.84
Spend To Date 1
0.0121
Fms Project Name
FY23 Non-Standard Pedestrian Ramp Upgrades
Agency Project Name
Upgrading pedestrian ramps at 61 non-standard locations in Manhattan.
Agency Project Description
Upgrading pedestrian ramps at 61 non-standard locations in Manhattan
Current Phase
Design
Current Phase Start
2023-02-13T00:00:00.000
Forecast Current Phase End
2025-02-01T00:00:00.000
Forecast Completion
2027-09-27T00:00:00.000
Actual Design Start
2023-02-13T00:00:00.000
Borough
Citywide
Community Board
Citywide
Budget Line
HW-0200, HW-0944
Ten Year Plan Category
PRIMARY STREET RECONSTRUCTION
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4400
Fms Id
NDF-IBZ
Total Budget
9099479.71
Spend To Date
1437834.82
Spend To Date 1
0.158
Fms Project Name
NDF - ENY IBZ Improvements, SEK002384
Agency Project Name
Van Sinderen Avenue Streetscape Improvements
Agency Project Description
Van Sinderen Avenue Streetscape Improvements.
Current Phase
Design
Current Phase Start
2018-06-08T00:00:00.000
Forecast Current Phase End
2024-10-16T00:00:00.000
Forecast Completion
2027-06-10T00:00:00.000
Actual Design Start
2018-06-08T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn
Budget Line
ED-0384, ED-DN605
Ten Year Plan Category
NEIGHBORHOOD REVITALIZATION
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4400
Fms Id
SEK002384
Total Budget
13154806.38
Spend To Date
507336.50
Spend To Date 1
0.0385
Fms Project Name
Combined SE rplcmt & dist WM Van Sinderen Av BK NDF-IBZ
Agency Project Name
Van Sinderen Avenue Streetscape Improvements
Agency Project Description
Van Sinderen Avenue Streetscape Improvements.
Current Phase
Design
Current Phase Start
2018-06-08T00:00:00.000
Forecast Current Phase End
2024-10-16T00:00:00.000
Forecast Completion
2027-06-10T00:00:00.000
Actual Design Start
2018-06-08T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn 05, Brooklyn 16
Budget Line
SE-0002K, WM-0001
Ten Year Plan Category
REPLACEMENT OR AUGMENTATION OF EXISTING SYSTEMS
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4401
Fms Id
HWQ1190A
Total Budget
131843295.60
Spend To Date
9757450.19
Spend To Date 1
0.074
Fms Project Name
Reconstruction of Queens Blvd Phase 1 (QED-1042A)
Agency Project Name
RECONSTRUCTION OF QUEENS BLVD - PHASE 1
Agency Project Description
Vision Zero - Queens Boulevard - Segment 1: Roosevelt Avenue to 73rd Street. Variety of safety and streetscape improvements including partial street reconstruction and resurfacing to address roadway conditions
Current Phase
Design
Current Phase Start
2016-08-11T00:00:00.000
Forecast Current Phase End
2024-01-30T00:00:00.000
Forecast Completion
2028-08-28T00:00:00.000
Actual Design Start
2016-08-11T00:00:00.000
Borough
Queens
Community Board
Queens
Budget Line
HW-0001Q, HW-0200, HW-0200, HW-D103, HW-Q001, TF-0002, TF-0002, TF-0502
Ten Year Plan Category
TRAFFIC WORK IN CONJUNCTION WITH HIGHWAY RECONSTRUCTION
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4401
Fms Id
QED-1042A
Total Budget
99443557.28
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
Watermain replacement & sewer repair on Queens Blvd-HWQ1190A
Agency Project Name
RECONSTRUCTION OF QUEENS BLVD - PHASE 1
Agency Project Description
Vision Zero - Queens Boulevard - Segment 1: Roosevelt Avenue to 73rd Street. Variety of safety and streetscape improvements including partial street reconstruction and resurfacing to address roadway conditions
Current Phase
Design
Current Phase Start
2016-08-11T00:00:00.000
Forecast Current Phase End
2024-01-30T00:00:00.000
Forecast Completion
2028-08-28T00:00:00.000
Actual Design Start
2016-08-11T00:00:00.000
Borough
Queens
Community Board
Queens 02
Budget Line
SE-0002Q, WM-0001, WM-0006
Ten Year Plan Category
TRUNK AND DISTRIBUTION MAIN REPLACEMENT
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4402
Fms Id
HWQ1190B
Total Budget
84291482.00
Spend To Date
1385539.95
Spend To Date 1
0.0164
Fms Project Name
Reconstruction of Queens Blvd Phase 2( QED-1042B)
Agency Project Name
RECONSTRUCTION OF QUEENS BLVD - PHASE 2
Agency Project Description
Vision Zero - Queens Boulevard - Segment 2: 73rd Street to Eliot Avenue. Variety of safety and streetscape improvements including partial street reconstruction and resurfacing to address roadway conditions
Current Phase
Design
Current Phase Start
2016-10-26T00:00:00.000
Forecast Current Phase End
2024-11-30T00:00:00.000
Forecast Completion
2030-08-31T00:00:00.000
Actual Design Start
2016-10-26T00:00:00.000
Borough
Queens
Community Board
Queens
Budget Line
HW-0001Q
Ten Year Plan Category
PRIMARY STREET RECONSTRUCTION
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4403
Fms Id
HWQ1190-C
Total Budget
98843642.00
Spend To Date
115426.76
Spend To Date 1
0.0011
Fms Project Name
Reconstruction of Queens Blvd Phase 3, QED-1042C
Agency Project Name
RECONSTRUCTION OF QUEENS BLVD - PHASE 3
Agency Project Description
Vision Zero - Queens Boulevard - Segment 3: Eliot Avenue to Yellowstone Boulevard. Variety of safety and streetscape improvements including partial street reconstruction and resurfacing to address roadway conditions.
Current Phase
Design
Current Phase Start
2018-04-26T00:00:00.000
Forecast Current Phase End
2027-11-30T00:00:00.000
Forecast Completion
2032-08-30T00:00:00.000
Actual Design Start
2018-04-26T00:00:00.000
Borough
Queens
Community Board
Queens
Budget Line
HW-0001Q, HW-D103
Ten Year Plan Category
PRIMARY STREET RECONSTRUCTION
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DEP
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DEP
Pid
4404
Fms Id
SER00201W
Total Budget
4712564.31
Spend To Date
4277388.72
Spend To Date 1
0.9076
Agency Project Name
VIT CLAY PIPE SEWERS - STATEN ISLAND
Agency Project Description
VIT CLAY PIPE SEWERS - STATEN ISLAND
Current Phase
Construction Procurement
Current Phase Start
2012-11-19T00:00:00.000
Actual Design Start
2012-02-09T00:00:00.000
Actual Design End
2012-11-19T00:00:00.000
Actual Construction
2012-11-19T00:00:00.000
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DEP
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DEP
Pid
4404
Fms Id
SER00201Z
Total Budget
7482540.07
Spend To Date
7143067.87
Spend To Date 1
0.9546
Agency Project Name
VIT CLAY PIPE SEWERS - STATEN ISLAND
Agency Project Description
VIT CLAY PIPE SEWERS - STATEN ISLAND
Current Phase
Construction Procurement
Current Phase Start
2015-09-29T00:00:00.000
Actual Design Start
2015-03-16T00:00:00.000
Actual Design End
2015-09-29T00:00:00.000
Actual Construction
2015-09-29T00:00:00.000
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DEP
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DEP
Pid
4405
Fms Id
SER0201ZA
Total Budget
10708987.56
Spend To Date
9981996.24
Spend To Date 1
0.9321
Agency Project Name
RECONSTRUCTION OF EXISTING SEWERS, STATEN ISLAND
Agency Project Description
VIT CLAY PIPE SEWERS - STATEN ISLAND
Current Phase
Construction Procurement
Current Phase Start
2017-10-16T00:00:00.000
Actual Design Start
2017-04-19T00:00:00.000
Actual Design End
2017-10-16T00:00:00.000
Actual Construction
2017-10-16T00:00:00.000
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DEP
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DEP
Pid
4405
Fms Id
SER0201ZB
Total Budget
10870000.00
Spend To Date
10489012.65
Spend To Date 1
0.9649
Agency Project Name
RECONSTRUCTION OF EXISTING SEWERS, STATEN ISLAND
Current Phase
Close-out
Actual Design Start
2018-09-24T00:00:00.000
Actual Design End
2018-12-21T00:00:00.000
Actual Construction
2018-12-21T00:00:00.000
Actual Construction 1
2020-06-22T00:00:00.000
Actual Construction Start
2020-06-22T00:00:00.000
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DEP
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DEP
Pid
4406
Fms Id
WM-LC-17
Total Budget
6857721.22
Spend To Date
2779190.79
Spend To Date 1
0.4052
Fms Project Name
Citywide Lining Contract for Water Mains
Agency Project Name
Water Main Lining Contract, Citywide
Agency Project Description
Water Main Lining Contract, Citywide
Current Phase
Construction
Current Phase Start
2017-12-04T00:00:00.000
Forecast Current Phase End
2024-03-15T00:00:00.000
Forecast Completion
2024-03-15T00:00:00.000
Actual Design Start
2016-08-04T00:00:00.000
Actual Design End
2016-12-22T00:00:00.000
Actual Construction
2016-12-22T00:00:00.000
Actual Construction 1
2017-12-04T00:00:00.000
Actual Construction Start
2017-12-04T00:00:00.000
Borough
Citywide
Community Board
Citywide
Budget Line
WM-0001
Ten Year Plan Category
AUGMENTATION OF WATER SUPPLY SYSTEMS
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DEP
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DEP
Pid
4407
Fms Id
QED-1027
Total Budget
41011436.25
Spend To Date
1435146.90
Spend To Date 1
0.0349
Fms Project Name
Replacement of Dist WM in 222nd St
Agency Project Name
WATER MAIN REPLACEMENT IN 222 STREET, QUEENS
Agency Project Description
WATER MAIN REPLACEMENT IN 222 STREET
Current Phase
Design
Current Phase Start
2023-08-02T00:00:00.000
Forecast Current Phase End
2025-12-29T00:00:00.000
Forecast Completion
2029-07-13T00:00:00.000
Actual Design Start
2023-08-02T00:00:00.000
Borough
Queens
Community Board
Queens 13
Budget Line
SE-0002Q, SE-0200Q, WM-0001
Ten Year Plan Category
TRUNK AND DISTRIBUTION MAIN REPLACEMENT
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DEP
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DEP
Pid
4408
Fms Id
MED682
Total Budget
6288000.00
Spend To Date
50000.00
Spend To Date 1
0.0079
Fms Project Name
WM work in Central Park W btwn W 81 & 85 Streets, MN
Agency Project Name
Water Main work in Central Park West between West 81st Street and West 85th Street and other locations
Agency Project Description
Water Main work in Central Park West between West 81st Street and West 85th Street and other locations, Borough of Manhattan
Current Phase
Design
Current Phase Start
2023-07-31T00:00:00.000
Forecast Current Phase End
2025-05-16T00:00:00.000
Forecast Completion
2028-04-10T00:00:00.000
Actual Design Start
2023-07-31T00:00:00.000
Borough
Manhattan
Community Board
Manhattan 07
Budget Line
WM-0001
Ten Year Plan Category
AUGMENTATION OF WATER SUPPLY SYSTEMS
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DEP
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DEP
Pid
4409
Fms Id
BED-819
Total Budget
46622894.45
Spend To Date
9210583.60
Spend To Date 1
0.1975
Fms Project Name
WM replacement in Oriental Blvd
Agency Project Name
WATERMAIN REPLACEMENT IN ORIENTAL BLVD, BROOKLYN
Agency Project Description
WATERMAIN REPLACEMENT IN ORIENTAL BLVD, BROOKLYN
Current Phase
Construction
Current Phase Start
2022-09-19T00:00:00.000
Forecast Current Phase End
2024-09-17T00:00:00.000
Forecast Completion
2024-09-17T00:00:00.000
Actual Design Start
2017-02-15T00:00:00.000
Actual Design End
2021-12-29T00:00:00.000
Actual Construction
2021-12-29T00:00:00.000
Actual Construction 1
2022-09-19T00:00:00.000
Actual Construction Start
2022-09-19T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn 15
Budget Line
F-0001, WM-0001, WM-0944
Ten Year Plan Category
TRUNK AND DISTRIBUTION MAIN REPLACEMENT
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202309
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4410
Fms Id
HWQ1182B
Total Budget
33623923.98
Spend To Date
15387083.69
Spend To Date 1
0.4576
Fms Project Name
Broad Channel Bulkheads - Phase II (SEQ200586)
Agency Project Name
BROAD CHANNEL BULKHEADS - PH II
Agency Project Description
West 14th Rd. from Cross Bay Blvd. to Dead end (water side)West 15th Rd. from Cross Bay Blvd. to Dead end (water side)West 16th Rd. from Cross Bay Blvd. to Dead end (water side)West 17th Rd. from Cross Bay Blvd. to Dead end (water side)
Current Phase
Construction
Current Phase Start
2020-06-15T00:00:00.000
Forecast Current Phase End
2024-06-14T00:00:00.000
Forecast Completion
2024-06-14T00:00:00.000
Actual Design Start
2015-06-01T00:00:00.000
Actual Design End
2019-06-21T00:00:00.000
Actual Construction
2019-06-21T00:00:00.000
Actual Construction 1
2020-06-15T00:00:00.000
Actual Construction Start
2020-06-15T00:00:00.000
Borough
Queens
Community Board
Queens
Budget Line
HW-0001Q, SE-0200Q, TF-0002, WM-0001
Ten Year Plan Category
TRUNK AND DISTRIBUTION MAIN REPLACEMENT
Agency Data Date
2024-02-16T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000