Capital Projects Dashboard - Citywide Budget and Schedule

All major capital infrastructure projects with a committed budget. Financial information and agency schedule details for each project are joined via FMS ID. Only projects in the design phase or later have project schedules displayed. This dataset is part of the Capital Projects Dashboard.

Note: Each row is uniquely identified by its Financial Management Service (FMS) ID. FMS ID is the unique ID that OMB uses for the FMS (Financial Information System). This ID can be universally joined with any OMB dataset that has the same field. The Capital Projects Dashboard is the result of joining OMB’s fiscal data with the agency’s schedule data. FMS IDs and agency projects don't always have a one-to-one relationship (i.e., one project schedule may correlate to multiple FMS IDs, and one FMS may correct to multiple projects with different schedules).

City Government Mayor's Office of Operations (OPS) Dataset fb86-vt7u 27 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2668
Fms Id
P-301VIE2
Total Budget
82152.91
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
VIETNAM VETERANS PLAZA RC M046-114M
Agency Project Name
Vietnam Veterans Plaza Reconstruction (Hurricane Sandy)
Agency Project Description
This project will reconstruct lighting and electrical components damaged by Hurricane Sandy at Vietnam Veterans Plaza.
Current Phase
(Completed)
Actual Design Start
2015-06-19T00:00:00.000
Actual Design End
2019-02-01T00:00:00.000
Actual Construction
2019-02-01T00:00:00.000
Actual Construction 1
2022-06-22T00:00:00.000
Actual Construction Start
2022-07-25T00:00:00.000
Actual Construction End
2023-07-21T00:00:00.000
Borough
Manhattan
Community Board
Manhattan
Budget Line
P-1018
Ten Year Plan Category
NEIGHBORHOOD PARKS AND PLAYGROUNDS
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2668
Fms Id
SANDY3-11
Total Budget
1926799.79
Spend To Date
525770.38
Spend To Date 1
0.2728
Fms Project Name
Vietnam Vet. Memorial Lighting (M046-114M)
Agency Project Name
Vietnam Veterans Plaza Reconstruction (Hurricane Sandy)
Agency Project Description
This project will reconstruct lighting and electrical components damaged by Hurricane Sandy at Vietnam Veterans Plaza.
Current Phase
(Completed)
Actual Design Start
2015-06-19T00:00:00.000
Actual Design End
2019-02-01T00:00:00.000
Actual Construction
2019-02-01T00:00:00.000
Actual Construction 1
2022-06-22T00:00:00.000
Actual Construction Start
2022-07-25T00:00:00.000
Actual Construction End
2023-07-21T00:00:00.000
Borough
Manhattan
Community Board
Manhattan
Budget Line
P-1018, P-I001
Ten Year Plan Category
NEIGHBORHOOD PARKS AND PLAYGROUNDS
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2669
Fms Id
P-2CIWALK
Total Budget
12039856.55
Spend To Date
575856.55
Spend To Date 1
0.0478
Fms Project Name
CONEY ISLAND BWALK - RC OF VARIOUS SEGMENT B169-220M
Agency Project Name
Coney Island Boardwalk Reconstruction
Agency Project Description
This project will reconstruct a portion of the Coney Island Boardwalk.
Current Phase
Construction Procurement
Current Phase Start
2023-09-28T00:00:00.000
Forecast Current Phase End
2024-09-27T00:00:00.000
Forecast Completion
2026-02-23T00:00:00.000
Actual Design Start
2021-02-22T00:00:00.000
Actual Design End
2023-09-28T00:00:00.000
Actual Construction
2023-09-28T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn
Budget Line
P-0007, P-1245, P-I001
Ten Year Plan Category
LARGE, MAJOR AND REGIONAL PARK RECONSTRUCTION
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2670
Fms Id
P-1PDSMRC
Total Budget
8766629.99
Spend To Date
2640099.53
Spend To Date 1
0.3011
Fms Project Name
PDF -St. Mary's Rec Ctr RC X045-115M
Agency Project Name
St. Mary's Park Recreation Center Reconstruction
Agency Project Description
This project will reconstruct St. Mary's Park Recreation Center.
Current Phase
Construction
Current Phase Start
2022-05-16T00:00:00.000
Forecast Current Phase End
2023-11-06T00:00:00.000
Forecast Completion
2025-04-18T00:00:00.000
Actual Design Start
2015-11-02T00:00:00.000
Actual Design End
2020-04-10T00:00:00.000
Actual Construction
2020-04-10T00:00:00.000
Actual Construction 1
2022-03-29T00:00:00.000
Actual Construction Start
2022-05-16T00:00:00.000
Borough
Bronx
Community Board
Bronx
Budget Line
P-1018
Ten Year Plan Category
MAJOR RECREATIONAL FACILITIES AND FACILITY RECONSTRUCTION
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2671
Fms Id
P-2PDSSRC
Total Budget
7936440.78
Spend To Date
669468.38
Spend To Date 1
0.0843
Fms Project Name
Sunset Pk Rec Ctr RC B087-115M
Agency Project Name
Sunset Park Bathhouse Reconstruction
Agency Project Description
This project will reconstruct the bathhouse in Sunset Park.
Current Phase
Construction
Current Phase Start
2023-09-25T00:00:00.000
Forecast Current Phase End
2025-03-22T00:00:00.000
Forecast Completion
2025-03-08T00:00:00.000
Actual Design Start
2015-11-05T00:00:00.000
Actual Design End
2021-09-23T00:00:00.000
Actual Construction
2021-09-23T00:00:00.000
Actual Construction 1
2023-04-19T00:00:00.000
Actual Construction Start
2023-09-25T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn
Budget Line
P-1018, P-I001
Ten Year Plan Category
MAJOR RECREATIONAL FACILITIES AND FACILITY RECONSTRUCTION
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2672
Fms Id
P-3PDHBRC
Total Budget
50725910.54
Spend To Date
2501167.04
Spend To Date 1
0.0493
Fms Project Name
Hansborough Rec Ctr M131-115M
Agency Project Name
Hansborough Recreation Center Reconstruction
Agency Project Description
This project will reconstruct the pool, entrance and interior spaces of the Hansborough Recreation Center.
Current Phase
Construction
Current Phase Start
2024-03-11T00:00:00.000
Forecast Current Phase End
2026-03-10T00:00:00.000
Forecast Completion
2026-03-10T00:00:00.000
Actual Design Start
2020-03-23T00:00:00.000
Actual Design End
2022-03-31T00:00:00.000
Actual Construction
2022-03-31T00:00:00.000
Actual Construction 1
2024-01-26T00:00:00.000
Actual Construction Start
2024-03-11T00:00:00.000
Borough
Manhattan
Community Board
Manhattan
Budget Line
P-0506, P-1008, P-1018, P-1250, P-D018
Ten Year Plan Category
MAJOR RECREATIONAL FACILITIES AND FACILITY RECONSTRUCTION
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2673
Fms Id
P-3PDTDRC
Total Budget
17630822.23
Spend To Date
6112427.89
Spend To Date 1
0.3466
Fms Project Name
Tony Dapolito Rec Ctr RC M103-115M
Agency Project Name
Tony Dapolito Recreation Center Stabilization
Agency Project Description
This project will stabilize the Tony Dapolito Recreation Center
Current Phase
Construction
Current Phase Start
2020-09-28T00:00:00.000
Forecast Current Phase End
2022-03-30T00:00:00.000
Forecast Completion
2024-04-19T00:00:00.000
Actual Design Start
2017-04-05T00:00:00.000
Actual Design End
2018-07-16T00:00:00.000
Actual Construction
2018-07-16T00:00:00.000
Actual Construction 1
2019-09-30T00:00:00.000
Actual Construction Start
2020-09-28T00:00:00.000
Borough
Manhattan
Community Board
Manhattan
Budget Line
P-0506, P-1018
Ten Year Plan Category
MAJOR RECREATIONAL FACILITIES AND FACILITY RECONSTRUCTION
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2674
Fms Id
P-4PDLBRC
Total Budget
23093270.75
Spend To Date
6139148.13
Spend To Date 1
0.2658
Fms Project Name
Lost Battalion Rec Ctr RC Q401-115M
Agency Project Name
Lost Battalion Hall Recreation Center Reconstruction
Agency Project Description
This project will reconstruct Lost Battalion Hall Recreation Center.
Current Phase
Construction
Current Phase Start
2022-07-19T00:00:00.000
Forecast Current Phase End
2024-01-09T00:00:00.000
Forecast Completion
2024-11-15T00:00:00.000
Actual Design Start
2017-10-06T00:00:00.000
Actual Design End
2020-04-09T00:00:00.000
Actual Construction
2020-04-09T00:00:00.000
Actual Construction 1
2022-03-25T00:00:00.000
Actual Construction Start
2022-07-19T00:00:00.000
Borough
Queens
Community Board
Queens
Budget Line
P-0245Q, P-0506, P-1018, P-D019
Ten Year Plan Category
MAJOR RECREATIONAL FACILITIES AND FACILITY RECONSTRUCTION
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2675
Fms Id
P-2PDBRC2
Total Budget
21306533.57
Spend To Date
5051950.73
Spend To Date 1
0.2371
Fms Project Name
Brownsville Rec Ctr RC B270-214M
Agency Project Name
Brownsville Recreation Center Reconstruction
Agency Project Description
This project will reconstruct the interior and infrastructure of Brownsville Recreation Center.
Current Phase
Construction
Current Phase Start
2022-03-14T00:00:00.000
Forecast Completion
2023-09-04T00:00:00.000
Actual Design Start
2016-05-17T00:00:00.000
Actual Design End
2017-08-24T00:00:00.000
Actual Construction
2017-08-24T00:00:00.000
Actual Construction 1
2022-01-06T00:00:00.000
Actual Construction Start
2022-03-14T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn
Budget Line
P-1018, P-I001
Ten Year Plan Category
MAJOR RECREATIONAL FACILITIES AND FACILITY RECONSTRUCTION
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2676
Fms Id
P-308MHM2
Total Budget
3535000.00
Spend To Date
263356.40
Spend To Date 1
0.0744
Fms Project Name
MERCHANT HOUSE MUSEUM- EAST FACADE & SHUTTER RESTO M318
Agency Project Name
Merchant's House Exterior Masonry and Stoop Reconstruction
Agency Project Description
This project will reconstruct the exterior masonry and stoop at the Merchant's House Museum.
Current Phase
Design
Current Phase Start
2022-05-13T00:00:00.000
Forecast Current Phase End
2023-05-31T00:00:00.000
Forecast Completion
2026-07-26T00:00:00.000
Actual Design Start
2022-05-13T00:00:00.000
Actual Design End
2023-06-29T00:00:00.000
Borough
Manhattan
Community Board
Manhattan, Manhattan 02
Budget Line
P-0245M, P-1018, P-1329, P-D018, P-I001, P-M245
Ten Year Plan Category
MAJOR RECREATIONAL FACILITIES AND FACILITY RECONSTRUCTION
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2677
Fms Id
P-306APMU
Total Budget
1781861.34
Spend To Date
219585.82
Spend To Date 1
0.1232
Fms Project Name
Albano Playground Handball Court Multi-use Conve M265-117M
Agency Project Name
Albano Playground Reconstruction
Agency Project Description
This project will reconstruct the play equipment, safety surfacing, handball courts, and asphalt multi-purpose play area and construct a new spray shower at Albano Playground.
Current Phase
Construction
Current Phase Start
2023-11-27T00:00:00.000
Forecast Current Phase End
2024-11-25T00:00:00.000
Forecast Completion
2024-11-25T00:00:00.000
Actual Design Start
2015-09-09T00:00:00.000
Actual Design End
2022-04-14T00:00:00.000
Actual Construction
2022-04-14T00:00:00.000
Actual Construction 1
2023-09-26T00:00:00.000
Actual Construction Start
2023-11-27T00:00:00.000
Borough
Manhattan
Community Board
Manhattan, Manhattan 06
Budget Line
P-D018, P-I001, P-M245
Ten Year Plan Category
NEIGHBORHOOD PARKS AND PLAYGROUNDS
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2678
Fms Id
P-503SNCS
Total Budget
7535557.70
Spend To Date
688200.25
Spend To Date 1
0.0913
Fms Project Name
Seaside Nature Pk CS construction R145-119M
Agency Project Name
Seaside Wildlife Nature Park Public Restroom Building Construction
Agency Project Description
This project will construct a public restroom building in Seaside Wildlife Nature Park
Current Phase
Construction
Current Phase Start
2023-07-17T00:00:00.000
Forecast Current Phase End
2025-01-06T00:00:00.000
Forecast Completion
2025-01-06T00:00:00.000
Actual Design Start
2018-12-07T00:00:00.000
Actual Design End
2020-06-30T00:00:00.000
Actual Construction
2020-06-30T00:00:00.000
Actual Construction 1
2023-02-23T00:00:00.000
Actual Construction Start
2023-07-17T00:00:00.000
Borough
Staten Island
Community Board
Staten Island, Staten Island 03
Budget Line
P-0245R, P-0505, P-I001
Ten Year Plan Category
NEIGHBORHOOD PARKS AND PLAYGROUNDS
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2679
Fms Id
P-415MEA2
Total Budget
4633643.28
Spend To Date
1350194.23
Spend To Date 1
0.2913
Fms Project Name
FMCP - MEADOW LAKE- PATHS Q099-215M
Agency Project Name
Flushing Meadows Corona Park Meadow Lake Northwest Area Reconstruction
Agency Project Description
This project will reconstruct the pedestrian and vehicle pathways in Flushing Meadow Park.
Current Phase
Construction
Current Phase Start
2022-12-05T00:00:00.000
Forecast Current Phase End
2023-12-04T00:00:00.000
Forecast Completion
2024-06-28T00:00:00.000
Actual Design Start
2019-06-13T00:00:00.000
Actual Design End
2020-10-15T00:00:00.000
Actual Construction
2020-10-15T00:00:00.000
Actual Construction 1
2022-09-20T00:00:00.000
Actual Construction Start
2022-12-05T00:00:00.000
Borough
Queens
Community Board
Queens, Queens 03, Queens 04, Queens 06, Queens 07, Queens 08
Budget Line
P-0013, P-I001
Ten Year Plan Category
LARGE, MAJOR AND REGIONAL PARK RECONSTRUCTION
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2680
Fms Id
P-409FPG3
Total Budget
3152821.20
Spend To Date
228288.23
Spend To Date 1
0.0724
Fms Project Name
FOREST PARK GREENHOUSES Q015-117MA1
Agency Project Name
Forest Park Greenhouse Palm House Reconstruction
Agency Project Description
This project will reconstruct the Palm House at the Forest Park Greenhouse.
Current Phase
Construction Procurement
Current Phase Start
2021-11-04T00:00:00.000
Forecast Current Phase End
2020-04-20T00:00:00.000
Forecast Completion
2026-03-26T00:00:00.000
Actual Design Start
2015-12-15T00:00:00.000
Actual Design End
2021-11-04T00:00:00.000
Actual Construction
2021-11-04T00:00:00.000
Borough
Queens
Community Board
Queens, Queens 05, Queens 06, Queens 09
Budget Line
P-0245Q, P-1018, P-D019, P-Q245
Ten Year Plan Category
LARGE, MAJOR AND REGIONAL PARK RECONSTRUCTION
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2680
Fms Id
SANDY4-21
Total Budget
278287.94
Spend To Date
16287.94
Spend To Date 1
0.0585
Fms Project Name
SANDY-FOREST PARK GREENHOUSE BROKEN GLASS REPLACEMENT
Agency Project Name
Forest Park Greenhouse Palm House Reconstruction
Agency Project Description
This project will reconstruct the Palm House at the Forest Park Greenhouse.
Current Phase
Construction Procurement
Current Phase Start
2021-11-04T00:00:00.000
Forecast Current Phase End
2020-04-20T00:00:00.000
Forecast Completion
2026-03-26T00:00:00.000
Actual Design Start
2015-12-15T00:00:00.000
Actual Design End
2021-11-04T00:00:00.000
Actual Construction
2021-11-04T00:00:00.000
Borough
Queens
Community Board
Queens
Budget Line
P-1018, P-I001
Ten Year Plan Category
LARGE, MAJOR AND REGIONAL PARK RECONSTRUCTION
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2681
Fms Id
P-218GOLF
Total Budget
2100352.50
Spend To Date
851102.93
Spend To Date 1
0.4052
Fms Project Name
BK Golf Alliance - Marine Pk. Golf Course - B057-119M
Agency Project Name
Marine Park Golf Course Path Reconstruction
Agency Project Description
This project will reconstruct the pavement, curbs, and drainage at the main entrance and areas adjacent to the clubhouse within Marine Park Golf Course.
Current Phase
(Completed)
Actual Design Start
2018-09-03T00:00:00.000
Actual Design End
2020-10-22T00:00:00.000
Actual Construction
2020-10-22T00:00:00.000
Actual Construction 1
2022-10-31T00:00:00.000
Actual Construction Start
2023-02-14T00:00:00.000
Actual Construction End
2023-10-31T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn 18, Brooklyn
Budget Line
P-D017, P-I001, P-K011
Ten Year Plan Category
LARGE, MAJOR AND REGIONAL PARK RECONSTRUCTION
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2682
Fms Id
P-102HNT2
Total Budget
418000.00
Spend To Date
68000.00
Spend To Date 1
0.1626
Fms Project Name
Hunts Point - Riverside Park - Dock Repair X336-119M
Agency Project Name
Hunts Point Riverside Park Dock Reconstruction
Agency Project Description
This project will reconstruct the dock in Hunts Point Riverside Park, including the piles, dock, gangway and pier.
Current Phase
Design
Current Phase Start
2019-05-23T00:00:00.000
Forecast Current Phase End
2020-08-28T00:00:00.000
Forecast Completion
2026-06-18T00:00:00.000
Actual Design Start
2019-05-23T00:00:00.000
Borough
Bronx
Community Board
Bronx, Bronx 02
Budget Line
P-D021
Ten Year Plan Category
NEIGHBORHOOD PARKS AND PLAYGROUNDS
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2683
Fms Id
P-1EDENPG
Total Budget
4690673.23
Spend To Date
1117351.57
Spend To Date 1
0.2382
Fms Project Name
Edenwald PLGD - basketball & handball crts (X165-116MA)
Agency Project Name
Edenwald Playground Basketball Courts and Mini Pool Reconstruction
Agency Project Description
This project will reconstruct the basketball courts, demolish the existing above-ground mini-pool and construct a new in-ground mini-pool at Edenwald Playground.
Current Phase
Construction
Current Phase Start
2022-11-14T00:00:00.000
Forecast Current Phase End
2024-02-12T00:00:00.000
Forecast Completion
2024-05-24T00:00:00.000
Actual Design Start
2015-10-07T00:00:00.000
Actual Design End
2020-07-01T00:00:00.000
Actual Construction
2020-07-01T00:00:00.000
Actual Construction 1
2022-08-25T00:00:00.000
Actual Construction Start
2022-11-14T00:00:00.000
Borough
Bronx
Community Board
Bronx, Bronx 12
Budget Line
P-0245X, P-I001, P-X245
Ten Year Plan Category
NEIGHBORHOOD PARKS AND PLAYGROUNDS
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2684
Fms Id
P-104HPRM
Total Budget
8070159.77
Spend To Date
509041.84
Spend To Date 1
0.063
Fms Project Name
Bridge Park-Highbridge Greenway promenade
Agency Project Name
Bridge Park Highbridge Greenway Promenade Construction
Agency Project Description
This project will construct a multi-modal pathway with lighting, a passive recreation area, green infrastructure, and shoreline restoration at Bridge Park.
Current Phase
Design
Current Phase Start
2019-06-04T00:00:00.000
Forecast Current Phase End
2020-12-01T00:00:00.000
Forecast Completion
2028-08-04T00:00:00.000
Actual Design Start
2019-06-04T00:00:00.000
Borough
Bronx
Community Board
Bronx, Bronx 04
Budget Line
P-0822, P-1018, P-D021, P-I001, P-X245
Ten Year Plan Category
NEIGHBORHOOD PARKS AND PLAYGROUNDS
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2685
Fms Id
NDF-DVDSO
Total Budget
11671930.39
Spend To Date
1929431.64
Spend To Date 1
0.1653
Fms Project Name
Neighborhood Dev. Fund-1801 Davidson X367-120M
Agency Project Name
Davidson Park Construction
Agency Project Description
This project will construct Davidson Park.
Current Phase
(Completed)
Actual Design Start
2019-12-03T00:00:00.000
Actual Design End
2021-01-21T00:00:00.000
Actual Construction
2021-01-21T00:00:00.000
Actual Construction 1
2022-10-28T00:00:00.000
Actual Construction Start
2022-11-07T00:00:00.000
Actual Construction End
2024-01-10T00:00:00.000
Borough
Bronx
Community Board
Bronx
Budget Line
ED-0384, P-I001
Ten Year Plan Category
NEIGHBORHOOD REVITALIZATION
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2686
Fms Id
P-413JH72
Total Budget
3627000.00
Spend To Date
262872.70
Spend To Date 1
0.0724
Fms Project Name
VIC HANSON/JHS 72 PLGD RC Q352
Agency Project Name
Rochdale Park Basketball Courts Reconstruction
Agency Project Description
This project will reconstruct the basketball courts at Rochdale Park.
Current Phase
Construction Procurement
Current Phase Start
2022-07-28T00:00:00.000
Forecast Current Phase End
2023-04-24T00:00:00.000
Forecast Completion
2025-09-24T00:00:00.000
Actual Design Start
2021-06-30T00:00:00.000
Actual Design End
2022-07-28T00:00:00.000
Actual Construction
2022-07-28T00:00:00.000
Borough
Queens
Community Board
Queens, Queens 13
Budget Line
P-D019, P-I001, P-Q245
Ten Year Plan Category
NEIGHBORHOOD PARKS AND PLAYGROUNDS
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2687
Fms Id
P-401SOC3
Total Budget
750000.00
Spend To Date
57831.82
Spend To Date 1
0.0771
Fms Project Name
SOCRATES SCULPTURE PARK -REPAIR TO SEAWALL
Agency Project Name
Socrates Sculpture Park Seawall Reconstruction (Hurricane Sandy)
Agency Project Description
This project will reconstruct a portion of the existing shoreline and upland path at Socrates Sculpture Park.
Current Phase
Design
Current Phase Start
2020-01-06T00:00:00.000
Forecast Current Phase End
2022-01-06T00:00:00.000
Forecast Completion
2025-05-04T00:00:00.000
Actual Design Start
2020-01-06T00:00:00.000
Actual Design End
2023-12-29T00:00:00.000
Borough
Queens
Community Board
Queens
Budget Line
P-Q245
Ten Year Plan Category
NEIGHBORHOOD PARKS AND PLAYGROUNDS
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2687
Fms Id
SANDY4-08
Total Budget
405287.00
Spend To Date
56795.31
Spend To Date 1
0.1401
Fms Project Name
PNP Socrates Sculpture Park
Agency Project Name
Socrates Sculpture Park Seawall Reconstruction (Hurricane Sandy)
Agency Project Description
This project will reconstruct a portion of the existing shoreline and upland path at Socrates Sculpture Park.
Current Phase
Design
Current Phase Start
2020-01-06T00:00:00.000
Forecast Current Phase End
2022-01-06T00:00:00.000
Forecast Completion
2025-05-04T00:00:00.000
Actual Design Start
2020-01-06T00:00:00.000
Actual Design End
2023-12-29T00:00:00.000
Borough
Queens
Community Board
Queens, Queens 01
Budget Line
P-1018
Ten Year Plan Category
NEIGHBORHOOD PARKS AND PLAYGROUNDS
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2688
Fms Id
P-108FTFR
Total Budget
4124360.21
Spend To Date
476113.29
Spend To Date 1
0.1154
Fms Project Name
Washington's Walk Fort Four Plgd comfort station- X038-118M
Agency Project Name
Washington's Walk Fort Four Playground Public Restroom Building Construction
Agency Project Description
This project will construct a public restroom building in Fort Four Playground at Washington's Walk.
Current Phase
Construction
Current Phase Start
2023-04-17T00:00:00.000
Forecast Current Phase End
2024-10-14T00:00:00.000
Forecast Completion
2024-10-14T00:00:00.000
Actual Design Start
2018-03-29T00:00:00.000
Actual Design End
2019-04-12T00:00:00.000
Actual Construction
2019-04-12T00:00:00.000
Actual Construction 1
2022-11-02T00:00:00.000
Actual Construction Start
2023-04-17T00:00:00.000
Borough
Bronx
Community Board
Bronx
Budget Line
P-0505, P-I001
Ten Year Plan Category
NEIGHBORHOOD PARKS AND PLAYGROUNDS
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2689
Fms Id
P-415PAVI
Total Budget
57222135.69
Spend To Date
19600441.47
Spend To Date 1
0.3425
Fms Project Name
FMCP - NYS PAVILION RC Q099-116M
Agency Project Name
New York State Pavilion Observation Towers Reconstruction - Phase 1
Agency Project Description
This project will reconstruct portions of the New York State Pavilion Observation Towers in Flushing Meadows Corona Park.
Current Phase
(Completed)
Actual Design Start
2015-09-21T00:00:00.000
Actual Design End
2018-04-11T00:00:00.000
Actual Construction
2018-04-11T00:00:00.000
Actual Construction 1
2019-07-02T00:00:00.000
Actual Construction Start
2019-10-29T00:00:00.000
Actual Construction End
2023-09-23T00:00:00.000
Borough
Queens
Community Board
Queens, Queens 03, Queens 04, Queens 06, Queens 07, Queens 08
Budget Line
P-0013, P-0245Q, P-D019, P-I001, P-Q001, P-Q003, P-Q005, P-Q138, P-Q245, P-Q708, P-Q771, P-Q847
Ten Year Plan Category
LARGE, MAJOR AND REGIONAL PARK RECONSTRUCTION
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2690
Fms Id
P-213WEST
Total Budget
4503911.38
Spend To Date
539803.60
Spend To Date 1
0.1198
Fms Project Name
West Playground CS B252-115M
Agency Project Name
West Playground Public Restroom Building Construction
Agency Project Description
This project will construct a public restroom building in West Playground.
Current Phase
Construction
Current Phase Start
2023-10-10T00:00:00.000
Forecast Current Phase End
2025-04-09T00:00:00.000
Forecast Completion
2025-01-28T00:00:00.000
Actual Design Start
2015-04-09T00:00:00.000
Actual Design End
2020-04-29T00:00:00.000
Actual Construction
2020-04-29T00:00:00.000
Actual Construction 1
2022-12-05T00:00:00.000
Actual Construction Start
2023-10-10T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn 13
Budget Line
P-1018, P-D017, P-I001, P-K011, P-K707
Ten Year Plan Category
NEIGHBORHOOD PARKS AND PLAYGROUNDS
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2691
Fms Id
P-208LTCS
Total Budget
7281881.78
Spend To Date
589400.35
Spend To Date 1
0.0809
Fms Project Name
Lincoln Terrace- Field House Construction B054-115M
Agency Project Name
Lincoln Terrace Park Field House Construction
Agency Project Description
This project will demolish the existing public restroom building and construct a new field house in Lincoln Terrace Park.
Current Phase
Construction
Current Phase Start
2023-09-18T00:00:00.000
Forecast Current Phase End
2025-03-18T00:00:00.000
Forecast Completion
2024-12-10T00:00:00.000
Actual Design Start
2015-04-08T00:00:00.000
Actual Design End
2020-04-28T00:00:00.000
Actual Construction
2020-04-28T00:00:00.000
Actual Construction 1
2022-12-12T00:00:00.000
Actual Construction Start
2023-09-18T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn 08
Budget Line
P-1018, P-D017, P-I001, P-K011, P-K707
Ten Year Plan Category
NEIGHBORHOOD PARKS AND PLAYGROUNDS
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2692
Fms Id
P-5BUNBCH
Total Budget
582407.00
Spend To Date
158086.65
Spend To Date 1
0.2714
Fms Project Name
Buono Beach-Reconstruction of Fountain
Agency Project Name
Buono Beach Fountain Reconstruction (Hurricane Sandy)
Agency Project Description
This project will reconstruct the electrical and mechanical components of the fountain at Buono Beach in Alice Austen Park.
Current Phase
(Completed)
Actual Design Start
2015-07-01T00:00:00.000
Actual Design End
2019-11-14T00:00:00.000
Actual Construction
2019-11-14T00:00:00.000
Actual Construction 1
2022-09-06T00:00:00.000
Actual Construction Start
2022-10-25T00:00:00.000
Actual Construction End
2023-10-23T00:00:00.000
Borough
Staten Island
Community Board
Staten Island
Budget Line
P-1018, P-D020
Ten Year Plan Category
BEACHES AND BOARDWALKS
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2692
Fms Id
SANDY5-37
Total Budget
973197.00
Spend To Date
250337.18
Spend To Date 1
0.2572
Fms Project Name
SANDY - BUONO BEACH FOUNTAIN REPAIR - R117-117MA
Agency Project Name
Buono Beach Fountain Reconstruction (Hurricane Sandy)
Agency Project Description
This project will reconstruct the electrical and mechanical components of the fountain at Buono Beach in Alice Austen Park.
Current Phase
(Completed)
Actual Design Start
2015-07-01T00:00:00.000
Actual Design End
2019-11-14T00:00:00.000
Actual Construction
2019-11-14T00:00:00.000
Actual Construction 1
2022-09-06T00:00:00.000
Actual Construction Start
2022-10-25T00:00:00.000
Actual Construction End
2023-10-23T00:00:00.000
Borough
Staten Island
Community Board
Staten Island
Budget Line
P-1018, P-I001
Ten Year Plan Category
BEACHES AND BOARDWALKS
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2693
Fms Id
P-6BOIL15
Total Budget
1241735.54
Spend To Date
371440.07
Spend To Date 1
0.2991
Fms Project Name
MOSHOLU PK CS, PROSPECT PK PAINT SHOP, BENSONHURST SR CTR
Agency Project Name
Bensonhurst Senior Recreation Center and Mosholu Parkway Public Restroom Building Boiler and Heating System Reconstruction
Agency Project Description
This project will reconstruct the boilers and heating systems at Bensonhurst Senior Recreation Center in Brooklyn and at the public restroom building in Mosholu Parkway in the Bronx.
Current Phase
(Completed)
Actual Design Start
2013-02-08T00:00:00.000
Actual Design End
2019-02-19T00:00:00.000
Actual Construction
2019-02-19T00:00:00.000
Actual Construction 1
2021-11-04T00:00:00.000
Actual Construction Start
2022-07-18T00:00:00.000
Actual Construction End
2023-07-13T00:00:00.000
Borough
Citywide
Community Board
Citywide
Budget Line
P-1018, P-1250, P-I001
Ten Year Plan Category
LARGE, MAJOR AND REGIONAL PARK RECONSTRUCTION
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2694
Fms Id
P-2CPIEPP
Total Budget
4165789.79
Spend To Date
1275310.78
Spend To Date 1
0.3061
Fms Project Name
CPI PH2 - R/C Epiphany Playground (B405 -116M)
Agency Project Name
Epiphany Playground Reconstruction
Agency Project Description
This project will reconstruct the playground, spray shower, seating, handball and basketball courts, perimeter fence, and security lighting at Epiphany Playground.
Current Phase
Construction
Current Phase Start
2022-08-29T00:00:00.000
Forecast Current Phase End
2023-08-28T00:00:00.000
Forecast Completion
2024-01-31T00:00:00.000
Actual Design Start
2016-03-14T00:00:00.000
Actual Design End
2020-10-16T00:00:00.000
Actual Construction
2020-10-16T00:00:00.000
Actual Construction 1
2022-07-21T00:00:00.000
Actual Construction Start
2022-08-29T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn, Brooklyn 01
Budget Line
P-1018, P-I001, WP-0169
Ten Year Plan Category
WATER QUALITY MANDATES
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2695
Fms Id
P-213SCRN
Total Budget
3257210.00
Spend To Date
584540.85
Spend To Date 1
0.1794
Fms Project Name
Scarangella Park Comfort Station Construction B106-117M
Agency Project Name
Scarangella Park Public Restroom Building Construction
Agency Project Description
This project will construct a new public restroom building in Scarangella Park.
Current Phase
Construction Procurement
Current Phase Start
2023-10-27T00:00:00.000
Forecast Current Phase End
2024-10-26T00:00:00.000
Forecast Completion
2026-12-22T00:00:00.000
Actual Design Start
2016-08-17T00:00:00.000
Actual Design End
2023-10-16T00:00:00.000
Actual Construction
2023-10-27T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn 13, Brooklyn
Budget Line
P-0245K, P-D017, P-I001
Ten Year Plan Category
NEIGHBORHOOD PARKS AND PLAYGROUNDS
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2696
Fms Id
P-407MAPL
Total Budget
7012071.44
Spend To Date
3898090.76
Spend To Date 1
0.5559
Fms Project Name
Maple Playground R/C Q211-117M
Agency Project Name
Maple Playground Reconstruction
Agency Project Description
This project will reconstruct Maple Playground.
Current Phase
(Completed)
Actual Design Start
2019-05-23T00:00:00.000
Actual Design End
2020-08-27T00:00:00.000
Actual Construction
2020-08-27T00:00:00.000
Actual Construction 1
2022-08-01T00:00:00.000
Actual Construction Start
2022-09-26T00:00:00.000
Actual Construction End
2023-09-13T00:00:00.000
Borough
Queens
Community Board
Queens, Queens 07
Budget Line
P-D019, P-I001, P-Q245
Ten Year Plan Category
NEIGHBORHOOD PARKS AND PLAYGROUNDS
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2697
Fms Id
P-4RAINE2
Total Budget
8075405.48
Spend To Date
543997.62
Spend To Date 1
0.0673
Fms Project Name
Rainey Pk Picnic Grove, Bsktball Ct, & Dog Run R/C Q048-119M
Agency Project Name
Rainey Park Playground, Picnic Grove and Basketball Court Reconstruction
Agency Project Description
This project will reconstruct the playground, picnic grove and basketball court at Rainey Park.
Current Phase
Construction
Current Phase Start
2023-09-11T00:00:00.000
Forecast Current Phase End
2024-09-09T00:00:00.000
Forecast Completion
2024-09-09T00:00:00.000
Actual Design Start
2019-05-30T00:00:00.000
Actual Design End
2021-09-14T00:00:00.000
Actual Construction
2021-09-14T00:00:00.000
Actual Construction 1
2023-07-07T00:00:00.000
Actual Construction Start
2023-09-11T00:00:00.000
Borough
Queens
Community Board
Queens, Queens 01
Budget Line
P-D019, P-I001, P-Q245
Ten Year Plan Category
NEIGHBORHOOD PARKS AND PLAYGROUNDS
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2698
Fms Id
P-412NAUT
Total Budget
6283393.23
Spend To Date
4232875.28
Spend To Date 1
0.6736
Fms Project Name
Nautilus Playground R/C Q448-119M
Agency Project Name
Nautilus Playground Reconstruction
Agency Project Description
This project will reconstruct Nautilus Playground.
Current Phase
(Completed)
Actual Design Start
2019-01-07T00:00:00.000
Actual Design End
2020-05-22T00:00:00.000
Actual Construction
2020-05-22T00:00:00.000
Actual Construction 1
2022-04-25T00:00:00.000
Actual Construction Start
2022-08-22T00:00:00.000
Actual Construction End
2023-08-21T00:00:00.000
Borough
Queens
Community Board
Queens, Queens 12
Budget Line
P-I001, P-Q245, TF-0502
Ten Year Plan Category
NEIGHBORHOOD PARKS AND PLAYGROUNDS
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2699
Fms Id
P-406PG62
Total Budget
4106500.00
Spend To Date
433106.28
Spend To Date 1
0.1054
Fms Project Name
Playground Sixty Two R/C Q377-120M
Agency Project Name
Playground 62 Reconstruction
Agency Project Description
This project will reconstruct Playground 62.
Current Phase
Construction Procurement
Current Phase Start
2022-06-14T00:00:00.000
Forecast Current Phase End
2023-03-11T00:00:00.000
Forecast Completion
2026-02-24T00:00:00.000
Actual Design Start
2020-11-18T00:00:00.000
Actual Design End
2022-06-14T00:00:00.000
Actual Construction
2022-06-14T00:00:00.000
Borough
Queens
Community Board
Queens, Queens 06
Budget Line
P-D019, P-I001, P-Q245, TF-0502
Ten Year Plan Category
TRAFFIC WORK IN CONJUNCTION WITH HIGHWAY RECONSTRUCTION
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2700
Fms Id
P-408HOV2
Total Budget
4817300.00
Spend To Date
464518.69
Spend To Date 1
0.0964
Fms Project Name
Hoover Playground Q220G-121M
Agency Project Name
Hoover Playground Reconstruction
Agency Project Description
This project will reconstruct Hoover Playground.
Current Phase
Design
Current Phase Start
2020-09-28T00:00:00.000
Forecast Current Phase End
2021-09-28T00:00:00.000
Forecast Completion
2026-01-25T00:00:00.000
Actual Design Start
2020-09-28T00:00:00.000
Borough
Queens
Community Board
Queens, Queens 08
Budget Line
P-D019, P-I001, P-Q245, TF-0502
Ten Year Plan Category
TRAFFIC WORK IN CONJUNCTION WITH HIGHWAY RECONSTRUCTION
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2701
Fms Id
P-414BCAP
Total Budget
3187100.00
Spend To Date
205049.59
Spend To Date 1
0.0643
Fms Project Name
Broad Channel American Park Q467-120M
Agency Project Name
Broad Channel American Park Field Reconstruction
Agency Project Description
This project will reconstruct the asphalt ballfield in Broad Channel American Park.
Current Phase
Construction Procurement
Current Phase Start
2022-11-02T00:00:00.000
Forecast Current Phase End
2023-07-30T00:00:00.000
Forecast Completion
2025-12-25T00:00:00.000
Actual Design Start
2020-11-11T00:00:00.000
Actual Design End
2022-11-02T00:00:00.000
Actual Construction
2022-11-02T00:00:00.000
Borough
Queens
Community Board
Queens, Queens 14
Budget Line
P-D019
Ten Year Plan Category
NEIGHBORHOOD PARKS AND PLAYGROUNDS
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2702
Fms Id
P-205SHNK
Total Budget
5633419.97
Spend To Date
825267.32
Spend To Date 1
0.1464
Fms Project Name
Sankofa Park RC B261-120M
Agency Project Name
Sankofa Park Reconstruction
Agency Project Description
This project will reconstruct the playground and construct an African Burial Ground commemorative area at Sankofa Park.
Current Phase
Construction
Current Phase Start
2023-11-06T00:00:00.000
Forecast Current Phase End
2024-11-04T00:00:00.000
Forecast Completion
2024-11-04T00:00:00.000
Actual Design Start
2019-06-27T00:00:00.000
Actual Design End
2022-02-23T00:00:00.000
Actual Construction
2022-02-23T00:00:00.000
Actual Construction 1
2023-07-26T00:00:00.000
Actual Construction Start
2023-11-06T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn 05, Brooklyn
Budget Line
P-1018, P-D017, P-I001
Ten Year Plan Category
NEIGHBORHOOD PARKS AND PLAYGROUNDS
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2703
Fms Id
P-404CROW
Total Budget
3969800.00
Spend To Date
192653.82
Spend To Date 1
0.0485
Fms Project Name
Crowley Playground R/C Q360J-121M
Agency Project Name
Crowley Playground Reconstruction
Agency Project Description
This project will reconstruct Crowley Playground.
Current Phase
Construction Procurement
Current Phase Start
2022-08-29T00:00:00.000
Forecast Current Phase End
2023-05-26T00:00:00.000
Forecast Completion
2026-03-27T00:00:00.000
Actual Design Start
2021-01-29T00:00:00.000
Actual Design End
2022-08-29T00:00:00.000
Actual Construction
2022-08-29T00:00:00.000
Borough
Queens
Community Board
Queens, Queens 04
Budget Line
P-D019, P-I001, P-Q245, TF-0502
Ten Year Plan Category
TRAFFIC WORK IN CONJUNCTION WITH HIGHWAY RECONSTRUCTION
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2704
Fms Id
P-401SFFE
Total Budget
325000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
Socrate Sculpture Park Building Expansion FFE Q465-117M
Agency Project Name
Socrates Sculpture Park Administration Building Construction
Agency Project Description
This project will construct a new administration building at Socrates Sculpture Park.
Current Phase
Construction
Current Phase Start
2022-08-15T00:00:00.000
Forecast Current Phase End
2024-02-13T00:00:00.000
Forecast Completion
2024-02-13T00:00:00.000
Actual Design Start
2016-05-17T00:00:00.000
Actual Design End
2019-08-07T00:00:00.000
Actual Construction
2019-08-07T00:00:00.000
Actual Construction 1
2022-06-02T00:00:00.000
Actual Construction Start
2022-08-15T00:00:00.000
Borough
Queens
Community Board
Queens, Queens 01
Budget Line
P-Q245
Ten Year Plan Category
NEIGHBORHOOD PARKS AND PLAYGROUNDS
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2704
Fms Id
P-401SOC2
Total Budget
6671154.00
Spend To Date
1677971.95
Spend To Date 1
0.2515
Fms Project Name
Socrates Sculpture Park Building Expansion Q465-117M
Agency Project Name
Socrates Sculpture Park Administration Building Construction
Agency Project Description
This project will construct a new administration building at Socrates Sculpture Park.
Current Phase
(Partner-managed)
Current Phase Start
2022-08-15T00:00:00.000
Forecast Current Phase End
2024-02-13T00:00:00.000
Forecast Completion
2024-02-13T00:00:00.000
Actual Design Start
2016-05-17T00:00:00.000
Actual Design End
2019-08-07T00:00:00.000
Actual Construction
2019-08-07T00:00:00.000
Actual Construction 1
2022-06-02T00:00:00.000
Actual Construction Start
2022-08-15T00:00:00.000
Borough
Queens
Community Board
Queens, Queens 01
Budget Line
P-D019, P-I001
Ten Year Plan Category
NEIGHBORHOOD PARKS AND PLAYGROUNDS
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2705
Fms Id
P-303SDRP
Total Budget
6043602.15
Spend To Date
436418.35
Spend To Date 1
0.0722
Fms Project Name
Sara D. Roosevelt Park - Pathways, sidewalks, exterior walls
Agency Project Name
Sara D. Roosevelt Park Rivington Street Playground Reconstruction
Agency Project Description
This project will reconstruct Rivington Street Playground at Sara D. Roosevelt Park.
Current Phase
Design
Current Phase Start
2021-12-13T00:00:00.000
Forecast Current Phase End
2023-03-10T00:00:00.000
Forecast Completion
2026-02-24T00:00:00.000
Actual Design Start
2021-12-13T00:00:00.000
Borough
Manhattan
Community Board
Manhattan
Budget Line
P-D018, P-I001, P-M245
Ten Year Plan Category
NEIGHBORHOOD PARKS AND PLAYGROUNDS
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2706
Fms Id
P-312INNC
Total Budget
3749947.07
Spend To Date
1095302.41
Spend To Date 1
0.292
Fms Project Name
Inwood Hill Nature Center M042 -116M
Agency Project Name
Inwood Hill Nature Center Post-Sandy Reconstruction
Agency Project Description
This project will reconstruct the Inwood Hill Nature Center at Inwood Hill Park due to damage caused by Hurricane Sandy.
Current Phase
(Completed)
Actual Design Start
2016-02-04T00:00:00.000
Actual Design End
2019-07-09T00:00:00.000
Actual Construction
2019-07-09T00:00:00.000
Actual Construction 1
2021-04-22T00:00:00.000
Actual Construction Start
2021-10-18T00:00:00.000
Actual Construction End
2023-09-01T00:00:00.000
Borough
Manhattan
Community Board
Manhattan
Budget Line
P-0506, P-1018
Ten Year Plan Category
NEIGHBORHOOD PARKS AND PLAYGROUNDS
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2706
Fms Id
SANDY3-12
Total Budget
2230577.90
Spend To Date
2180443.07
Spend To Date 1
0.9775
Fms Project Name
SANDY-Inwood Hill Nature Center M042-116MA1
Agency Project Name
Inwood Hill Nature Center Post-Sandy Reconstruction
Agency Project Description
This project will reconstruct the Inwood Hill Nature Center at Inwood Hill Park due to damage caused by Hurricane Sandy.
Current Phase
(Completed)
Actual Design Start
2016-02-04T00:00:00.000
Actual Design End
2019-07-09T00:00:00.000
Actual Construction
2019-07-09T00:00:00.000
Actual Construction 1
2021-04-22T00:00:00.000
Actual Construction Start
2021-10-18T00:00:00.000
Actual Construction End
2023-09-01T00:00:00.000
Borough
Manhattan
Community Board
Manhattan
Budget Line
P-1018, P-I001
Ten Year Plan Category
NEIGHBORHOOD PARKS AND PLAYGROUNDS
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2707
Fms Id
P-2BELTPE
Total Budget
11361310.92
Spend To Date
956011.97
Spend To Date 1
0.0841
Fms Project Name
Mill Basin Bridge Trees
Agency Project Name
Belt Parkway Tree Planting and Ecological Restoration
Agency Project Description
This project will plant trees within the Belt Parkway right-of-way. It will also restore natural areas adjacent to the Parkway.
Current Phase
Construction
Current Phase Start
2023-11-06T00:00:00.000
Forecast Current Phase End
2026-11-04T00:00:00.000
Forecast Completion
2026-09-02T00:00:00.000
Actual Design Start
2018-07-18T00:00:00.000
Actual Design End
2021-03-30T00:00:00.000
Actual Construction
2021-03-30T00:00:00.000
Actual Construction 1
2023-03-20T00:00:00.000
Actual Construction Start
2023-11-06T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn
Budget Line
HB-1023, P-I001, PU-0200
Ten Year Plan Category
MISCELLANEOUS ENERGY EFFICIENCY AND SUSTAINABILITY
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2708
Fms Id
P-5RECSI
Total Budget
2932690.00
Spend To Date
270628.08
Spend To Date 1
0.0922
Fms Project Name
Lyons Rec Ctr RC in Staten Island R043-119M
Agency Project Name
Lyons Recreation Center Reconstruction
Agency Project Description
This project will partially reconstruct Lyons Pool Recreation Center.
Current Phase
Construction
Current Phase Start
2023-03-27T00:00:00.000
Forecast Current Phase End
2024-03-25T00:00:00.000
Forecast Completion
2024-03-25T00:00:00.000
Actual Design Start
2016-01-04T00:00:00.000
Actual Design End
2019-03-29T00:00:00.000
Actual Construction
2019-03-29T00:00:00.000
Actual Construction 1
2022-09-16T00:00:00.000
Actual Construction Start
2023-03-27T00:00:00.000
Borough
Staten Island
Community Board
Staten Island
Budget Line
P-0505, P-1018, P-I001
Ten Year Plan Category
NEIGHBORHOOD PARKS AND PLAYGROUNDS
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2709
Fms Id
P-201MCBH
Total Budget
12242147.20
Spend To Date
3694612.44
Spend To Date 1
0.3017
Fms Project Name
McCarren -RC Bathhouse B058-117M
Agency Project Name
McCarren Park Bathhouse Roof & Exterior Walls Reconstruction
Agency Project Description
This project will reconstruct the roof and exterior masonry walls at the McCarren Park Bathhouse.
Current Phase
Construction
Current Phase Start
2022-05-16T00:00:00.000
Forecast Current Phase End
2024-11-10T00:00:00.000
Forecast Completion
2024-11-10T00:00:00.000
Actual Design Start
2016-06-13T00:00:00.000
Actual Design End
2020-01-28T00:00:00.000
Actual Construction
2020-01-28T00:00:00.000
Actual Construction 1
2021-11-26T00:00:00.000
Actual Construction Start
2022-05-16T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn, Brooklyn 01
Budget Line
P-1018, P-I001
Ten Year Plan Category
LARGE, MAJOR AND REGIONAL PARK RECONSTRUCTION
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2710
Fms Id
P-6TREEP1
Total Budget
15987500.00
Spend To Date
9402730.55
Spend To Date 1
0.5881
Fms Project Name
Procurement of Street Trees Region 1-CNYG-3916M
Agency Project Name
Citywide Procurement of Street Trees from Region 1
Agency Project Description
The project will furnish and deliver approximately 8,000 street trees per year, beginning in Fall 2017 through Spring 2025 for a total of approximately 64,000 trees for planting Citywide.
Current Phase
Construction
Current Phase Start
2018-07-01T00:00:00.000
Forecast Current Phase End
2026-06-28T00:00:00.000
Forecast Completion
2026-06-28T00:00:00.000
Actual Design Start
2016-05-06T00:00:00.000
Actual Design End
2016-06-07T00:00:00.000
Actual Construction
2016-06-07T00:00:00.000
Actual Construction 1
2018-03-09T00:00:00.000
Actual Construction Start
2018-07-01T00:00:00.000
Borough
Citywide
Community Board
Citywide
Budget Line
P-0822, P-1018, P-I001
Ten Year Plan Category
LAND ACQUISITION AND TREE PLANTING
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DPR • Sponsor Agency: DPR
Reporting Period
202309
Managing Agency
DPR
Sponsor Agency
DPR
Pid
2711
Fms Id
P-6TREEP2
Total Budget
13386000.00
Spend To Date
2981863.97
Spend To Date 1
0.2227
Fms Project Name
Procurement of Street Trees Region 2-CNYG-4016M
Agency Project Name
Citywide Procurement of Street Trees from Region 2
Agency Project Description
The project will furnish and deliver approximately 8,000 street trees per year, beginning in Fall 2017 through Spring 2025 for a total of approximately 64,000 trees for planting Citywide.
Current Phase
Construction
Current Phase Start
2018-07-02T00:00:00.000
Forecast Current Phase End
2026-06-29T00:00:00.000
Forecast Completion
2026-06-29T00:00:00.000
Actual Design Start
2016-05-06T00:00:00.000
Actual Design End
2016-06-07T00:00:00.000
Actual Construction
2016-06-07T00:00:00.000
Actual Construction 1
2018-03-09T00:00:00.000
Actual Construction Start
2018-07-02T00:00:00.000
Borough
Citywide
Community Board
Citywide
Budget Line
P-0822, P-1018, P-I001
Ten Year Plan Category
LAND ACQUISITION AND TREE PLANTING
Agency Data Date
2024-02-23T00:00:00.000
Fms Data Date
2023-10-23T00:00:00.000