Capital Projects Dashboard - Citywide Budget and Schedule

All major capital infrastructure projects with a committed budget. Financial information and agency schedule details for each project are joined via FMS ID. Only projects in the design phase or later have project schedules displayed. This dataset is part of the Capital Projects Dashboard.

Note: Each row is uniquely identified by its Financial Management Service (FMS) ID. FMS ID is the unique ID that OMB uses for the FMS (Financial Information System). This ID can be universally joined with any OMB dataset that has the same field. The Capital Projects Dashboard is the result of joining OMB’s fiscal data with the agency’s schedule data. FMS IDs and agency projects don't always have a one-to-one relationship (i.e., one project schedule may correlate to multiple FMS IDs, and one FMS may correct to multiple projects with different schedules).

City Government Mayor's Office of Operations (OPS) Dataset fb86-vt7u 27 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DEP
Pid
3868
Fms Id
MIBBNC04B
Total Budget
43248000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
Storm and sanitary sewer installation
Agency Project Name
Storm sewer installation and water main replacement in Hunter Avenue between Haven Avenue and Nugent Avenue, as well as other locations.
Current Phase
Pre-Design
Borough
Staten Island
Community Board
Staten Island 02
Budget Line
SE-0002R, SE-0200R, WM-0001
Ten Year Plan Category
BLUEBELT PROGRAM
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DEP
Pid
3869
Fms Id
QED-1054
Total Budget
23027029.03
Spend To Date
4427851.31
Spend To Date 1
0.1922
Fms Project Name
Dist WM work in Ellwell Crescent from Alderton to Carlton St
Agency Project Name
Distribution Water Main work in Ellwell Crescent from Alderton Street to Carlton Street, as well as other locations listed in Page 3 of attached CPI. Borough of Queens.
Current Phase
Construction
Current Phase Start
2022-09-12T00:00:00.000
Forecast Current Phase End
2024-09-10T00:00:00.000
Forecast Completion
2024-09-10T00:00:00.000
Actual Design Start
2021-02-25T00:00:00.000
Actual Design End
2022-02-10T00:00:00.000
Actual Construction
2022-02-10T00:00:00.000
Actual Construction 1
2022-09-12T00:00:00.000
Actual Construction Start
2022-09-12T00:00:00.000
Borough
Queens
Community Board
Queens
Budget Line
TF-0502, WM-0001, WM-0944
Ten Year Plan Category
TRUNK AND DISTRIBUTION MAIN REPLACEMENT
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DEP
Pid
3870
Fms Id
RED394
Total Budget
21921000.00
Spend To Date
595447.75
Spend To Date 1
0.0271
Fms Project Name
Area contract - Install Dist WM throughout BKLYN & SI
Agency Project Name
Install Distribution water mains throughout Brooklyn and Staten Island as directed by Distribution Engineer.
Current Phase
Construction Procurement
Current Phase Start
2023-02-02T00:00:00.000
Forecast Current Phase End
2023-11-26T00:00:00.000
Forecast Completion
2025-11-25T00:00:00.000
Actual Design Start
2022-06-09T00:00:00.000
Actual Design End
2023-02-02T00:00:00.000
Actual Construction
2023-02-02T00:00:00.000
Borough
Citywide
Community Board
Citywide
Budget Line
EP-0007, WM-0001, WM-0944
Ten Year Plan Category
UTILITY RELOCATION FOR SE AND WM PROJECTS
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DEP
Pid
3870
Fms Id
RED395AC
Total Budget
18805000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
Area Contract Replacmt & Install Dist WM throughout BK & SI
Agency Project Name
Install Distribution water mains throughout Brooklyn and Staten Island as directed by Distribution Engineer.
Current Phase
Design
Current Phase Start
2022-11-02T00:00:00.000
Forecast Current Phase End
2023-11-20T00:00:00.000
Forecast Completion
2025-12-27T00:00:00.000
Actual Design Start
2022-11-02T00:00:00.000
Borough
Citywide
Community Board
Citywide
Budget Line
WM-0001
Ten Year Plan Category
AUGMENTATION OF WATER SUPPLY SYSTEMS
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DOT
Pid
3872
Fms Id
SANDHWSIB
Total Budget
2240000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
Swaim & Huguenot Ave Improvements
Agency Project Name
Reconstruction of segments of Huguenot and Swaim Avenues
Current Phase
Design
Current Phase Start
2021-06-15T00:00:00.000
Forecast Current Phase End
2023-11-30T00:00:00.000
Forecast Completion
2025-12-29T00:00:00.000
Actual Design Start
2021-06-15T00:00:00.000
Borough
Staten Island
Community Board
Staten Island
Budget Line
HW-0001R
Ten Year Plan Category
PRIMARY STREET RECONSTRUCTION
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DEP
Pid
3873
Fms Id
SE885AVWE
Total Budget
135309934.00
Spend To Date
135298575.34
Spend To Date 1
0.9999
Fms Project Name
SEQ - 150th St Spine Phase II DOT Van Wyck Exp -Trunk Combi
Agency Project Name
150th Street Spine: Phase II - DOT Van Wyck Expressway - Trunk Combined Sewer
Current Phase
Construction
Current Phase Start
2022-05-27T00:00:00.000
Forecast Current Phase End
2025-04-14T00:00:00.000
Forecast Completion
2025-04-14T00:00:00.000
Actual Design Start
2020-03-02T00:00:00.000
Actual Design End
2022-07-10T00:00:00.000
Actual Construction
2022-07-10T00:00:00.000
Actual Construction 1
2022-05-27T00:00:00.000
Actual Construction Start
2022-05-27T00:00:00.000
Borough
Queens
Community Board
Queens 12, Queens 13
Budget Line
SE-0002Q, SE-0200Q
Ten Year Plan Category
REPLACEMENT OR AUGMENTATION OF EXISTING SYSTEMS
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DEP
Pid
3875
Fms Id
SER0201ZB
Total Budget
10870000.00
Spend To Date
10489012.65
Spend To Date 1
0.9649
Agency Project Name
RECONSTRUCTION OF EXISTING SEWERS, STATEN ISLAND
Current Phase
Close-out
Actual Design Start
2018-09-24T00:00:00.000
Actual Design End
2018-12-21T00:00:00.000
Actual Construction
2018-12-21T00:00:00.000
Actual Construction 1
2020-06-22T00:00:00.000
Actual Construction Start
2020-06-22T00:00:00.000
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DEP
Pid
3876
Fms Id
SER200309
Total Budget
7762480.39
Spend To Date
649035.91
Spend To Date 1
0.0836
Fms Project Name
Strm swr R+Ext & WM Work, Maguire Avenue
Agency Project Name
REPL. AND EXT. OF STORM SEWERS IN MAGUIRE AVE
Current Phase
Design
Current Phase Start
2019-06-24T00:00:00.000
Forecast Current Phase End
2027-10-29T00:00:00.000
Forecast Completion
2029-06-29T00:00:00.000
Actual Design Start
2019-06-24T00:00:00.000
Borough
Staten Island
Community Board
Staten Island 03
Budget Line
SE-0002R, SE-0200R, WM-0001
Ten Year Plan Category
REPLACEMENT OR AUGMENTATION OF EXISTING SYSTEMS
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DCAS
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DCAS
Pid
3877
Fms Id
70MULBREC
Total Budget
170000000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
70 MULBERRY STREET - RECONSTRUCTION
Agency Project Name
70 MULBERRY STREET - RECONSTRUCTION
Current Phase
Design
Current Phase Start
2022-06-15T00:00:00.000
Forecast Current Phase End
2024-03-20T00:00:00.000
Forecast Completion
2028-03-29T00:00:00.000
Actual Design Start
2022-06-15T00:00:00.000
Borough
Manhattan
Community Board
Manhattan 01
Budget Line
PW-0077
Ten Year Plan Category
RENOVATION OF OTHER CITY-OWNED FACILITIES
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DOC
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DOC
Pid
3879
Fms Id
BBJ-K
Total Budget
3341621249.85
Spend To Date
29486165.94
Spend To Date 1
0.0088
Fms Project Name
Boro Based Jails New Brooklyn Detention Facility DesignBuild
Agency Project Name
Dismantal of Brooklyn Detention Facility
Current Phase
Construction
Current Phase Start
2022-03-14T00:00:00.000
Forecast Current Phase End
2023-12-15T00:00:00.000
Forecast Completion
2023-12-15T00:00:00.000
Actual Design Start
2021-12-20T00:00:00.000
Actual Design End
2022-03-07T00:00:00.000
Actual Construction
2022-03-07T00:00:00.000
Actual Construction 1
2022-03-14T00:00:00.000
Actual Construction Start
2022-03-14T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn
Budget Line
C-0114
Ten Year Plan Category
New Jail Facilities
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DOC
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DOC
Pid
3880
Fms Id
BBJ-K
Total Budget
3341621249.85
Spend To Date
29486165.94
Spend To Date 1
0.0088
Fms Project Name
Boro Based Jails New Brooklyn Detention Facility DesignBuild
Agency Project Name
BBJ Construction of New Brooklyn Detention Facility
Current Phase
Design
Current Phase Start
2023-07-06T00:00:00.000
Forecast Current Phase End
2024-04-30T00:00:00.000
Forecast Completion
2029-03-05T00:00:00.000
Actual Design Start
2023-07-06T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn
Budget Line
C-0114
Ten Year Plan Category
New Jail Facilities
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DOC
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DOC
Pid
3881
Fms Id
BBJ-M
Total Budget
2058413174.80
Spend To Date
46628720.30
Spend To Date 1
0.0226
Fms Project Name
Boro Based Jail New Manhattan Detention Facility DesignBuild
Agency Project Name
Dismantal of Manhattan Detention Facility
Current Phase
Construction
Current Phase Start
2022-04-25T00:00:00.000
Forecast Current Phase End
2024-09-04T00:00:00.000
Forecast Completion
2024-09-04T00:00:00.000
Actual Design Start
2021-12-27T00:00:00.000
Actual Design End
2022-04-18T00:00:00.000
Actual Construction
2022-04-18T00:00:00.000
Actual Construction 1
2022-04-25T00:00:00.000
Actual Construction Start
2022-04-25T00:00:00.000
Borough
Manhattan
Community Board
Manhattan
Budget Line
C-0114
Ten Year Plan Category
New Jail Facilities
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DOC
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DOC
Pid
3882
Fms Id
BBJ-Q
Total Budget
1984973583.60
Spend To Date
26688885.94
Spend To Date 1
0.0134
Fms Project Name
Boro Based Jails New Queens Detention Facility DesignBuild
Agency Project Name
Dismantal of Queens Detention Facility
Current Phase
Construction
Current Phase Start
2023-04-25T00:00:00.000
Forecast Current Phase End
2023-12-29T00:00:00.000
Forecast Completion
2023-12-29T00:00:00.000
Actual Design Start
2021-12-27T00:00:00.000
Actual Design End
2023-04-25T00:00:00.000
Actual Construction
2023-04-25T00:00:00.000
Actual Construction 1
2023-04-25T00:00:00.000
Actual Construction Start
2023-04-25T00:00:00.000
Borough
Queens
Community Board
Queens
Budget Line
C-0114
Ten Year Plan Category
New Jail Facilities
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DOC
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DOC
Pid
3883
Fms Id
BBJ-X
Total Budget
1932382709.88
Spend To Date
47678402.37
Spend To Date 1
0.0246
Fms Project Name
Boro Based Jails New Bronx Detention Facility DesignBuild
Agency Project Name
Dismantal of Bronx Detention Facility
Current Phase
Construction
Current Phase Start
2022-07-13T00:00:00.000
Forecast Current Phase End
2023-12-26T00:00:00.000
Forecast Completion
2023-12-26T00:00:00.000
Actual Design Start
2022-06-17T00:00:00.000
Actual Design End
2022-07-13T00:00:00.000
Actual Construction
2022-07-13T00:00:00.000
Actual Construction 1
2022-07-13T00:00:00.000
Actual Construction Start
2022-07-13T00:00:00.000
Borough
Bronx
Community Board
Bronx
Budget Line
C-0114
Ten Year Plan Category
New Jail Facilities
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DOC
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DOC
Pid
3884
Fms Id
C75EWGRVC
Total Budget
15019000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
Emergency Work for GRVC
Agency Project Name
Renovation of George R Vierno Center (GRVC) at Rikers Island
Current Phase
(Completed)
Actual Design Start
2021-10-16T00:00:00.000
Actual Design End
2021-10-30T00:00:00.000
Actual Construction
2021-10-30T00:00:00.000
Actual Construction 1
2021-11-01T00:00:00.000
Actual Construction Start
2021-11-01T00:00:00.000
Actual Construction End
2023-06-30T00:00:00.000
Borough
Bronx
Community Board
Bronx
Budget Line
C-0075
Ten Year Plan Category
BUILDING SYSTEMS AND INFRASTRUCTURE
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DOC
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DOC
Pid
3885
Fms Id
C75EWRMSC
Total Budget
96031673.72
Spend To Date
84109612.90
Spend To Date 1
0.8758
Fms Project Name
Emergency Work for RMSC
Agency Project Name
Renovation of Rose M. Singer Center (RMSC) at Rikers Island
Current Phase
Close-out
Actual Design Start
2021-09-30T00:00:00.000
Actual Design End
2021-09-30T00:00:00.000
Actual Construction
2021-09-30T00:00:00.000
Actual Construction 1
2021-10-01T00:00:00.000
Actual Construction Start
2021-10-01T00:00:00.000
Actual Construction End
2023-06-30T00:00:00.000
Borough
Bronx
Community Board
Bronx
Budget Line
C-0075
Ten Year Plan Category
BUILDING SYSTEMS AND INFRASTRUCTURE
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DOC
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DOC
Pid
3886
Fms Id
C75EWRNDC
Total Budget
37753257.48
Spend To Date
34161729.74
Spend To Date 1
0.9048
Fms Project Name
Emergency Work for RNDC
Agency Project Name
Renovation of Robert N. Davoren Complex (RNDC) at Rikers Island
Current Phase
Close-out
Actual Design Start
2021-09-30T00:00:00.000
Actual Design End
2021-09-30T00:00:00.000
Actual Construction
2021-09-30T00:00:00.000
Actual Construction 1
2021-10-01T00:00:00.000
Actual Construction Start
2021-10-01T00:00:00.000
Actual Construction End
2023-06-30T00:00:00.000
Borough
Bronx
Community Board
Bronx
Budget Line
C-0075
Ten Year Plan Category
BUILDING SYSTEMS AND INFRASTRUCTURE
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DOC
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DOC
Pid
3887
Fms Id
C75EWNIC
Total Budget
23482795.40
Spend To Date
21133156.92
Spend To Date 1
0.8999
Fms Project Name
Emergency Work for NIC
Agency Project Name
Renovation of North Infirmary Command (NIC) at Rikers Island
Current Phase
(Completed)
Actual Design Start
2021-09-30T00:00:00.000
Actual Design End
2021-09-30T00:00:00.000
Actual Construction
2021-09-30T00:00:00.000
Actual Construction 1
2021-10-01T00:00:00.000
Actual Construction Start
2021-10-01T00:00:00.000
Actual Construction End
2023-02-28T00:00:00.000
Borough
Bronx
Community Board
Bronx
Budget Line
C-0075
Ten Year Plan Category
BUILDING SYSTEMS AND INFRASTRUCTURE
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DOC
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DOC
Pid
3888
Fms Id
C75EWAMKC
Total Budget
28005625.00
Spend To Date
22257895.14
Spend To Date 1
0.7947
Fms Project Name
Emergency Work for AMKC
Agency Project Name
Renovation of Various Complexes at Rikers Island
Current Phase
Construction
Current Phase Start
2021-10-01T00:00:00.000
Forecast Current Phase End
2024-07-17T00:00:00.000
Forecast Completion
2024-07-17T00:00:00.000
Actual Design Start
2021-09-30T00:00:00.000
Actual Design End
2021-09-30T00:00:00.000
Actual Construction
2021-09-30T00:00:00.000
Actual Construction 1
2021-10-01T00:00:00.000
Actual Construction Start
2021-10-01T00:00:00.000
Borough
Bronx
Community Board
Bronx
Budget Line
C-0075
Ten Year Plan Category
BUILDING SYSTEMS AND INFRASTRUCTURE
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DOC
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DOC
Pid
3888
Fms Id
C75EWRMSC
Total Budget
96031673.72
Spend To Date
84109612.90
Spend To Date 1
0.8758
Fms Project Name
Emergency Work for RMSC
Agency Project Name
Renovation of Various Complexes at Rikers Island
Current Phase
Construction
Current Phase Start
2021-10-01T00:00:00.000
Forecast Current Phase End
2024-07-17T00:00:00.000
Forecast Completion
2024-07-17T00:00:00.000
Actual Design Start
2021-09-30T00:00:00.000
Actual Design End
2021-09-30T00:00:00.000
Actual Construction
2021-09-30T00:00:00.000
Actual Construction 1
2021-10-01T00:00:00.000
Actual Construction Start
2021-10-01T00:00:00.000
Borough
Bronx
Community Board
Bronx
Budget Line
C-0075
Ten Year Plan Category
BUILDING SYSTEMS AND INFRASTRUCTURE
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DOC
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DOC
Pid
3888
Fms Id
C75EWRNDC
Total Budget
37753257.48
Spend To Date
34161729.74
Spend To Date 1
0.9048
Fms Project Name
Emergency Work for RNDC
Agency Project Name
Renovation of Various Complexes at Rikers Island
Current Phase
Construction
Current Phase Start
2021-10-01T00:00:00.000
Forecast Current Phase End
2024-07-17T00:00:00.000
Forecast Completion
2024-07-17T00:00:00.000
Actual Design Start
2021-09-30T00:00:00.000
Actual Design End
2021-09-30T00:00:00.000
Actual Construction
2021-09-30T00:00:00.000
Actual Construction 1
2021-10-01T00:00:00.000
Actual Construction Start
2021-10-01T00:00:00.000
Borough
Bronx
Community Board
Bronx
Budget Line
C-0075
Ten Year Plan Category
BUILDING SYSTEMS AND INFRASTRUCTURE
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: FDNY
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
FDNY
Pid
3889
Fms Id
F175EC268
Total Budget
32936687.00
Spend To Date
2954923.64
Spend To Date 1
0.0897
Fms Project Name
NEW FIREHOUSE - EC268
Agency Project Name
NEW FIREHOUSE - EC268
Current Phase
Design
Current Phase Start
2019-10-17T00:00:00.000
Forecast Current Phase End
2023-12-18T00:00:00.000
Forecast Completion
2026-07-15T00:00:00.000
Actual Design Start
2019-10-17T00:00:00.000
Borough
Queens
Community Board
Queens 14
Budget Line
F-0175
Ten Year Plan Category
NEW FACILITIES AND RENOVATIONS
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: FDNY
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
FDNY
Pid
3890
Fms Id
F175EMS17
Total Budget
44837996.88
Spend To Date
3963912.09
Spend To Date 1
0.0884
Fms Project Name
EMS Station 17 - New Facility
Agency Project Name
EMS Station 17 - New Facility
Current Phase
Construction Procurement
Current Phase Start
2023-05-12T00:00:00.000
Forecast Current Phase End
2023-12-11T00:00:00.000
Forecast Completion
2025-12-11T00:00:00.000
Actual Design Start
2019-01-18T00:00:00.000
Actual Design End
2023-05-12T00:00:00.000
Actual Construction
2023-05-12T00:00:00.000
Borough
Citywide
Community Board
Citywide
Budget Line
F-0001, F-0175
Ten Year Plan Category
NEW FACILITIES AND RENOVATIONS
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: NYCHA
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
NYCHA
Pid
3891
Fms Id
HAM20BVBG
Total Budget
10438226.21
Spend To Date
1381190.35
Spend To Date 1
0.1323
Fms Project Name
VAN DYKE BOXING GYM
Agency Project Name
Van Dyke Boxing Gym Community Center Interior Renovation
Current Phase
Design
Current Phase Start
2021-06-14T00:00:00.000
Forecast Current Phase End
2023-12-22T00:00:00.000
Forecast Completion
2025-07-01T00:00:00.000
Actual Design Start
2021-06-14T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn 16
Budget Line
HA-0001
Ten Year Plan Category
LOW TO MODERATE INCOME PUBLIC HOUSING UPGRADE
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: NYCHA
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
NYCHA
Pid
3892
Fms Id
HAM20BVCC
Total Budget
10442570.51
Spend To Date
1303990.40
Spend To Date 1
0.1248
Fms Project Name
BROWNSVILLE COMMUNITY CENTER
Agency Project Name
Brownsville Houses Community Center Interior Renovation
Current Phase
Design
Current Phase Start
2021-06-14T00:00:00.000
Forecast Current Phase End
2023-12-22T00:00:00.000
Forecast Completion
2025-07-01T00:00:00.000
Actual Design Start
2021-06-14T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn 16
Budget Line
HA-0001
Ten Year Plan Category
LOW TO MODERATE INCOME PUBLIC HOUSING UPGRADE
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DHS
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DHS
Pid
3893
Fms Id
HH112BLEN
Total Budget
8990459.09
Spend To Date
223778.38
Spend To Date 1
0.0248
Fms Project Name
Bellevue Auditorium Structural Reconstruction
Agency Project Name
Investigatory Probes of Cellar columns, beams & slabs
Current Phase
Construction
Current Phase Start
2023-04-28T00:00:00.000
Forecast Current Phase End
2024-12-31T00:00:00.000
Forecast Completion
2024-12-31T00:00:00.000
Actual Design Start
2021-09-03T00:00:00.000
Actual Design End
2022-07-20T00:00:00.000
Actual Construction
2022-07-20T00:00:00.000
Actual Construction 1
2023-04-28T00:00:00.000
Actual Construction Start
2023-04-28T00:00:00.000
Borough
Manhattan
Community Board
Manhattan
Budget Line
HH-0112
Ten Year Plan Category
SHELTERS FOR HOMELESS INDIVIDUALS
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DHS
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DHS
Pid
3894
Fms Id
HH112BLFX
Total Budget
5010000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
BELLEVUE - FACADE RESTORATION & WINDOW REPLACEMENT
Agency Project Name
Bellevue Men’s Shelter Partial East Façade Restoration and Window Replacement
Current Phase
Construction Procurement
Current Phase Start
2022-07-06T00:00:00.000
Forecast Current Phase End
2024-07-30T00:00:00.000
Forecast Completion
2025-01-31T00:00:00.000
Actual Design Start
2021-12-16T00:00:00.000
Actual Design End
2022-07-06T00:00:00.000
Actual Construction
2022-07-06T00:00:00.000
Borough
Manhattan
Community Board
Manhattan 06
Budget Line
HH-0112
Ten Year Plan Category
SHELTERS FOR HOMELESS INDIVIDUALS
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DHS
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DHS
Pid
3895
Fms Id
HH112PJFC
Total Budget
7624777.00
Spend To Date
621522.87
Spend To Date 1
0.0815
Fms Project Name
PAMOJA HOUSE - FACADE REHABILITATION/RESTORATION
Agency Project Name
Façade Stabilization
Current Phase
Construction
Current Phase Start
2023-04-25T00:00:00.000
Forecast Current Phase End
2024-08-30T00:00:00.000
Forecast Completion
2024-08-30T00:00:00.000
Actual Design Start
2022-03-16T00:00:00.000
Actual Design End
2022-05-24T00:00:00.000
Actual Construction
2022-05-24T00:00:00.000
Actual Construction 1
2023-04-25T00:00:00.000
Actual Construction Start
2023-04-25T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn
Budget Line
HH-0112
Ten Year Plan Category
SHELTERS FOR HOMELESS INDIVIDUALS
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: HRA
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
HRA
Pid
3897
Fms Id
HR25BRCS
Total Budget
129370756.00
Spend To Date
3675058.26
Spend To Date 1
0.0284
Fms Project Name
Brownsville Community Center DESIGN BUILD
Agency Project Name
444 Thomas Boyland Community Center
Current Phase
Construction
Current Phase Start
2023-05-01T00:00:00.000
Forecast Current Phase End
2026-05-18T00:00:00.000
Forecast Completion
2026-05-18T00:00:00.000
Actual Design Start
2023-02-15T00:00:00.000
Actual Design End
2023-04-28T00:00:00.000
Actual Construction
2023-04-28T00:00:00.000
Actual Construction 1
2023-05-01T00:00:00.000
Actual Construction Start
2023-05-01T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn
Budget Line
HR-0025
Ten Year Plan Category
SOCIAL SERVICES BUILDINGS
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: BPL
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
BPL
Pid
3898
Fms Id
LBC17CDOP
Total Budget
1323515.40
Spend To Date
583594.83
Spend To Date 1
0.4409
Fms Project Name
CLARENDON OUTDOOR PLAZA
Agency Project Name
CLARENDON OUTDOOR PLAZA
Current Phase
Construction
Current Phase Start
2022-09-19T00:00:00.000
Forecast Current Phase End
2023-10-31T00:00:00.000
Forecast Completion
2023-10-31T00:00:00.000
Actual Design Start
2019-11-27T00:00:00.000
Actual Design End
2022-05-19T00:00:00.000
Actual Construction
2022-05-19T00:00:00.000
Actual Construction 1
2022-09-19T00:00:00.000
Actual Construction Start
2022-09-19T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn 17
Budget Line
LB-0104, LB-D104
Ten Year Plan Category
ESSENTIAL RECONSTRUCTION OF FACILITIES
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: BPL
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
BPL
Pid
3899
Fms Id
LBK16STRF
Total Budget
2322685.00
Spend To Date
849189.83
Spend To Date 1
0.3656
Fms Project Name
Saratoga Envelope Rehab
Agency Project Name
SARATOGA LIBRARY BUILDING ENVELOPE REHABILITATION
Current Phase
Construction
Current Phase Start
2022-10-12T00:00:00.000
Forecast Current Phase End
2023-09-29T00:00:00.000
Forecast Completion
2023-09-29T00:00:00.000
Actual Design Start
2019-03-05T00:00:00.000
Actual Design End
2022-02-25T00:00:00.000
Actual Construction
2022-02-25T00:00:00.000
Actual Construction 1
2022-10-12T00:00:00.000
Actual Construction Start
2022-10-12T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn 16
Budget Line
LB-0104, LB-D104, LB-K001
Ten Year Plan Category
ESSENTIAL RECONSTRUCTION OF FACILITIES
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: BPL
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
BPL
Pid
3900
Fms Id
LBM18EPOH
Total Budget
33800500.00
Spend To Date
3236470.24
Spend To Date 1
0.0957
Fms Project Name
Eastern Parkway Overhaul
Agency Project Name
EASTERN PARKWAY LIBRARY MAJOR RENOVATIONS
Current Phase
Design
Current Phase Start
2018-06-28T00:00:00.000
Forecast Current Phase End
2023-10-12T00:00:00.000
Forecast Completion
2026-11-30T00:00:00.000
Actual Design Start
2018-06-28T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn 09
Budget Line
LB-0104, LB-D104
Ten Year Plan Category
ESSENTIAL RECONSTRUCTION OF FACILITIES
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: BPL
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
BPL
Pid
3901
Fms Id
LBP21WIBR
Total Budget
13425000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
WASHINGTON IRVING RENOVATION
Agency Project Name
WASHINGTON IRVING BRANCH RENOVATION
Current Phase
Design
Current Phase Start
2023-07-24T00:00:00.000
Forecast Current Phase End
2025-08-04T00:00:00.000
Forecast Completion
2028-04-15T00:00:00.000
Actual Design Start
2023-07-24T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn 04
Budget Line
LB-0101, LB-0104, LB-0108, LB-D104
Ten Year Plan Category
ESSENTIAL RECONSTRUCTION OF FACILITIES
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: NYPL
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
NYPL
Pid
3902
Fms Id
LN18ALELE
Total Budget
2036335.00
Spend To Date
37000.00
Spend To Date 1
0.0181
Fms Project Name
ALLERTON - Elevator Replacement - 3 stop
Agency Project Name
"ALLERTON - Elevator Replacement - 3 stop
Current Phase
Design
Current Phase Start
2022-04-07T00:00:00.000
Forecast Current Phase End
2024-03-08T00:00:00.000
Forecast Completion
2025-10-31T00:00:00.000
Actual Design Start
2022-04-07T00:00:00.000
Borough
Bronx
Community Board
Bronx 11
Budget Line
LN-0008, LN-X001
Ten Year Plan Category
ESSENTIAL RECONSTRUCTION OF FACILITIES
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: NYPL
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
NYPL
Pid
3903
Fms Id
LN18CDSGN
Total Budget
6345642.00
Spend To Date
4795616.61
Spend To Date 1
0.7557
Agency Project Name
5 Carnegie Renovations - DSGN
Current Phase
Close-out
Actual Design Start
2018-09-12T00:00:00.000
Actual Design End
2018-12-07T00:00:00.000
Actual Construction
2018-12-07T00:00:00.000
Actual Construction 1
2019-06-03T00:00:00.000
Actual Construction Start
2019-06-03T00:00:00.000
Actual Construction End
2023-01-15T00:00:00.000
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: NYPL
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
NYPL
Pid
3904
Fms Id
LN18MRBOI
Total Budget
2779023.21
Spend To Date
75621.65
Spend To Date 1
0.0272
Fms Project Name
Morrisania - Boiler Replacement
Agency Project Name
Morrisania - Boiler Replacement
Current Phase
Design
Current Phase Start
2022-04-14T00:00:00.000
Forecast Current Phase End
2023-12-15T00:00:00.000
Forecast Completion
2025-09-01T00:00:00.000
Actual Design Start
2022-04-14T00:00:00.000
Borough
Bronx
Community Board
Bronx 03
Budget Line
LN-D008
Ten Year Plan Category
ESSENTIAL RECONSTRUCTION OF FACILITIES
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: NYPL
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
NYPL
Pid
3905
Fms Id
LNRA17NDP
Total Budget
6453843.31
Spend To Date
176010.07
Spend To Date 1
0.0272
Fms Project Name
NEW DORP - HVAC System Replacement
Agency Project Name
New Dorp Library HVAC system Removal and Replacement
Current Phase
Design
Current Phase Start
2022-03-08T00:00:00.000
Forecast Current Phase End
2023-10-08T00:00:00.000
Forecast Completion
2026-08-17T00:00:00.000
Actual Design Start
2022-03-08T00:00:00.000
Borough
Staten Island
Community Board
Staten Island 02
Budget Line
LN-0008, LN-D008, LN-R001
Ten Year Plan Category
ESSENTIAL RECONSTRUCTION OF FACILITIES
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: NYPL
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
NYPL
Pid
3906
Fms Id
LNXA20WKF
Total Budget
3590000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
Wakefield - Infrastructure and ADA Upgrades
Agency Project Name
ADA Upgrade
Current Phase
Design
Current Phase Start
2023-03-03T00:00:00.000
Forecast Current Phase End
2024-08-26T00:00:00.000
Forecast Completion
2026-10-05T00:00:00.000
Actual Design Start
2023-03-03T00:00:00.000
Borough
Bronx
Community Board
Bronx
Budget Line
LN-0008, LN-D008, LN-I001, LN-X001
Ten Year Plan Category
ESSENTIAL RECONSTRUCTION OF FACILITIES
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: QPL
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
QPL
Pid
3907
Fms Id
LQAUB-RG
Total Budget
941000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
Auburndale - Reading Garden
Agency Project Name
Auburndale - Exterior Reading Garden
Current Phase
Pre-Design
Borough
Queens
Community Board
Queens
Budget Line
LQ-D122, LQ-Q122
Ten Year Plan Category
SUPPORT SERVICES IMPROVEMENTS
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: QPL
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
QPL
Pid
3908
Fms Id
LQBPEXPN
Total Budget
15353960.00
Spend To Date
1490772.33
Spend To Date 1
0.097
Fms Project Name
BAISLEY PARK - Branch Renovation
Agency Project Name
Baisley Park Library - Renovation
Current Phase
Design
Current Phase Start
2020-11-09T00:00:00.000
Forecast Current Phase End
2024-11-14T00:00:00.000
Forecast Completion
2027-07-31T00:00:00.000
Actual Design Start
2020-11-09T00:00:00.000
Borough
Queens
Community Board
Queens 12
Budget Line
LQ-0122, LQ-0122, LQ-D122, LQ-D122, LQ-Q005, LQ-Q122, LQ-Q122
Ten Year Plan Category
REPLACEMENT BRANCHES
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: QPL
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
QPL
Pid
3909
Fms Id
LQBW-EXP
Total Budget
13456438.70
Spend To Date
673587.86
Spend To Date 1
0.05
Fms Project Name
Briarwood: Branch Renovation
Agency Project Name
Briarwood Community Branch Library
Current Phase
Design
Current Phase Start
2022-10-24T00:00:00.000
Forecast Current Phase End
2024-04-02T00:00:00.000
Forecast Completion
2027-10-04T00:00:00.000
Actual Design Start
2022-10-24T00:00:00.000
Borough
Queens
Community Board
Queens
Budget Line
LQ-0122, LQ-D122, LQ-Q122
Ten Year Plan Category
ESSENTIAL RECONSTRUCTION OF FACILITIES
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: QPL
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
QPL
Pid
3910
Fms Id
LQC122-JH
Total Budget
33346647.73
Spend To Date
1363790.12
Spend To Date 1
0.0408
Fms Project Name
JACKSON HEIGHTS - Branch Expansion & Renovation
Agency Project Name
Jackson Heights - Comprehensive Renovation and Expansion
Current Phase
Design
Current Phase Start
2021-10-06T00:00:00.000
Forecast Current Phase End
2024-03-13T00:00:00.000
Forecast Completion
2028-03-31T00:00:00.000
Actual Design Start
2021-10-06T00:00:00.000
Borough
Queens
Community Board
Queens 03
Budget Line
LQ-0122, LQ-0122, LQ-D122, LQ-D122
Ten Year Plan Category
REPLACEMENT BRANCHES
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: QPL
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
QPL
Pid
3911
Fms Id
LQD122-CL
Total Budget
6301663.00
Spend To Date
1813792.46
Spend To Date 1
0.2878
Fms Project Name
Queens Central Library Renovation - Pass-Through
Agency Project Name
Queens Central Library Renovation
Current Phase
Close-out
Actual Design Start
2019-04-23T00:00:00.000
Actual Design End
2019-04-30T00:00:00.000
Actual Construction
2019-04-30T00:00:00.000
Actual Construction 1
2019-07-19T00:00:00.000
Actual Construction Start
2019-07-19T00:00:00.000
Actual Construction End
2023-04-28T00:00:00.000
Borough
Queens
Community Board
Queens 12
Budget Line
LQ-0122
Ten Year Plan Category
ESSENTIAL RECONSTRUCTION OF FACILITIES
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: QPL
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
QPL
Pid
3912
Fms Id
LQD122LAE
Total Budget
15209000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
LAURELTON: Branch Renovation
Agency Project Name
Laurelton - Exterior & Interior Renovation
Current Phase
Design
Current Phase Start
2023-04-17T00:00:00.000
Forecast Current Phase End
2024-03-26T00:00:00.000
Forecast Completion
2027-07-26T00:00:00.000
Actual Design Start
2023-04-17T00:00:00.000
Borough
Queens
Community Board
Queens
Budget Line
LQ-0122, LQ-D122, LQ-Q122
Ten Year Plan Category
RECONSTRUCTION NECESSARY TO MAINTAIN FACILITIES
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: QPL
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
QPL
Pid
3913
Fms Id
LQEM19FFA
Total Budget
7020575.44
Spend To Date
324812.27
Spend To Date 1
0.0462
Fms Project Name
FLUSHING: FIRE ALARM
Agency Project Name
Flushing - Replacement of the Fire Alarm System(s)
Current Phase
Design
Current Phase Start
2021-10-29T00:00:00.000
Forecast Current Phase End
2023-06-23T00:00:00.000
Forecast Completion
2024-12-18T00:00:00.000
Actual Design Start
2021-10-29T00:00:00.000
Borough
Queens
Community Board
Queens
Budget Line
LQ-0122, LQ-D122
Ten Year Plan Category
ESSENTIAL RECONSTRUCTION OF FACILITIES
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: QPL
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
QPL
Pid
3914
Fms Id
LQEM19FLU
Total Budget
1548322.97
Spend To Date
232741.58
Spend To Date 1
0.1503
Fms Project Name
FLUSHING:Emergency Functionality
Agency Project Name
Flushing - Day Tank Replacement for Emergency Generator
Current Phase
Design
Current Phase Start
2021-11-22T00:00:00.000
Forecast Current Phase End
2023-05-12T00:00:00.000
Forecast Completion
2024-10-01T00:00:00.000
Actual Design Start
2021-11-22T00:00:00.000
Borough
Queens
Community Board
Queens
Budget Line
LQ-0122
Ten Year Plan Category
ESSENTIAL RECONSTRUCTION OF FACILITIES
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: QPL
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
QPL
Pid
3915
Fms Id
LQRS-EXTR
Total Budget
26376000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
ROSEDALE: Branch Expansion and Renovation
Agency Project Name
Rosedale - Renovation and Expansion of Existing Facility
Current Phase
Design
Current Phase Start
2023-01-13T00:00:00.000
Forecast Current Phase End
2024-09-30T00:00:00.000
Forecast Completion
2027-11-01T00:00:00.000
Actual Design Start
2023-01-13T00:00:00.000
Borough
Queens
Community Board
Queens
Budget Line
LQ-0122, LQ-0122, LQ-D122, LQ-D122, LQ-Q122, LQ-Q122, LQ-Q122
Ten Year Plan Category
SUPPORT SERVICES IMPROVEMENTS
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DPR
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DPR
Pid
3916
Fms Id
NDF-CRLYN
Total Budget
92699238.75
Spend To Date
5989128.71
Spend To Date 1
0.0646
Fms Project Name
Mary Cali Dalton Recreation Center DB
Agency Project Name
Mary Cali Dalton Recreation Center
Current Phase
Design
Current Phase Start
2022-04-18T00:00:00.000
Forecast Current Phase End
2024-01-02T00:00:00.000
Forecast Completion
2025-10-15T00:00:00.000
Actual Design Start
2022-04-18T00:00:00.000
Borough
Staten Island
Community Board
Staten Island
Budget Line
ED-0384, P-1018
Ten Year Plan Category
NEIGHBORHOOD REVITALIZATION
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DCAS
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DCAS
Pid
3917
Fms Id
NDF-DAVID
Total Budget
3554000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
NDF - DAVIDSON AVE COMMUNITY CENTER
Agency Project Name
DAVIDSON AVE COMMUNITY CENTER
Current Phase
Design
Current Phase Start
2023-03-02T00:00:00.000
Forecast Current Phase End
2024-07-03T00:00:00.000
Forecast Completion
2026-11-04T00:00:00.000
Actual Design Start
2023-03-02T00:00:00.000
Borough
Bronx
Community Board
Bronx 05
Budget Line
ED-0384
Ten Year Plan Category
NEIGHBORHOOD REVITALIZATION
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DPR
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DPR
Pid
3918
Fms Id
P-1ORCHMO
Total Budget
48373814.32
Spend To Date
8759467.50
Spend To Date 1
0.181
Fms Project Name
Orchard Beach M&O Facility Reconstruction DB
Agency Project Name
Orchard Beach Maintenance and Operations Building Site Work & New Construction
Current Phase
Construction
Current Phase Start
2023-01-23T00:00:00.000
Forecast Current Phase End
2025-06-02T00:00:00.000
Forecast Completion
2025-06-02T00:00:00.000
Actual Design Start
2022-03-18T00:00:00.000
Actual Design End
2023-01-20T00:00:00.000
Actual Construction
2023-01-20T00:00:00.000
Actual Construction 1
2023-01-23T00:00:00.000
Actual Construction Start
2023-01-23T00:00:00.000
Borough
Bronx
Community Board
Bronx
Budget Line
P-0715, P-1018, P-D021
Ten Year Plan Category
BEACHES AND BOARDWALKS
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000