Capital Projects Dashboard - Citywide Budget and Schedule

All major capital infrastructure projects with a committed budget. Financial information and agency schedule details for each project are joined via FMS ID. Only projects in the design phase or later have project schedules displayed. This dataset is part of the Capital Projects Dashboard.

Note: Each row is uniquely identified by its Financial Management Service (FMS) ID. FMS ID is the unique ID that OMB uses for the FMS (Financial Information System). This ID can be universally joined with any OMB dataset that has the same field. The Capital Projects Dashboard is the result of joining OMB’s fiscal data with the agency’s schedule data. FMS IDs and agency projects don't always have a one-to-one relationship (i.e., one project schedule may correlate to multiple FMS IDs, and one FMS may correct to multiple projects with different schedules).

City Government Mayor's Office of Operations (OPS) Dataset fb86-vt7u 27 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DHS
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DHS
Pid
4120
Fms Id
HH112CWFR
Total Budget
2797476.08
Spend To Date
2217576.97
Spend To Date 1
0.7927
Fms Project Name
COMMONWEALTH AVENUE FIRE SAFETY SYSTEM
Agency Project Name
1150 Commonwealth Ave: Fire Alarm Upgrade
Agency Project Description
Installation of new building wide fire alarm system for Commonwealth Avenue Shelter
Current Phase
Construction
Current Phase Start
2018-06-13T00:00:00.000
Forecast Current Phase End
2023-12-29T00:00:00.000
Forecast Completion
2023-12-29T00:00:00.000
Actual Design Start
2016-10-19T00:00:00.000
Actual Design End
2017-06-09T00:00:00.000
Actual Construction
2017-06-09T00:00:00.000
Actual Construction 1
2018-06-13T00:00:00.000
Actual Construction Start
2018-06-13T00:00:00.000
Borough
Bronx
Community Board
Bronx
Budget Line
HH-0112
Ten Year Plan Category
SHELTERS FOR HOMELESS INDIVIDUALS
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DCAS
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DCAS
Pid
4121
Fms Id
PW293QBLV
Total Budget
11667577.93
Spend To Date
9558569.37
Spend To Date 1
0.8192
Fms Project Name
120-55 QUEENS BLVD - FIRE ALARM
Agency Project Name
BOROUGH HALL: 120-55 QUEENS BLVD FIRE ALARM UPGRAD
Agency Project Description
Installation of new building wide fire alarm system for Queen Borough Hall
Current Phase
Construction
Current Phase Start
2021-06-16T00:00:00.000
Forecast Current Phase End
2023-09-29T00:00:00.000
Forecast Completion
2023-09-29T00:00:00.000
Actual Design Start
2017-05-27T00:00:00.000
Actual Design End
2019-12-27T00:00:00.000
Actual Construction
2019-12-27T00:00:00.000
Actual Construction 1
2021-06-16T00:00:00.000
Actual Construction Start
2021-06-16T00:00:00.000
Borough
Queens
Community Board
Queens 01
Budget Line
PW-0293
Ten Year Plan Category
LEGAL MANDATES AND CORRECTION OF UNSAFE CONDITIONS
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DHS
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DHS
Pid
4122
Fms Id
HH115JCFB
Total Budget
1669175.94
Spend To Date
244008.79
Spend To Date 1
0.1461
Fms Project Name
JENNIE CLARK RESIDENCE - FIRE ALARM UPGRADE
Agency Project Name
Jennie Clark: Fire Alarm Upgrade
Agency Project Description
Installation of new building wide fire alarm system.
Current Phase
Design
Current Phase Start
2016-02-23T00:00:00.000
Forecast Current Phase End
2024-04-11T00:00:00.000
Forecast Completion
2026-01-06T00:00:00.000
Actual Design Start
2016-02-23T00:00:00.000
Borough
Manhattan
Community Board
Manhattan
Budget Line
HH-0115
Ten Year Plan Category
SHELTERS FOR HOMELESS FAMILIES
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DHS
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DHS
Pid
4123
Fms Id
HH115SRFA
Total Budget
1161921.08
Spend To Date
1108517.66
Spend To Date 1
0.954
Fms Project Name
ROSE MCCARTHY - FIRE ALARM SYSTEM UPGRADE
Agency Project Name
Rose McCarthy Family Residence: Fire alarm Upgrade
Agency Project Description
Installation of new building wide fire alarm system.
Current Phase
Close-out
Actual Design Start
2016-03-18T00:00:00.000
Actual Design End
2016-09-23T00:00:00.000
Actual Construction
2016-09-23T00:00:00.000
Actual Construction 1
2018-06-27T00:00:00.000
Actual Construction Start
2018-06-27T00:00:00.000
Actual Construction End
2023-07-19T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn
Budget Line
HH-0115
Ten Year Plan Category
SHELTERS FOR HOMELESS FAMILIES
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DEP
Pid
4124
Fms Id
CT2-INTER
Total Budget
15977316.90
Spend To Date
5550311.73
Spend To Date 1
0.3473
Fms Project Name
CITY TUNNEL #2, REPLACE GUARD VALVES @ 16A
Agency Project Name
INSTALL. OF NEW TRUNK MAIN, VALVES & APPURT. @16A
Agency Project Description
INSTALLATION OF NEW TRUNK MAIN, VALVES & APPURTENANCES IN SHAFT 16A, BROOKLYN.
Current Phase
Construction
Current Phase Start
2020-06-22T00:00:00.000
Forecast Current Phase End
2023-12-21T00:00:00.000
Forecast Completion
2023-12-21T00:00:00.000
Actual Design Start
2014-12-16T00:00:00.000
Actual Design End
2018-06-28T00:00:00.000
Actual Construction
2018-06-28T00:00:00.000
Actual Construction 1
2020-06-22T00:00:00.000
Actual Construction Start
2020-06-22T00:00:00.000
Borough
Citywide
Community Board
Citywide
Budget Line
WM-0105
Ten Year Plan Category
WATER QUALITY PRESERVATION
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DEP
Pid
4125
Fms Id
MED-619
Total Budget
21701505.18
Spend To Date
2045567.66
Spend To Date 1
0.0942
Fms Project Name
Trunk Main replacement, b'way b/t w 93 & 97 st, Manh
Agency Project Name
NEW 36" TRUNK MAIN IN BROADWAY, MN
Agency Project Description
Installation of New Trunk Water Main in Broadway between W. 93rd Street and W. 97th Street, etc. in the Borough of Manhattan
Current Phase
Design
Current Phase Start
2016-05-24T00:00:00.000
Forecast Current Phase End
2023-12-28T00:00:00.000
Forecast Completion
2027-08-22T00:00:00.000
Actual Design Start
2016-05-24T00:00:00.000
Borough
Manhattan
Community Board
Manhattan 07
Budget Line
SE-0002M, TF-0502, WM-0001, WM-0006
Ten Year Plan Category
TRUNK AND DISTRIBUTION MAIN REPLACEMENT
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4126
Fms Id
HWP21KRC
Total Budget
7416306.00
Spend To Date
212893.60
Spend To Date 1
0.0287
Fms Project Name
Non-Standard Installs - Brooklyn and Staten Island
Agency Project Name
Installation of pedestrian ramps at 44 non-standard corners in Brooklyn and Staten Island.
Agency Project Description
Installation of pedestrian ramps at 44 non standard corners in Brooklyn and Staten Island.
Current Phase
Design
Current Phase Start
2022-07-28T00:00:00.000
Forecast Current Phase End
2024-07-16T00:00:00.000
Forecast Completion
2027-04-14T00:00:00.000
Actual Design Start
2022-07-28T00:00:00.000
Borough
Citywide
Community Board
Citywide
Budget Line
HW-0200
Ten Year Plan Category
PEDESTRIAN RAMP CONSTRUCTION
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4127
Fms Id
HWP2021TA
Total Budget
7234396.00
Spend To Date
331236.13
Spend To Date 1
0.0457
Fms Project Name
Non-Standard Installs - TA
Agency Project Name
Installation of pedestrian ramps at 44 non-standard locations in Manhattan, Bronx, Staten Island, Brooklyn, and Queens.
Agency Project Description
Installation of pedestrian ramps at 44 non-standard locations in Manhattan, Bronx, Staten Island, Brooklyn, and Queens
Current Phase
Design
Current Phase Start
2022-08-02T00:00:00.000
Forecast Current Phase End
2024-07-21T00:00:00.000
Forecast Completion
2027-07-14T00:00:00.000
Actual Design Start
2022-08-02T00:00:00.000
Borough
Citywide
Community Board
Citywide
Budget Line
HW-0200
Ten Year Plan Category
PEDESTRIAN RAMP CONSTRUCTION
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4128
Fms Id
HWP2021LM
Total Budget
8572497.00
Spend To Date
674148.36
Spend To Date 1
0.0786
Fms Project Name
Non-Standard Installs - Landmark
Agency Project Name
Installation of pedestrian ramps at 54 non-standard landmarked locations in Manhattan, Brooklyn, and Queens.
Agency Project Description
Installation of pedestrian ramps at 54 non-standard landmarked locations in Manhattan, Brooklyn, and Queens
Current Phase
Design
Current Phase Start
2022-08-04T00:00:00.000
Forecast Current Phase End
2024-07-23T00:00:00.000
Forecast Completion
2027-03-18T00:00:00.000
Actual Design Start
2022-08-04T00:00:00.000
Borough
Citywide
Community Board
Citywide
Budget Line
HW-0200
Ten Year Plan Category
PEDESTRIAN RAMP CONSTRUCTION
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4129
Fms Id
HWP21MXQC
Total Budget
8449000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
Non-Standard Installs - Manhattan, Bronx, Queens
Agency Project Name
Installation of pedestrian ramps at 51 non-standard intersections in Manhattan, Bronx, and Queens.
Agency Project Description
Installation of pedestrian ramps at non-standard corners in Manhattan, Bronx, and Queens.
Current Phase
Design
Current Phase Start
2023-04-05T00:00:00.000
Forecast Current Phase End
2025-03-24T00:00:00.000
Forecast Completion
2028-02-15T00:00:00.000
Actual Design Start
2023-04-05T00:00:00.000
Borough
Citywide
Community Board
Citywide
Budget Line
HW-0200
Ten Year Plan Category
PEDESTRIAN RAMP CONSTRUCTION
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4130
Fms Id
HWP21KQC
Total Budget
8104275.00
Spend To Date
388094.97
Spend To Date 1
0.0478
Fms Project Name
Non-Standard Installs - Brooklyn and Queens
Agency Project Name
Installation of pedestrian ramps at 48 non-standard locations in Brooklyn and Queens.
Agency Project Description
Installation of pedestrian ramps at non-standard locations in Brooklyn and Queens..
Current Phase
Design
Current Phase Start
2022-08-04T00:00:00.000
Forecast Current Phase End
2024-07-23T00:00:00.000
Forecast Completion
2027-04-21T00:00:00.000
Actual Design Start
2022-08-04T00:00:00.000
Borough
Citywide
Community Board
Citywide
Budget Line
HW-0200
Ten Year Plan Category
PEDESTRIAN RAMP CONSTRUCTION
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DEP
Pid
4131
Fms Id
SEQ200558
Total Budget
13621741.40
Spend To Date
1653479.03
Spend To Date 1
0.1213
Fms Project Name
Install of storm SE & replacement of sanitary SE&dist.WM
Agency Project Name
SEQ - Install of storm SE & replacement of sanitar
Agency Project Description
Installation of storm sewers and replacement of sanitary sewers and distribution water mains at Eton St. between Barrington St. and Wexford Terrace.
Current Phase
Construction
Current Phase Start
2023-03-06T00:00:00.000
Forecast Current Phase End
2025-08-31T00:00:00.000
Forecast Completion
2025-08-31T00:00:00.000
Actual Design Start
2019-09-27T00:00:00.000
Actual Design End
2022-02-09T00:00:00.000
Actual Construction
2022-02-09T00:00:00.000
Actual Construction 1
2023-03-06T00:00:00.000
Actual Construction Start
2023-03-06T00:00:00.000
Borough
Queens
Community Board
Queens
Budget Line
HW-0200, SE-0002Q, SE-0200Q, SE-0944, WM-0001
Ten Year Plan Category
TRUNK AND DISTRIBUTION MAIN REPLACEMENT
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DEP
Pid
4132
Fms Id
SE-842A1
Total Budget
141030850.75
Spend To Date
6871562.13
Spend To Date 1
0.0487
Fms Project Name
SEQ - Storm Sewer Outlet in 224th Street
Agency Project Name
STORM SEWER OUTLET IN 224TH ST
Agency Project Description
Installation of storm sewers at 224th St and 149th Ave and along the access road through Idlewild Parks known as Springfield Lane (Spine Farmers Blvd)
Current Phase
Construction Procurement
Current Phase Start
2022-06-06T00:00:00.000
Forecast Current Phase End
2023-09-12T00:00:00.000
Forecast Completion
2026-09-10T00:00:00.000
Actual Design Start
2016-01-04T00:00:00.000
Actual Design End
2022-06-06T00:00:00.000
Actual Construction
2022-06-06T00:00:00.000
Borough
Queens
Community Board
Queens 13
Budget Line
EP-0007, HW-0001Q, SE-0200Q, TF-0502, WM-0001, WM-0006
Ten Year Plan Category
UTILITY RELOCATION FOR SE AND WM PROJECTS
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DEP, DOT
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DEP, DOT
Pid
4133
Fms Id
HWR669C
Total Budget
82379118.17
Spend To Date
63964341.01
Spend To Date 1
0.7764
Fms Project Name
RECONSTRUCTION OF ROMA, HETT, ETC, SAND669C
Agency Project Name
ROMA & HETT AVENUE, STATEN IS (W/SE-413A/SE-414A)
Agency Project Description
Installation of Storm, Sanitary Sewers in the following Streets:=================================1- Cedar Grove Avenue between Ebbitts Street and new Dorp Lane.2- Milton Avenue between Ebbitts Street and new Dorp Lane.3- Finley Avenue between Ebbitts Street and new Dorp Lane.4- Roma Avenue between Ebbitts Street and new Dorp Lane.5- Hett Avenue between Ebbitts Street and new Dorp Lane.6- Marine Way between Cedar Grove and Milton Avenue7- Beacon Avenue between Roma Avenue and Milton Avenue.8- Dustan Avenue between Marine way and Milton Avenue.9- Garibaldi Avenue between Roma Avenue and Cedar Grove Avenue.10- Cedar Grove Court between Cedar Grove Avenue and Dustan Street.11- Topping Street between Cedar Grove Avenue and Dustan Street.12- Center Way between Cedar Grove Avenue and Dustan Street.13- Neptune Street between Cedar Grove Avenue and Dustan Street.14- Seafoam Street between Cedar Grove Avenue and Dustan Street.15- Waterside Street between Cedar Grove Avenue and Dustan Street.16- Maple Terrace between Cedar Grove Avenue and Dustan Street.17- Herman Street between Cedar Grove Avenue and Dustan Street.18- Neutral Avenue between Cedar Grove Avenue and Dustan Street.19- Milbank Drive between Cedar Grove Avenue and Dustan Street.
Current Phase
Construction
Current Phase Start
2019-04-01T00:00:00.000
Forecast Current Phase End
2024-04-22T00:00:00.000
Forecast Completion
2024-04-22T00:00:00.000
Actual Design Start
2014-10-15T00:00:00.000
Actual Design End
2017-12-15T00:00:00.000
Actual Construction
2017-12-15T00:00:00.000
Actual Construction 1
2019-04-01T00:00:00.000
Actual Construction Start
2019-04-01T00:00:00.000
Borough
Staten Island
Community Board
Staten Island 02
Budget Line
HW-0001R, HW-0001R, HW-0061, HW-0669, SE-0200R, WM-0001
Ten Year Plan Category
SIDEWALK RECONSTRUCTION
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DEP, DOT
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DEP, DOT
Pid
4133
Fms Id
SE-413A
Total Budget
1267200.69
Spend To Date
1170218.61
Spend To Date 1
0.9234
Fms Project Name
STM/SAN IN CEDAR GROVE AV - EBBITTS ST & NEW DROP LANE
Agency Project Name
ROMA & HETT AVENUE, STATEN IS (W/SE-413A/SE-414A)
Agency Project Description
Installation of Storm, Sanitary Sewers in the following Streets:=================================1- Cedar Grove Avenue between Ebbitts Street and new Dorp Lane.2- Milton Avenue between Ebbitts Street and new Dorp Lane.3- Finley Avenue between Ebbitts Street and new Dorp Lane.4- Roma Avenue between Ebbitts Street and new Dorp Lane.5- Hett Avenue between Ebbitts Street and new Dorp Lane.6- Marine Way between Cedar Grove and Milton Avenue7- Beacon Avenue between Roma Avenue and Milton Avenue.8- Dustan Avenue between Marine way and Milton Avenue.9- Garibaldi Avenue between Roma Avenue and Cedar Grove Avenue.10- Cedar Grove Court between Cedar Grove Avenue and Dustan Street.11- Topping Street between Cedar Grove Avenue and Dustan Street.12- Center Way between Cedar Grove Avenue and Dustan Street.13- Neptune Street between Cedar Grove Avenue and Dustan Street.14- Seafoam Street between Cedar Grove Avenue and Dustan Street.15- Waterside Street between Cedar Grove Avenue and Dustan Street.16- Maple Terrace between Cedar Grove Avenue and Dustan Street.17- Herman Street between Cedar Grove Avenue and Dustan Street.18- Neutral Avenue between Cedar Grove Avenue and Dustan Street.19- Milbank Drive between Cedar Grove Avenue and Dustan Street.
Current Phase
Construction
Current Phase Start
2019-04-01T00:00:00.000
Forecast Current Phase End
2024-04-22T00:00:00.000
Forecast Completion
2024-04-22T00:00:00.000
Actual Design Start
2014-10-15T00:00:00.000
Actual Design End
2017-12-15T00:00:00.000
Actual Construction
2017-12-15T00:00:00.000
Actual Construction 1
2019-04-01T00:00:00.000
Actual Construction Start
2019-04-01T00:00:00.000
Borough
Staten Island
Community Board
Staten Island 02
Budget Line
SE-0413, SE-0414, WM-0001
Ten Year Plan Category
TRUNK AND DISTRIBUTION MAIN REPLACEMENT
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DEP, DOT
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DEP, DOT
Pid
4133
Fms Id
SE-414A
Total Budget
0.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
SANITRY SEWER IN CEDAR GROVE AV- EBBITS ST & DORPLANE
Agency Project Name
ROMA & HETT AVENUE, STATEN IS (W/SE-413A/SE-414A)
Agency Project Description
Installation of Storm, Sanitary Sewers in the following Streets:=================================1- Cedar Grove Avenue between Ebbitts Street and new Dorp Lane.2- Milton Avenue between Ebbitts Street and new Dorp Lane.3- Finley Avenue between Ebbitts Street and new Dorp Lane.4- Roma Avenue between Ebbitts Street and new Dorp Lane.5- Hett Avenue between Ebbitts Street and new Dorp Lane.6- Marine Way between Cedar Grove and Milton Avenue7- Beacon Avenue between Roma Avenue and Milton Avenue.8- Dustan Avenue between Marine way and Milton Avenue.9- Garibaldi Avenue between Roma Avenue and Cedar Grove Avenue.10- Cedar Grove Court between Cedar Grove Avenue and Dustan Street.11- Topping Street between Cedar Grove Avenue and Dustan Street.12- Center Way between Cedar Grove Avenue and Dustan Street.13- Neptune Street between Cedar Grove Avenue and Dustan Street.14- Seafoam Street between Cedar Grove Avenue and Dustan Street.15- Waterside Street between Cedar Grove Avenue and Dustan Street.16- Maple Terrace between Cedar Grove Avenue and Dustan Street.17- Herman Street between Cedar Grove Avenue and Dustan Street.18- Neutral Avenue between Cedar Grove Avenue and Dustan Street.19- Milbank Drive between Cedar Grove Avenue and Dustan Street.
Current Phase
Construction
Current Phase Start
2019-04-01T00:00:00.000
Forecast Current Phase End
2024-04-22T00:00:00.000
Forecast Completion
2024-04-22T00:00:00.000
Actual Design Start
2014-10-15T00:00:00.000
Actual Design End
2017-12-15T00:00:00.000
Actual Construction
2017-12-15T00:00:00.000
Actual Construction 1
2019-04-01T00:00:00.000
Actual Construction Start
2019-04-01T00:00:00.000
Borough
Staten Island
Community Board
Staten Island 02
Budget Line
SE-0414
Ten Year Plan Category
EXTENSIONS TO ACCOMMODATE NEW DEVELOPMENT
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DEP
Pid
4134
Fms Id
SEQ200605
Total Budget
8534000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
SEQ - Installation of relief sewer,storm sewers&WM(HWQ1206)
Agency Project Name
Installation of temporary relief sewer, storm sewers, and water mains along 166th St, Hendrickson Pl, and 108th ave, near Allen Cathedral Senior Residence.
Agency Project Description
Installation of temporary relief sewer, storm sewers, and water mains along 166th St, Hendrickson Pl, and 108th ave, near Allen Cathedral Senior Residence.
Current Phase
Pre-Design
Borough
Queens
Community Board
Queens 12
Budget Line
SE-0002Q, SE-0200Q, WM-0001
Ten Year Plan Category
TRUNK AND DISTRIBUTION MAIN REPLACEMENT
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DHS
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DHS
Pid
4135
Fms Id
HH112HSFA
Total Budget
3979769.68
Spend To Date
775508.94
Spend To Date 1
0.1948
Fms Project Name
HELP SEC - FIRE SAFETY
Agency Project Name
HELP USA:1 Wards Island: Fire Alarm Upgrade
Agency Project Description
Installation on new building wide fire alarm system at HELP 1 - Wards Island
Current Phase
Design
Current Phase Start
2018-01-03T00:00:00.000
Forecast Current Phase End
2024-07-19T00:00:00.000
Forecast Completion
2026-04-16T00:00:00.000
Actual Design Start
2018-01-03T00:00:00.000
Borough
Manhattan
Community Board
Manhattan
Budget Line
HH-0112
Ten Year Plan Category
SHELTERS FOR HOMELESS INDIVIDUALS
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DCAS
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DCAS
Pid
4136
Fms Id
PW348-72
Total Budget
22716000.00
Spend To Date
2366935.33
Spend To Date 1
0.1041
Fms Project Name
FUEL TANK REPLACEMENT
Agency Project Name
FUEL TANK REPLACEMENT
Agency Project Description
Installation, replacement, closure of gasoline and diesel underground/aboveground storage tanks at multiple locations within the Bronx.
Current Phase
Construction
Current Phase Start
2022-06-28T00:00:00.000
Forecast Current Phase End
2024-05-11T00:00:00.000
Forecast Completion
2024-05-11T00:00:00.000
Actual Design Start
2018-06-05T00:00:00.000
Actual Design End
2020-01-31T00:00:00.000
Actual Construction
2020-01-31T00:00:00.000
Actual Construction 1
2022-06-28T00:00:00.000
Actual Construction Start
2022-06-28T00:00:00.000
Borough
Citywide
Community Board
Citywide
Budget Line
PW-0348
Ten Year Plan Category
LEGAL MANDATES AND CORRECTION OF UNSAFE CONDITIONS
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: NYPL
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
NYPL
Pid
4137
Fms Id
LNCL15CAS
Total Budget
11069748.36
Spend To Date
1535132.39
Spend To Date 1
0.1386
Fms Project Name
CASTLE HILL: Partial Interior Renovation
Agency Project Name
Castle Hill Renovation Projects
Agency Project Description
INTERIOR & EXTERIOR RENOVATION
Current Phase
Design
Current Phase Start
2015-05-04T00:00:00.000
Forecast Current Phase End
2023-11-10T00:00:00.000
Forecast Completion
2026-03-26T00:00:00.000
Actual Design Start
2015-05-04T00:00:00.000
Borough
Bronx
Community Board
Bronx
Budget Line
LN-0008, LN-0101X, LN-D004, LN-D008, LN-X001
Ten Year Plan Category
RECONSTRUCTION NECESSARY TO MAINTAIN FACILITIES
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DOHMH
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DOHMH
Pid
4138
Fms Id
CMERECORD
Total Budget
6355000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
OCME - Records Room Reconstruction at 421 East 26th St, Manh
Agency Project Name
Records Room Reconstruction at 421 East 26th St, Manhattan.
Agency Project Description
Interior renovation of portions of fourth floor to facilitate movement of Evidence Storage/Operations from the cellar and consolidating these along with the Division of Records on a single floor, offices, storage areas, new restrooms, new pantry, structural modifications for separate evidence storage exhaust ventilation to roof, and all associated MEP scope.
Current Phase
Pre-Design
Borough
Manhattan
Community Board
Manhattan 01
Budget Line
HL-0083
Ten Year Plan Category
OCME
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DCAS
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DCAS
Pid
4139
Fms Id
PW77417DA
Total Budget
8927169.93
Spend To Date
1044119.14
Spend To Date 1
0.1169
Fms Project Name
120-55 QUEENS BLVD.- QUEENS DA TRAINING ROOM
Agency Project Name
120-55 QUEENS BLVD.- QUEENS DA TRAINING ROOM
Agency Project Description
Interior renovation of space in Queens Borough Hall for the Queens DA
Current Phase
Construction
Current Phase Start
2023-05-16T00:00:00.000
Forecast Current Phase End
2024-09-09T00:00:00.000
Forecast Completion
2024-09-09T00:00:00.000
Actual Design Start
2014-04-21T00:00:00.000
Actual Design End
2021-12-03T00:00:00.000
Actual Construction
2021-12-03T00:00:00.000
Actual Construction 1
2023-05-16T00:00:00.000
Actual Construction Start
2023-05-16T00:00:00.000
Borough
Queens
Community Board
Queens 01
Budget Line
PW-0077, PW-0293
Ten Year Plan Category
REHABILITATION OF CITY-OWNED OFFICE SPACE
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4140
Fms Id
HWM10INWD
Total Budget
29312000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
Inwood 10th Avenue Improvements, NDF-IWHRG
Agency Project Name
Inwood 10th Avenue Safety Improvements
Agency Project Description
Inwood 10th Avenue Safety Improvements along 10th Avenue at Fort George Multisite, Harlem River Drive Gateway, Dyckman Rest Intersection, and Nagle Avenue, Borough of Manhattan
Current Phase
Pre-Design
Borough
Bronx
Community Board
Bronx
Budget Line
HW-0001
Ten Year Plan Category
PRIMARY STREET RECONSTRUCTION
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4141
Fms Id
BED833
Total Budget
2052000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
Rel.& Inst.WMs Flatland Ave bet Ralph Ave & E 76 St HWK2048
Agency Project Name
JAMAICA BAY GREENWAY-PAERDEGAT AVE N CONNECTOR
Agency Project Description
Jamaica Bay Greenway - Paerdegat Avenue North Connector
Current Phase
Construction Procurement
Current Phase Start
2023-08-03T00:00:00.000
Forecast Current Phase End
2024-04-03T00:00:00.000
Forecast Completion
2026-04-02T00:00:00.000
Actual Design Start
2017-08-04T00:00:00.000
Actual Design End
2023-08-03T00:00:00.000
Actual Construction
2023-08-03T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn 18
Budget Line
EP-0007, WM-0001
Ten Year Plan Category
UTILITY RELOCATION FOR SE AND WM PROJECTS
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4141
Fms Id
HWK2048
Total Budget
7969900.95
Spend To Date
1505266.97
Spend To Date 1
0.1888
Fms Project Name
Jamaica Bay Greenway - Paerdegat Ave.N Connector BED-833
Agency Project Name
JAMAICA BAY GREENWAY-PAERDEGAT AVE N CONNECTOR
Agency Project Description
Jamaica Bay Greenway - Paerdegat Avenue North Connector
Current Phase
Construction Procurement
Current Phase Start
2023-08-03T00:00:00.000
Forecast Current Phase End
2024-04-03T00:00:00.000
Forecast Completion
2026-04-02T00:00:00.000
Actual Design Start
2017-08-04T00:00:00.000
Actual Design End
2023-08-03T00:00:00.000
Actual Construction
2023-08-03T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn
Budget Line
HW-0001K, HW-0200, HW-0200, TF-0002, TF-0502
Ten Year Plan Category
TRAFFIC WORK IN CONJUNCTION WITH HIGHWAY RECONSTRUCTION
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DCAS
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DCAS
Pid
4142
Fms Id
CO281TOIL
Total Budget
13515620.07
Spend To Date
4464994.29
Spend To Date 1
0.3303
Fms Project Name
120 SCHERMERHORN ST.- CODE COMPLIANT TOILET UPGRADE
Agency Project Name
Central Courts Building:120 Schermerhorn St.
Agency Project Description
Kings County Criminal Courthouse ADA Toilets at 120 Schermerhorn Street - Renovate existing Men's and Women's public restrooms and holding cell facilities, and provide new public restrooms and all in compliance with ADA standards.
Current Phase
Construction
Current Phase Start
2022-01-24T00:00:00.000
Forecast Current Phase End
2024-05-17T00:00:00.000
Forecast Completion
2024-05-17T00:00:00.000
Actual Design Start
2016-10-18T00:00:00.000
Actual Design End
2019-07-18T00:00:00.000
Actual Construction
2019-07-18T00:00:00.000
Actual Construction 1
2022-01-24T00:00:00.000
Actual Construction Start
2022-01-24T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn 02
Budget Line
CO-0264, CO-0281
Ten Year Plan Category
RECONSTRUCTION/RENOVATION OF COURT FACILITIES
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DHS
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DHS
Pid
4143
Fms Id
HH112KELC
Total Budget
6754000.00
Spend To Date
728344.15
Spend To Date 1
0.1078
Fms Project Name
282 EAST 3RD STREET - ELECTRICAL UPGRADE
Agency Project Name
East 3rd Street Shelter Building Upgrade
Agency Project Description
Kitchen and Electrical Upgrade at E. 3rd St Shelter
Current Phase
Design
Current Phase Start
2019-10-11T00:00:00.000
Forecast Current Phase End
2024-08-28T00:00:00.000
Forecast Completion
2026-11-17T00:00:00.000
Actual Design Start
2019-10-11T00:00:00.000
Borough
Manhattan
Community Board
Manhattan
Budget Line
HH-0112
Ten Year Plan Category
SHELTERS FOR HOMELESS INDIVIDUALS
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: QPL
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
QPL
Pid
4144
Fms Id
LQLAROOF
Total Budget
2333981.91
Spend To Date
480648.41
Spend To Date 1
0.2059
Fms Project Name
LAURELTON ROOF
Agency Project Name
Laurelton Roof Replacement
Agency Project Description
Laurelton Library Branch restoration of exterior and roof
Current Phase
Construction
Current Phase Start
2023-07-24T00:00:00.000
Forecast Current Phase End
2024-08-12T00:00:00.000
Forecast Completion
2024-08-12T00:00:00.000
Actual Design Start
2016-09-26T00:00:00.000
Actual Design End
2020-02-07T00:00:00.000
Actual Construction
2020-02-07T00:00:00.000
Actual Construction 1
2023-07-24T00:00:00.000
Actual Construction Start
2023-07-24T00:00:00.000
Borough
Queens
Community Board
Queens
Budget Line
LQ-0122, LQ-D122
Ten Year Plan Category
RECONSTRUCTION NECESSARY TO MAINTAIN FACILITIES
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: BPL
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
BPL
Pid
4145
Fms Id
LBC14LDRF
Total Budget
1224986.56
Spend To Date
388721.53
Spend To Date 1
0.3173
Fms Project Name
LEONARD ROOF REPLACEMENT
Agency Project Name
Leonard Roof Replacement
Agency Project Description
Leonard Library Roof Replacement
Current Phase
Construction
Current Phase Start
2022-08-04T00:00:00.000
Forecast Current Phase End
2024-07-25T00:00:00.000
Forecast Completion
2024-07-25T00:00:00.000
Actual Design Start
2015-03-17T00:00:00.000
Actual Design End
2021-02-23T00:00:00.000
Actual Construction
2021-02-23T00:00:00.000
Actual Construction 1
2022-08-04T00:00:00.000
Actual Construction Start
2022-08-04T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn 01
Budget Line
LB-0104, LB-D104
Ten Year Plan Category
ESSENTIAL RECONSTRUCTION OF FACILITIES
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4146
Fms Id
HWMMLEXAV
Total Budget
21693018.20
Spend To Date
701941.24
Spend To Date 1
0.0323
Fms Project Name
Lexington Av Pedestrian Safety Improvement MED678 DSGN BUILD
Agency Project Name
Lexington Avenue Pedestrian Safety Improvements
Agency Project Description
Lexington Avenue Pedestrian Safety Improvements
Current Phase
Pre-Design
Borough
Manhattan
Community Board
Manhattan
Budget Line
HW-0001, HW-0001M, HW-0200, HW-0944, TF-0002, TF-0502
Ten Year Plan Category
TRAFFIC WORK IN CONJUNCTION WITH HIGHWAY RECONSTRUCTION
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4146
Fms Id
MED678
Total Budget
9006806.80
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
WM Rplmt Lexington Av btwn E 45 & E 49 St, MN HWMMLEXAV-DB
Agency Project Name
Lexington Avenue Pedestrian Safety Improvements
Agency Project Description
Lexington Avenue Pedestrian Safety Improvements
Current Phase
Pre-Design
Borough
Manhattan
Community Board
Manhattan 05, Manhattan 06
Budget Line
WM-0001
Ten Year Plan Category
AUGMENTATION OF WATER SUPPLY SYSTEMS
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DCAS
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DCAS
Pid
4148
Fms Id
CO277FA
Total Budget
8682801.73
Spend To Date
609233.80
Spend To Date 1
0.0701
Fms Project Name
25-10 COURT HOUSE SQ.- FIRE ALARM SYSTEM
Agency Project Name
126 Long Island City Courthouse: Fire Alarms
Agency Project Description
Long Island City Courthouse, Fire Alarm, 25-10 Court Square - • The Court Square Courthouse building will be provided with a new addressable non-proprietary fire alarm system and new complete sprinkler system.
Current Phase
Design
Current Phase Start
2022-03-30T00:00:00.000
Forecast Current Phase End
2024-08-28T00:00:00.000
Forecast Completion
2027-06-24T00:00:00.000
Actual Design Start
2022-03-30T00:00:00.000
Borough
Queens
Community Board
Queens 02
Budget Line
CO-0264, CO-0277
Ten Year Plan Category
RECONSTRUCTION/RENOVATION OF COURT FACILITIES
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DCAS
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DCAS
Pid
4149
Fms Id
E17-0001
Total Budget
9501718.00
Spend To Date
1773702.66
Spend To Date 1
0.1866
Fms Project Name
DCAS - LOUIS J LEFKOWITZ - ENERGY EFFICIENCY UPGRADE
Agency Project Name
Louis Lefkowitz Building Energy Efficiency Upgrade
Agency Project Description
Louis Lefkowitz Building Energy Efficiency Upgrade - to improve building performance and reduce energy consumption and greenhouse gas emissions.
Current Phase
Construction
Current Phase Start
2022-08-24T00:00:00.000
Forecast Current Phase End
2024-08-30T00:00:00.000
Forecast Completion
2024-08-30T00:00:00.000
Actual Design Start
2019-03-14T00:00:00.000
Actual Design End
2021-08-09T00:00:00.000
Actual Construction
2021-08-09T00:00:00.000
Actual Construction 1
2022-08-24T00:00:00.000
Actual Construction Start
2022-08-24T00:00:00.000
Borough
Manhattan
Community Board
Manhattan 02
Budget Line
PU-0025, PU-0025
Ten Year Plan Category
MISCELLANEOUS ENERGY EFFICIENCY AND SUSTAINABILITY
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: QPL
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
QPL
Pid
4150
Fms Id
LQD122-WN
Total Budget
21024857.66
Spend To Date
1628031.68
Spend To Date 1
0.0774
Fms Project Name
WOODHAVEN - Renovation
Agency Project Name
Woodhaven ADA, Elevator & Exterior Rehabilitation
Agency Project Description
Major renovation including ADA upgrades
Current Phase
Design
Current Phase Start
2015-08-25T00:00:00.000
Forecast Current Phase End
2024-04-05T00:00:00.000
Forecast Completion
2026-07-30T00:00:00.000
Actual Design Start
2015-08-25T00:00:00.000
Borough
Queens
Community Board
Queens 09
Budget Line
LQ-0122, LQ-D122, LQ-Q122
Ten Year Plan Category
RECONSTRUCTION NECESSARY TO MAINTAIN FACILITIES
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DCAS
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DCAS
Pid
4151
Fms Id
CO283TOIL
Total Budget
14267992.00
Spend To Date
1151027.24
Spend To Date 1
0.0806
Fms Project Name
100 CENTRE ST.- CODE COMPLIANT TOILET UPGRADE
Agency Project Name
Criminal Courthouse: 100 Centre Street
Agency Project Description
Manhattan Criminal Court, ADA Toilets, 100 Centre Street - The objective of the project is to provide accessible public restrooms and holding cell facilities in compliance with ADA standards.
Current Phase
Design
Current Phase Start
2017-09-27T00:00:00.000
Forecast Current Phase End
2024-03-31T00:00:00.000
Forecast Completion
2027-11-07T00:00:00.000
Actual Design Start
2017-09-27T00:00:00.000
Borough
Manhattan
Community Board
Manhattan 01
Budget Line
CO-0283
Ten Year Plan Category
RECONSTRUCTION/RENOVATION OF COURT FACILITIES
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DCAS
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DCAS
Pid
4152
Fms Id
CO283WT
Total Budget
4827000.00
Spend To Date
241845.58
Spend To Date 1
0.0501
Fms Project Name
100 CENTRE STREET - WATER TANK
Agency Project Name
100 CENTRE STREET - WATER TANK
Agency Project Description
Manhattan Criminal Courthouse, house tanks, 100 Centre Street - Replacement of existing house tanks and associated structural support for the water tanks located on the 20th Floor.
Current Phase
Construction
Current Phase Start
2023-07-25T00:00:00.000
Forecast Current Phase End
2025-07-23T00:00:00.000
Forecast Completion
2025-07-23T00:00:00.000
Actual Design Start
2018-01-01T00:00:00.000
Actual Design End
2022-02-11T00:00:00.000
Actual Construction
2022-02-11T00:00:00.000
Actual Construction 1
2023-07-25T00:00:00.000
Actual Construction Start
2023-07-25T00:00:00.000
Borough
Manhattan
Community Board
Manhattan 01
Budget Line
CO-0264, CO-0283
Ten Year Plan Category
RECONSTRUCTION/RENOVATION OF COURT FACILITIES
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DCAS
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DCAS
Pid
4153
Fms Id
CO285FIRE
Total Budget
14523484.00
Spend To Date
897515.61
Spend To Date 1
0.0617
Fms Project Name
60 LAFAYETTE ST - FIRE ALARM UPGRADE
Agency Project Name
Family Crthouse:60 Lafayette St NY.FireAlarmUpgrad
Agency Project Description
Manhattan Family Court, Fire Alarm Upgrade, 60 Lafayette Street - Replacement of the fire alarm system with a new addressable non-proprietary system and a new fire protection system. The goal of the project is to improve the life safety system for the building and to provide infrastructure for future office space renovations for the next 20 years.
Current Phase
Design
Current Phase Start
2019-11-26T00:00:00.000
Forecast Current Phase End
2024-02-29T00:00:00.000
Forecast Completion
2027-09-20T00:00:00.000
Actual Design Start
2019-11-26T00:00:00.000
Borough
Manhattan
Community Board
Manhattan 01
Budget Line
CO-0264, CO-0285
Ten Year Plan Category
RECONSTRUCTION/RENOVATION OF COURT FACILITIES
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: NYCHA
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
NYCHA
Pid
4154
Fms Id
HAM18MHCC
Total Budget
8064834.58
Spend To Date
2121048.35
Spend To Date 1
0.2629
Fms Project Name
Mariner's Harbor Community Center
Agency Project Name
Mariners Harbor Community Center
Agency Project Description
Mariner's Harbor Community Center - Renovate space in NYCHA Housing Complex at Mariner's Harbor into a Community Center.
Current Phase
Construction
Current Phase Start
2022-12-07T00:00:00.000
Forecast Current Phase End
2024-05-07T00:00:00.000
Forecast Completion
2024-05-07T00:00:00.000
Actual Design Start
2021-02-11T00:00:00.000
Actual Design End
2022-01-25T00:00:00.000
Actual Construction
2022-01-25T00:00:00.000
Actual Construction 1
2022-12-07T00:00:00.000
Actual Construction Start
2022-12-07T00:00:00.000
Borough
Staten Island
Community Board
Staten Island
Budget Line
HA-0001, HR-0025
Ten Year Plan Category
SOCIAL SERVICES BUILDINGS
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DCAS
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DCAS
Pid
4155
Fms Id
CO301LL
Total Budget
8809634.40
Spend To Date
3445431.87
Spend To Date 1
0.391
Fms Project Name
130 STUYVESANT PL - FACADE REPAIRS LOCAL LAW 11
Agency Project Name
130 STUYVESANT PLACE EXTERIOR REHAB, DESIGN PHASE
Agency Project Description
Mark A. Costantino Judicial Center, 130 Stuyvesant Place, Exterior Rehab - Reconstruct the masonry wall at the south facade and bulkhead. Roof replacement and related work at the roof parapets, copings and railings are also included.
Current Phase
Construction
Current Phase Start
2021-12-13T00:00:00.000
Forecast Current Phase End
2024-04-13T00:00:00.000
Forecast Completion
2024-04-13T00:00:00.000
Actual Design Start
2018-04-09T00:00:00.000
Actual Design End
2020-09-09T00:00:00.000
Actual Construction
2020-09-09T00:00:00.000
Actual Construction 1
2021-12-13T00:00:00.000
Actual Construction Start
2021-12-13T00:00:00.000
Borough
Staten Island
Community Board
Staten Island 01
Budget Line
CO-0301
Ten Year Plan Category
RECONSTRUCTION/RENOVATION OF COURT FACILITIES
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DCAS
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DCAS
Pid
4156
Fms Id
CO301PD
Total Budget
6445011.76
Spend To Date
2277295.73
Spend To Date 1
0.3533
Fms Project Name
130 STUYVESANT PL.- PARKING GARAGE DECK
Agency Project Name
130 Stuyvesant Pl. - Parking Garage Deck
Agency Project Description
Mark A. Costantino Judicial Center, 130 Stuyvesant Place, Parking Deck, 130 Stuyvesant Place - Renovate the surface deck of the parking garage including pavement, drains, lighting, vehicle access gates and access point to the building entrance for ADA accessibility.
Current Phase
Construction
Current Phase Start
2021-12-13T00:00:00.000
Forecast Current Phase End
2024-04-13T00:00:00.000
Forecast Completion
2024-04-13T00:00:00.000
Actual Design Start
2017-06-28T00:00:00.000
Actual Design End
2020-09-09T00:00:00.000
Actual Construction
2020-09-09T00:00:00.000
Actual Construction 1
2021-12-13T00:00:00.000
Actual Construction Start
2021-12-13T00:00:00.000
Borough
Staten Island
Community Board
Staten Island 01
Budget Line
CO-0301
Ten Year Plan Category
RECONSTRUCTION/RENOVATION OF COURT FACILITIES
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: HPD
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
HPD
Pid
4157
Fms Id
HAM17GHSE
Total Budget
17743059.30
Spend To Date
2971497.27
Spend To Date 1
0.1674
Fms Project Name
MARLBOROUGH HOUSES BSCAH GREENHOUSE DESIGN BUILD
Agency Project Name
MARLBORO GREENHOUSE
Agency Project Description
MARLBORO AGRICULTURE EDUCATION CENTER AT MARLBORO HOUSES - Building a new building to house a greenhouse, community kitchen, and educational spaces for The Campaign Against Hunger (TCAH) in NYCHA owned Marlborough Houses in Brooklyn using Design Build project delivery method.
Current Phase
Design
Current Phase Start
2022-08-15T00:00:00.000
Forecast Current Phase End
2023-11-29T00:00:00.000
Forecast Completion
2025-05-21T00:00:00.000
Actual Design Start
2022-08-15T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn 13
Budget Line
HA-K001, HD-I001
Ten Year Plan Category
OTHER PUBLIC HOUSING SUPPORT INVESTMENTS
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: BPL
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
BPL
Pid
4158
Fms Id
LBC16MD2F
Total Budget
9156003.92
Spend To Date
1064271.30
Spend To Date 1
0.1162
Fms Project Name
MIDWOOD 2ND FLOOR RENOVATIONS
Agency Project Name
Midwood 2nd Floor Renovation
Agency Project Description
Midwood Library will undergo a 2nd Floor Interior Renovation. The work scope will include the replacement of the HVAC system, Fire Alarm, second floor Security System and the installation of a new BMS. The work scope will also include the replacement of the roofing system and bulkhead restoration.
Current Phase
Construction Procurement
Current Phase Start
2023-03-15T00:00:00.000
Forecast Current Phase End
2024-01-05T00:00:00.000
Forecast Completion
2025-06-28T00:00:00.000
Actual Design Start
2016-07-15T00:00:00.000
Actual Design End
2023-03-15T00:00:00.000
Actual Construction
2023-03-15T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn 14
Budget Line
LB-0104, LB-D104
Ten Year Plan Category
ESSENTIAL RECONSTRUCTION OF FACILITIES
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: NYPL
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
NYPL
Pid
4159
Fms Id
LNEA13MHU
Total Budget
4384987.71
Spend To Date
1514439.43
Spend To Date 1
0.3453
Fms Project Name
Mosholu: New Roof and Exterior Work
Agency Project Name
Mosholu Roof, Exterior & HVAC Upgrade
Agency Project Description
Mosholu Library roof replacement and perform exterior renovation work.
Current Phase
Construction
Current Phase Start
2021-12-01T00:00:00.000
Forecast Current Phase End
2023-12-31T00:00:00.000
Forecast Completion
2023-12-31T00:00:00.000
Actual Design Start
2014-11-20T00:00:00.000
Actual Design End
2018-12-14T00:00:00.000
Actual Construction
2018-12-14T00:00:00.000
Actual Construction 1
2021-12-01T00:00:00.000
Actual Construction Start
2021-12-01T00:00:00.000
Borough
Bronx
Community Board
Bronx, Bronx 07
Budget Line
LN-0008, LN-0101M, LN-D008
Ten Year Plan Category
ESSENTIAL RECONSTRUCTION OF FACILITIES
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: NYPL
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
NYPL
Pid
4160
Fms Id
LNCA13MOT
Total Budget
3989028.47
Spend To Date
3607454.34
Spend To Date 1
0.9043
Fms Project Name
MOTT HAVEN: HVAC
Agency Project Name
Mott Haven HVAC Upgrade
Agency Project Description
Mott Haven Library HVAC system replacement.
Current Phase
(Completed)
Actual Design Start
2014-01-23T00:00:00.000
Actual Design End
2018-10-02T00:00:00.000
Actual Construction
2018-10-02T00:00:00.000
Actual Construction 1
2019-08-01T00:00:00.000
Actual Construction Start
2019-08-01T00:00:00.000
Actual Construction End
2023-07-20T00:00:00.000
Borough
Bronx
Community Board
Bronx, Bronx 01
Budget Line
LN-0008, LN-D008
Ten Year Plan Category
ESSENTIAL RECONSTRUCTION OF FACILITIES
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: NYPL
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
NYPL
Pid
4161
Fms Id
LNCA14MBG
Total Budget
3150696.14
Spend To Date
2478050.20
Spend To Date 1
0.7865
Fms Project Name
HVAC and Related Work
Agency Project Name
Muhlenberg HVAC & Related Work
Agency Project Description
Muhlenberg Library Replacement of HVAC systems.
Current Phase
Construction
Current Phase Start
2022-01-18T00:00:00.000
Forecast Current Phase End
2024-02-14T00:00:00.000
Forecast Completion
2024-02-14T00:00:00.000
Actual Design Start
2015-08-24T00:00:00.000
Actual Design End
2020-12-04T00:00:00.000
Actual Construction
2020-12-04T00:00:00.000
Actual Construction 1
2022-01-18T00:00:00.000
Actual Construction Start
2022-01-18T00:00:00.000
Borough
Manhattan
Community Board
Manhattan
Budget Line
LN-0008
Ten Year Plan Category
ESSENTIAL RECONSTRUCTION OF FACILITIES
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DOT
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DOT
Pid
4162
Fms Id
HWPEDSF4
Total Budget
21601244.89
Spend To Date
15445182.55
Spend To Date 1
0.715
Fms Project Name
Multi-Site Pedestrian Safety
Agency Project Name
MULTI-SITE PEDESTRIAN SAFETY
Agency Project Description
Multi-Site Pedestrian Safety, Citywide
Current Phase
Construction
Current Phase Start
2019-02-05T00:00:00.000
Forecast Current Phase End
2023-12-29T00:00:00.000
Forecast Completion
2023-12-29T00:00:00.000
Actual Design Start
2014-08-07T00:00:00.000
Actual Design End
2017-12-15T00:00:00.000
Actual Construction
2017-12-15T00:00:00.000
Actual Construction 1
2019-02-05T00:00:00.000
Actual Construction Start
2019-02-05T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn 99
Budget Line
HW-0988
Ten Year Plan Category
PRIMARY STREET RECONSTRUCTION
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DCLA
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DCLA
Pid
4163
Fms Id
PV241EXTR
Total Budget
4867973.00
Spend To Date
701995.68
Spend To Date 1
0.1442
Fms Project Name
MCNY - Exterior Facade Rehabilitation
Agency Project Name
MCNY Exterior Rehabilitation & Restoration
Agency Project Description
Museum of the City of New York (MCNY) - Exterior Façade Rehabilitation and Restoration.
Current Phase
Design
Current Phase Start
2018-08-07T00:00:00.000
Forecast Current Phase End
2023-09-30T00:00:00.000
Forecast Completion
2025-09-20T00:00:00.000
Actual Design Start
2018-08-07T00:00:00.000
Borough
Manhattan
Community Board
Manhattan
Budget Line
PV-0241, PV-0467, PV-D241, PV-I001, PV-M241
Ten Year Plan Category
ESSENTIAL RECONSTRUCTION OF FACILITIES
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DEP
Pid
4164
Fms Id
HED-562
Total Budget
32970489.18
Spend To Date
1672264.74
Spend To Date 1
0.0507
Fms Project Name
New 46" Trunk Water Main in E.233rd St. Bronx
Agency Project Name
NEW 48" TRUNK WATER MAIN IN E 233 STREET
Agency Project Description
New 48" Trunk Water Main in E 233rd Street between Bronxwood Avenue & Baychester Avenue, etc.
Current Phase
Design
Current Phase Start
2015-10-01T00:00:00.000
Forecast Current Phase End
2024-11-15T00:00:00.000
Forecast Completion
2027-08-17T00:00:00.000
Actual Design Start
2015-10-01T00:00:00.000
Borough
Bronx
Community Board
Bronx 12
Budget Line
SE-0002X, WM-0001, WM-0006
Ten Year Plan Category
EXTENSIONS TO ACCOMMODATE NEW DEVELOPMENT
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: NYPD
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
NYPD
Pid
4165
Fms Id
SANDBOMB
Total Budget
23395823.41
Spend To Date
2369508.53
Spend To Date 1
0.1012
Fms Project Name
Reconstruct Hurricane Sandy Damaged Bomb Sq bldg
Agency Project Name
BOMB SQUAD BUILDING RECONSTRUCTION
Agency Project Description
New building to replace existing Bomb Squad building damaged during Sandy storm. Two story building to house training, offices, lockers and vehicle storage. Existing building to be demolished and area to be landscaped upon completion of new building.
Current Phase
Construction Procurement
Current Phase Start
2022-11-15T00:00:00.000
Forecast Current Phase End
2023-12-04T00:00:00.000
Forecast Completion
2024-09-30T00:00:00.000
Actual Design Start
2014-04-15T00:00:00.000
Actual Design End
2022-11-15T00:00:00.000
Actual Construction
2022-11-15T00:00:00.000
Borough
Bronx
Community Board
Bronx 10
Budget Line
PO-0079, PU-0025
Ten Year Plan Category
POLICE FACILITIES
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Sponsor Agency: DHS
Reporting Period
202305
Managing Agency
DDC
Sponsor Agency
DHS
Pid
4166
Fms Id
HH112FWFA
Total Budget
8007329.14
Spend To Date
604383.65
Spend To Date 1
0.0754
Fms Project Name
FT. WASHINGTON - FIRE ALARM
Agency Project Name
FORT WASHINGTON ARMORY: FIRE ALARM UPGRADE
Agency Project Description
New building wide fire alarm system
Current Phase
Design
Current Phase Start
2016-01-13T00:00:00.000
Forecast Current Phase End
2024-08-28T00:00:00.000
Forecast Completion
2027-02-09T00:00:00.000
Actual Design Start
2016-01-13T00:00:00.000
Borough
Manhattan
Community Board
Manhattan
Budget Line
HH-0112
Ten Year Plan Category
SHELTERS FOR HOMELESS INDIVIDUALS
Agency Data Date
2023-09-01T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000