Capital Projects Dashboard - Citywide Budget and Schedule

All major capital infrastructure projects with a committed budget. Financial information and agency schedule details for each project are joined via FMS ID. Only projects in the design phase or later have project schedules displayed. This dataset is part of the Capital Projects Dashboard.

Note: Each row is uniquely identified by its Financial Management Service (FMS) ID. FMS ID is the unique ID that OMB uses for the FMS (Financial Information System). This ID can be universally joined with any OMB dataset that has the same field. The Capital Projects Dashboard is the result of joining OMB’s fiscal data with the agency’s schedule data. FMS IDs and agency projects don't always have a one-to-one relationship (i.e., one project schedule may correlate to multiple FMS IDs, and one FMS may correct to multiple projects with different schedules).

City Government Mayor's Office of Operations (OPS) Dataset fb86-vt7u 27 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
580
Fms Id
OB-133-L
Total Budget
93559180.61
Spend To Date
3113435.06
Spend To Date 1
0.0332
Fms Project Name
SLUDGE THICKENING IMPROVEMENT @ OAKWOOD BEACH WPCP
Agency Project Name
OB-133-L - Oakwood Beach WWTP Sludge Thickening Improvements
Agency Project Description
SLUDGE THICKENING IMPROVEMENT @ OAKWOOD BEACH WPCP
Current Phase
Construction Procurement
Current Phase Start
2021-08-23T00:00:00.000
Forecast Current Phase End
2023-05-29T00:00:00.000
Forecast Completion
2025-12-02T00:00:00.000
Actual Design Start
2018-08-02T00:00:00.000
Actual Design End
2021-08-22T00:00:00.000
Actual Construction
2021-08-23T00:00:00.000
Borough
Staten Island
Community Board
Staten Island
Budget Line
WP-0112
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
581
Fms Id
OB-134-L
Total Budget
48773262.24
Spend To Date
4710027.66
Spend To Date 1
0.0965
Fms Project Name
POWER DISTRIBUTION AT OAKWOOD BEACH WPCP
Agency Project Name
OB-134-L - Oakwood Beach WWTP Power Distribution Improvements
Agency Project Description
POWER DISTRIBUTION AT OAKWOOD BEACH WPCP
Current Phase
Design
Current Phase Start
2022-06-01T00:00:00.000
Forecast Current Phase End
2026-06-01T00:00:00.000
Forecast Completion
2026-06-01T00:00:00.000
Actual Design Start
2022-06-01T00:00:00.000
Borough
Staten Island
Community Board
Staten Island
Budget Line
WP-0112
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
582
Fms Id
OB-135-L
Total Budget
52958000.00
Spend To Date
611100.68
Spend To Date 1
0.0115
Fms Project Name
HEADWORKS AT OAKWOOD BEACH WPCP
Agency Project Name
OB-135-L - Oakwood Beach WWTP Headworks Improvements
Agency Project Description
HEADWORKS AT OAKWOOD BEACH WPCP
Current Phase
Design
Current Phase Start
2023-03-01T00:00:00.000
Forecast Current Phase End
2025-01-20T00:00:00.000
Forecast Completion
2029-06-02T00:00:00.000
Actual Design Start
2023-03-01T00:00:00.000
Borough
Staten Island
Community Board
Staten Island
Budget Line
WP-0112
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
583
Fms Id
OB-136-L
Total Budget
35926789.75
Spend To Date
1755656.04
Spend To Date 1
0.0488
Fms Project Name
INSTALLATION OF (2) MAIN TRANSFORMERS @ OAKWOOD BEACH WPCP
Agency Project Name
OB-136-L - Oakwood Beach WWTP EO-2022 Upgrades
Agency Project Description
INSTALLATION OF (2) MAIN TRANSFORMERS @ OAKWOOD BEACH WPCP
Current Phase
Design
Current Phase Start
2022-12-01T00:00:00.000
Forecast Current Phase End
2024-04-25T00:00:00.000
Forecast Completion
2027-08-18T00:00:00.000
Actual Design Start
2022-12-01T00:00:00.000
Borough
Staten Island
Community Board
Staten Island
Budget Line
WP-0112
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
584
Fms Id
PR-138-L
Total Budget
72438705.39
Spend To Date
3336103.26
Spend To Date 1
0.046
Fms Project Name
RECONSTRUCT MAIN SEWAGE PUMP CONTROLS @ PORT RICHMOND WWTP
Agency Project Name
PR-138-L - Reconstruct Main Sewage Pump Controls at Port Richmond WWTP
Agency Project Description
RECONSTRUCT MAIN SEWAGE PUMP CONTROLS @ PORT RICHMOND WWTP
Current Phase
Design
Current Phase Start
2019-11-27T00:00:00.000
Forecast Current Phase End
2023-06-01T00:00:00.000
Forecast Completion
2026-09-01T00:00:00.000
Actual Design Start
2019-11-27T00:00:00.000
Actual Design End
2022-09-29T00:00:00.000
Actual Construction
2022-09-30T00:00:00.000
Borough
Staten Island
Community Board
Staten Island
Budget Line
WP-0112
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
585
Fms Id
PS-284
Total Budget
31938727.00
Spend To Date
1789387.81
Spend To Date 1
0.056
Fms Project Name
CLEARVIEW PUMPING STATION
Agency Project Name
PS-284 - Reconstruction of Clearview Pump Station
Agency Project Description
CLEARVIEW PUMPING STATION
Current Phase
Construction
Current Phase Start
2022-12-07T00:00:00.000
Forecast Current Phase End
2024-12-04T00:00:00.000
Forecast Completion
2024-12-05T00:00:00.000
Actual Design Start
2015-12-24T00:00:00.000
Actual Design End
2021-05-27T00:00:00.000
Actual Construction
2021-05-28T00:00:00.000
Actual Construction 1
2022-12-06T00:00:00.000
Actual Construction Start
2022-12-07T00:00:00.000
Borough
Queens
Community Board
Queens, Queens 07
Budget Line
WP-0269
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
586
Fms Id
TI-167-L
Total Budget
5839354.91
Spend To Date
4570526.76
Spend To Date 1
0.7827
Fms Project Name
RECONSTRUCTION OF SEAWALL/DOCK @ TALLMAN ISLAND WPCP
Agency Project Name
TI-167-L - Bulkhead & Dock Improvemts
Agency Project Description
RECONSTRUCTION OF SEAWALL/DOCK @ TALLMAN ISLAND WPCP
Current Phase
Design
Current Phase Start
2019-09-18T00:00:00.000
Forecast Current Phase End
2023-06-30T00:00:00.000
Forecast Completion
2024-12-23T00:00:00.000
Actual Design Start
2019-09-18T00:00:00.000
Actual Design End
2023-06-30T00:00:00.000
Borough
Queens
Community Board
Queens, Queens 07
Budget Line
WP-0112
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
587
Fms Id
TI-168-L
Total Budget
48905108.00
Spend To Date
3874941.22
Spend To Date 1
0.0792
Fms Project Name
HEADWORKS IMPROVEMENTS AT THE TALLMAN ISLAND WPCP
Agency Project Name
TI-168-L - Headworks Improvements
Agency Project Description
HEADWORKS IMPROVEMENTS AT THE TALLMAN ISLAND WPCP
Current Phase
Design
Current Phase Start
2019-06-13T00:00:00.000
Forecast Current Phase End
2023-06-30T00:00:00.000
Forecast Completion
2026-10-16T00:00:00.000
Actual Design Start
2019-06-13T00:00:00.000
Actual Design End
2023-06-30T00:00:00.000
Borough
Queens
Community Board
Queens, Queens 07
Budget Line
WP-0112
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
588
Fms Id
TI-169-L
Total Budget
62972436.59
Spend To Date
5598505.93
Spend To Date 1
0.0889
Fms Project Name
RECONSTRUCT OF THE POWER DISTRIBUTION AT TALLMAN ISLAND WPCP
Agency Project Name
TI-169-L - Power Distribution Improvements
Agency Project Description
RECONSTRUCT OF THE POWER DISTRIBUTION AT TALLMAN ISLAND WPCP
Current Phase
Construction Procurement
Current Phase Start
2021-10-13T00:00:00.000
Forecast Current Phase End
2023-06-01T00:00:00.000
Forecast Completion
2026-03-17T00:00:00.000
Actual Design Start
2019-06-12T00:00:00.000
Actual Design End
2021-10-12T00:00:00.000
Actual Construction
2021-10-13T00:00:00.000
Borough
Queens
Community Board
Queens, Queens 07
Budget Line
WP-0112
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
589
Fms Id
TI-5
Total Budget
14043470.14
Spend To Date
11124156.33
Spend To Date 1
0.7921
Fms Project Name
TALLMAN ISLAND LANDSCAPING UPGRADE & MISC. SITE IMPROVEMENTS
Agency Project Name
TI-5 - Tallman Island Landscaping and Miscellaneous Site Work
Agency Project Description
TALLMAN ISLAND LANDSCAPING UPGRADE & MISC. SITE IMPROVEMENTS
Current Phase
Construction
Current Phase Start
2021-03-31T00:00:00.000
Forecast Current Phase End
2023-06-30T00:00:00.000
Forecast Completion
2023-06-30T00:00:00.000
Actual Design Start
2015-05-21T00:00:00.000
Actual Design End
2019-02-08T00:00:00.000
Actual Construction
2019-02-09T00:00:00.000
Actual Construction 1
2021-03-30T00:00:00.000
Actual Construction Start
2021-03-31T00:00:00.000
Borough
Queens
Community Board
Queens 07
Budget Line
WP-0249
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
590
Fms Id
TI-006
Total Budget
10310000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
WESTERN CRIBWALL REPLACEMENT AT THE TALLMAN ISLAND WRRF
Agency Project Name
TI-6 - Western Cribwall Replacement at the Tallman Island WRRF
Agency Project Description
RECONSTRUCTION OF SEAWALL/DOCK @ TALLMAN ISLAND WPCP
Current Phase
Pre-Design
Borough
Queens
Community Board
Queens, Queens 07
Budget Line
WP-0112
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
591
Fms Id
CS-GC-SFS
Total Budget
1439526763.25
Spend To Date
291384951.91
Spend To Date 1
0.2024
Fms Project Name
CONSTRUCTION OF GOWANUS CSO RETENTION FAC SUPERFUND SITE
Agency Project Name
CSO-GC-SUPER-OH-CP1 - Owls Head CSO Facility- Demolition and Site Preparation
Agency Project Description
CONSTRUCTION OF GOWANUS CSO RETENTION FAC SUPERFUND SITE
Current Phase
Construction Procurement
Current Phase Start
2022-10-21T00:00:00.000
Forecast Current Phase End
2023-08-09T00:00:00.000
Forecast Completion
2025-02-09T00:00:00.000
Actual Design Start
2021-04-25T00:00:00.000
Actual Design End
2022-10-20T00:00:00.000
Actual Construction
2022-10-21T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn 16
Budget Line
WP-0169
Ten Year Plan Category
WATER QUALITY MANDATES
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
592
Fms Id
CS-GC-SFS
Total Budget
1439526763.25
Spend To Date
291384951.91
Spend To Date 1
0.2024
Fms Project Name
CONSTRUCTION OF GOWANUS CSO RETENTION FAC SUPERFUND SITE
Agency Project Name
CSO-GC-SUPER-OH-CP2 - Owls Head CSO Facility- Excavation and Foundation
Agency Project Description
CONSTRUCTION OF GOWANUS CSO RETENTION FAC SUPERFUND SITE
Current Phase
Design
Current Phase Start
2020-05-01T00:00:00.000
Forecast Current Phase End
2023-05-30T00:00:00.000
Forecast Completion
2028-02-29T00:00:00.000
Actual Design Start
2020-05-01T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn 16
Budget Line
WP-0169
Ten Year Plan Category
WATER QUALITY MANDATES
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
593
Fms Id
CS-GC-SFS
Total Budget
1439526763.25
Spend To Date
291384951.91
Spend To Date 1
0.2024
Fms Project Name
CONSTRUCTION OF GOWANUS CSO RETENTION FAC SUPERFUND SITE
Agency Project Name
CSO-GC-SUPER-OH-CP3 - Owls Head CSO Facility- Structures and Conveyance
Agency Project Description
CONSTRUCTION OF GOWANUS CSO RETENTION FAC SUPERFUND SITE
Current Phase
Pre-Design
Borough
Brooklyn
Community Board
Brooklyn 16
Budget Line
WP-0169
Ten Year Plan Category
WATER QUALITY MANDATES
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
594
Fms Id
HP-254-L
Total Budget
27647759.00
Spend To Date
2166913.32
Spend To Date 1
0.0783
Fms Project Name
TRC - CONS OF DECHLORINATION FACILITY @ HUNTS POINT WWTP
Agency Project Name
HP-254 Installation of Dechlorination System at Hunts Point WRRF
Agency Project Description
Installation of Dechlorination System at Hunts Point WRRF
Current Phase
Design
Current Phase Start
2022-09-01T00:00:00.000
Forecast Current Phase End
2023-08-17T00:00:00.000
Forecast Completion
2027-07-26T00:00:00.000
Actual Design Start
2022-09-01T00:00:00.000
Borough
Bronx
Community Board
Bronx
Budget Line
WP-0112, WP-0282, WP-0282
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
595
Fms Id
OB-144-L
Total Budget
22792885.36
Spend To Date
1385591.56
Spend To Date 1
0.0607
Fms Project Name
TRC - CONS OF DISINFECTION FACILITIES AT OAKWOOD BEACH
Agency Project Name
OB-144 Installation of Dechlorination Systems at Oakwood Beach WWTP
Agency Project Description
Installation of Decholorination Systems at Oakwood Beach WWTP
Current Phase
Construction
Current Phase Start
2020-03-05T00:00:00.000
Forecast Current Phase End
2023-11-30T00:00:00.000
Forecast Completion
2023-12-01T00:00:00.000
Actual Design Start
2017-12-20T00:00:00.000
Actual Design End
2019-04-30T00:00:00.000
Actual Construction
2019-05-01T00:00:00.000
Actual Construction 1
2020-03-04T00:00:00.000
Actual Construction Start
2020-03-05T00:00:00.000
Borough
Staten Island
Community Board
Staten Island
Budget Line
WP-0282
Ten Year Plan Category
CONSENT DECREE UPGRADING AND CONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
596
Fms Id
OH-112-L
Total Budget
206350000.00
Spend To Date
6156136.50
Spend To Date 1
0.0298
Fms Project Name
REPLACE MAIN SEWAGE PUMPS & PIPING AT OWLS HEAD WPCP
Agency Project Name
OH-112: Reconstruction of the Main Sewage Pumps System at Owl's Head WRRF
Agency Project Description
Reconstruction of the Main Sewage Pumps System at Owl's Head WRRF
Current Phase
Design
Current Phase Start
2023-03-01T00:00:00.000
Forecast Current Phase End
2025-04-23T00:00:00.000
Forecast Completion
2032-06-22T00:00:00.000
Actual Design Start
2023-03-01T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn
Budget Line
WP-0112
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
597
Fms Id
OH-91-L
Total Budget
64038291.64
Spend To Date
34387098.35
Spend To Date 1
0.5369
Fms Project Name
RECONSTRUCTION OF SEA WALL AND DOCK @ OWLS HEAD WWTP
Agency Project Name
OH-91 - Reconstruction of the West and North Docks at the OH WWTP
Agency Project Description
Reconstruction of the West and North Docks at the OH WWTP
Current Phase
Construction
Current Phase Start
2020-02-24T00:00:00.000
Forecast Current Phase End
2024-05-08T00:00:00.000
Forecast Completion
2024-05-09T00:00:00.000
Actual Design Start
2017-08-18T00:00:00.000
Actual Design End
2019-07-26T00:00:00.000
Actual Construction
2019-07-27T00:00:00.000
Actual Construction 1
2020-02-23T00:00:00.000
Actual Construction Start
2020-02-24T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn
Budget Line
WP-0112
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
598
Fms Id
OH-92-L
Total Budget
30499000.00
Spend To Date
3319354.48
Spend To Date 1
0.1088
Fms Project Name
TRC - CONS OF DISINFECTION FACILITIES AT OWLS HEAD WPCP
Agency Project Name
OH-92 Installation of Dechlorination Systems at Owl's Head WWTP
Agency Project Description
Installation of Dechlorination Systems at Owls Head WWTP
Current Phase
Close-out
Actual Design Start
2017-12-19T00:00:00.000
Actual Design End
2019-05-02T00:00:00.000
Actual Construction
2019-05-03T00:00:00.000
Actual Construction 1
2020-03-29T00:00:00.000
Actual Construction Start
2020-03-30T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn
Budget Line
WP-0282
Ten Year Plan Category
CONSENT DECREE UPGRADING AND CONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
599
Fms Id
PS-286
Total Budget
15190000.00
Spend To Date
90000.00
Spend To Date 1
0.0059
Fms Project Name
ST ALBANS PUMPING STATION
Agency Project Name
PS-286 - ST Albans Pumping Station
Agency Project Description
ST Albans Pumping Station
Current Phase
Design
Current Phase Start
2022-06-01T00:00:00.000
Forecast Current Phase End
2025-06-01T00:00:00.000
Forecast Completion
2026-11-15T00:00:00.000
Actual Design Start
2022-06-01T00:00:00.000
Borough
Queens
Community Board
Queens, Queens 12
Budget Line
WP-0269
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
600
Fms Id
PS-293
Total Budget
75000000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
RECONSTRUCTION AT HOWARD BEACH PUMPING STATION
Agency Project Name
PS-293 - Reconstruction at Howard Beach Pumping Station
Agency Project Description
Reconstruction at Howard Beach Pumping Station
Current Phase
Design
Current Phase Start
2022-06-01T00:00:00.000
Forecast Current Phase End
2025-06-01T00:00:00.000
Forecast Completion
2027-07-19T00:00:00.000
Actual Design Start
2022-06-01T00:00:00.000
Borough
Queens
Community Board
Queens, Queens 10
Budget Line
WP-0269
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
601
Fms Id
PS-304
Total Budget
2330000.00
Spend To Date
210000.00
Spend To Date 1
0.0901
Fms Project Name
RECONSTRUCTION AT GLENDALE PUMPING STATION
Agency Project Name
PS-304 - Reconstruction at Glendale Pumping Station
Agency Project Description
Reconstruction at Glendale Pumping Station
Current Phase
Design
Current Phase Start
2021-06-24T00:00:00.000
Forecast Current Phase End
2023-06-01T00:00:00.000
Forecast Completion
2026-06-01T00:00:00.000
Actual Design Start
2021-06-24T00:00:00.000
Actual Design End
2022-12-27T00:00:00.000
Actual Construction
2022-12-28T00:00:00.000
Borough
Queens
Community Board
Queens, Queens 05
Budget Line
WP-0269
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
602
Fms Id
BB-215-L
Total Budget
67831434.33
Spend To Date
35251527.99
Spend To Date 1
0.5196
Fms Project Name
POWER DISTRIBUTION AT BOWERY BAY WPCP
Agency Project Name
BB-215-L - Power Distribution at Bowery Bay WWTP
Agency Project Description
Power Distribution at Bowery Bay WWTP
Current Phase
Construction
Current Phase Start
2020-01-29T00:00:00.000
Forecast Current Phase End
2024-12-23T00:00:00.000
Forecast Completion
2024-12-24T00:00:00.000
Actual Design Start
2015-11-13T00:00:00.000
Actual Design End
2018-08-16T00:00:00.000
Actual Construction
2018-08-17T00:00:00.000
Actual Construction 1
2020-01-28T00:00:00.000
Actual Construction Start
2020-01-29T00:00:00.000
Borough
Queens
Community Board
Queens, Queens 01
Budget Line
WP-0112
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
603
Fms Id
BB-216-L
Total Budget
133050651.24
Spend To Date
5600771.31
Spend To Date 1
0.042
Fms Project Name
RECONSTRUCTION OF PRIMARY TANKS AT BOWERY BAY WPCP
Agency Project Name
BB-216-L - Reconstruction Of Primary Tanks at Bowery Bay WPCP
Agency Project Description
RECONSTRUCTION OF PRIMARY TANKS AT BOWERY BAY WPCP
Current Phase
Design
Current Phase Start
2019-07-24T00:00:00.000
Forecast Current Phase End
2023-06-01T00:00:00.000
Forecast Completion
2027-12-23T00:00:00.000
Actual Design Start
2019-07-24T00:00:00.000
Actual Design End
2022-11-13T00:00:00.000
Actual Construction
2022-11-14T00:00:00.000
Borough
Queens
Community Board
Queens, Queens 01
Budget Line
WP-0112
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
605
Fms Id
NR-108-L
Total Budget
122.75
Spend To Date
122.75
Spend To Date 1
1.00
Agency Project Name
NR-108-L - North River WRRF- Interior Structural and Drainage Improvements
Agency Project Description
North River WRRF - Interior Structural and Drainage Improvements
Current Phase
Pre-Design
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
606
Fms Id
NR-111-L
Total Budget
168522812.62
Spend To Date
488868.85
Spend To Date 1
0.0029
Fms Project Name
RECONSTRUCTION OF PRIMARY TANKS AT NORTH RIVER WPCP
Agency Project Name
NR-111-L - North River WWTP Primary Treatment Improvements
Agency Project Description
RECONSTRUCTION OF PRIMARY TANKS AT NORTH RIVER WPCP
Current Phase
Design
Current Phase Start
2022-08-01T00:00:00.000
Forecast Current Phase End
2026-08-31T00:00:00.000
Forecast Completion
2028-07-27T00:00:00.000
Actual Design Start
2022-08-01T00:00:00.000
Borough
Manhattan
Community Board
Manhattan, Manhattan 09
Budget Line
WP-0112
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
607
Fms Id
NR-115-L
Total Budget
83241181.50
Spend To Date
2447853.58
Spend To Date 1
0.0294
Fms Project Name
RECONSTRUCT POWER DISTRIBUTION EQUIPMENT @ NORTH RIVER WWTP
Agency Project Name
NR-115-L - Reconstruct Power Distribution Equipment at North River WWTP
Agency Project Description
RECONSTRUCT POWER DISTRIBUTION EQUIPMENT @ NORTH RIVER WWTP
Current Phase
Pre-Design
Borough
Manhattan
Community Board
Manhattan, Manhattan 09
Budget Line
WP-0112
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
608
Fms Id
NR-COGEN
Total Budget
339832221.58
Spend To Date
314373290.30
Spend To Date 1
0.925
Fms Project Name
NORTH RIVER WWTP COGENERATION AND ELECTRIFICATION
Agency Project Name
NR-38 - North River WWTP Cogeneration and Electrification
Agency Project Description
North River WWTP Cogeneration and Electrification
Current Phase
Construction
Current Phase Start
2017-08-14T00:00:00.000
Forecast Current Phase End
2024-01-18T00:00:00.000
Forecast Completion
2024-01-19T00:00:00.000
Actual Design Start
2013-07-01T00:00:00.000
Actual Design End
2016-03-16T00:00:00.000
Actual Construction
2016-03-17T00:00:00.000
Actual Construction 1
2017-08-13T00:00:00.000
Actual Construction Start
2017-08-14T00:00:00.000
Borough
Manhattan
Community Board
Manhattan, Manhattan 09
Budget Line
WP-0164
Ten Year Plan Category
PLANT COMPONENT STABILIZATION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
609
Fms Id
NR-COGEN
Total Budget
339832221.58
Spend To Date
314373290.30
Spend To Date 1
0.925
Fms Project Name
NORTH RIVER WWTP COGENERATION AND ELECTRIFICATION
Agency Project Name
NR-44 - Riverbank State Park Feeder Separation
Agency Project Description
NORTH RIVER WWTP COGENERATION AND ELECTRIFICATION
Current Phase
Construction
Current Phase Start
2020-10-30T00:00:00.000
Forecast Current Phase End
2023-06-30T00:00:00.000
Forecast Completion
2023-06-30T00:00:00.000
Actual Design Start
2015-02-20T00:00:00.000
Actual Design End
2015-09-16T00:00:00.000
Actual Construction
2015-09-17T00:00:00.000
Actual Construction 1
2020-10-29T00:00:00.000
Actual Construction Start
2020-10-30T00:00:00.000
Borough
Manhattan
Community Board
Manhattan, Manhattan 09
Budget Line
WP-0164
Ten Year Plan Category
PLANT COMPONENT STABILIZATION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
610
Fms Id
NR-STRUCT
Total Budget
496136457.68
Spend To Date
11026495.80
Spend To Date 1
0.0222
Fms Project Name
STRUCTURAL IMPROVEMENTS AT NORTH RIVER WPCP
Agency Project Name
NR-STRUCT: North River WWTP Structural Improvements Program
Agency Project Description
STRUCTURAL IMPROVEMENTS AT NORTH RIVER WPCP
Current Phase
Pre-Design
Borough
Manhattan
Community Board
Manhattan, Manhattan 09
Budget Line
WP-0164
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
611
Fms Id
OH-88-L
Total Budget
194539303.86
Spend To Date
303.86
Spend To Date 1
0.00
Fms Project Name
RECONSTRUCTION OF FINAL TANKS AT OWLS HEAD WPCP
Agency Project Name
OH-88-L - Owls Head WWTP Final Settling System Rehabilitation
Agency Project Description
RECONSTRUCTION OF FINAL TANKS AT OWLS HEAD WPCP
Current Phase
Design
Current Phase Start
2022-07-01T00:00:00.000
Forecast Current Phase End
2024-07-26T00:00:00.000
Forecast Completion
2029-06-09T00:00:00.000
Actual Design Start
2022-07-01T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn
Budget Line
WP-0112
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
612
Fms Id
PR-134-L
Total Budget
158854000.00
Spend To Date
326440.42
Spend To Date 1
0.002
Fms Project Name
RECONSTRUCT FINAL SETTLING SYSTEM EQUIPMENT @ PORT RICHMOND
Agency Project Name
PR-134-L - Reconstruct Final Settling System Equipment at Port Richmond
Agency Project Description
RECONSTRUCT FINAL SETTLING SYSTEM EQUIPMENT @ PORT RICHMOND
Current Phase
Design
Current Phase Start
2022-04-01T00:00:00.000
Forecast Current Phase End
2024-04-30T00:00:00.000
Forecast Completion
2028-09-15T00:00:00.000
Actual Design Start
2022-04-01T00:00:00.000
Borough
Staten Island
Community Board
Staten Island
Budget Line
WP-0112
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
613
Fms Id
PS-277
Total Budget
49872370.38
Spend To Date
4837603.78
Spend To Date 1
0.0969
Fms Project Name
RECONSTRUCTION AT 108 STREET PUMPING STATION
Agency Project Name
PS-277 - Reconstruction at 108 Street Pumping Station
Agency Project Description
RECONSTRUCTION AT 108 STREET PUMPING STATION
Current Phase
Construction
Current Phase Start
2021-08-16T00:00:00.000
Forecast Current Phase End
2024-02-28T00:00:00.000
Forecast Completion
2024-02-29T00:00:00.000
Actual Design Start
2018-04-05T00:00:00.000
Actual Design End
2019-01-02T00:00:00.000
Actual Construction
2019-01-03T00:00:00.000
Actual Construction 1
2021-08-15T00:00:00.000
Actual Construction Start
2021-08-16T00:00:00.000
Borough
Queens
Community Board
Queens
Budget Line
WP-0269
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
614
Fms Id
PS-290
Total Budget
50467000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
CONNER STREET PUMPING STATION
Agency Project Name
PS-290 - Connor Street Pumping Station
Agency Project Description
Connor Street Pumping Station
Current Phase
Design
Current Phase Start
2023-04-01T00:00:00.000
Forecast Current Phase End
2026-06-01T00:00:00.000
Forecast Completion
2026-06-01T00:00:00.000
Actual Design Start
2023-04-01T00:00:00.000
Borough
Bronx
Community Board
Bronx
Budget Line
WP-0269
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
615
Fms Id
PS-296
Total Budget
8490000.00
Spend To Date
586978.02
Spend To Date 1
0.0691
Fms Project Name
RECONSTRUCTION AT MELVIN PUMPING STATION
Agency Project Name
PS-296 - Reconstruction at Melvin Pumping Station
Agency Project Description
RECONSTRUCTION AT MELVIN PUMPING STATION
Current Phase
Design
Current Phase Start
2018-06-22T00:00:00.000
Forecast Current Phase End
2024-06-01T00:00:00.000
Forecast Completion
2025-05-28T00:00:00.000
Actual Design Start
2018-06-22T00:00:00.000
Actual Design End
2022-07-26T00:00:00.000
Actual Construction
2022-07-27T00:00:00.000
Borough
Staten Island
Community Board
Staten Island
Budget Line
WP-0269
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
616
Fms Id
PS-313
Total Budget
23166730.44
Spend To Date
8123165.88
Spend To Date 1
0.3506
Fms Project Name
RECONSTRUCTION OF 235TH STREET PUMPING STATION
Agency Project Name
PS-313 - Reconstruction of 235TH Street Pumping Station
Agency Project Description
RECONSTRUCTION OF 235TH STREET PUMPING STATION
Current Phase
Construction
Current Phase Start
2021-07-12T00:00:00.000
Forecast Current Phase End
2024-04-18T00:00:00.000
Forecast Completion
2024-04-19T00:00:00.000
Actual Design Start
2017-06-30T00:00:00.000
Actual Design End
2019-05-12T00:00:00.000
Actual Construction
2019-05-13T00:00:00.000
Actual Construction 1
2021-07-11T00:00:00.000
Actual Construction Start
2021-07-12T00:00:00.000
Borough
Bronx
Community Board
Bronx
Budget Line
WP-0269
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
617
Fms Id
PS-317
Total Budget
68225000.00
Spend To Date
547303.14
Spend To Date 1
0.008
Fms Project Name
RECONSTRUCT VICTORY BOULEVARD PUMPING STATION STATEN ISLAND
Agency Project Name
PS-317 - Reconstruction Victory Blvd Pumping Station Staten Island
Agency Project Description
RECONSTRUCT VICTORY BOULEVARD PUMPING STATION STATEN ISLAND
Current Phase
Construction Procurement
Current Phase Start
2020-06-13T00:00:00.000
Forecast Current Phase End
2023-06-30T00:00:00.000
Forecast Completion
2025-06-17T00:00:00.000
Actual Design Start
2018-03-22T00:00:00.000
Actual Design End
2020-06-12T00:00:00.000
Actual Construction
2020-06-13T00:00:00.000
Actual Construction 1
2022-12-09T00:00:00.000
Actual Construction Start
2022-12-10T00:00:00.000
Borough
Staten Island
Community Board
Staten Island
Budget Line
WP-0269
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
618
Fms Id
PS-324
Total Budget
27586000.00
Spend To Date
320000.00
Spend To Date 1
0.0116
Fms Project Name
RECONSTRUCTION OF CANAL STREET PUMPING STATION, MANHATTAN
Agency Project Name
PS-324 - Reconstruction of Canal Street Pumping Station, Manhattan
Agency Project Description
RECONSTRUCTION OF CANAL STREET PUMPING STATION, MANHATTAN
Current Phase
Design
Current Phase Start
2017-12-26T00:00:00.000
Forecast Current Phase End
2026-06-01T00:00:00.000
Forecast Completion
2026-07-31T00:00:00.000
Actual Design Start
2017-12-26T00:00:00.000
Actual Design End
2022-09-07T00:00:00.000
Actual Construction
2022-09-08T00:00:00.000
Borough
Manhattan
Community Board
Manhattan
Budget Line
WP-0269
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
619
Fms Id
PS-288
Total Budget
17900000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
233RD STREET PUMPING STATION
Agency Project Name
PS-BX - Reconstruction of 233rd Street and 154th Street PSs
Agency Project Description
Reconstruction of 233rd Street and 154th Street PSs
Current Phase
Design
Current Phase Start
2023-01-05T00:00:00.000
Forecast Current Phase End
2026-06-01T00:00:00.000
Forecast Completion
2024-11-18T00:00:00.000
Actual Design Start
2023-01-05T00:00:00.000
Borough
Bronx
Community Board
Bronx
Budget Line
WP-0269
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
619
Fms Id
PS-291
Total Budget
20310000.00
Spend To Date
590000.00
Spend To Date 1
0.029
Fms Project Name
154TH STREET PUMPING STATION
Agency Project Name
PS-BX - Reconstruction of 233rd Street and 154th Street PSs
Agency Project Description
Reconstruction of 233rd Street and 154th Street PSs
Current Phase
Design
Current Phase Start
2023-01-05T00:00:00.000
Forecast Current Phase End
2026-06-01T00:00:00.000
Forecast Completion
2024-11-18T00:00:00.000
Actual Design Start
2023-01-05T00:00:00.000
Borough
Queens
Community Board
Queens, Queens 07
Budget Line
WP-0269
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
620
Fms Id
PS-278
Total Budget
62394000.00
Spend To Date
285334.95
Spend To Date 1
0.0045
Fms Project Name
PARK DRIVE EAST
Agency Project Name
PS-QNS 2 - Reconstruction of Little Neck, Linden Place, and Park Drive East PSs
Agency Project Description
PARK DRIVE EAST | RECONSTRUCTIONOF LINDEN PLACE PUMPING STATION
Current Phase
Design
Current Phase Start
2020-11-24T00:00:00.000
Forecast Current Phase End
2023-06-01T00:00:00.000
Forecast Completion
2026-04-05T00:00:00.000
Actual Design Start
2020-11-24T00:00:00.000
Actual Design End
2022-10-04T00:00:00.000
Actual Construction
2022-10-05T00:00:00.000
Borough
Manhattan
Community Board
Manhattan
Budget Line
WP-0269
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
620
Fms Id
PS-292
Total Budget
49546000.00
Spend To Date
227677.81
Spend To Date 1
0.0045
Fms Project Name
RECONSTRUCTIONOF LINDEN PLACE PUMPING STATION
Agency Project Name
PS-QNS 2 - Reconstruction of Little Neck, Linden Place, and Park Drive East PSs
Agency Project Description
PARK DRIVE EAST | RECONSTRUCTIONOF LINDEN PLACE PUMPING STATION
Current Phase
Design
Current Phase Start
2020-11-24T00:00:00.000
Forecast Current Phase End
2023-06-01T00:00:00.000
Forecast Completion
2026-04-05T00:00:00.000
Actual Design Start
2020-11-24T00:00:00.000
Actual Design End
2022-10-04T00:00:00.000
Actual Construction
2022-10-05T00:00:00.000
Borough
Queens
Community Board
Queens, Queens 07
Budget Line
WP-0269
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
621
Fms Id
PS-295
Total Budget
64780000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
RECONSTRUCTION AT MERSEREAU PUMPING STATION
Agency Project Name
PS-SI - Reconstruction of Mersereau, Richmond Ave and Mayflower Ave PSs
Agency Project Description
RECONSTRUCTION AT MERSEREAU PUMPING STATION | RECONSTRUCT MAYFLOWER AVENUE PUMPING STATION, STATEN ISLAND | RECONSTRUCT RICHMOND AVENUE PUMPING STATION, STATEN ISLAND
Current Phase
Design
Current Phase Start
2022-06-01T00:00:00.000
Forecast Current Phase End
2023-06-29T00:00:00.000
Forecast Completion
2027-07-01T00:00:00.000
Actual Design Start
2022-06-01T00:00:00.000
Borough
Staten Island
Community Board
Staten Island
Budget Line
WP-0269
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
621
Fms Id
PS-322
Total Budget
50200000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
RECONSTRUCT MAYFLOWER AVENUE PUMPING STATION, STATEN ISLAND
Agency Project Name
PS-SI - Reconstruction of Mersereau, Richmond Ave and Mayflower Ave PSs
Agency Project Description
RECONSTRUCTION AT MERSEREAU PUMPING STATION | RECONSTRUCT MAYFLOWER AVENUE PUMPING STATION, STATEN ISLAND | RECONSTRUCT RICHMOND AVENUE PUMPING STATION, STATEN ISLAND
Current Phase
Design
Current Phase Start
2022-06-01T00:00:00.000
Forecast Current Phase End
2023-06-29T00:00:00.000
Forecast Completion
2027-07-01T00:00:00.000
Actual Design Start
2022-06-01T00:00:00.000
Borough
Staten Island
Community Board
Staten Island
Budget Line
WP-0269
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
621
Fms Id
PS-323
Total Budget
32650000.00
Spend To Date
150000.00
Spend To Date 1
0.0045
Fms Project Name
RECONSTRUCT RICHMOND AVENUE PUMPING STATION, STATEN ISLAND
Agency Project Name
PS-SI - Reconstruction of Mersereau, Richmond Ave and Mayflower Ave PSs
Agency Project Description
RECONSTRUCTION AT MERSEREAU PUMPING STATION | RECONSTRUCT MAYFLOWER AVENUE PUMPING STATION, STATEN ISLAND | RECONSTRUCT RICHMOND AVENUE PUMPING STATION, STATEN ISLAND
Current Phase
Design
Current Phase Start
2022-06-01T00:00:00.000
Forecast Current Phase End
2023-06-29T00:00:00.000
Forecast Completion
2027-07-01T00:00:00.000
Actual Design Start
2022-06-01T00:00:00.000
Borough
Staten Island
Community Board
Staten Island
Budget Line
WP-0269
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
622
Fms Id
CI-119-L
Total Budget
143752942.51
Spend To Date
67871265.33
Spend To Date 1
0.4721
Fms Project Name
RECONSTRUCTION OF GATES & MSP MOTORS & CONTROLS @ C.I.
Agency Project Name
CI-119 - Replacement of the Main Sewage Pumps System at Coney Island WWTP
Agency Project Description
RECONSTRUCTION OF GATES & MSP MOTORS & CONTROLS @ C.I.
Current Phase
Construction
Current Phase Start
2021-02-22T00:00:00.000
Forecast Current Phase End
2025-02-19T00:00:00.000
Forecast Completion
2025-02-20T00:00:00.000
Actual Design Start
2019-03-26T00:00:00.000
Actual Design End
2019-12-20T00:00:00.000
Actual Construction
2019-12-21T00:00:00.000
Actual Construction 1
2021-02-21T00:00:00.000
Actual Construction Start
2021-02-22T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn
Budget Line
WP-0112
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
623
Fms Id
HP-238-L
Total Budget
366591552.21
Spend To Date
55763225.63
Spend To Date 1
0.1521
Fms Project Name
REPLACEMENT OF THE DIGESTER @ THE HUNTS POINT WWTP
Agency Project Name
HP-238-L - Replacement of The Digester at The Hunts Point WWTP
Agency Project Description
REPLACEMENT OF THE DIGESTER @ THE HUNTS POINT WWTP
Current Phase
Construction
Current Phase Start
2022-04-04T00:00:00.000
Forecast Current Phase End
2026-04-02T00:00:00.000
Forecast Completion
2026-04-03T00:00:00.000
Actual Design Start
2017-10-22T00:00:00.000
Actual Design End
2020-10-12T00:00:00.000
Actual Construction
2020-10-13T00:00:00.000
Actual Construction 1
2022-04-03T00:00:00.000
Actual Construction Start
2022-04-04T00:00:00.000
Borough
Bronx
Community Board
Bronx
Budget Line
WP-0112
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
624
Fms Id
JA-179-L
Total Budget
47294536.43
Spend To Date
9686910.90
Spend To Date 1
0.2048
Fms Project Name
INSTALLATION OF EMERGENCY GENERATORS AT JAMAICA WPCP
Agency Project Name
JA-179-L - Jamaica Emergency Generators Upgrade
Agency Project Description
INSTALLATION OF EMERGENCY GENERATORS AT JAMAICA WPCP
Current Phase
Construction
Current Phase Start
2022-08-01T00:00:00.000
Forecast Current Phase End
2025-07-20T00:00:00.000
Forecast Completion
2025-07-21T00:00:00.000
Actual Design Start
2014-12-01T00:00:00.000
Actual Design End
2020-07-20T00:00:00.000
Actual Construction
2020-07-21T00:00:00.000
Actual Construction 1
2022-07-31T00:00:00.000
Actual Construction Start
2022-08-01T00:00:00.000
Borough
Queens
Community Board
Queens, Queens 10
Budget Line
WP-0112
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
625
Fms Id
PR-132-L
Total Budget
56855941.00
Spend To Date
1436829.33
Spend To Date 1
0.0252
Fms Project Name
RECONSTRUCTION OF SEA WALL/SLUDGE DOCK IMPROVEMENTS
Agency Project Name
PR-132-L - Reconstruction of Sea Wall/Sludge Dock Improvements
Agency Project Description
RECONSTRUCTION OF SEA WALL/SLUDGE DOCK IMPROVEMENTS
Current Phase
Pre-Design
Borough
Staten Island
Community Board
Staten Island
Budget Line
WP-0112
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DEP • Sponsor Agency: DEP
Reporting Period
202305
Managing Agency
DEP
Sponsor Agency
DEP
Pid
626
Fms Id
PR-135-L
Total Budget
80421426.00
Spend To Date
2119768.31
Spend To Date 1
0.0263
Fms Project Name
RECONSTRUCT POWER DISTRIBUTION EQUIPMENT @ PORT RICHMOND
Agency Project Name
PR-135-L - Reconstruct Power Distribution Equipment at Port Richmond
Agency Project Description
RECONSTRUCT POWER DISTRIBUTION EQUIPMENT @ PORT RICHMOND
Current Phase
Pre-Design
Borough
Staten Island
Community Board
Staten Island
Budget Line
WP-0112
Ten Year Plan Category
PLANT UPGRADING AND RECONSTRUCTION
Agency Data Date
2023-07-07T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000