NYC Rezoning Tracker

Pursuant to Local Law 175 of 2016, the City is responsible for publishing a list of capital and programmatic commitments associated with neighborhood-scale rezonings, and an annual progress report detailing the status of each initiative. These rezoning commitments are the product of comprehensive and community-driven planning processes in each neighborhood (East New York; Greater East Midtown; Downtown Far Rockaway; East Harlem; Jerome Avenue; and Inwood) and have been organized by policy domain (Housing; Open Space; Community Resources; Transportation; and Economic and Workforce Development).

City Government Mayor's Office of Operations (OPS) Dataset fd95-5ihz 10 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
2019
Year: 2019 • Rezoning Area: East New York • Map Order: 43
Year
2019
Rezoning Area
East New York
Commitment Title
Renovate the City-owned industrial building to create modern industrial space for six industrial companies
Map Order
43
Rezoning Policy Domain
Economic Development
Lead Agency
ECONOMIC DEVELOPMENT CORPORATION (EDC)
Commitment Stage
In Progress
Statement From Source Document Poa
The 30,000 square foot city-owned industrial building at Powell Street and Pitkin Avenue is currently underutilized and in poor condition. EDC will invest city capital to complete major capital upgrades to the building's exterior and interior, including new lighting, facade repair, signage and mechanical systems. The improvements will result in more modern industrial space accommodating six industrial tenants and around 60 new jobs.
Timeline: The first phase of improvements will begin Q3 2016; the second phase of work is anticipated to begin Q3 2017
Capital Funding: $6 million
Original Schedule
2016-2019
Narrative
Construction has commenced and is anticipated to be complete by Summer 2020.
2021
Year: 2021 • Rezoning Area: East New York • Map Order: 43
Year
2021
Rezoning Area
East New York
Commitment Title
Renovate the City-owned industrial building to create modern industrial space for six industrial companies
Map Order
43
Rezoning Policy Domain
Economic Development
Lead Agency
ECONOMIC DEVELOPMENT CORPORATION (EDC)
Commitment Stage
In Progress
Statement From Source Document Poa
The 30,000 square foot city-owned industrial building at Powell Street and Pitkin Avenue is currently underutilized and in poor condition. EDC will invest city capital to complete major capital upgrades to the building's exterior and interior, including new lighting, facade repair, signage and mechanical systems. The improvements will result in more modern industrial space accommodating six industrial tenants and around 60 new jobs.
Timeline: The first phase of improvements will begin Q3 2016; the second phase of work is anticipated to begin Q3 2017
Capital Funding: $6 million
Original Schedule
2016-2019
Narrative
Project construction is underway with expected completion by fall 2021. EDC will work with local stakeholders and the community board to advertise industrial space available for rent when the building construction is completed.
2022
Year: 2022 • Rezoning Area: East New York • Map Order: 43
Year
2022
Rezoning Area
East New York
Commitment Title
Renovate the City-owned industrial building to create modern industrial space for six industrial companies
Map Order
43
Rezoning Policy Domain
Economic Development
Lead Agency
ECONOMIC DEVELOPMENT CORPORATION (EDC)
Commitment Stage
In Progress
Statement From Source Document Poa
The 30,000 square foot city-owned industrial building at Powell Street and Pitkin Avenue is currently underutilized and in poor condition. EDC will invest city capital to complete major capital upgrades to the building's exterior and interior, including new lighting, facade repair, signage and mechanical systems. The improvements will result in more modern industrial space accommodating six industrial tenants and around 60 new jobs.
Timeline: The first phase of improvements will begin Q3 2016; the second phase of work is anticipated to begin Q3 2017
Capital Funding: $6 million
Original Schedule
2016-2019
Narrative
Project construction is underway with expected completion by the end of 2023. EDC will work with local stakeholders and the community board to advertise industrial space available for rent when the building construction is near completion.
2022
Year: 2022 • Rezoning Area: Gowanus • Commitment Title: Renovate the Pacific Street Library
Year
2022
Rezoning Area
Gowanus
Commitment Title
Renovate the Pacific Street Library
Map Order
23
Rezoning Policy Domain
Community Resources
Lead Agency
NEW YORK PUBLIC LIBRARY - RESEARCH (NYPL)
Commitment Stage
Not Started
Statement From Source Document Poa
One of the Brooklyn’s historic Carnegie libraries, Pacific Street Library serves as a cultural touchpoint and community center for the Gowanus neighborhood as well as the surrounding area. Improvements to the Pacific Street Library are critical to providing access, programming, and resources to all library patrons.
Brooklyn Public Library (BPL) will make significant state of good repair investments at Pacific Street Library including the installation of an elevator to all three building floors and upgrades to the building's structural, mechanical, plumbing, and electrical systems, and localized upgrades to the building interior and exterior.
Original Schedule
2023 Start
Narrative
The balance of funding Brooklyn Public Library needed to fully fund the Pacific Library project was allocated to BPL in this years' Executive Budget. Using the $34.9 million funds allocated BPL will proceed with the full overhaul. BPL expects to begin design later in FY 23.
2018
Year: 2018 • Rezoning Area: East Harlem • Commitment Title: Renovations of La Marqueta
Year
2018
Rezoning Area
East Harlem
Commitment Title
Renovations of La Marqueta
Map Order
30
Rezoning Policy Domain
Open Space
Lead Agency
ECONOMIC DEVELOPMENT CORPORATION (EDC)
Commitment Stage
In Progress
Statement From Source Document Poa
La Marqueta is located along Park Avenue, between E111th Street and E119th Street underneath the Park Avenue viaduct. Since its inception in 1936, La Marqueta has steadfastly remained a landmark in East Harlem. The Speaker's Office and the New York City Economic Development Corporation (NYCEDC) have engaged in a feasibility study to develop goals and a framework for future investments at La Marqueta. This work led to a conceptual plan for Lots 1 through 8 that illustrates and reflects the goals and framework developed through the feasibility study. The next step will be to move from concept phase to design phase, which is anticipated to be in FY18, after which construction is anticipated to start in the winter of 2019. An overview of the organizational structure for La Marqueta is included as an exhibit to this POA. Moving forward, NYCEDC is open to exploring public-private partnerships to further activate the public market.
Original Schedule
2019
Narrative
La Marqueta is located along Park Avenue, between E111th Street and E119th Street underneath the Park Avenue viaduct. Since its inception in 1936, La Marqueta has steadfastly remained a landmark in East Harlem. The City Council and EDC have engaged in a feasibility study to develop goals and a framework for future investments at La Marqueta. This work led to a conceptual plan for Lots 1 through 8 that illustrates and reflects the goals and framework developed through the feasibility study. The next step will be to move from concept phase to design phase, which is anticipated to be in Fiscal Year 19, after which construction is anticipated to start in Spring of 2020. Capital improvement work began in June, 2018 at Lot 5-La Placita, with an expected completion date is December, 2018. ACACIA and Council Member Ayala are working on the formation of FolaM (Friends of La Marqueta, an independent community non-profit). While their deadline was set for May 21, 2018, EDC granted two extra months for the formation of the non-profit. Once FolaM is formed, EDC will start the RFP process for public-private partnership with an organization to further activate La Marqueta.
2019
Year: 2019 • Rezoning Area: East Harlem • Commitment Title: Renovations of La Marqueta
Year
2019
Rezoning Area
East Harlem
Commitment Title
Renovations of La Marqueta
Map Order
30
Rezoning Policy Domain
Open Space
Lead Agency
ECONOMIC DEVELOPMENT CORPORATION (EDC)
Commitment Stage
In Progress
Statement From Source Document Poa
La Marqueta is located along Park Avenue, between E111th Street and E119th Street underneath the Park Avenue viaduct. Since its inception in 1936, La Marqueta has steadfastly remained a landmark in East Harlem. The Speaker's Office and the New York City Economic Development Corporation (NYCEDC) have engaged in a feasibility study to develop goals and a framework for future investments at La Marqueta. This work led to a conceptual plan for Lots 1 through 8 that illustrates and reflects the goals and framework developed through the feasibility study. The next step will be to move from concept phase to design phase, which is anticipated to be in FY18, after which construction is anticipated to start in the winter of 2019. An overview of the organizational structure for La Marqueta is included as an exhibit to this POA. Moving forward, NYCEDC is open to exploring public-private partnerships to further activate the public market.
Original Schedule
2019
Narrative
EDC in partnership with the Council Member and the Friends of La Marqueta (FoLM) released a market partner competitive procurement this April. Once selected, EDC will fund the new market partner. The current market partner's (ACACIA) contract was extended through June 2019. The Friends of La Marqueta and EDC established a joint Memorandum of Understanding to outline roles and responsibilities to help activate the market. La Placita is under construction and is set for completion this Summer. Redevelopment for La Marquetas other lots will begin design late-2019. Redevelopment for all lots is anticipated to take approximately 70 months, pending additional City Capital and MTA approvals.
2019
Year: 2019 • Rezoning Area: Inwood • Commitment Title: Repair two pools at GWEC
Year
2019
Rezoning Area
Inwood
Commitment Title
Repair two pools at GWEC
Map Order
45
Rezoning Policy Domain
Community Resources
Lead Agency
SCHOOL CONSTRUCTION AUTHORITY (SCA)
Commitment Stage
In Progress
Statement From Source Document Poa
The City will refurbish the two pools in GWEC to allow expanded programming for the schools at GWEC and allow them to be open to the public through a private, non-profit operator. The improvements include new HVAC system, electrical upgrades, floor waterproofing and new tiling for the existing "Girls Pool", as well as structural work, new filtration system, new HVAC system, electrical upgrades, and lighting for the Boys' pool, which is currently not used. The improvements would also include new roofing for both pools, new bleachers, and complete upgrades to the girls' and boys' locker rooms to make them usable. The pools would be available for public programming during non-school hours through DOE's permit process. DOE and SCA will work with the local Council Member's office throughout the design and construction and permit processes.
Original Schedule
FY 2020 Design Start
Narrative
SCA is working with DOE and the local Council Member to develop the design for refurbishing the two pools at GWEC.
2021
Year: 2021 • Rezoning Area: East Harlem • Commitment Title: Renovations of La Marqueta
Year
2021
Rezoning Area
East Harlem
Commitment Title
Renovations of La Marqueta
Map Order
30
Rezoning Policy Domain
Open Space
Lead Agency
ECONOMIC DEVELOPMENT CORPORATION (EDC)
Commitment Stage
In Progress
Statement From Source Document Poa
La Marqueta is located along Park Avenue, between E111th Street and E119th Street underneath the Park Avenue viaduct. Since its inception in 1936, La Marqueta has steadfastly remained a landmark in East Harlem. The Speaker's Office and the New York City Economic Development Corporation (NYCEDC) have engaged in a feasibility study to develop goals and a framework for future investments at La Marqueta. This work led to a conceptual plan for Lots 1 through 8 that illustrates and reflects the goals and framework developed through the feasibility study. The next step will be to move from concept phase to design phase, which is anticipated to be in FY18, after which construction is anticipated to start in the winter of 2019. An overview of the organizational structure for La Marqueta is included as an exhibit to this POA. Moving forward, NYCEDC is open to exploring public-private partnerships to further activate the public market.
Original Schedule
2019
Narrative
EDC in partnership with the Council Member and the Friends of La Marqueta (FoLM) released a community partner competitive procurement in spring 2020. Due to the COVID-19 pandemic, the selection process was paused. The La Placita capital project is also delayed with completion now set for summer 2021. Redevelopment design work for all of La Marqueta was also paused due to the COVID-19 pandemic and the pending viaduct replacement work scheduled by MTA. It is anticipated that MTA will commence remedial work on the viaduct (from approx. 115th Street to approx. 123rd Street) in the second and third quarters of 2022. Once the project work resumes, EDC plans to commence the design phase of market redevelopment and will work closely with MTA, the Council Member, and FoLM to ensure project success and alignment.
2022
Year: 2022 • Rezoning Area: East Harlem • Commitment Title: Renovations of La Marqueta
Year
2022
Rezoning Area
East Harlem
Commitment Title
Renovations of La Marqueta
Map Order
30
Rezoning Policy Domain
Open Space
Lead Agency
ECONOMIC DEVELOPMENT CORPORATION (EDC)
Commitment Stage
In Progress
Statement From Source Document Poa
La Marqueta is located along Park Avenue, between E111th Street and E119th Street underneath the Park Avenue viaduct. Since its inception in 1936, La Marqueta has steadfastly remained a landmark in East Harlem. The Speaker's Office and the New York City Economic Development Corporation (NYCEDC) have engaged in a feasibility study to develop goals and a framework for future investments at La Marqueta. This work led to a conceptual plan for Lots 1 through 8 that illustrates and reflects the goals and framework developed through the feasibility study. The next step will be to move from concept phase to design phase, which is anticipated to be in FY18, after which construction is anticipated to start in the winter of 2019. An overview of the organizational structure for La Marqueta is included as an exhibit to this POA. Moving forward, NYCEDC is open to exploring public-private partnerships to further activate the public market.
Original Schedule
2019
Narrative
Due to the Park Avenue Viaduct replacement project being conducted by MTA from 115th St to 123rd St, EDC in concert with Friends of La Marqueta and local community stakeholders are re-evaluating the approach to market redevelopment which will involve revising the 2018 Concept Plan in light of these MTA disruptions. Pending alignment on redevelopment approach and plan, EDC proposes to release an RFP for a Design Consultant to commence plan revisions.
2019
Year: 2019 • Rezoning Area: Inwood • Commitment Title: Repair and reopen High Bridge Water Tower
Year
2019
Rezoning Area
Inwood
Commitment Title
Repair and reopen High Bridge Water Tower
Map Order
30
Rezoning Policy Domain
Open Space
Lead Agency
DEPARTMENT OF PARKS AND RECREATION (DPR)
Commitment Stage
Done
Statement From Source Document Poa
Building on the successful 2015 reopening of the historic High Bridge, NYC Parks is now advancing the restoration of the High Bridge Water Tower. The project, currently out to bid in the procurement process, will stabilize the historic structure and establish public access. Pending successful procurement Parks expects the project to begin construction in late 2018. For project updates, please visit: https://www.nycgovparks.org/planning-and-building/capital-project-tracker/project/5937.
Original Schedule
FY 2018 Design Start
Narrative
DPR expects to begin construction in summer 2019 pending successful procurement.
2021
Year: 2021 • Rezoning Area: Inwood • Commitment Title: Repair and reopen High Bridge Water Tower
Year
2021
Rezoning Area
Inwood
Commitment Title
Repair and reopen High Bridge Water Tower
Map Order
30
Rezoning Policy Domain
Open Space
Lead Agency
DEPARTMENT OF PARKS AND RECREATION (DPR)
Commitment Stage
Done
Statement From Source Document Poa
Building on the successful 2015 reopening of the historic High Bridge, NYC Parks is now advancing the restoration of the High Bridge Water Tower. The project, currently out to bid in the procurement process, will stabilize the historic structure and establish public access. Pending successful procurement Parks expects the project to begin construction in late 2018. For project updates, please visit: https://www.nycgovparks.org/planning-and-building/capital-project-tracker/project/5937.
Original Schedule
FY 2018 Design Start
Narrative
Construction started in September 2019. Construction completion is expected by late 2021.
2022
Year: 2022 • Rezoning Area: Inwood • Commitment Title: Repair and reopen High Bridge Water Tower
Year
2022
Rezoning Area
Inwood
Commitment Title
Repair and reopen High Bridge Water Tower
Map Order
30
Rezoning Policy Domain
Open Space
Lead Agency
DEPARTMENT OF PARKS AND RECREATION (DPR)
Commitment Stage
Done
Statement From Source Document Poa
Building on the successful 2015 reopening of the historic High Bridge, NYC Parks is now advancing the restoration of the High Bridge Water Tower. The project, currently out to bid in the procurement process, will stabilize the historic structure and establish public access. Pending successful procurement Parks expects the project to begin construction in late 2018. For project updates, please visit: https://www.nycgovparks.org/planning-and-building/capital-project-tracker/project/5937.
Original Schedule
FY 2018 Design Start
Narrative
DPR finished construction in October 2021.
2021
Year: 2021 • Rezoning Area: Bay Street • Commitment Title: Repair the Ornamental Fountain at Tappen Park
Year
2021
Rezoning Area
Bay Street
Commitment Title
Repair the Ornamental Fountain at Tappen Park
Map Order
26
Rezoning Policy Domain
Open Space
Lead Agency
DEPARTMENT OF PARKS AND RECREATION (DPR)
Commitment Stage
Done
Statement From Source Document Poa
Tappen Park's Village Hall building is a historic landmark that was built in 1889 and first
operated as the home of the Village of Edgewater's municipal and civic activities. Now vacant
and in a state of disrepair, the building most recently housed municipal offices and a health
clinic. The City commits $5.7 million to repair the building's roof and transfer jurisdiction of the
structure to NYC Parks. Once repair work is complete, NYC Parks intends to activate the building
with a concession, programming space and public restrooms.
Original Schedule
2020
Narrative
Construction to repair the Ornamental Fountain at Tappen Park started in fall 2020.
2022
Year: 2022 • Rezoning Area: Bay Street • Commitment Title: Repair the Ornamental Fountain at Tappen Park
Year
2022
Rezoning Area
Bay Street
Commitment Title
Repair the Ornamental Fountain at Tappen Park
Map Order
26
Rezoning Policy Domain
Open Space
Lead Agency
DEPARTMENT OF PARKS AND RECREATION (DPR)
Commitment Stage
Done
Statement From Source Document Poa
Tappen Park's Village Hall building is a historic landmark that was built in 1889 and first
operated as the home of the Village of Edgewater's municipal and civic activities. Now vacant
and in a state of disrepair, the building most recently housed municipal offices and a health
clinic. The City commits $5.7 million to repair the building's roof and transfer jurisdiction of the
structure to NYC Parks. Once repair work is complete, NYC Parks intends to activate the building
with a concession, programming space and public restrooms.
Original Schedule
2020
Narrative
Repairs to the Ornamental Fountain at Tappen Park were completed in October 2021.
2021
Year: 2021 • Rezoning Area: Inwood • Commitment Title: Repair two pools at GWEC
Year
2021
Rezoning Area
Inwood
Commitment Title
Repair two pools at GWEC
Map Order
45
Rezoning Policy Domain
Community Resources
Lead Agency
SCHOOL CONSTRUCTION AUTHORITY (SCA)
Commitment Stage
In Progress
Statement From Source Document Poa
The City will refurbish the two pools in GWEC to allow expanded programming for the schools at GWEC and allow them to be open to the public through a private, non-profit operator. The improvements include new HVAC system, electrical upgrades, floor waterproofing and new tiling for the existing "Girls Pool", as well as structural work, new filtration system, new HVAC system, electrical upgrades, and lighting for the Boys' pool, which is currently not used. The improvements would also include new roofing for both pools, new bleachers, and complete upgrades to the girls' and boys' locker rooms to make them usable. The pools would be available for public programming during non-school hours through DOE's permit process. DOE and SCA will work with the local Council Member's office throughout the design and construction and permit processes.
Original Schedule
FY 2020 Design Start
Narrative
The designs for repairing the two pools at the George Washington Education Campus (GWEC) are complete and pending approvals.
2022
Year: 2022 • Rezoning Area: Inwood • Commitment Title: Repair two pools at GWEC
Year
2022
Rezoning Area
Inwood
Commitment Title
Repair two pools at GWEC
Map Order
45
Rezoning Policy Domain
Community Resources
Lead Agency
SCHOOL CONSTRUCTION AUTHORITY (SCA)
Commitment Stage
In Progress
Statement From Source Document Poa
The City will refurbish the two pools in GWEC to allow expanded programming for the schools at GWEC and allow them to be open to the public through a private, non-profit operator. The improvements include new HVAC system, electrical upgrades, floor waterproofing and new tiling for the existing "Girls Pool", as well as structural work, new filtration system, new HVAC system, electrical upgrades, and lighting for the Boys' pool, which is currently not used. The improvements would also include new roofing for both pools, new bleachers, and complete upgrades to the girls' and boys' locker rooms to make them usable. The pools would be available for public programming during non-school hours through DOE's permit process. DOE and SCA will work with the local Council Member's office throughout the design and construction and permit processes.
Original Schedule
FY 2020 Design Start
Narrative
Pool project design complete. Project to commence construction in July 2022. Project completion is anticipated for January 2025.
2019
Year: 2019 • Rezoning Area: Inwood • Map Order: 32
Year
2019
Rezoning Area
Inwood
Commitment Title
Repair waterfront infrastructure along the Harlem River (from south of Dyckman Street to West 155th Street)
Map Order
32
Rezoning Policy Domain
Open Space
Lead Agency
ECONOMIC DEVELOPMENT CORPORATION (EDC)
Commitment Stage
In Progress
Statement From Source Document Poa
The City will complete the reconstruction and/or restoration of multiple waterfront structures from south of Dyckman Street to West 155th Street. The repairs are anticipated to address the structural integrity of waterfront edge structures to ensure the public's safe continued use and enjoyment of open space amenities on the water and to protect critical roadways like the Harlem River Drive.
Original Schedule
FY 2020 Design Start
Narrative
The Harlem River waterfront between Dyckman Street and West 155th Street is part of a larger Manhattan Waterfront Greenway capital project stretching to East 125th St. EDC will repair and reconstruct bulkheads and seawalls to ensure the longevity of the waterfront. EDC has selected a designer for the project and expects to begin construction in 2021.
2021
Year: 2021 • Rezoning Area: Inwood • Map Order: 32
Year
2021
Rezoning Area
Inwood
Commitment Title
Repair waterfront infrastructure along the Harlem River (from south of Dyckman Street to West 155th Street)
Map Order
32
Rezoning Policy Domain
Open Space
Lead Agency
ECONOMIC DEVELOPMENT CORPORATION (EDC)
Commitment Stage
In Progress
Statement From Source Document Poa
The City will complete the reconstruction and/or restoration of multiple waterfront structures from south of Dyckman Street to West 155th Street. The repairs are anticipated to address the structural integrity of waterfront edge structures to ensure the public's safe continued use and enjoyment of open space amenities on the water and to protect critical roadways like the Harlem River Drive.
Original Schedule
FY 2020 Design Start
Narrative
The Harlem River waterfront between Dyckman Street and West 155th Street is part of a larger Manhattan Waterfront Greenway capital project stretching to East 125th St. EDC will repair and reconstruct bulkheads and seawalls to ensure the longevity of the waterfront, and has selected a designer for the project. The design is expected to be completed by the end of 2021, and construction is anticipated to start for early 2022.
2022
Year: 2022 • Rezoning Area: Inwood • Map Order: 32
Year
2022
Rezoning Area
Inwood
Commitment Title
Repair waterfront infrastructure along the Harlem River (from south of Dyckman Street to West 155th Street)
Map Order
32
Rezoning Policy Domain
Open Space
Lead Agency
ECONOMIC DEVELOPMENT CORPORATION (EDC)
Commitment Stage
In Progress
Statement From Source Document Poa
The City will complete the reconstruction and/or restoration of multiple waterfront structures from south of Dyckman Street to West 155th Street. The repairs are anticipated to address the structural integrity of waterfront edge structures to ensure the public's safe continued use and enjoyment of open space amenities on the water and to protect critical roadways like the Harlem River Drive.
Original Schedule
FY 2020 Design Start
Narrative
The Harlem River waterfront between Dyckman Street and West 155th Street is part of a larger Manhattan Waterfront Greenway capital project stretching to East 125th St. EDC will repair and reconstruct bulkheads and seawalls to ensure the longevity of the waterfront, and has selected a designer for the project. The design is expected to be completed by the end in 2022.
2019
Year: 2019 • Rezoning Area: Inwood • Map Order: 29
Year
2019
Rezoning Area
Inwood
Commitment Title
Repair waterfront structures near Dyckman Pier, improve public access to Dyckman Pier, and build a new dock
Map Order
29
Rezoning Policy Domain
Open Space
Lead Agency
ECONOMIC DEVELOPMENT CORPORATION (EDC)
Commitment Stage
In Progress
Statement From Source Document Poa
The City will complete the reconstruction and/or restoration of multiple waterfront structures in the vicinity of the Dyckman Street pier, to address critical structural issues. The repairs are anticipated to include the Inwood Canoe Pier and nearby timber bulkhead, and the Dyckman Street Fishing Pier, as well as routine upkeep of the nearby structures, revetments and shorelines.
The City will also make improvements to the west end of Dyckman Street, at the entrance to the Dyckman Street Pier, to make the pier more inviting to the public by reconfiguring physical access and adding recreational amenities, landscaping, and signage making it clear which areas of the site are open to the public, and will specify public hours. The City will also construct a new floating dock along the Hudson River in the vicinity of Dyckman Pier. The City will coordinate with the local Council Member on project scope and will provide updates as the project progresses and as operations are determined. The optimal location will be determined based on site conditions, including water depth. The dock will be designed to allow side-loading cultural and excursion vessels to use the facilities, and will support increased visitation, economic development, and enhanced leisure activities in the neighborhood.
Original Schedule
FY 2020 Design Start
Narrative
EDC has developed a project scope to replace the Inwood Canoe Pier and associated bulkhead, replace the Dyckman Street Fishing Pier with a new high-level platform, and improve public access to the pier; relocate piles that support the existing dock; and install a new floating dock. EDC expects to begin design in summer 2019, begin construction in 2020, and complete construction in 2021.
2021
Year: 2021 • Rezoning Area: Inwood • Map Order: 29
Year
2021
Rezoning Area
Inwood
Commitment Title
Repair waterfront structures near Dyckman Pier, improve public access to Dyckman Pier, and build a new dock
Map Order
29
Rezoning Policy Domain
Open Space
Lead Agency
ECONOMIC DEVELOPMENT CORPORATION (EDC)
Commitment Stage
In Progress
Statement From Source Document Poa
The City will complete the reconstruction and/or restoration of multiple waterfront structures in the vicinity of the Dyckman Street pier, to address critical structural issues. The repairs are anticipated to include the Inwood Canoe Pier and nearby timber bulkhead, and the Dyckman Street Fishing Pier, as well as routine upkeep of the nearby structures, revetments and shorelines.
The City will also make improvements to the west end of Dyckman Street, at the entrance to the Dyckman Street Pier, to make the pier more inviting to the public by reconfiguring physical access and adding recreational amenities, landscaping, and signage making it clear which areas of the site are open to the public, and will specify public hours. The City will also construct a new floating dock along the Hudson River in the vicinity of Dyckman Pier. The City will coordinate with the local Council Member on project scope and will provide updates as the project progresses and as operations are determined. The optimal location will be determined based on site conditions, including water depth. The dock will be designed to allow side-loading cultural and excursion vessels to use the facilities, and will support increased visitation, economic development, and enhanced leisure activities in the neighborhood.
Original Schedule
FY 2020 Design Start
Narrative
EDC developed a project scope to repair waterfront structures near Dyckman Pier. The scope includes work to replace the Inwood Canoe Pier and associated bulkhead, replace the Dyckman Street Fishing Pier with a new high-level platform, improve public access to the pier, relocate piles that support the existing dock, and install a new floating dock. In spring 2021, EDC transferred management of this project to DPR. DPR expects to begin design in late 2021.
2022
Year: 2022 • Rezoning Area: Inwood • Map Order: 29
Year
2022
Rezoning Area
Inwood
Commitment Title
Repair waterfront structures near Dyckman Pier, improve public access to Dyckman Pier, and build a new dock
Map Order
29
Rezoning Policy Domain
Open Space
Lead Agency
ECONOMIC DEVELOPMENT CORPORATION (EDC)
Commitment Stage
In Progress
Statement From Source Document Poa
The City will complete the reconstruction and/or restoration of multiple waterfront structures in the vicinity of the Dyckman Street pier, to address critical structural issues. The repairs are anticipated to include the Inwood Canoe Pier and nearby timber bulkhead, and the Dyckman Street Fishing Pier, as well as routine upkeep of the nearby structures, revetments and shorelines.
The City will also make improvements to the west end of Dyckman Street, at the entrance to the Dyckman Street Pier, to make the pier more inviting to the public by reconfiguring physical access and adding recreational amenities, landscaping, and signage making it clear which areas of the site are open to the public, and will specify public hours. The City will also construct a new floating dock along the Hudson River in the vicinity of Dyckman Pier. The City will coordinate with the local Council Member on project scope and will provide updates as the project progresses and as operations are determined. The optimal location will be determined based on site conditions, including water depth. The dock will be designed to allow side-loading cultural and excursion vessels to use the facilities, and will support increased visitation, economic development, and enhanced leisure activities in the neighborhood.
Original Schedule
FY 2020 Design Start
Narrative
Design work is underway, having kicked off in June 2022.
2019
Year: 2019 • Rezoning Area: Jerome • Commitment Title: Repave key streets along the corridor
Year
2019
Rezoning Area
Jerome
Commitment Title
Repave key streets along the corridor
Map Order
42
Rezoning Policy Domain
Transportation & Infrastructure
Lead Agency
DEPARTMENT OF TRANSPORTATION (DOT)
Commitment Stage
Done
Statement From Source Document Poa
DOT will resurface the following streets within the Jerome Ave Neighborhood Study Area:   Jerome Avenue from E 175th Street to E Tremont Avenue         E 179th Street between Jerome Ave and Grand Concourse         Creston Avenue from E 178th St to E 183rd St         E 163rd St from Grand Concourse to Teller Ave         Sheridan Avenue from E 161st Street to E 167th Street         DOT will inspect streets on a regular basis to include in annual resurfacing schedule.
Original Schedule
Spring 2018
Narrative
DOT completed the resurfacing of the following streets: E 179th Street between Jerome Avenue and Grand Concourse, Creston Avenue from E 178th Street to E 183rd Street, E 163rd Street from Grand Concourse to Teller Avenue, and Sheridan Avenue from E 161st Street to E 167th Street in August and September of 2018. DOT resurfaced Jerome Avenue from E 175th Street to E Tremont Avenue in April 2019.
2021
Year: 2021 • Rezoning Area: Jerome • Commitment Title: Repave key streets along the corridor
Year
2021
Rezoning Area
Jerome
Commitment Title
Repave key streets along the corridor
Map Order
42
Rezoning Policy Domain
Transportation & Infrastructure
Lead Agency
DEPARTMENT OF TRANSPORTATION (DOT)
Commitment Stage
Done
Statement From Source Document Poa
DOT will resurface the following streets within the Jerome Ave Neighborhood Study Area:   Jerome Avenue from E 175th Street to E Tremont Avenue         E 179th Street between Jerome Ave and Grand Concourse         Creston Avenue from E 178th St to E 183rd St         E 163rd St from Grand Concourse to Teller Ave         Sheridan Avenue from E 161st Street to E 167th Street         DOT will inspect streets on a regular basis to include in annual resurfacing schedule.
Original Schedule
Spring 2018
Narrative
DOT completed the resurfacing of the following streets: E 179th Street between Jerome Avenue and Grand Concourse, Creston Avenue from E 178th Street to E 183rd Street, E 163rd Street from Grand Concourse to Teller Avenue, and Sheridan Avenue from E 161st Street to E 167th Street in August and September of 2018. DOT resurfaced Jerome Avenue from E 175th Street to E Tremont Avenue in April 2019.
2022
Year: 2022 • Rezoning Area: Jerome • Commitment Title: Repave key streets along the corridor
Year
2022
Rezoning Area
Jerome
Commitment Title
Repave key streets along the corridor
Map Order
42
Rezoning Policy Domain
Transportation & Infrastructure
Lead Agency
DEPARTMENT OF TRANSPORTATION (DOT)
Commitment Stage
Done
Statement From Source Document Poa
DOT will resurface the following streets within the Jerome Ave Neighborhood Study Area:   Jerome Avenue from E 175th Street to E Tremont Avenue         E 179th Street between Jerome Ave and Grand Concourse         Creston Avenue from E 178th St to E 183rd St         E 163rd St from Grand Concourse to Teller Ave         Sheridan Avenue from E 161st Street to E 167th Street         DOT will inspect streets on a regular basis to include in annual resurfacing schedule.
Original Schedule
Spring 2018
Narrative
DOT completed the resurfacing of the following streets: E 179th Street between Jerome Avenue and Grand Concourse, Creston Avenue from E 178th Street to E 183rd Street, E 163rd Street from Grand Concourse to Teller Avenue, and Sheridan Avenue from E 161st Street to E 167th Street in August and September of 2018. DOT resurfaced Jerome Avenue from E 175th Street to E Tremont Avenue in April 2019.
2024
Year: 2024 • Rezoning Area: Bay Street • Commitment Title: Ensure childcare and school planning reflect need as development occurs
Year
2024
Rezoning Area
Bay Street
Commitment Title
Ensure childcare and school planning reflect need as development occurs
Rezoning Policy Domain
Community Resources
Lead Agency
SCHOOL CONSTRUCTION AUTHORITY (SCA)
Commitment Stage
In Progress
Statement From Source Document Poa
The City is committed to strengthening and expanding access to high quality early childhood education and care. Ensuring there are adequate childcare options as part of any plan for growth is an essential element to success. Future childcare and school planning will reflect the need for seats as new development occurs and need is created. DOE will conclude the RFP available citywide to all providers of early childhood care for birth-five until June 13, 2019, and will update the Council Member about providers selected to work in the North Shore.
Original Schedule
FY 2025 - FY 2029
Narrative
SCA is committed to strengthening and expanding access to high quality early childhood education and care. Ensuring there are adequate childcare options is an essential element to success of any plan for growth. Future childcare and school planning will reflect the need for seats as new development occurs and generates further demand.
2022
Year: 2022 • Rezoning Area: Gowanus • Commitment Title: Report on compliance with the Unified Stormwater Rule.
Year
2022
Rezoning Area
Gowanus
Commitment Title
Report on compliance with the Unified Stormwater Rule.
Map Order
47
Rezoning Policy Domain
Transportation & Infrastructure
Lead Agency
DEPARTMENT OF ENVIRONMENTAL PROTECTION (DEP)
Commitment Stage
Not Started
Statement From Source Document Poa
• In DEP’s Green Infrastructure Annual Report, DEP will provide updates on projects that comply with the USWR by implementing green infrastructure projects. Monitoring of green infrastructure practices is conducted through DEP’s comprehensive Research and Development (R&D) Program. DEP collects crucial performance and co-benefits data and undertakes extensive analysis. Work completed under the R&D Program supports the overall NYC Green Infrastructure Program as well as the development and execution of combined sewer overflow reduction strategies by reviewing performance over time, supporting analysis on performance-based maintenance and operations, and by conducting cost-benefits analyses of various green infrastructure designs. Updates on the R&D Program are shared annually through NYC Green Infrastructure Annual Report.
In addition, as part of the permitted site connection process the City will prepare an annual report on applicable project approvals and completions for the preceding calendar year within the Gowanus Canal Sewershed. This information will include the anticipated sanitary discharge, development site storm flow, allowable flow from the site and/or the stormwater release rate from the site submitted. Data will be made publicly available and easy to access for individual sites and summarized for the Gowanus Canal Sewershed. DEP will provide twice annual updates on compliance with USWR through the green infrastructure program.
Original Schedule
TBD
Narrative
• In DEP’s Green Infrastructure Annual Report, DEP will provide updates on projects that comply with the USWR by implementing green infrastructure projects. Monitoring of green infrastructure practices is conducted through DEP’s comprehensive Research and Development (R&D) Program. DEP collects crucial performance and co-benefits data and undertakes extensive analysis. Work completed under the R&D Program supports the overall NYC Green Infrastructure Program as well as the development and execution of combined sewer overflow reduction strategies by reviewing performance over time, supporting analysis on performance-based maintenance and operations, and by conducting cost-benefits analyses of various green infrastructure designs. Updates on the R&D Program are shared annually through NYC Green Infrastructure Annual Report.
In addition, as part of the permitted site connection process the City will prepare an annual report on applicable project approvals and completions for the preceding calendar year within the Gowanus Canal Sewershed. This information will include the anticipated sanitary discharge, development site storm flow, allowable flow from the site and/or the stormwater release rate from the site submitted. Data will be made publicly available and easy to access for individual sites and summarized for the Gowanus Canal Sewershed. DEP will provide twice annual updates on compliance with USWR through the green infrastructure program.
2021
Year: 2021 • Rezoning Area: Greater East Midtown • Commitment Title: Report on residential conversion activity in East Midtown
Year
2021
Rezoning Area
Greater East Midtown
Commitment Title
Report on residential conversion activity in East Midtown
Map Order
5
Rezoning Policy Domain
Housing
Lead Agency
DEPARTMENT OF CITY PLANNING (DCP)
Commitment Stage
Done with Ongoing Work
Statement From Source Document Poa
We have not seen evidence that the ability for owners to convert their properties to residential uses as-of-right poses issues for this area. Nonetheless at your request, DCP will report back to the Manhattan Borough President's Office and the City Council on the prevalence of residential conversions and any associated impacts in the rezoning boundaries in both 3 years and 5 years time.
Original Schedule
2017-2022
Narrative
DCP released its three-year report on residential conversion activity in East Midtown to the Manhattan Borough President and City Council in August 2020. DCP will release its five-year report in August 2022.
2022
Year: 2022 • Rezoning Area: Greater East Midtown • Commitment Title: Report on residential conversion activity in East Midtown
Year
2022
Rezoning Area
Greater East Midtown
Commitment Title
Report on residential conversion activity in East Midtown
Map Order
5
Rezoning Policy Domain
Housing
Lead Agency
DEPARTMENT OF CITY PLANNING (DCP)
Commitment Stage
Done with Ongoing Work
Statement From Source Document Poa
We have not seen evidence that the ability for owners to convert their properties to residential uses as-of-right poses issues for this area. Nonetheless at your request, DCP will report back to the Manhattan Borough President's Office and the City Council on the prevalence of residential conversions and any associated impacts in the rezoning boundaries in both 3 years and 5 years time.
Original Schedule
2017-2022
Narrative
DCP released its three-year report on residential conversion activity in East Midtown to the Manhattan Borough President and City Council in August 2020. DCP will release its five-year report in August 2022.
2018
Year: 2018 • Rezoning Area: Far Rockaway • Map Order: 52
Year
2018
Rezoning Area
Far Rockaway
Commitment Title
Require developers, general contractors, and subcontractors on major projects in Downtown Far Rockaway to use HireNYC
Map Order
52
Rezoning Policy Domain
Economic Development
Lead Agency
HOUSING PRESERVATION AND DEVELOPMENT (HPD)
Commitment Stage
Done with Ongoing Work
Statement From Source Document Poa
All firms working on HPD and other City projects receiving more than $1 million in City subsidy ($2 million from HPD) are required to share job openings in entry- and mid-level construction positions with HireNYC, post at the local Workforce1 Center in Arverne, and interview any qualified candidates.
Original Schedule
2017-ongoing
Narrative
All firms working on HPD and other City projects receiving more than $1 million in City subsidy ($2 million from HPD) must comply with the City's HireNYC program. This requires them to source job placements for entry- and mid-level construction positions from the Workforce1 system, including the Rockaway Workforce1 Center in Arverne, and interview any qualified candidates.
2019
Year: 2019 • Rezoning Area: Far Rockaway • Map Order: 52
Year
2019
Rezoning Area
Far Rockaway
Commitment Title
Require developers, general contractors, and subcontractors on major projects in Downtown Far Rockaway to use HireNYC
Map Order
52
Rezoning Policy Domain
Economic Development
Lead Agency
HOUSING PRESERVATION AND DEVELOPMENT (HPD)
Commitment Stage
Done with Ongoing Work
Statement From Source Document Poa
All firms working on HPD and other City projects receiving more than $1 million in City subsidy ($2 million from HPD) are required to share job openings in entry- and mid-level construction positions with HireNYC, post at the local Workforce1 Center in Arverne, and interview any qualified candidates.
Original Schedule
2017-ongoing
Narrative
All firms working on HPD and other City projects receiving more than $1 million in City subsidy ($2 million from HPD) must comply with the City's HireNYC program. This requires them to source job placements for entry- and mid-level construction positions from the Workforce1 system, including the Rockaway Workforce1 Center in Arverne, and interview any qualified candidates.
2021
Year: 2021 • Rezoning Area: Far Rockaway • Map Order: 52
Year
2021
Rezoning Area
Far Rockaway
Commitment Title
Require developers, general contractors, and subcontractors on major projects in Downtown Far Rockaway to use HireNYC
Map Order
52
Rezoning Policy Domain
Economic Development
Lead Agency
HOUSING PRESERVATION AND DEVELOPMENT (HPD)
Commitment Stage
Done with Ongoing Work
Statement From Source Document Poa
All firms working on HPD and other City projects receiving more than $1 million in City subsidy ($2 million from HPD) are required to share job openings in entry- and mid-level construction positions with HireNYC, post at the local Workforce1 Center in Arverne, and interview any qualified candidates.
Original Schedule
2017-ongoing
Narrative
All firms working on HPD and other City projects receiving more than $1 million in City subsidy ($2 million from HPD) must comply with the City's HireNYC program. This requires them to source job placements for entry- and mid-level construction positions from the Workforce1 system, including the Rockaway Workforce1 Center in Arverne, and interview any qualified candidates.
2022
Year: 2022 • Rezoning Area: Far Rockaway • Map Order: 52
Year
2022
Rezoning Area
Far Rockaway
Commitment Title
Require developers, general contractors, and subcontractors on major projects in Downtown Far Rockaway to use HireNYC
Map Order
52
Rezoning Policy Domain
Economic Development
Lead Agency
HOUSING PRESERVATION AND DEVELOPMENT (HPD)
Commitment Stage
Done with Ongoing Work
Statement From Source Document Poa
All firms working on HPD and other City projects receiving more than $1 million in City subsidy ($2 million from HPD) are required to share job openings in entry- and mid-level construction positions with HireNYC, post at the local Workforce1 Center in Arverne, and interview any qualified candidates.
Original Schedule
2017-ongoing
Narrative
All firms working on HPD and other City projects receiving more than $1 million in City subsidy ($2 million from HPD) must comply with the City's HireNYC program. This requires them to source job placements for entry- and mid-level construction positions from the Workforce1 system, including the Rockaway Workforce1 Center in Arverne, and interview any qualified candidates.
2018
Year: 2018 • Rezoning Area: Far Rockaway • Commitment Title: Require HPD RFP respondents to implement a targeted hiring outreach plan
Year
2018
Rezoning Area
Far Rockaway
Commitment Title
Require HPD RFP respondents to implement a targeted hiring outreach plan
Map Order
51
Rezoning Policy Domain
Economic Development
Lead Agency
HOUSING PRESERVATION AND DEVELOPMENT (HPD)
Commitment Stage
Done with Ongoing Work
Statement From Source Document Poa
HPD will require respondents to any HPD RFPs in Downtown Far Rockaway to demonstrate a plan for targeted employment outreach to residents of the Rockaways related to the proposed project(s). Applicants will be required to comply with and report on their outreach.
Original Schedule
2017-ongoing
Narrative
In all Requests for Proposals for the development of City-owned property, respondents must demonstrate a plan for outreach to residents of the local community district related to employment opportunities generated by the proposed project. Outreach may be demonstrated by activities such as training programs, job placement activities, the applicants' own staffing practices, and/or the applicants' contracting practices. Applicants will be required to comply with their outreach plans and report regularly on outreach activities
2019
Year: 2019 • Rezoning Area: Far Rockaway • Commitment Title: Require HPD RFP respondents to implement a targeted hiring outreach plan
Year
2019
Rezoning Area
Far Rockaway
Commitment Title
Require HPD RFP respondents to implement a targeted hiring outreach plan
Map Order
51
Rezoning Policy Domain
Economic Development
Lead Agency
HOUSING PRESERVATION AND DEVELOPMENT (HPD)
Commitment Stage
Done with Ongoing Work
Statement From Source Document Poa
HPD will require respondents to any HPD RFPs in Downtown Far Rockaway to demonstrate a plan for targeted employment outreach to residents of the Rockaways related to the proposed project(s). Applicants will be required to comply with and report on their outreach.
Original Schedule
2017-ongoing
Narrative
In all Requests for Proposals for the development of City-owned property, respondents must demonstrate a plan for outreach to residents of the local community district related to employment opportunities generated by the proposed project. Outreach may be demonstrated by activities such as training programs, job placement activities, the applicants' own staffing practices, and/or the applicants' contracting practices. Applicants will be required to comply with their outreach plans and report regularly on outreach activities
2021
Year: 2021 • Rezoning Area: Far Rockaway • Commitment Title: Require HPD RFP respondents to implement a targeted hiring outreach plan
Year
2021
Rezoning Area
Far Rockaway
Commitment Title
Require HPD RFP respondents to implement a targeted hiring outreach plan
Map Order
51
Rezoning Policy Domain
Economic Development
Lead Agency
HOUSING PRESERVATION AND DEVELOPMENT (HPD)
Commitment Stage
Done with Ongoing Work
Statement From Source Document Poa
HPD will require respondents to any HPD RFPs in Downtown Far Rockaway to demonstrate a plan for targeted employment outreach to residents of the Rockaways related to the proposed project(s). Applicants will be required to comply with and report on their outreach.
Original Schedule
2017-ongoing
Narrative
For all HPD financed projects exceeding $2 million, respondents must demonstrate a plan for outreach to residents of the local community district related to employment opportunities generated by the proposed project. Outreach may be demonstrated by activities such as training programs, job placement activities, the applicants' own staffing practices, and/or the applicants' contracting practices. Applicants will be required to comply with their outreach plans and report regularly on outreach activities.
2022
Year: 2022 • Rezoning Area: Far Rockaway • Commitment Title: Require HPD RFP respondents to implement a targeted hiring outreach plan
Year
2022
Rezoning Area
Far Rockaway
Commitment Title
Require HPD RFP respondents to implement a targeted hiring outreach plan
Map Order
51
Rezoning Policy Domain
Economic Development
Lead Agency
HOUSING PRESERVATION AND DEVELOPMENT (HPD)
Commitment Stage
Done with Ongoing Work
Statement From Source Document Poa
HPD will require respondents to any HPD RFPs in Downtown Far Rockaway to demonstrate a plan for targeted employment outreach to residents of the Rockaways related to the proposed project(s). Applicants will be required to comply with and report on their outreach.
Original Schedule
2017-ongoing
Narrative
For all HPD financed projects exceeding $2 million, respondents must demonstrate a plan for outreach to residents of the local community district related to employment opportunities generated by the proposed project. Outreach may be demonstrated by activities such as training programs, job placement activities, the applicants' own staffing practices, and/or the applicants' contracting practices. Applicants will be required to comply with their outreach plans and report regularly on outreach activities.
2022
Year: 2022 • Rezoning Area: Gowanus • Commitment Title: Require notification of development in school siting opportunities.
Year
2022
Rezoning Area
Gowanus
Commitment Title
Require notification of development in school siting opportunities.
Map Order
28
Rezoning Policy Domain
Transportation & Infrastructure
Lead Agency
SCHOOL CONSTRUCTION AUTHORITY (SCA)
Commitment Stage
Not Started
Statement From Source Document Poa
DOB will notify the SCA, DOE, and affected Community Board when an owner/developer files plans to conduct demolition or excavation work on any project in the Gowanus Rezoning area to afford SCA/DOE and the Developer notice of a potential opportunity to construct a school within a mixed-use development, should the site be feasible, a school capacity need has been identified and the school need has been funded in the SCA/DOE’s Capital Plan. SCA/DOE shall have the final right to determine whether an identified site is feasible and needed for the construction of a funded school program at the time it receives notification.
The Gowanus Special District along the Canal contains zoning rules that encourage the inclusion of public schools as part of new mixed-use residential buildings if seats are needed, as determined by the SCA.
Original Schedule
2021 Start
Narrative
Per the Agreement for the Gowanus Rezoning, this is commitment under DOB's purview. To date DOB has not notified the SCA of any school siting opportunities in the rezoning area.
2018
Year: 2018 • Rezoning Area: Far Rockaway • Map Order: 43
Year
2018
Rezoning Area
Far Rockaway
Commitment Title
Reserve $91 million in Capital Funding for implementation of the Downtown Far Rockaway Redevelopment Project
Map Order
43
Rezoning Policy Domain
Economic Development
Lead Agency
ECONOMIC DEVELOPMENT CORPORATION (EDC)
Commitment Stage
In Progress
Statement From Source Document Poa
As a demonstration of the Administration's commitment to realizing the goals of the Downtown Far Rockaway Roadmap for Action and the Downtown Far Rockaway Redevelopment Project, the City has pledged $91million in Capital Funding for implementation. These funds are reserved to facilitate activation of key underutilized properties within the rezoning area. The City will provide annual updates to Council Member on the utilization of these pledged funds. If, through the course of implementation of the project or by June 2021, there is a surplus of funds remaining AND it is clear that such funds will not be needed and can be repurposed, the City will work in consultation with the Council Member to reprogram funds for other related projects in the area.
Original Schedule
2017-2021
Narrative
EDC, in coordination with other City agencies, is in the planning stages of deploying funds from the $91 million Capital Reserve to advance the goals of the Downtown Far Rockaway Roadmap for Action. EDC will provide an update to the Council Member on the utilization of these funds in Fiscal Year 2019, after the preliminary capital plan is complete.
2019
Year: 2019 • Rezoning Area: Far Rockaway • Map Order: 43
Year
2019
Rezoning Area
Far Rockaway
Commitment Title
Reserve $91 million in Capital Funding for implementation of the Downtown Far Rockaway Redevelopment Project
Map Order
43
Rezoning Policy Domain
Economic Development
Lead Agency
ECONOMIC DEVELOPMENT CORPORATION (EDC)
Commitment Stage
In Progress
Statement From Source Document Poa
As a demonstration of the Administration's commitment to realizing the goals of the Downtown Far Rockaway Roadmap for Action and the Downtown Far Rockaway Redevelopment Project, the City has pledged $91million in Capital Funding for implementation. These funds are reserved to facilitate activation of key underutilized properties within the rezoning area. The City will provide annual updates to Council Member on the utilization of these pledged funds. If, through the course of implementation of the project or by June 2021, there is a surplus of funds remaining AND it is clear that such funds will not be needed and can be repurposed, the City will work in consultation with the Council Member to reprogram funds for other related projects in the area.
Original Schedule
2017-2021
Narrative
EDC, in coordination with other City agencies, is guiding the continued deployment of funds from the $91 million Capital Reserve to advance the goals of the Downtown Far Rockaway Roadmap for Action. EDC updated the Council Member on the utilization of these funds in Fiscal 2019.
2024
Year: 2024 • Rezoning Area: Bay Street • Rezoning Policy Domain: Community Resources
Year
2024
Rezoning Area
Bay Street
Commitment Title
Explore feasibility of siting an educational complex at the former Staten Island Hospital Site
Rezoning Policy Domain
Community Resources
Lead Agency
SCHOOL CONSTRUCTION AUTHORITY (SCA)
Commitment Stage
In Progress
Statement From Source Document Poa
After pending litigation is completed and if a finding favorable to the City of New York is made, the City will explore the feasibility of acquiring 101 Castleton for redevelopment into an educational complex, if there is seat need and funding is available in the SCA Capital Plan at such future date. Redevelopment for alternative public uses may also be explored.
Original Schedule
FY 2025 - FY 2029
Narrative
The City has jurisdiction over the property. The SCA is working with other City agencies to develop a school in the Stapleton Waterfront area. This site is not needed as we have a location in the Stapleton Waterfront for a school.
2021
Year: 2021 • Rezoning Area: Far Rockaway • Map Order: 43
Year
2021
Rezoning Area
Far Rockaway
Commitment Title
Reserve $91 million in Capital Funding for implementation of the Downtown Far Rockaway Redevelopment Project
Map Order
43
Rezoning Policy Domain
Economic Development
Lead Agency
ECONOMIC DEVELOPMENT CORPORATION (EDC)
Commitment Stage
In Progress
Statement From Source Document Poa
As a demonstration of the Administration's commitment to realizing the goals of the Downtown Far Rockaway Roadmap for Action and the Downtown Far Rockaway Redevelopment Project, the City has pledged $91million in Capital Funding for implementation. These funds are reserved to facilitate activation of key underutilized properties within the rezoning area. The City will provide annual updates to Council Member on the utilization of these pledged funds. If, through the course of implementation of the project or by June 2021, there is a surplus of funds remaining AND it is clear that such funds will not be needed and can be repurposed, the City will work in consultation with the Council Member to reprogram funds for other related projects in the area.
Original Schedule
2017-2021
Narrative
EDC, in coordination with other City agencies, is guiding the continued deployment of funds from the $91 million Capital Reserve to advance the goals of the Downtown Far Rockaway Roadmap for Action.
2022
Year: 2022 • Rezoning Area: Far Rockaway • Map Order: 43
Year
2022
Rezoning Area
Far Rockaway
Commitment Title
Reserve $91 million in Capital Funding for implementation of the Downtown Far Rockaway Redevelopment Project
Map Order
43
Rezoning Policy Domain
Economic Development
Lead Agency
ECONOMIC DEVELOPMENT CORPORATION (EDC)
Commitment Stage
In Progress
Statement From Source Document Poa
As a demonstration of the Administration's commitment to realizing the goals of the Downtown Far Rockaway Roadmap for Action and the Downtown Far Rockaway Redevelopment Project, the City has pledged $91million in Capital Funding for implementation. These funds are reserved to facilitate activation of key underutilized properties within the rezoning area. The City will provide annual updates to Council Member on the utilization of these pledged funds. If, through the course of implementation of the project or by June 2021, there is a surplus of funds remaining AND it is clear that such funds will not be needed and can be repurposed, the City will work in consultation with the Council Member to reprogram funds for other related projects in the area.
Original Schedule
2017-2021
Narrative
EDC, in coordination with H+H, Parks and DOH, and in response to a call-to-action from the local Council Member and City Council Land Use in 2020, is working to deliver a holistic approach to improving community health outcomes. At the center of the initiative is the delivery of a new H+H/Gotham Health clinic in the downtown core.
2019
Year: 2019 • Rezoning Area: Inwood • Commitment Title: Restore the North Cove and create a North Cove park
Year
2019
Rezoning Area
Inwood
Commitment Title
Restore the North Cove and create a North Cove park
Map Order
27
Rezoning Policy Domain
Open Space
Lead Agency
ECONOMIC DEVELOPMENT CORPORATION (EDC)
Commitment Stage
In Progress
Original Schedule
FY 2019 Design Start
Narrative
EDC will restore the North Cove, site of an informal community space and wildlife habitat, and reclaim City-owned property currently used for parking to become part of a new park. A designer was selected in May 2019 and design is expected to be complete in Winter 2020-2021. The design of the new park will be informed by engagement with the Inwood community.
2021
Year: 2021 • Rezoning Area: Inwood • Commitment Title: Restore the North Cove and create a North Cove park
Year
2021
Rezoning Area
Inwood
Commitment Title
Restore the North Cove and create a North Cove park
Map Order
27
Rezoning Policy Domain
Open Space
Lead Agency
ECONOMIC DEVELOPMENT CORPORATION (EDC)
Commitment Stage
In Progress
Original Schedule
FY 2019 Design Start
Narrative
EDC will restore the North Cove, the site of an informal community space and wildlife habitat, and reclaim City-owned property currently used for parking to become part of a new park.  A designer was selected in May 2019. Due to the COVID-19 pandemic, the design contract registration was paused. Once the work resumes, the design of the new park will be informed by engagement with the Inwood community.
2022
Year: 2022 • Rezoning Area: Inwood • Commitment Title: Restore the North Cove and create a North Cove park
Year
2022
Rezoning Area
Inwood
Commitment Title
Restore the North Cove and create a North Cove park
Map Order
27
Rezoning Policy Domain
Open Space
Lead Agency
ECONOMIC DEVELOPMENT CORPORATION (EDC)
Commitment Stage
In Progress
Original Schedule
FY 2019 Design Start
Narrative
EDC will restore the North Cove, the site of an informal community space and wildlife habitat, and reclaim City-owned property currently used for parking to become part of a new park.  A designer was selected in May 2019. Due to the COVID-19 pandemic, the design contract registration was paused. Design is expected to start in 2023 and will be informed by engagement with the Inwood community.
2017
Year: 2017 • Rezoning Area: East New York • Commitment Title: Resurface portions of Fulton Street and Ridgewood Avenue
Year
2017
Rezoning Area
East New York
Commitment Title
Resurface portions of Fulton Street and Ridgewood Avenue
Map Order
29
Rezoning Policy Domain
Transportation & Infrastructure
Lead Agency
DEPARTMENT OF TRANSPORTATION (DOT)
Commitment Stage
Done
Statement From Source Document Poa
Resurface roads along Fulton Street from Essex Street to Hale Street and along Ridgewood Avenue from Jamaica Avenue to Elton Street and from Euclid Avenue to Eldert Lane.
Timeline: Ridgewood Avenue resurfacing underway; Fulton Street resurfacing scheduled to begin Spring 2017
Capital Funding: $412,000
Original Schedule
2016-2017
Narrative
In Spring 2016, DOT resurfaced Ridgewood Avenue between Jamaica Avenue and Elton Street and between Euclid Avenue and Eldert Lane. In Spring 2017, DOT resurfaced Fulton Street between Essex Street and Hale Street.
2018
Year: 2018 • Rezoning Area: East New York • Commitment Title: Resurface portions of Fulton Street and Ridgewood Avenue
Year
2018
Rezoning Area
East New York
Commitment Title
Resurface portions of Fulton Street and Ridgewood Avenue
Map Order
29
Rezoning Policy Domain
Transportation & Infrastructure
Lead Agency
DEPARTMENT OF TRANSPORTATION (DOT)
Commitment Stage
Done
Statement From Source Document Poa
Resurface roads along Fulton Street from Essex Street to Hale Street and along Ridgewood Avenue from Jamaica Avenue to Elton Street and from Euclid Avenue to Eldert Lane.
Timeline: Ridgewood Avenue resurfacing underway; Fulton Street resurfacing scheduled to begin Spring 2017
Capital Funding: $412,000
Original Schedule
2016-2017
Narrative
In Spring 2016, DOT resurfaced Ridgewood Avenue between Jamaica Avenue and Elton Street and between Euclid Avenue and Eldert Lane. In Spring 2017, DOT resurfaced Fulton Street between Essex Street and Hale Street.
2019
Year: 2019 • Rezoning Area: East New York • Commitment Title: Resurface portions of Fulton Street and Ridgewood Avenue
Year
2019
Rezoning Area
East New York
Commitment Title
Resurface portions of Fulton Street and Ridgewood Avenue
Map Order
29
Rezoning Policy Domain
Transportation & Infrastructure
Lead Agency
DEPARTMENT OF TRANSPORTATION (DOT)
Commitment Stage
Done
Statement From Source Document Poa
Resurface roads along Fulton Street from Essex Street to Hale Street and along Ridgewood Avenue from Jamaica Avenue to Elton Street and from Euclid Avenue to Eldert Lane.
Timeline: Ridgewood Avenue resurfacing underway; Fulton Street resurfacing scheduled to begin Spring 2017
Capital Funding: $412,000
Original Schedule
2016-2017
Narrative
In Spring 2016, DOT resurfaced Ridgewood Avenue between Jamaica Avenue and Elton Street and between Euclid Avenue and Eldert Lane. In Spring 2017, DOT resurfaced Fulton Street between Essex Street and Hale Street.
2021
Year: 2021 • Rezoning Area: East New York • Commitment Title: Resurface portions of Fulton Street and Ridgewood Avenue
Year
2021
Rezoning Area
East New York
Commitment Title
Resurface portions of Fulton Street and Ridgewood Avenue
Map Order
29
Rezoning Policy Domain
Transportation & Infrastructure
Lead Agency
DEPARTMENT OF TRANSPORTATION (DOT)
Commitment Stage
Done
Statement From Source Document Poa
Resurface roads along Fulton Street from Essex Street to Hale Street and along Ridgewood Avenue from Jamaica Avenue to Elton Street and from Euclid Avenue to Eldert Lane.
Timeline: Ridgewood Avenue resurfacing underway; Fulton Street resurfacing scheduled to begin Spring 2017
Capital Funding: $412,000
Original Schedule
2016-2017
Narrative
In Spring 2016, DOT resurfaced Ridgewood Avenue between Jamaica Avenue and Elton Street and between Euclid Avenue and Eldert Lane. In Spring 2017, DOT resurfaced Fulton Street between Essex Street and Hale Street.