Commitment Title
Working with community stakeholders, plan for the development of an enclosed consolidated DSNY sanitation facility for M10 and M11, which meets LEED gold standards
Statement From Source Document Poa
DSNY will immediately begin planning for a permanent, long-term facility to serve District 11 sanitation needs, which includes the following goals: Explore options for a permanent consolidated facility that could house multiple garages, including: District 11, District 10, District 9, and/or the Manhattan Lot Cleaning Unit.
Assess suitable sites for the permanent facility that will serve residents for the next 100 years. Explore all City-owned sites and appropriate privately-owned sites in Manhattan Community Boards 9, 10, and 11, as well as potential acquisition of the entire Block 1792.
DSNY will engage with local stakeholders on a quarterly basis starting in Q4 2017. The stakeholder group will include representatives from Community Board 11, the local Council Member, the Manhattan Borough President, and additional members that the stakeholders identify. The stakeholder group will provide feedback and accountability on the following tasks:1. Developing a shared vision with H+H for future use of existing East 99th Street DSNY facility that reflects the needs of H+H and the community. 2. Providing ongoing community feedback on the construction and operation of the East 127th Street facility. 3. Formalizing a community-engagement process for planning a permanent consolidated facility. This process will include clear benchmarks: o Establish shared priorities/goals with the stakeholder group for the permanent sanitation facility (Q2 2018).
o Share site and building program options with the stakeholder group, including a survey of viable sites, potential building programs for each site, costs associated with acquiring and building a garage on each site, and the critical path to acquiring and developing those sites (Q4 2018).
o Community consensus and agreement on preferred alternative site (Q2 2019).
o Contingent on the above, timeline and further milestones for site selection, budget allocation, feasibility, design, and construction (Q2 2019).
o Contingent on establishing community consensus on a proposed site and securing the necessary funding to develop the facility. DSNY's goal is to complete a facility by 2027.
Narrative
DSNY completed the build-out of the new DSNY facility on Manhattan Block 1792. This facility is currently on a long-term lease which extends through 2051. DSNY moved its M11 garage into this new facility in June 2022. All efforts to find alternative facility locations for M9 and M10 have been exhausted. DSNY’s M11A Broom Garage remains operational at the existing East 99th Street H+H location. DSNY is working closely with the City Housing Activation Task Force to determine the viability of finding an alternative location to move this operation.