Capital Projects

All major infrastructure and information technology projects with a budget of $25 million or more that are currently active (in the design, procurement, or construction phase).

City Government Mayor's Office of Operations (OPS) Dataset n7gv-k5yt 16 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
Hansborough Recreation Center Reconstruction
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 1090 • Project Name: Hansborough Recreation Center Reconstruction
Date Reported As Of
2022-09-01T00:00:00.000
Pid
1090
Project Name
Hansborough Recreation Center Reconstruction
Description
This project will reconstruct the pool, entrance and interior spaces of the Hansborough Recreation Center.
Category
Parks
Managing Agency
DPR
Client Agency
DPR
Current Phase
Construction Procurement
Design Start
2020-03-23T00:00:00.000
Budget Forecast
36668800.00
Latest Budget Changes
0.00
Total Budget Changes
-4700000.00
Forecast Completion
2025-08-27T00:00:00.000
Latest Schedule Changes
186
Total Schedule Changes
186
Reconstruction of the Ashokan Headworks
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 834 • Project Name: Reconstruction of the Ashokan Headworks
Date Reported As Of
2022-09-01T00:00:00.000
Pid
834
Project Name
Reconstruction of the Ashokan Headworks
Description
CAT-213
Category
Water Supply
Borough
Upstate
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2020-08-07T00:00:00.000
Budget Forecast
316432595.75
Latest Budget Changes
-16634236.00
Total Budget Changes
41950858.00
Forecast Completion
2028-04-16T00:00:00.000
Latest Schedule Changes
164
Total Schedule Changes
-67
Cross River and Croton Falls Dam Refacing
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 1092 • Project Name: Cross River and Croton Falls Dam Refacing
Date Reported As Of
2022-09-01T00:00:00.000
Pid
1092
Project Name
Cross River and Croton Falls Dam Refacing
Description
Provide design and design services during construction for the dam refacing, and drainage work at Cross River and Croton Falls Dams, including but not limited to resurface fascia, address seepage from the dams face.
Category
Water Supply
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2021-03-23T00:00:00.000
Budget Forecast
69145800.00
Latest Budget Changes
23950000.00
Total Budget Changes
23950000.00
Forecast Completion
2027-03-31T00:00:00.000
Latest Schedule Changes
124
Total Schedule Changes
298
Installation of Dechlorination System at Hunts Point WRRF
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 1094 • Project Name: Installation of Dechlorination System at Hunts Point WRRF
Date Reported As Of
2022-09-01T00:00:00.000
Pid
1094
Project Name
Installation of Dechlorination System at Hunts Point WRRF
Description
Install a Dechlorination System, replace the existing chlorination system including chemical storage tanks, metering pumps, electrical distribution equipment and upgrade the HVAC within the existing Chlorination Building.
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2021-05-25T00:00:00.000
Budget Forecast
27900000.00
Latest Budget Changes
337490.00
Total Budget Changes
-6856021.00
Forecast Completion
2027-06-21T00:00:00.000
Latest Schedule Changes
86
Total Schedule Changes
-9
Bush Terminal Development Site Preparation
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 1086 • Project Name: Bush Terminal Development Site Preparation
Date Reported As Of
2022-09-01T00:00:00.000
Pid
1086
Project Name
Bush Terminal Development Site Preparation
Description
Sitework (including but not limited to: excavation, utility, and bulkhead work) at Bush Terminal in preparation of the Steiner Studio campus.
Category
Industrial Development
Managing Agency
EDC
Client Agency
EDC
Current Phase
Construction Procurement
Design Start
2021-03-01T00:00:00.000
Budget Forecast
29000000.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2025-05-31T00:00:00.000
Latest Schedule Changes
121
Total Schedule Changes
517
Reconstruction of Power Distribution at Wards Island WWTP
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 453 • Project Name: Reconstruction of Power Distribution at Wards Island WWTP
Date Reported As Of
2022-09-01T00:00:00.000
Pid
453
Project Name
Reconstruction of Power Distribution at Wards Island WWTP
Description
Upgrades significant portions of the electrical distribution infrastructure including 3 power center installations, 15 motor control centers, 6 automatic transfer switches and 20 transformers throughout the plant
Category
Wastewater Treatment
Borough
Manhattan
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2019-06-04T00:00:00.000
Budget Forecast
149106268.26
Latest Budget Changes
18732762.04
Total Budget Changes
33489860.26
Forecast Completion
2028-03-04T00:00:00.000
Latest Schedule Changes
182
Total Schedule Changes
1147
4Th Ave. Safety Improvements Phase II-Vision Zero
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 833 • Project Name: 4Th Ave. Safety Improvements Phase II-Vision Zero
Date Reported As Of
2022-09-01T00:00:00.000
Pid
833
Project Name
4Th Ave. Safety Improvements Phase II-Vision Zero
Description
4TH AVENUE SAFETY IMPROVEMENTS PHASE II - VISION ZERO GREAT STREETS
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction
Design Start
2017-06-01T00:00:00.000
Budget Forecast
62852000.00
Latest Budget Changes
-5000.00
Total Budget Changes
-11525000.00
Forecast Completion
2024-06-17T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1106
Croton Above Ground Structure And Landscaping
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 747 • Project Name: Croton Above Ground Structure And Landscaping
Date Reported As Of
2022-09-01T00:00:00.000
Pid
747
Project Name
Croton Above Ground Structure And Landscaping
Description
The new Mosholu Golf Course Club House, together with fifty-five Driving Range Tee Boxes and ten-acres of re-landscaping comprise the phase IV and final of the vast DEP Croton Water Treatment Plant project, currently under construction in Van Cortlandt Park in the Bronx. Through a multifunctional design strategy the project reinstates the pre-existing golf program and facility, creates civic space for community use and ensures security for a multi-billion dollar public works facility.
Category
Industrial Development
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2012-05-23T00:00:00.000
Budget Forecast
133625000.00
Latest Budget Changes
845000.00
Total Budget Changes
75117000.00
Forecast Completion
2023-01-23T00:00:00.000
Latest Schedule Changes
-31
Total Schedule Changes
897
Brooklyn P.S. at 4302 4TH AVE
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 949 • Project Name: Brooklyn P.S. at 4302 4TH AVE
Date Reported As Of
2022-09-01T00:00:00.000
Pid
949
Project Name
Brooklyn P.S. at 4302 4TH AVE
Description
NEW SCHOOL (PHASE II)
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2017-11-17T00:00:00.000
Budget Forecast
66058403.00
Latest Budget Changes
0.00
Total Budget Changes
-221356.00
Forecast Completion
2023-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
365
Madison Avenue Bridge Reconstruction
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 114 • Project Name: Madison Avenue Bridge Reconstruction
Date Reported As Of
2022-09-01T00:00:00.000
Pid
114
Project Name
Madison Avenue Bridge Reconstruction
Description
Replace the electrical and mechanical systems of the Madison Avenue Bridge.
Category
Bridges
Borough
Manhattan, Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2011-02-14T00:00:00.000
Budget Forecast
55424399.00
Latest Budget Changes
-293443.00
Total Budget Changes
2036997.00
Forecast Completion
2023-01-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1628
Reconstruct Final Settling System Equipment at Port Richmond
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 947 • Project Name: Reconstruct Final Settling System Equipment at Port Richmond
Date Reported As Of
2022-09-01T00:00:00.000
Pid
947
Project Name
Reconstruct Final Settling System Equipment at Port Richmond
Description
Rehabilitation of the Final Settling Tanks at Port Richomnd Wastewater Resources Recovery Facility.
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2021-11-16T00:00:00.000
Budget Forecast
176068861.00
Latest Budget Changes
47633202.00
Total Budget Changes
30972687.00
Forecast Completion
2028-06-17T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
205
Bronx Public School @ 639 ST ANN'S AVENUE
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 1089 • Project Name: Bronx Public School @ 639 ST ANN'S AVENUE
Date Reported As Of
2022-09-01T00:00:00.000
Pid
1089
Project Name
Bronx Public School @ 639 ST ANN'S AVENUE
Description
NEW SCHOOL
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2019-08-29T00:00:00.000
Budget Forecast
93838545.00
Latest Budget Changes
0.00
Total Budget Changes
-1926038.00
Forecast Completion
2024-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
0
East River Esplanade Stabilization and Reconstruction Phase 2
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 1082 • Project Name: East River Esplanade Stabilization and Reconstruction Phase 2
Date Reported As Of
2022-09-01T00:00:00.000
Pid
1082
Project Name
East River Esplanade Stabilization and Reconstruction Phase 2
Description
This project will stabilize and reconstruct portions of the East River Esplanade.
Category
Parks
Managing Agency
DPR
Client Agency
DPR
Current Phase
Construction Procurement
Design Start
2019-02-01T00:00:00.000
Budget Forecast
29475000.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2024-11-16T00:00:00.000
Latest Schedule Changes
-7
Total Schedule Changes
156
North River WWTP Primary Treatment Improvements
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 945 • Project Name: North River WWTP Primary Treatment Improvements
Date Reported As Of
2022-09-01T00:00:00.000
Pid
945
Project Name
North River WWTP Primary Treatment Improvements
Description
Rehabilitation of the Primary Settling Tanks at North River Wastewater Resources Recovery Facility.
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2021-05-17T00:00:00.000
Budget Forecast
199919275.00
Latest Budget Changes
-397308.00
Total Budget Changes
35891899.00
Forecast Completion
2028-08-06T00:00:00.000
Latest Schedule Changes
78
Total Schedule Changes
121
East 180th Street over Metro North Railroad (Harrison Line)
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 811 • Project Name: East 180th Street over Metro North Railroad (Harrison Line)
Date Reported As Of
2022-09-01T00:00:00.000
Pid
811
Project Name
East 180th Street over Metro North Railroad (Harrison Line)
Description
Rehabilitation of East 180th Street Bridge over Metro North Railroad, the Bronx
Category
Bridges
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2017-02-06T00:00:00.000
Budget Forecast
33959655.00
Latest Budget Changes
533976.00
Total Budget Changes
4194366.00
Forecast Completion
2023-09-29T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
664
Flushing Meadows Corona Park Electrical Vault Reconstruction (Hurricane Sandy)
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 1083 • Project Name: Flushing Meadows Corona Park Electrical Vault Reconstruction (Hurricane Sandy)
Date Reported As Of
2022-09-01T00:00:00.000
Pid
1083
Project Name
Flushing Meadows Corona Park Electrical Vault Reconstruction (Hurricane Sandy)
Description
This project will reconstruct the electrical vaults in Flushing Meadows Corona Park that were damaged by Hurricane Sandy.
Category
Parks
Managing Agency
DPR
Client Agency
DPR
Current Phase
Design
Design Start
2019-08-21T00:00:00.000
Budget Forecast
56237000.00
Latest Budget Changes
-3590909.00
Total Budget Changes
-3555909.00
Bronx River CSO Reduction
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 943 • Project Name: Bronx River CSO Reduction
Date Reported As Of
2022-09-01T00:00:00.000
Pid
943
Project Name
Bronx River CSO Reduction
Description
The project will provide hydraulic relief to Outfalls HP-007 and HP-009 by creating new sewers parallel to the existing combined sewers. It will also provide floatables control at Outfall HP-011 by replacing Regulator 5.
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
WWC
Current Phase
Construction Procurement
Design Start
2020-04-16T00:00:00.000
Budget Forecast
184348203.00
Latest Budget Changes
0.00
Total Budget Changes
1210235.00
Forecast Completion
2028-03-11T00:00:00.000
Latest Schedule Changes
-278
Total Schedule Changes
-712
HILL DR (TERRACE BR) OVER PROSPECT PARK LAKE BIN 2244120
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 1073 • Project Name: HILL DR (TERRACE BR) OVER PROSPECT PARK LAKE BIN 2244120
Date Reported As Of
2022-09-01T00:00:00.000
Pid
1073
Project Name
HILL DR (TERRACE BR) OVER PROSPECT PARK LAKE BIN 2244120
Description
Hill Dr (Terrace Br) over Prospect Park Lake
Category
Bridges
Managing Agency
DOT
Client Agency
NYC Parks
Current Phase
Design
Design Start
2020-01-06T00:00:00.000
Budget Forecast
0.00
Latest Budget Changes
-27845976.00
Total Budget Changes
-785268.00
Forecast Completion
2028-12-06T00:00:00.000
Latest Schedule Changes
120
Total Schedule Changes
636
Mobile Radios
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 1079 • Project Name: Mobile Radios
Date Reported As Of
2022-09-01T00:00:00.000
Pid
1079
Project Name
Mobile Radios
Description
Mobile Radios Procurement - Vehicular and Fixed Location Installations
Category
Public Safety and Criminal Justice
Managing Agency
FDNY
Current Phase
IT
Budget Forecast
29091961.57
Latest Budget Changes
29091961.57
Total Budget Changes
-8074214.27
Forecast Completion
2024-06-30T00:00:00.000
Total Schedule Changes
0
West 79th Street over Amtrak and Rotunda Complex Rehabilitation
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 801 • Project Name: West 79th Street over Amtrak and Rotunda Complex Rehabilitation
Date Reported As Of
2022-09-01T00:00:00.000
Pid
801
Project Name
West 79th Street over Amtrak and Rotunda Complex Rehabilitation
Description
Rehabilitate the W. 79th St Bridge over Amtrak and Rotunda Complex
Category
Bridges, Streets and Roadways
Borough
Manhattan
Managing Agency
DOT
Client Agency
DOT, DPR
Current Phase
Construction
Design Start
2000-07-10T00:00:00.000
Budget Forecast
187556898.00
Latest Budget Changes
-7690583.00
Total Budget Changes
-51088528.00
Forecast Completion
2025-05-16T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
604
Reconstruction of the Port Jervis Wastewater Treatment Plant
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 444 • Project Name: Reconstruction of the Port Jervis Wastewater Treatment Plant
Date Reported As Of
2022-09-01T00:00:00.000
Pid
444
Project Name
Reconstruction of the Port Jervis Wastewater Treatment Plant
Description
Reconstruction of the Port Jervis WWTP as required based on the effluent limits proposed by the Delaware River Basin Commission (DRBC)
Category
Wastewater Treatment
Borough
Port Jervis
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2014-06-17T00:00:00.000
Budget Forecast
60624916.55
Latest Budget Changes
-299395.44
Total Budget Changes
9428438.55
Forecast Completion
2026-10-04T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2445
BROAD CHANNEL BULKHEADS - PH II
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 617 • Project Name: BROAD CHANNEL BULKHEADS - PH II
Date Reported As Of
2022-09-01T00:00:00.000
Pid
617
Project Name
BROAD CHANNEL BULKHEADS - PH II
Description
West 14th Rd. from Cross Bay Blvd. to Dead end (water side) West 15th Rd. from Cross Bay Blvd. to Dead end (water side) West 16th Rd. from Cross Bay Blvd. to Dead end (water side) West 17th Rd. from Cross Bay Blvd. to Dead end (water side)
Category
Industrial Development
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction
Design Start
2015-06-01T00:00:00.000
Budget Forecast
92714000.00
Latest Budget Changes
0.00
Total Budget Changes
61781000.00
Forecast Completion
2024-06-14T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
-74
Reconstruction Of Arthur Kill Road, Phase I
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 741 • Project Name: Reconstruction Of Arthur Kill Road, Phase I
Date Reported As Of
2022-09-01T00:00:00.000
Pid
741
Project Name
Reconstruction Of Arthur Kill Road, Phase I
Description
Reconstruction of Arthur Kill Rd from Clark Avenue to Richmond Avenue including widening of roadway
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2016-12-16T00:00:00.000
Budget Forecast
60299000.00
Latest Budget Changes
9893000.00
Total Budget Changes
22503000.00
Forecast Completion
2026-05-15T00:00:00.000
Latest Schedule Changes
197
Total Schedule Changes
1415
CSO Hutchinson River Disinfection Facility
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 944 • Project Name: CSO Hutchinson River Disinfection Facility
Date Reported As Of
2022-09-01T00:00:00.000
Pid
944
Project Name
CSO Hutchinson River Disinfection Facility
Description
Construction of 1,200 double barrel 14W x 10H conduit to provide 2.8 MG of CSO storage; bar screens/baffle-weir system for floatables control; PS to drain conduit after each rain event; new outfall to provide relief for events which exceed 2.8 MG.
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2022-09-22T00:00:00.000
Budget Forecast
210852514.00
Latest Budget Changes
-16012288.00
Total Budget Changes
-24577348.00
Forecast Completion
2032-11-19T00:00:00.000
Latest Schedule Changes
811
Total Schedule Changes
894
Parking Meters Retrofitted for License Plate Recognition
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 1069 • Project Name: Parking Meters Retrofitted for License Plate Recognition
Date Reported As Of
2022-09-01T00:00:00.000
Pid
1069
Project Name
Parking Meters Retrofitted for License Plate Recognition
Category
Streets and Roadways
Managing Agency
DOT
Current Phase
Construction
Budget Forecast
43522500.00
Latest Budget Changes
2010000.00
Total Budget Changes
-500.00
HEMPSTEAD AVE OVER BCIP RAMP NB BIN 2266149
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 1050 • Project Name: HEMPSTEAD AVE OVER BCIP RAMP NB BIN 2266149
Date Reported As Of
2022-09-01T00:00:00.000
Pid
1050
Project Name
HEMPSTEAD AVE OVER BCIP RAMP NB BIN 2266149
Description
Rehabilitation of Hempstead Avenue Bridges over Cross island Parkway (Northbound)
Category
Bridges, Streets and Roadways
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2022-01-31T00:00:00.000
Budget Forecast
33743042.00
Latest Budget Changes
1575042.00
Total Budget Changes
597042.00
Forecast Completion
2030-07-07T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
402
Reconstruction Of Primary Tanks at Bowery Bay WPCP
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 942 • Project Name: Reconstruction Of Primary Tanks at Bowery Bay WPCP
Date Reported As Of
2022-09-01T00:00:00.000
Pid
942
Project Name
Reconstruction Of Primary Tanks at Bowery Bay WPCP
Description
Reconstruction Of Primary Tanks at Bowery Bay WPCP
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2019-09-27T00:00:00.000
Budget Forecast
131364829.00
Latest Budget Changes
3089221.00
Total Budget Changes
74442173.00
Forecast Completion
2027-06-23T00:00:00.000
Latest Schedule Changes
-16
Total Schedule Changes
636
HEMPSTEAD AVE BR/CIP 2231780
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 1049 • Project Name: HEMPSTEAD AVE BR/CIP 2231780
Date Reported As Of
2022-09-01T00:00:00.000
Pid
1049
Project Name
HEMPSTEAD AVE BR/CIP 2231780
Description
Rehabilitation of Hempstead Avenue Bridge over Cross island Parkway
Category
Bridges, Streets and Roadways
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2022-01-31T00:00:00.000
Budget Forecast
88672189.00
Latest Budget Changes
86393000.00
Total Budget Changes
1747189.00
Forecast Completion
2030-04-23T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
327
Rondout-West Branch Bypass Tunnel Construction Project 2
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 409 • Project Name: Rondout-West Branch Bypass Tunnel Construction Project 2
Date Reported As Of
2022-09-01T00:00:00.000
Pid
409
Project Name
Rondout-West Branch Bypass Tunnel Construction Project 2
Description
To address existing leaks in the Delaware Aqueduct, a 3-mile bypass tunnel will be constructed near the town of Roseton and the existing tunnel will be repaired near the town of Wawarsing.
Category
Water Supply
Borough
Marlboro
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2012-03-23T00:00:00.000
Budget Forecast
907089832.76
Latest Budget Changes
13932373.76
Total Budget Changes
202552329.25
Forecast Completion
2024-10-14T00:00:00.000
Latest Schedule Changes
366
Total Schedule Changes
256
Purchase and Install Speed Cameras in School Zones Areas
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 1071 • Project Name: Purchase and Install Speed Cameras in School Zones Areas
Date Reported As Of
2022-09-01T00:00:00.000
Pid
1071
Project Name
Purchase and Install Speed Cameras in School Zones Areas
Category
Streets and Roadways
Managing Agency
DOT
Client Agency
DOT
Budget Forecast
256354467.00
Latest Budget Changes
64811399.00
Total Budget Changes
-19999521.00
33rd Street West of 11th Avenue (Hudson Yards)
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 1043 • Project Name: 33rd Street West of 11th Avenue (Hudson Yards)
Date Reported As Of
2022-09-01T00:00:00.000
Pid
1043
Project Name
33rd Street West of 11th Avenue (Hudson Yards)
Category
Bridges
Managing Agency
DOT
Client Agency
EDC
Current Phase
Design
Design Start
2017-04-01T00:00:00.000
Budget Forecast
100196144.00
Latest Budget Changes
196040.00
Total Budget Changes
-1399960.00
Forecast Completion
2029-05-04T00:00:00.000
Latest Schedule Changes
113
Total Schedule Changes
611
Dumbo and Vinegar Hill Area Roadway Reconstruction and Renovation
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 193 • Project Name: Dumbo and Vinegar Hill Area Roadway Reconstruction and Renovation
Date Reported As Of
2022-09-01T00:00:00.000
Pid
193
Project Name
Dumbo and Vinegar Hill Area Roadway Reconstruction and Renovation
Description
Reconstruction DUMBO/Vinegar Hill Area including Trunk and Distribution water main replacement; Installation of HLSS and Combined Sewer replacement; Restoration of Belgian block in Water Street; Street lighting and Traffic Signal work.
Category
Streets and Roadways
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction
Design Start
2012-06-07T00:00:00.000
Budget Forecast
131339000.00
Latest Budget Changes
929000.00
Total Budget Changes
96724000.00
Forecast Completion
2024-06-04T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
3253
FUEL TANK REPLACEMENT - 71
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 935 • Project Name: FUEL TANK REPLACEMENT - 71
Date Reported As Of
2022-09-01T00:00:00.000
Pid
935
Project Name
FUEL TANK REPLACEMENT - 71
Description
By Notice To Proceed letter dated September 21, 2018, the New York City Department of Design and Construction (“DDC”) directed PMS Construction Management Corp. (“PMS”) to commence work on Capis ID PW348-71, Contract No. 20191404531 CM/Design/Build for the Replacement and Upgrade of Petroleum Storage Tanks for the Borough of Manhattan. The contract was awarded for a maximum fee of $28,026,750.00 and was partially registered by the Comptroller on September 21, 2018 in the amount of $4,885,000.00. The term of the contract is 1,095 consecutive calendar days from September 21, 2018. Contract termination date is September 19, 2021.
Category
Industrial Development
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Construction
Design Start
2018-10-02T00:00:00.000
Budget Forecast
32709000.00
Latest Budget Changes
0.00
Total Budget Changes
3444000.00
Forecast Completion
2024-03-20T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
548
Hillview Reservoir Chemical Addition Facilities
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 669 • Project Name: Hillview Reservoir Chemical Addition Facilities
Date Reported As Of
2022-09-01T00:00:00.000
Pid
669
Project Name
Hillview Reservoir Chemical Addition Facilities
Description
This project provides new chemical addition and support facilities at Hillview Reservoir.
Category
Water Supply
Borough
City of Yonkers
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2020-03-17T00:00:00.000
Budget Forecast
540271602.01
Latest Budget Changes
56566302.01
Total Budget Changes
159902202.01
Forecast Completion
2029-03-28T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
82
Owls Head WWTP Final Settling System Rehabilitation
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 946 • Project Name: Owls Head WWTP Final Settling System Rehabilitation
Date Reported As Of
2022-09-01T00:00:00.000
Pid
946
Project Name
Owls Head WWTP Final Settling System Rehabilitation
Description
Rehabilitation of the Final Settling Tanks at Owls Head Wastewater Resources Recovery Facility.
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2021-11-09T00:00:00.000
Budget Forecast
209226836.00
Latest Budget Changes
469096.00
Total Budget Changes
-3573164.00
Forecast Completion
2028-08-06T00:00:00.000
Latest Schedule Changes
-292
Total Schedule Changes
345
Far Rockaway New Facility
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 730 • Project Name: Far Rockaway New Facility
Date Reported As Of
2022-09-01T00:00:00.000
Pid
730
Project Name
Far Rockaway New Facility
Description
Construction of a new 18,000 sq.ft. Branch employing the latest technology and sustainable design.
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
Libraries-QBPL
Current Phase
Construction
Design Start
2012-01-10T00:00:00.000
Budget Forecast
39531557.09
Latest Budget Changes
0.00
Total Budget Changes
-623757.91
Forecast Completion
2023-02-01T00:00:00.000
Latest Schedule Changes
247
Total Schedule Changes
-78
Pier 42 and East River Park Connector Program
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 1085 • Project Name: Pier 42 and East River Park Connector Program
Date Reported As Of
2022-09-01T00:00:00.000
Pid
1085
Project Name
Pier 42 and East River Park Connector Program
Description
Abatement, demolition, and replacement of shed with an upland park on Pier 42 in Manhattan.
Category
Parks
Managing Agency
EDC
Client Agency
DPR
Current Phase
Construction
Design Start
2017-06-01T00:00:00.000
Budget Forecast
60215737.00
Latest Budget Changes
100000.00
Total Budget Changes
100000.00
Forecast Completion
2023-08-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
214
Brooklyn Public School 710 Pre-K
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 1097 • Project Name: Brooklyn Public School 710 Pre-K
Date Reported As Of
2022-09-01T00:00:00.000
Pid
1097
Project Name
Brooklyn Public School 710 Pre-K
Description
NEW SCHOOL
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2019-06-17T00:00:00.000
Budget Forecast
38697915.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2023-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
0
The Reconstruction of The Lower Catskill Aqueduct
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 667 • Project Name: The Reconstruction of The Lower Catskill Aqueduct
Date Reported As Of
2022-09-01T00:00:00.000
Pid
667
Project Name
The Reconstruction of The Lower Catskill Aqueduct
Description
Reconstruction of Aqueduct structures; Replacement of mechanical equipment; cleaning the aqueduct interior & rehabilitation & repair of cracks & leaks. All relevent assessments, investigations, piloting, plans and reports.
Category
Water Supply
Borough
Citywide
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2019-04-15T00:00:00.000
Budget Forecast
249500116.00
Latest Budget Changes
39271.00
Total Budget Changes
-65760729.00
Forecast Completion
2027-11-27T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1421
Upgrade of Paerdegat, Avenue U, and 19th Street Pumping Stations
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 1039 • Project Name: Upgrade of Paerdegat, Avenue U, and 19th Street Pumping Stations
Date Reported As Of
2022-09-01T00:00:00.000
Pid
1039
Project Name
Upgrade of Paerdegat, Avenue U, and 19th Street Pumping Stations
Description
Design for the reconstruction or rehabilitation of the Paerdegat, Avenue U, and 19th Street Pumping Stations.
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2022-09-01T00:00:00.000
Budget Forecast
101030936.00
Latest Budget Changes
-8003328.00
Total Budget Changes
-8003328.00
Forecast Completion
2027-05-09T00:00:00.000
Latest Schedule Changes
525
Total Schedule Changes
525
Catskill Aqueduct Repair and Rehabilitation
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 478 • Project Name: Catskill Aqueduct Repair and Rehabilitation
Date Reported As Of
2022-09-01T00:00:00.000
Pid
478
Project Name
Catskill Aqueduct Repair and Rehabilitation
Description
Project to ensure the reliability of the 74 mile upper Catskill Aqueduct, including replacement of mechanical components, leak mitigation, and biofilm removal/condition assessment.
Category
Water Supply
Borough
Citywide
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2015-06-19T00:00:00.000
Budget Forecast
242269503.18
Latest Budget Changes
-2000000.00
Total Budget Changes
9642889.68
Forecast Completion
2022-11-15T00:00:00.000
Latest Schedule Changes
106
Total Schedule Changes
1517
Sewer When & Where Contract In S.E. Queens
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 793 • Project Name: Sewer When & Where Contract In S.E. Queens
Date Reported As Of
2022-09-01T00:00:00.000
Pid
793
Project Name
Sewer When & Where Contract In S.E. Queens
Description
SEWER WHEN & WHERE CONTRACT IN South East Queens. NEW STORM SEWER CONSTRUCTION, REPLACEMENT OR UPGRADES TO SANITARY SEWERS AND WATER MAIN IN PROJECT AREAS. GREEN INFRASTRUCTURE PROJECTS IN CONJUNCTION WITH WHEN & WHERE PROJECTS.
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2018-05-14T00:00:00.000
Budget Forecast
36804000.00
Latest Budget Changes
530000.00
Total Budget Changes
7404000.00
Forecast Completion
2025-09-22T00:00:00.000
Latest Schedule Changes
31
Total Schedule Changes
1834
DOH Public Health Lab
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 909 • Project Name: DOH Public Health Lab
Date Reported As Of
2022-09-01T00:00:00.000
Pid
909
Project Name
DOH Public Health Lab
Description
The construction of an approximately 230,000 sq ft municipal Public Health Lab building for DOHMH.
Category
Health and Hospitals
Managing Agency
EDC
Client Agency
DOHMH
Current Phase
Construction Procurement
Design Start
2019-01-01T00:00:00.000
Budget Forecast
633132280.00
Latest Budget Changes
0.00
Total Budget Changes
19334959.71
Forecast Completion
2025-01-01T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1
Lower Concourse Initiative
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 575 • Project Name: Lower Concourse Initiative
Date Reported As Of
2022-09-01T00:00:00.000
Pid
575
Project Name
Lower Concourse Initiative
Description
The Project will improve the roadways and pedestrian facilities. The Project will consist of roadway reconstruction within Exterior Street between East 138th Street and East 150th Street.
Category
Industrial Development
Borough
Bronx
Managing Agency
EDC
Client Agency
EDC
Current Phase
Construction
Design Start
2017-04-01T00:00:00.000
Budget Forecast
84520367.00
Latest Budget Changes
0.00
Total Budget Changes
-5100000.00
Forecast Completion
2023-09-01T00:00:00.000
Latest Schedule Changes
63
Total Schedule Changes
730
Ped Safety Upgrades on Atlantic Avenue, Phase 2
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 519 • Project Name: Ped Safety Upgrades on Atlantic Avenue, Phase 2
Date Reported As Of
2022-09-01T00:00:00.000
Pid
519
Project Name
Ped Safety Upgrades on Atlantic Avenue, Phase 2
Description
PED. SAFETY UPGRADES ON ATLANTIC AVE - PH 2, BROOKLYN
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction
Design Start
2016-08-04T00:00:00.000
Budget Forecast
40012000.00
Latest Budget Changes
-1000.00
Total Budget Changes
10136496.00
Forecast Completion
2024-05-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1400
Williamsburg Bridge Miscellaneous Repairs and Painting
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 599 • Project Name: Williamsburg Bridge Miscellaneous Repairs and Painting
Date Reported As Of
2022-09-01T00:00:00.000
Pid
599
Project Name
Williamsburg Bridge Miscellaneous Repairs and Painting
Description
Scope includes paint the south side of the bridge, repair flags and structural steel, evaluate PP20 Bearings, evaluate tension rods at mid-span of the bridge, repair bridge cables and suspenders, replace modular joint, investigate the feasibility of additional clearance at towers, and resurface bridge decks with new waterproofing membrane.
Category
Bridges
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction Procurement
Design Start
2018-08-15T00:00:00.000
Budget Forecast
228073406.00
Latest Budget Changes
20690839.00
Total Budget Changes
52784947.00
Forecast Completion
2026-06-18T00:00:00.000
Latest Schedule Changes
58
Total Schedule Changes
362
TLC - NEW OFFICE FACILITY - 24-55 BQE WEST
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 665 • Project Name: TLC - NEW OFFICE FACILITY - 24-55 BQE WEST
Date Reported As Of
2022-09-01T00:00:00.000
Pid
665
Project Name
TLC - NEW OFFICE FACILITY - 24-55 BQE WEST
Description
Replace existing administration wing; provide new parking and new inspection lane within the facility.
Category
Other Government Facilities
Borough
Queens
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Construction
Design Start
2015-09-15T00:00:00.000
Budget Forecast
152476000.00
Latest Budget Changes
120000.00
Total Budget Changes
75370000.00
Forecast Completion
2026-05-01T00:00:00.000
Latest Schedule Changes
403
Total Schedule Changes
1248
Park Avenue Tunnel (Murray Hill)
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 536 • Project Name: Park Avenue Tunnel (Murray Hill)
Date Reported As Of
2022-09-01T00:00:00.000
Pid
536
Project Name
Park Avenue Tunnel (Murray Hill)
Description
Repair Park Avenue tunnel, located in Midtown, Manhattan.
Category
Bridges
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2006-08-01T00:00:00.000
Budget Forecast
43024414.00
Latest Budget Changes
-3371857.00
Total Budget Changes
-17773389.61
Forecast Completion
2023-05-02T00:00:00.000
Latest Schedule Changes
272
Total Schedule Changes
1568
Revenue Cycle Implementation
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 723 • Project Name: Revenue Cycle Implementation
Date Reported As Of
2022-09-01T00:00:00.000
Pid
723
Project Name
Revenue Cycle Implementation
Description
The Epic Revenue Cycle system will be enterprise-wide and help increase revenue (by proper billing of services provided) in addition to ensuring patient safety and improved patient care, a top priority in workflows.
Category
Health and Hospitals, IT
Borough
Citywide
Managing Agency
HHC
Client Agency
H+H
Current Phase
IT
Budget Forecast
289117990.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2023-12-31T00:00:00.000
Latest Schedule Changes
365
Total Schedule Changes
1279
Reconstruction of Mersereau, Richmond Ave and Mayflower Ave PSs
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 1040 • Project Name: Reconstruction of Mersereau, Richmond Ave and Mayflower Ave PSs
Date Reported As Of
2022-09-01T00:00:00.000
Pid
1040
Project Name
Reconstruction of Mersereau, Richmond Ave and Mayflower Ave PSs
Description
Design & DSDC for the upgrade of three NYCDEP Pumping Stations. The scope of the project is to provide a safe, reliable, efficient, resilient and low maintenance pumping station for the Operating Bureau.
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2021-04-30T00:00:00.000
Budget Forecast
155194829.80
Latest Budget Changes
15655216.80
Total Budget Changes
45860651.80
Forecast Completion
2025-11-07T00:00:00.000
Latest Schedule Changes
182
Total Schedule Changes
641