All major infrastructure and information technology projects with a budget of $25 million or more that are currently active (in the design, procurement, or construction phase).
City GovernmentMayor's Office of Operations (OPS)
Dataset n7gv-k5yt
16 fields
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 619 • Project Name: RECONSTRUCTION OF QUEENS BLVD - PHASE 2
Date Reported As Of
2022-09-01T00:00:00.000
Pid
619
Project Name
RECONSTRUCTION OF QUEENS BLVD - PHASE 2
Description
Vision Zero - Queens Boulevard - Segment 2: 73rd Street to Eliot Avenue. Variety of safety and streetscape improvements including partial street reconstruction and resurfacing to address roadway conditions
Category
Industrial Development
Borough
Queens
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2016-10-26T00:00:00.000
Budget Forecast
86043000.00
Latest Budget Changes
1000000.00
Total Budget Changes
14201000.00
Forecast Completion
2029-08-13T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2315
The Reconstruction of The Lower Catskill Aqueduct
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 667 • Project Name: The Reconstruction of The Lower Catskill Aqueduct
Date Reported As Of
2022-09-01T00:00:00.000
Pid
667
Project Name
The Reconstruction of The Lower Catskill Aqueduct
Description
Reconstruction of Aqueduct structures; Replacement of mechanical equipment; cleaning the aqueduct interior & rehabilitation & repair of cracks & leaks. All relevent assessments, investigations, piloting, plans and reports.
Category
Water Supply
Borough
Citywide
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2019-04-15T00:00:00.000
Budget Forecast
249500116.00
Latest Budget Changes
39271.00
Total Budget Changes
-65760729.00
Forecast Completion
2027-11-27T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1421
Manhattan Greenway: East Midtown
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 859 • Project Name: Manhattan Greenway: East Midtown
Date Reported As Of
2022-09-01T00:00:00.000
Pid
859
Project Name
Manhattan Greenway: East Midtown
Description
The East Midtown Waterfront Greenway project involves the creation of a waterfront esplanade between East 53rd and East 59th Streets.
Category
Parks
Managing Agency
EDC
Client Agency
EDC
Current Phase
Construction
Design Start
2017-10-01T00:00:00.000
Budget Forecast
154840000.00
Latest Budget Changes
0.00
Total Budget Changes
24840000.00
Forecast Completion
2023-12-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
487
FUEL TANK & SUMP REPLACEMENTS - MANHATTAN/S.I.
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 900 • Project Name: FUEL TANK & SUMP REPLACEMENTS - MANHATTAN/S.I.
Date Reported As Of
2022-09-01T00:00:00.000
Pid
900
Project Name
FUEL TANK & SUMP REPLACEMENTS - MANHATTAN/S.I.
Description
CITYWIDE FUEL TANK REPLACEMENT PROGRAM FOR NEW 2015 EPA PETROLEUM BULK STORAGE REGULATIONS
Category
Industrial Development
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Construction
Design Start
2019-07-17T00:00:00.000
Budget Forecast
25646000.00
Latest Budget Changes
100000.00
Total Budget Changes
-1754000.00
Forecast Completion
2025-01-22T00:00:00.000
Latest Schedule Changes
-158
Total Schedule Changes
663
Queens Public School 41 SSBA Addition
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 1105 • Project Name: Queens Public School 41 SSBA Addition
Date Reported As Of
2022-09-01T00:00:00.000
Pid
1105
Project Name
Queens Public School 41 SSBA Addition
Description
ADDITION / DEMOLITION
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2019-08-05T00:00:00.000
Budget Forecast
70755417.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2024-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
0
Combined Sewer In 70Th Street, Queens
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 788 • Project Name: Combined Sewer In 70Th Street, Queens
Date Reported As Of
2022-09-01T00:00:00.000
Pid
788
Project Name
Combined Sewer In 70Th Street, Queens
Description
COMBINED SEWER IN 70TH STREET, QUEENS
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2016-08-31T00:00:00.000
Budget Forecast
132158000.00
Latest Budget Changes
7385000.00
Total Budget Changes
94201000.00
Forecast Completion
2023-08-10T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1155
TRAVIS AVENUE WIDENING
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 1240 • Project Name: TRAVIS AVENUE WIDENING
Date Reported As Of
2022-09-01T00:00:00.000
Pid
1240
Project Name
TRAVIS AVENUE WIDENING
Description
TRAVIS AVENUE WIDENING
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2015-01-15T00:00:00.000
Budget Forecast
85637000.00
Latest Budget Changes
30000.00
Total Budget Changes
50000.00
Forecast Completion
2027-10-22T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1029
Ped Safety Upgrades on Atlantic Avenue, Phase 2
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 519 • Project Name: Ped Safety Upgrades on Atlantic Avenue, Phase 2
Date Reported As Of
2022-09-01T00:00:00.000
Pid
519
Project Name
Ped Safety Upgrades on Atlantic Avenue, Phase 2
Description
PED. SAFETY UPGRADES ON ATLANTIC AVE - PH 2, BROOKLYN
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction
Design Start
2016-08-04T00:00:00.000
Budget Forecast
40012000.00
Latest Budget Changes
-1000.00
Total Budget Changes
10136496.00
Forecast Completion
2024-05-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1400
FDR Rehabilitation, Northbound (East 42nd to 49th Streets)
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 502 • Project Name: FDR Rehabilitation, Northbound (East 42nd to 49th Streets)
Date Reported As Of
2022-09-01T00:00:00.000
Pid
502
Project Name
FDR Rehabilitation, Northbound (East 42nd to 49th Streets)
Description
Repair the northbound FDR from East 42nd to 49th Streets.
Category
Bridges
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2016-08-30T00:00:00.000
Budget Forecast
87080178.00
Latest Budget Changes
8420000.00
Total Budget Changes
-2802822.00
Forecast Completion
2029-08-12T00:00:00.000
Latest Schedule Changes
124
Total Schedule Changes
1816
Headworks Improvements at Tallman Island
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 906 • Project Name: Headworks Improvements at Tallman Island
Date Reported As Of
2022-09-01T00:00:00.000
Pid
906
Project Name
Headworks Improvements at Tallman Island
Description
Headworks Improvements
Category
Industrial Development
Managing Agency
DEP
Client Agency
WWC
Current Phase
Construction Procurement
Design Start
2019-07-07T00:00:00.000
Budget Forecast
52030751.00
Latest Budget Changes
0.00
Total Budget Changes
19975649.96
Forecast Completion
2026-08-14T00:00:00.000
Latest Schedule Changes
-83
Total Schedule Changes
586
Bronx Public School 87 Addition
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 1103 • Project Name: Bronx Public School 87 Addition
Date Reported As Of
2022-09-01T00:00:00.000
Pid
1103
Project Name
Bronx Public School 87 Addition
Description
ADDITION / EXISTING SCHOOL RENOVATION WORK
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2019-09-23T00:00:00.000
Budget Forecast
70834393.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2024-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
0
Shore Road Bridge over Hutchinson River
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 541 • Project Name: Shore Road Bridge over Hutchinson River
Date Reported As Of
2022-09-01T00:00:00.000
Pid
541
Project Name
Shore Road Bridge over Hutchinson River
Description
Replace the Shore Road Bridge over the Hutchinson River with a new bridge.
Category
Bridges, Streets and Roadways
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-06-30T00:00:00.000
Budget Forecast
340732843.00
Latest Budget Changes
3266615.00
Total Budget Changes
-19049921.84
Forecast Completion
2029-07-24T00:00:00.000
Latest Schedule Changes
115
Total Schedule Changes
1477
Throgs Neck Pumping Station Rehabilitation and Improvements
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 722 • Project Name: Throgs Neck Pumping Station Rehabilitation and Improvements
Date Reported As Of
2022-09-01T00:00:00.000
Pid
722
Project Name
Throgs Neck Pumping Station Rehabilitation and Improvements
Description
Throgs Neck Pumping Station Rehabilitation and Improvements
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2018-06-30T00:00:00.000
Budget Forecast
67397822.86
Latest Budget Changes
-2248.39
Total Budget Changes
25708336.86
Forecast Completion
2025-12-16T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1306
Revenue Cycle Implementation
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 723 • Project Name: Revenue Cycle Implementation
Date Reported As Of
2022-09-01T00:00:00.000
Pid
723
Project Name
Revenue Cycle Implementation
Description
The Epic Revenue Cycle system will be enterprise-wide and help increase revenue (by proper billing of services provided) in addition to ensuring patient safety and improved patient care, a top priority in workflows.
Category
Health and Hospitals, IT
Borough
Citywide
Managing Agency
HHC
Client Agency
H+H
Current Phase
IT
Budget Forecast
289117990.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2023-12-31T00:00:00.000
Latest Schedule Changes
365
Total Schedule Changes
1279
Storm Mitigation Loan Program at Hunts Point
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 672 • Project Name: Storm Mitigation Loan Program at Hunts Point
Date Reported As Of
2022-09-01T00:00:00.000
Pid
672
Project Name
Storm Mitigation Loan Program at Hunts Point
Description
SMLP portion for Hunts Point WWTP as part of the New York City Wastewater Resiliency Program.
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2018-04-16T00:00:00.000
Budget Forecast
61753279.02
Latest Budget Changes
-8508482.82
Total Budget Changes
20080597.79
Forecast Completion
2023-11-17T00:00:00.000
Latest Schedule Changes
273
Total Schedule Changes
1091
79th St Boat Basin
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 862 • Project Name: 79th St Boat Basin
Date Reported As Of
2022-09-01T00:00:00.000
Pid
862
Project Name
79th St Boat Basin
Description
Reconstruction of bulkhead and piers at 79th St Boat Basin on behalf of NYCDPR .
Category
Parks
Managing Agency
EDC
Client Agency
DPR
Current Phase
Design
Design Start
2019-06-13T00:00:00.000
Budget Forecast
89219175.00
Latest Budget Changes
0.00
Total Budget Changes
-1131246.67
Forecast Completion
2026-03-11T00:00:00.000
Latest Schedule Changes
184
Total Schedule Changes
1036
Queens Public School 343 New Construction
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 1111 • Project Name: Queens Public School 343 New Construction
Date Reported As Of
2022-09-01T00:00:00.000
Pid
1111
Project Name
Queens Public School 343 New Construction
Description
NEW SCHOOL
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2020-03-03T00:00:00.000
Budget Forecast
70167105.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2023-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
0
Oakwood Beach WWTP Headworks Improvements
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 450 • Project Name: Oakwood Beach WWTP Headworks Improvements
Date Reported As Of
2022-09-01T00:00:00.000
Pid
450
Project Name
Oakwood Beach WWTP Headworks Improvements
Description
Replacement of six bar screens, grit bin vibrator, six ring flushing pumps, six main sewage pumps and assoc. piping/valves and motor control center, replacement of four exhaust fans, gas and oxygen detectors and a 15 KVA transformer
Category
Wastewater Treatment
Borough
Staten Island
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2023-02-01T00:00:00.000
Budget Forecast
83229440.00
Latest Budget Changes
0.00
Total Budget Changes
31867440.00
Forecast Completion
2029-04-25T00:00:00.000
Latest Schedule Changes
-100
Total Schedule Changes
2857
CONSTRUCTION OF BMPs NC 6 AND 15 - SI
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 631 • Project Name: CONSTRUCTION OF BMPs NC 6 AND 15 - SI
Date Reported As Of
2022-09-01T00:00:00.000
Pid
631
Project Name
CONSTRUCTION OF BMPs NC 6 AND 15 - SI
Description
CONSTRUCTION OF BMP’s NC 6 AND 15, STORM AND SANITARY SEWERS INSTALLATION, SI
Category
Industrial Development
Borough
Staten Island
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2017-08-14T00:00:00.000
Budget Forecast
33450000.00
Latest Budget Changes
1171000.00
Total Budget Changes
1921000.00
Forecast Completion
2024-06-09T00:00:00.000
Latest Schedule Changes
556
Total Schedule Changes
925
Brooklyn Public School 676 New Construction
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 1100 • Project Name: Brooklyn Public School 676 New Construction
Implementation of coastal resiliency measures to protect Battery Park and adjacent upland neighborhoods from storm surges and sea level rise.
Category
Parks
Managing Agency
EDC
Client Agency
City Hall
Current Phase
Construction Procurement
Design Start
2020-12-01T00:00:00.000
Budget Forecast
165700000.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2025-04-01T00:00:00.000
Latest Schedule Changes
32
Total Schedule Changes
-29
Bronx Public School 077 Addition
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 1101 • Project Name: Bronx Public School 077 Addition
Date Reported As Of
2022-09-01T00:00:00.000
Pid
1101
Project Name
Bronx Public School 077 Addition
Description
ADDITION / EXISTING SCHOOL RENOVATION WORK (PHASE I) / DEMOLITION (PHASE II)
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2019-09-25T00:00:00.000
Budget Forecast
86862349.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2024-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
0
Gilboa Dam Reconstruction, Phase III
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 405 • Project Name: Gilboa Dam Reconstruction, Phase III
Date Reported As Of
2022-09-01T00:00:00.000
Pid
405
Project Name
Gilboa Dam Reconstruction, Phase III
Description
Gilboa Dam Reconstruction Project includes construction of a new low level outlet (LLO) consisting of 2,000 feet of tunneling , an access shaft, oulet structure and gate valve controls.
Category
Water Supply
Borough
Upstate
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2004-03-18T00:00:00.000
Budget Forecast
200712336.70
Latest Budget Changes
1641564.89
Total Budget Changes
10376533.49
Forecast Completion
2023-03-26T00:00:00.000
Latest Schedule Changes
104
Total Schedule Changes
1113
Pelham Parkway Bridge Reconstruction over Hutchinson Parkway
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 506 • Project Name: Pelham Parkway Bridge Reconstruction over Hutchinson Parkway
Date Reported As Of
2022-09-01T00:00:00.000
Pid
506
Project Name
Pelham Parkway Bridge Reconstruction over Hutchinson Parkway
Description
Replace/Rehab the Pelham Parkway bridge over Hutchinson River Parkway, Bronx.
Category
Bridges, Streets and Roadways
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-11-08T00:00:00.000
Budget Forecast
66783092.00
Latest Budget Changes
-528000.00
Total Budget Changes
10338071.57
Forecast Completion
2029-06-16T00:00:00.000
Latest Schedule Changes
419
Total Schedule Changes
1934
Riverside Drive/West 158th Street Bridge Rehabilitation
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 113 • Project Name: Riverside Drive/West 158th Street Bridge Rehabilitation
Date Reported As Of
2022-09-01T00:00:00.000
Pid
113
Project Name
Riverside Drive/West 158th Street Bridge Rehabilitation
Description
Replace deck of the Riverside Drive viaduct/ bridge over West 158th Street.
Category
Bridges, Streets and Roadways
Borough
Manhattan
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2014-10-22T00:00:00.000
Budget Forecast
144569858.00
Latest Budget Changes
-8567168.00
Total Budget Changes
96922794.00
Forecast Completion
2025-05-21T00:00:00.000
Latest Schedule Changes
676
Total Schedule Changes
2152
Brooklyn Public School 748 New Construction
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 1098 • Project Name: Brooklyn Public School 748 New Construction
Date Reported As Of
2022-09-01T00:00:00.000
Pid
1098
Project Name
Brooklyn Public School 748 New Construction
Description
LEASE
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2018-02-23T00:00:00.000
Budget Forecast
31421420.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2023-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
0
Storm Mitigation Loan Program at Red Hook
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 721 • Project Name: Storm Mitigation Loan Program at Red Hook
Date Reported As Of
2022-09-01T00:00:00.000
Pid
721
Project Name
Storm Mitigation Loan Program at Red Hook
Description
SMLP portion for Red Hook WWTP as part of the New York City Wastewater Resiliency Program.
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2018-11-01T00:00:00.000
Budget Forecast
43033453.47
Latest Budget Changes
3954554.49
Total Budget Changes
13549422.97
Forecast Completion
2023-07-31T00:00:00.000
Latest Schedule Changes
333
Total Schedule Changes
921
South Bronx East-West Crosstown SBS
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 1008 • Project Name: South Bronx East-West Crosstown SBS
Date Reported As Of
2022-09-01T00:00:00.000
Pid
1008
Project Name
South Bronx East-West Crosstown SBS
Description
The South Bronx Crosstown SBS capital project (BRT) will add bus pads and construct bus bulbs, curb and median extensions, and pedestrian islands for enhanced pedestrian safety and access improvements.
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2019-07-01T00:00:00.000
Budget Forecast
53738000.00
Latest Budget Changes
20000.00
Total Budget Changes
3130000.00
Forecast Completion
2027-06-01T00:00:00.000
Latest Schedule Changes
210
Total Schedule Changes
626
Storm Sewer Outlet In 224Th St
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 784 • Project Name: Storm Sewer Outlet In 224Th St
Date Reported As Of
2022-09-01T00:00:00.000
Pid
784
Project Name
Storm Sewer Outlet In 224Th St
Description
Installation of storm sewers at 224th St and 149th Ave and along the access road through Idlewild Parks known as Springfield Lane (Spine Farmers Blvd)
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction Procurement
Design Start
2016-01-04T00:00:00.000
Budget Forecast
157553000.00
Latest Budget Changes
465000.00
Total Budget Changes
155854000.00
Forecast Completion
2026-03-29T00:00:00.000
Latest Schedule Changes
-49
Total Schedule Changes
1238
Wyckoff Avenue Street Reconstruction
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 191 • Project Name: Wyckoff Avenue Street Reconstruction
Date Reported As Of
2022-09-01T00:00:00.000
Pid
191
Project Name
Wyckoff Avenue Street Reconstruction
Description
Reconstruction of Wyckoff Avenue from Flushing Avenue to Cooper Avenue, in the Boroughs of Brooklyn and Queens..
Category
Streets and Roadways
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Trans. & Env. Protection
Current Phase
Design
Design Start
2017-03-29T00:00:00.000
Budget Forecast
77097000.00
Latest Budget Changes
580000.00
Total Budget Changes
43926000.00
Forecast Completion
2027-02-27T00:00:00.000
Latest Schedule Changes
-397
Total Schedule Changes
226
GI - GRAVESEND BAY CSO - PHASE III
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 1199 • Project Name: GI - GRAVESEND BAY CSO - PHASE III
Date Reported As Of
2022-09-01T00:00:00.000
Pid
1199
Project Name
GI - GRAVESEND BAY CSO - PHASE III
Description
GREEN INFRASTRUCTURE IN OH-015 GRAVESEND BAY CSO PH 3
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2017-08-01T00:00:00.000
Budget Forecast
49132000.00
Latest Budget Changes
6390000.00
Total Budget Changes
-372000.00
Forecast Completion
2025-11-19T00:00:00.000
Latest Schedule Changes
161
Total Schedule Changes
189
P.S./I.S. @ 3761 10TH AVENUE - Manhattan
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 1222 • Project Name: P.S./I.S. @ 3761 10TH AVENUE - Manhattan
Date Reported As Of
2022-09-01T00:00:00.000
Pid
1222
Project Name
P.S./I.S. @ 3761 10TH AVENUE - Manhattan
Description
NEW SCHOOL
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2021-03-24T00:00:00.000
Budget Forecast
143089415.00
Latest Budget Changes
9539089.00
Total Budget Changes
9539089.00
Forecast Completion
2024-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
0
Orchard Beach Pavilion
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 858 • Project Name: Orchard Beach Pavilion
Date Reported As Of
2022-09-01T00:00:00.000
Pid
858
Project Name
Orchard Beach Pavilion
Description
The restoration of the existing landmarked Orchard Beach Pavilion (located in Bronx, NY) which includes the construction of an ADA ramp at the main entrance of the Pavilion to improve accessibility to the beach passageway.
Category
Parks
Managing Agency
EDC
Client Agency
DPR
Current Phase
Construction Procurement
Design Start
2018-11-30T00:00:00.000
Budget Forecast
87652588.00
Latest Budget Changes
0.00
Total Budget Changes
35628847.00
Forecast Completion
2025-02-28T00:00:00.000
Latest Schedule Changes
-31
Total Schedule Changes
942
Brooklyn Public School 710 Pre-K
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 1097 • Project Name: Brooklyn Public School 710 Pre-K
Date Reported As Of
2022-09-01T00:00:00.000
Pid
1097
Project Name
Brooklyn Public School 710 Pre-K
Description
NEW SCHOOL
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2019-06-17T00:00:00.000
Budget Forecast
38697915.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2023-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
0
Jerome Reservoir and Aqueduct Rehabilitation
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 448 • Project Name: Jerome Reservoir and Aqueduct Rehabilitation
Date Reported As Of
2022-09-01T00:00:00.000
Pid
448
Project Name
Jerome Reservoir and Aqueduct Rehabilitation
Description
Improvements to: fencing, vegetation, roadway, drainage, ext. above-ground retaining walls. Including repair of dam inlet archway & wingwall, re-pointing of stones & reinforcement of east reservoir wall, & leakage/seepage protection within OCA.
Category
Water Supply
Borough
Bronx
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2016-02-24T00:00:00.000
Budget Forecast
57966722.86
Latest Budget Changes
711099.77
Total Budget Changes
-833277.14
Forecast Completion
2026-12-29T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2363
Queens Public School 472 New Construction
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 1099 • Project Name: Queens Public School 472 New Construction
Date Reported As Of
2022-09-01T00:00:00.000
Pid
1099
Project Name
Queens Public School 472 New Construction
Description
NEW SCHOOL
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2019-01-07T00:00:00.000
Budget Forecast
251284250.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2025-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
0
Bronx Public School 469 New Construction
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 1102 • Project Name: Bronx Public School 469 New Construction
Date Reported As Of
2022-09-01T00:00:00.000
Pid
1102
Project Name
Bronx Public School 469 New Construction
Description
NEW SCHOOL / PLAYGROUND REDEVELOPMENT
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2020-03-13T00:00:00.000
Budget Forecast
80509310.00
Latest Budget Changes
0.00
Total Budget Changes
-505800.00
Forecast Completion
2024-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
0
P.S. 138 - BRONX Addition
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 1220 • Project Name: P.S. 138 - BRONX Addition
Date Reported As Of
2022-09-01T00:00:00.000
Pid
1220
Project Name
P.S. 138 - BRONX Addition
Description
ADDITION
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2020-10-26T00:00:00.000
Budget Forecast
81207595.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2024-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
0
Construction Of Sanitary Sewers, Storm Sewers (Bm
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 760 • Project Name: Construction Of Sanitary Sewers, Storm Sewers (Bm
Date Reported As Of
2022-09-01T00:00:00.000
Pid
760
Project Name
Construction Of Sanitary Sewers, Storm Sewers (Bm
Description
Construction of storm sewers, sanitary sewers, water mains and Best Management Practice (BMP) NC-16 in Mason Avenue area, Borough of Staten Island.
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2016-08-29T00:00:00.000
Budget Forecast
70400000.00
Latest Budget Changes
845000.00
Total Budget Changes
37691000.00
Forecast Completion
2023-06-26T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
595
Storm Sanitary Sewer Repl Springfield Gardens
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 790 • Project Name: Storm Sanitary Sewer Repl Springfield Gardens
Date Reported As Of
2022-09-01T00:00:00.000
Pid
790
Project Name
Storm Sanitary Sewer Repl Springfield Gardens
Description
SPRINGFIELD GARDENS RECONSTRUCTION PHASE 5; STORM AND SANITARY SEWER EXTENSIONS AND UPGRADES AND WATER MAIN REPLACEMENT IN 146TH AVENUE BETWEEN 153RD PLACE AND 159TH STREET, ETC, BOROUGH OF QUEENS (HWQ662G)
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2018-05-09T00:00:00.000
Budget Forecast
113177000.00
Latest Budget Changes
400000.00
Total Budget Changes
35414000.00
Forecast Completion
2027-09-15T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1097
Metropolitan Hospital Perimeter Flood Protection
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 562 • Project Name: Metropolitan Hospital Perimeter Flood Protection
Date Reported As Of
2022-09-01T00:00:00.000
Pid
562
Project Name
Metropolitan Hospital Perimeter Flood Protection
Description
Flood mitigation system to protect Metropolitan's campus from future flooding due and sea level rise
Category
Industrial Development
Borough
Manhattan
Managing Agency
EDC
Client Agency
H+H
Current Phase
Construction
Design Start
2016-12-01T00:00:00.000
Budget Forecast
108206086.00
Latest Budget Changes
-1426264.00
Total Budget Changes
27046705.00
Forecast Completion
2024-11-21T00:00:00.000
Latest Schedule Changes
-862
Total Schedule Changes
1452
Sewer When & Where Seq
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 794 • Project Name: Sewer When & Where Seq
Date Reported As Of
2022-09-01T00:00:00.000
Pid
794
Project Name
Sewer When & Where Seq
Description
NEW STORM SEWER CONSTRUCTION, REPLACEMENT OR UPGRADES TO SANITARY SEWERS AND WATER MAINS IN PROJECT AREAS. GREEN INFRASTRUCTURE PROJECTS TO BE DONE IN CONJUNCTION WITH THESE CAPITAL IMPROVEMENTS
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2020-03-09T00:00:00.000
Budget Forecast
28200000.00
Latest Budget Changes
0.00
Total Budget Changes
3200000.00
Forecast Completion
2026-02-16T00:00:00.000
Latest Schedule Changes
211
Total Schedule Changes
1377
P.S. 96 - QUEENS Addition
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 1221 • Project Name: P.S. 96 - QUEENS Addition
Date Reported As Of
2022-09-01T00:00:00.000
Pid
1221
Project Name
P.S. 96 - QUEENS Addition
Description
ADDITION / EXISTING BUILDING RENOVATION WORK / EXISTING BUILDING-AUDITORIUM / EXISTING BUILDING-CAFETERIA
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2021-02-26T00:00:00.000
Budget Forecast
71785778.00
Latest Budget Changes
-3902865.00
Total Budget Changes
-3902865.00
Forecast Completion
2024-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
0
Kensico Eastview Connection Tunnel Construction
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 554 • Project Name: Kensico Eastview Connection Tunnel Construction
Date Reported As Of
2022-09-01T00:00:00.000
Pid
554
Project Name
Kensico Eastview Connection Tunnel Construction
Description
The redundant connection between Kensico and Hillview Reservoirs provides resiliency against planned or unplanned tunnel outages to deliver water.
Category
Water Supply
Borough
Valhalla
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2017-08-01T00:00:00.000
Budget Forecast
2058435326.00
Latest Budget Changes
101238889.40
Total Budget Changes
881770648.00
Forecast Completion
2033-12-05T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
3132
Bronx Sanitation Garage Construction: Community District 9, 10, 11
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 573 • Project Name: Bronx Sanitation Garage Construction: Community District 9, 10, 11
Date Reported As Of
2022-09-01T00:00:00.000
Pid
573
Project Name
Bronx Sanitation Garage Construction: Community District 9, 10, 11
Description
Construction of new Sanitation garage facility to serve Bronx community districts 9, 10, and 11 to be located at Zerega Avenue in the Bronx
Category
Sanitation
Borough
Bronx
Managing Agency
DSNY
Client Agency
DSNY
Current Phase
Design
Design Start
2017-08-01T00:00:00.000
Budget Forecast
341795000.00
Latest Budget Changes
0.00
Total Budget Changes
268983862.56
Forecast Completion
2030-06-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1919
Central Park Light Infrastructure
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 586 • Project Name: Central Park Light Infrastructure
Date Reported As Of
2022-09-01T00:00:00.000
Pid
586
Project Name
Central Park Light Infrastructure
Description
Install, remove, and furnish equipment for electrical work associated with traffic signals, lighting, and distribution systems in Central Park, Manhattan.
Category
Parks, Streets and Roadways
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2016-04-29T00:00:00.000
Budget Forecast
39771188.00
Latest Budget Changes
335712.00
Total Budget Changes
-3323649.60
Forecast Completion
2023-06-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1535
Raise Shorelines Citywide
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 689 • Project Name: Raise Shorelines Citywide
Date Reported As Of
2022-09-01T00:00:00.000
Pid
689
Project Name
Raise Shorelines Citywide
Description
The design and construction of shoreline reconstruction projects necessary to provide Citywide protection from future flooding caused by elevated seal elvels.
Category
Industrial Development
Borough
Citywide
Managing Agency
EDC
Client Agency
ORR
Current Phase
Design
Design Start
2017-08-01T00:00:00.000
Budget Forecast
60422401.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2024-09-30T00:00:00.000
Latest Schedule Changes
274
Total Schedule Changes
639
Electronic Medical Records Upgrade
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 403 • Project Name: Electronic Medical Records Upgrade
Date Reported As Of
2022-09-01T00:00:00.000
Pid
403
Project Name
Electronic Medical Records Upgrade
Description
The EPIC - EMR Program: Electronic Medical Records (EMR) System - a single enterprise-wide EMR to meet the needs of HHC's expansive size and improve patient care will replace the legacy EMR - QuadraMed, which is over 25 years old.
Category
Health and Hospitals, IT
Borough
Citywide
Managing Agency
HHC
Client Agency
H+H
Current Phase
IT
Budget Forecast
764063231.00
Latest Budget Changes
0.00
Total Budget Changes
15184947.00
Forecast Completion
2023-12-31T00:00:00.000
Latest Schedule Changes
365
Total Schedule Changes
2032
Roosevelt Avenue Bridge Superstructure and Substructure Repairs
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 101 • Project Name: Roosevelt Avenue Bridge Superstructure and Substructure Repairs
Date Reported As Of
2022-09-01T00:00:00.000
Pid
101
Project Name
Roosevelt Avenue Bridge Superstructure and Substructure Repairs
Description
Repair the bridge superstructure and substructure and install a new concrete-filled steel grid deck.
Category
Bridges
Borough
Queens
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2003-03-10T00:00:00.000
Budget Forecast
161859565.00
Latest Budget Changes
21960722.00
Total Budget Changes
23798213.00
Forecast Completion
2023-08-07T00:00:00.000
Latest Schedule Changes
242
Total Schedule Changes
2003
Installation of Dechlorination System at Hunts Point WRRF
Date Reported As Of: 2022-09-01T00:00:00.000 • Pid: 1094 • Project Name: Installation of Dechlorination System at Hunts Point WRRF
Date Reported As Of
2022-09-01T00:00:00.000
Pid
1094
Project Name
Installation of Dechlorination System at Hunts Point WRRF
Description
Install a Dechlorination System, replace the existing chlorination system including chemical storage tanks, metering pumps, electrical distribution equipment and upgrade the HVAC within the existing Chlorination Building.