Capital Projects

All major infrastructure and information technology projects with a budget of $25 million or more that are currently active (in the design, procurement, or construction phase).

City Government Mayor's Office of Operations (OPS) Dataset n7gv-k5yt 16 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
Porpoise Bridge In Flushing Meadows-Corona Park
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 749 • Project Name: Porpoise Bridge In Flushing Meadows-Corona Park
Date Reported As Of
2022-04-01T00:00:00.000
Pid
749
Project Name
Porpoise Bridge In Flushing Meadows-Corona Park
Description
Feasibility Study for the repair and or restoration for Porpoise (Tide Gate) Bridge in Flushing Meadows Corona Park.
Category
Bridges
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2017-09-18T00:00:00.000
Budget Forecast
63979000.00
Latest Budget Changes
0.00
Total Budget Changes
82000.00
Forecast Completion
2026-05-06T00:00:00.000
Latest Schedule Changes
30
Total Schedule Changes
1110
Brooklyn Public School 253 Addition
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1110 • Project Name: Brooklyn Public School 253 Addition
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1110
Project Name
Brooklyn Public School 253 Addition
Description
ADDITION
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2020-03-09T00:00:00.000
Budget Forecast
75767435.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2024-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
0
Sewer When & Where Seq
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 794 • Project Name: Sewer When & Where Seq
Date Reported As Of
2022-04-01T00:00:00.000
Pid
794
Project Name
Sewer When & Where Seq
Description
NEW STORM SEWER CONSTRUCTION, REPLACEMENT OR UPGRADES TO SANITARY SEWERS AND WATER MAINS IN PROJECT AREAS. GREEN INFRASTRUCTURE PROJECTS TO BE DONE IN CONJUNCTION WITH THESE CAPITAL IMPROVEMENTS
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2020-03-09T00:00:00.000
Budget Forecast
28200000.00
Latest Budget Changes
0.00
Total Budget Changes
3200000.00
Forecast Completion
2025-07-20T00:00:00.000
Latest Schedule Changes
90
Total Schedule Changes
1377
Roosevelt Avenue Bridge Superstructure and Substructure Repairs
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 101 • Project Name: Roosevelt Avenue Bridge Superstructure and Substructure Repairs
Date Reported As Of
2022-04-01T00:00:00.000
Pid
101
Project Name
Roosevelt Avenue Bridge Superstructure and Substructure Repairs
Description
Repair the bridge superstructure and substructure and install a new concrete-filled steel grid deck.
Category
Bridges
Borough
Queens
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2003-03-10T00:00:00.000
Budget Forecast
139898843.00
Latest Budget Changes
-2317594.00
Total Budget Changes
23798213.00
Forecast Completion
2022-12-08T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2003
253 Broadway Landmark's Space Renovations
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 639 • Project Name: 253 Broadway Landmark's Space Renovations
Date Reported As Of
2022-04-01T00:00:00.000
Pid
639
Project Name
253 Broadway Landmark's Space Renovations
Description
Renovate 4 floors of the building to create new office space for the Landmarks Preservation Commission, including new hearing room.
Category
Other Government Facilities
Borough
Manhattan
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Construction
Design Start
2013-01-23T00:00:00.000
Budget Forecast
69056000.00
Latest Budget Changes
-684000.00
Total Budget Changes
35010000.00
Forecast Completion
2022-12-31T00:00:00.000
Latest Schedule Changes
122
Total Schedule Changes
1696
Brooklyn Supreme Court Fire Alarm System Upgrade
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 510 • Project Name: Brooklyn Supreme Court Fire Alarm System Upgrade
Date Reported As Of
2022-04-01T00:00:00.000
Pid
510
Project Name
Brooklyn Supreme Court Fire Alarm System Upgrade
Description
Brooklyn Supreme Court, Fire Alarm, Sprinkler, 360 Adams Street - New addressable fire detection and alarm system and new sprinkler system.
Category
Public Safety and Criminal Justice
Borough
Brooklyn
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Design
Design Start
2017-03-31T00:00:00.000
Budget Forecast
90193000.00
Latest Budget Changes
32000.00
Total Budget Changes
47003000.00
Forecast Completion
2026-06-30T00:00:00.000
Latest Schedule Changes
92
Total Schedule Changes
1533
Bronx Public School 108 Addition
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1109 • Project Name: Bronx Public School 108 Addition
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1109
Project Name
Bronx Public School 108 Addition
Description
ADDITION
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2020-01-17T00:00:00.000
Budget Forecast
86927350.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2024-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
0
Pelham Parkway Bridge Reconstruction over Hutchinson Parkway
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 506 • Project Name: Pelham Parkway Bridge Reconstruction over Hutchinson Parkway
Date Reported As Of
2022-04-01T00:00:00.000
Pid
506
Project Name
Pelham Parkway Bridge Reconstruction over Hutchinson Parkway
Description
Replace/Rehab the Pelham Parkway bridge over Hutchinson River Parkway, Bronx.
Category
Bridges, Streets and Roadways
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-11-08T00:00:00.000
Budget Forecast
67311092.00
Latest Budget Changes
7623562.00
Total Budget Changes
10338071.57
Forecast Completion
2028-04-23T00:00:00.000
Latest Schedule Changes
102
Total Schedule Changes
1934
Queens Public School 032 Addition
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1108 • Project Name: Queens Public School 032 Addition
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1108
Project Name
Queens Public School 032 Addition
Description
ADDITION
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2020-02-24T00:00:00.000
Budget Forecast
67965151.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2024-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
0
Replacement of The Digester at The Hunts Point WWTP
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 580 • Project Name: Replacement of The Digester at The Hunts Point WWTP
Date Reported As Of
2022-04-01T00:00:00.000
Pid
580
Project Name
Replacement of The Digester at The Hunts Point WWTP
Description
Construction of New Anaerobic Digesters
Category
Wastewater Treatment
Borough
Bronx
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2017-10-22T00:00:00.000
Budget Forecast
393773004.14
Latest Budget Changes
-64880897.86
Total Budget Changes
72852004.14
Forecast Completion
2026-04-04T00:00:00.000
Latest Schedule Changes
87
Total Schedule Changes
1355
Red Hook Recreation Area Track 1, Soccer Fields 3-5, and Ballfields 1-4 Reconstruction
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 974 • Category: Parks
Date Reported As Of
2022-04-01T00:00:00.000
Pid
974
Project Name
Red Hook Recreation Area Track 1, Soccer Fields 3-5, and Ballfields 1-4 Reconstruction
Description
This project will reconstruct the track & field and convert three soccer fields and four ballfields from natural turf to synthetic turf at Red Hook Recreation Area.
Category
Parks
Managing Agency
DPR
Client Agency
DPR
Current Phase
Construction
Design Start
2017-11-01T00:00:00.000
Budget Forecast
68712000.00
Latest Budget Changes
0.00
Total Budget Changes
-10555000.00
Forecast Completion
2023-01-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1082
Queens Public School 489 Annex
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1107 • Project Name: Queens Public School 489 Annex
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1107
Project Name
Queens Public School 489 Annex
Description
NEW SCHOOL
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2019-12-16T00:00:00.000
Budget Forecast
79171750.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2024-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
0
Bainbridge Avenue Trunk Water Main
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 454 • Project Name: Bainbridge Avenue Trunk Water Main
Date Reported As Of
2022-04-01T00:00:00.000
Pid
454
Project Name
Bainbridge Avenue Trunk Water Main
Description
Replacement of Trunk Water Main in Bainbridge Avenue Between Gunhill Road and Holly Lane and in Jerome Avenue Between Holly Lane and E233th Street, etc. Also, New 36" WM in West Burnside Avenue & Phelan Place
Category
Water Supply
Borough
Bronx
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2014-03-17T00:00:00.000
Budget Forecast
69710000.00
Latest Budget Changes
625000.00
Total Budget Changes
25547000.00
Forecast Completion
2023-06-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1687
West 35th Street over Amtrak
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 696 • Project Name: West 35th Street over Amtrak
Date Reported As Of
2022-04-01T00:00:00.000
Pid
696
Project Name
West 35th Street over Amtrak
Description
Repair the West 35th Street bridge over Amtrak, Manhattan
Category
Bridges
Borough
Manhattan
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2018-11-21T00:00:00.000
Budget Forecast
32671034.00
Latest Budget Changes
-500000.00
Total Budget Changes
-621966.00
Forecast Completion
2030-12-10T00:00:00.000
Latest Schedule Changes
988
Total Schedule Changes
2846
Studio Museum in Harlem New Building
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 896 • Project Name: Studio Museum in Harlem New Building
Date Reported As Of
2022-04-01T00:00:00.000
Pid
896
Project Name
Studio Museum in Harlem New Building
Description
The Project will combine two adjacent lots on 125th Street: the sculpture court, City-owned lot 11, and the Museum building on lot 9, owned by the Museum. Existing structures on both lots will be demolished for the new, six story 82,000sf City owned building.
Category
Arts and Culture
Managing Agency
DDC
Client Agency
Cultural Affairs
Current Phase
Construction
Design Start
2018-09-25T00:00:00.000
Budget Forecast
59001000.00
Latest Budget Changes
70000.00
Total Budget Changes
-190000.00
Forecast Completion
2024-06-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
856
2nd Avenue Watermain Trunk Construction
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 388 • Project Name: 2nd Avenue Watermain Trunk Construction
Date Reported As Of
2022-04-01T00:00:00.000
Pid
388
Project Name
2nd Avenue Watermain Trunk Construction
Description
Trunk and Distribution Main Connection to shaft 32B in 2nd Ave., etc., together with all work incidental thereto, Borough of Manhattan. 2nd Avenue from East 33rd Street to East 37th Street
Category
Water Supply
Borough
Manhattan
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2013-09-30T00:00:00.000
Budget Forecast
52913000.00
Latest Budget Changes
147000.00
Total Budget Changes
-7266000.00
Forecast Completion
2023-07-27T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2113
Sewer When & Where Contract In S.E. Queens
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 793 • Project Name: Sewer When & Where Contract In S.E. Queens
Date Reported As Of
2022-04-01T00:00:00.000
Pid
793
Project Name
Sewer When & Where Contract In S.E. Queens
Description
SEWER WHEN & WHERE CONTRACT IN South East Queens. NEW STORM SEWER CONSTRUCTION, REPLACEMENT OR UPGRADES TO SANITARY SEWERS AND WATER MAIN IN PROJECT AREAS. GREEN INFRASTRUCTURE PROJECTS IN CONJUNCTION WITH WHEN & WHERE PROJECTS.
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2018-05-14T00:00:00.000
Budget Forecast
36274000.00
Latest Budget Changes
-176000.00
Total Budget Changes
7404000.00
Forecast Completion
2025-08-22T00:00:00.000
Latest Schedule Changes
122
Total Schedule Changes
1834
Coney Island Hospital CSS Building and Perimeter Flood Protection
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 561 • Project Name: Coney Island Hospital CSS Building and Perimeter Flood Protection
Date Reported As Of
2022-04-01T00:00:00.000
Pid
561
Project Name
Coney Island Hospital CSS Building and Perimeter Flood Protection
Description
Renovation of CIH to advance the City’s resiliency plan, repair damages, and protect the hospital from future disasters.
Category
Health and Hospitals
Borough
Brooklyn
Managing Agency
EDC
Client Agency
H+H
Current Phase
Construction
Design Start
2016-02-01T00:00:00.000
Budget Forecast
695449514.00
Latest Budget Changes
9597645.00
Total Budget Changes
30635879.93
Forecast Completion
2023-12-31T00:00:00.000
Latest Schedule Changes
139
Total Schedule Changes
1243
Pelham Parkway Roadway Reconstruction, Phase 2
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 180 • Project Name: Pelham Parkway Roadway Reconstruction, Phase 2
Date Reported As Of
2022-04-01T00:00:00.000
Pid
180
Project Name
Pelham Parkway Roadway Reconstruction, Phase 2
Description
Pelham Pkwy main road W/B from Bronx River Pkwy to Hutchinson River Pkwy Pelham Pkwy North Service Rd. (S/R) from Bronx Park East to Eastchester Rd. Stillwell Ave from westbound mainline to north service road
Category
Streets and Roadways
Borough
Bronx
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction
Design Start
2002-02-15T00:00:00.000
Budget Forecast
158429000.00
Latest Budget Changes
2617000.00
Total Budget Changes
125164000.00
Forecast Completion
2023-12-22T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2869
Queens Public School 343 New Construction
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1111 • Project Name: Queens Public School 343 New Construction
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1111
Project Name
Queens Public School 343 New Construction
Description
NEW SCHOOL
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2020-03-03T00:00:00.000
Budget Forecast
70167105.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2023-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
0
Construction of Gowanus CSO retention FAC Superfund Site
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 550 • Project Name: Construction of Gowanus CSO retention FAC Superfund Site
Date Reported As Of
2022-04-01T00:00:00.000
Pid
550
Project Name
Construction of Gowanus CSO retention FAC Superfund Site
Description
CSO Facilities, bulkheads, pilots and other requirements to comply with Gowanus Canal Superfund Adminstrative Orders
Category
Industrial Development
Borough
Brooklyn
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction Procurement
Design Start
2017-11-22T00:00:00.000
Budget Forecast
1547300000.00
Latest Budget Changes
0.00
Total Budget Changes
432995114.00
Forecast Completion
2031-11-25T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1086
TRAVIS AVENUE WIDENING
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1240 • Project Name: TRAVIS AVENUE WIDENING
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1240
Project Name
TRAVIS AVENUE WIDENING
Description
TRAVIS AVENUE WIDENING
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2015-01-15T00:00:00.000
Budget Forecast
85607000.00
Latest Budget Changes
20000.00
Total Budget Changes
50000.00
Forecast Completion
2027-10-22T00:00:00.000
Latest Schedule Changes
1029
Total Schedule Changes
1029
Ped Safety Upgrades on Atlantic Avenue, Phase 2
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 519 • Project Name: Ped Safety Upgrades on Atlantic Avenue, Phase 2
Date Reported As Of
2022-04-01T00:00:00.000
Pid
519
Project Name
Ped Safety Upgrades on Atlantic Avenue, Phase 2
Description
PED. SAFETY UPGRADES ON ATLANTIC AVE - PH 2, BROOKLYN
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction
Design Start
2016-08-04T00:00:00.000
Budget Forecast
40013000.00
Latest Budget Changes
469000.00
Total Budget Changes
10136496.00
Forecast Completion
2024-05-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1400
P.S. 163 - BRONX New Construction
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1219 • Project Name: P.S. 163 - BRONX New Construction
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1219
Project Name
P.S. 163 - BRONX New Construction
Description
NEW SCHOOL / DEMOLITION OF EXISTING X163 BUILDING
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction Procurement
Design Start
2019-12-06T00:00:00.000
Budget Forecast
105558715.00
Latest Budget Changes
-7624613.00
Total Budget Changes
-6925988.00
Forecast Completion
2024-12-13T00:00:00.000
Latest Schedule Changes
101
Total Schedule Changes
0
Queens Public School 41 SSBA Addition
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1105 • Project Name: Queens Public School 41 SSBA Addition
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1105
Project Name
Queens Public School 41 SSBA Addition
Description
ADDITION / DEMOLITION
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2019-08-05T00:00:00.000
Budget Forecast
70755417.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2024-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
0
Brooklyn Public School 322 New Construction
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1104 • Project Name: Brooklyn Public School 322 New Construction
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1104
Project Name
Brooklyn Public School 322 New Construction
Description
NEW SCHOOL
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2020-06-04T00:00:00.000
Budget Forecast
85395900.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2024-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
0
West Tremont Avenue over Metro North Railroad
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 503 • Project Name: West Tremont Avenue over Metro North Railroad
Date Reported As Of
2022-04-01T00:00:00.000
Pid
503
Project Name
West Tremont Avenue over Metro North Railroad
Description
Replace/Rehab the West Tremont Avenue bridge over the Metro North line, located in the Bronx.
Category
Bridges
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2018-01-16T00:00:00.000
Budget Forecast
91424088.00
Latest Budget Changes
6368000.00
Total Budget Changes
37794543.00
Forecast Completion
2027-01-06T00:00:00.000
Latest Schedule Changes
56
Total Schedule Changes
1253
Brooklyn Public School 730 New Construction
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 876 • Project Name: Brooklyn Public School 730 New Construction
Date Reported As Of
2022-04-01T00:00:00.000
Pid
876
Project Name
Brooklyn Public School 730 New Construction
Description
NEW SCHOOL
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2018-01-26T00:00:00.000
Budget Forecast
66249461.00
Latest Budget Changes
0.00
Total Budget Changes
6379885.00
Forecast Completion
2023-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
730
Raise Shorelines Citywide
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 689 • Project Name: Raise Shorelines Citywide
Date Reported As Of
2022-04-01T00:00:00.000
Pid
689
Project Name
Raise Shorelines Citywide
Description
The design and construction of shoreline reconstruction projects necessary to provide Citywide protection from future flooding caused by elevated seal elvels.
Category
Industrial Development
Borough
Citywide
Managing Agency
EDC
Client Agency
ORR
Current Phase
Design
Design Start
2017-08-01T00:00:00.000
Budget Forecast
60422401.00
Latest Budget Changes
-9.00
Total Budget Changes
0.00
Forecast Completion
2023-12-31T00:00:00.000
Latest Schedule Changes
184
Total Schedule Changes
639
Bronx Public School 468 New Construction
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1106 • Project Name: Bronx Public School 468 New Construction
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1106
Project Name
Bronx Public School 468 New Construction
Description
NEW SCHOOL
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2020-01-16T00:00:00.000
Budget Forecast
80833865.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2024-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
0
Flatbush Avenue Trunk Watermain Replacement
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 370 • Project Name: Flatbush Avenue Trunk Watermain Replacement
Date Reported As Of
2022-04-01T00:00:00.000
Pid
370
Project Name
Flatbush Avenue Trunk Watermain Replacement
Description
72" Trunk Water Main and Combined Sewer Replacement in Flatbush Ave. between Sterling Pl. and 8th Ave., etc., Borough of Brooklyn.
Category
Wastewater Treatment
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2014-11-24T00:00:00.000
Budget Forecast
57915000.00
Latest Budget Changes
1555000.00
Total Budget Changes
39272000.00
Forecast Completion
2023-09-29T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2266
Bronx Public School 87 Addition
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1103 • Project Name: Bronx Public School 87 Addition
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1103
Project Name
Bronx Public School 87 Addition
Description
ADDITION / EXISTING SCHOOL RENOVATION WORK
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2019-09-23T00:00:00.000
Budget Forecast
70834393.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2024-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
0
Park Avenue Tunnel (Murray Hill)
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 536 • Project Name: Park Avenue Tunnel (Murray Hill)
Date Reported As Of
2022-04-01T00:00:00.000
Pid
536
Project Name
Park Avenue Tunnel (Murray Hill)
Description
Repair Park Avenue tunnel, located in Midtown, Manhattan.
Category
Bridges
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2006-08-01T00:00:00.000
Budget Forecast
46396271.00
Latest Budget Changes
-6440696.00
Total Budget Changes
-17773389.61
Forecast Completion
2022-08-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1568
New Storm Sewer N Conduit Av-Baisley Blvd
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 792 • Project Name: New Storm Sewer N Conduit Av-Baisley Blvd
Date Reported As Of
2022-04-01T00:00:00.000
Pid
792
Project Name
New Storm Sewer N Conduit Av-Baisley Blvd
Description
Storm, Sanitary and Water Mains work in North Conduit between Baisley Blvd and Guy Brewer Blvd, South Queens
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2018-07-30T00:00:00.000
Budget Forecast
113711000.00
Latest Budget Changes
0.00
Total Budget Changes
31711000.00
Forecast Completion
2028-04-22T00:00:00.000
Latest Schedule Changes
575
Total Schedule Changes
1619
Croton Above Ground Structure And Landscaping
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 747 • Project Name: Croton Above Ground Structure And Landscaping
Date Reported As Of
2022-04-01T00:00:00.000
Pid
747
Project Name
Croton Above Ground Structure And Landscaping
Description
The new Mosholu Golf Course Club House, together with fifty-five Driving Range Tee Boxes and ten-acres of re-landscaping comprise the phase IV and final of the vast DEP Croton Water Treatment Plant project, currently under construction in Van Cortlandt Park in the Bronx. Through a multifunctional design strategy the project reinstates the pre-existing golf program and facility, creates civic space for community use and ensures security for a multi-billion dollar public works facility.
Category
Industrial Development
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2012-05-23T00:00:00.000
Budget Forecast
132780000.00
Latest Budget Changes
25336000.00
Total Budget Changes
75117000.00
Forecast Completion
2023-02-23T00:00:00.000
Latest Schedule Changes
22
Total Schedule Changes
897
Bronx Animal Care Center
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 893 • Project Name: Bronx Animal Care Center
Date Reported As Of
2022-04-01T00:00:00.000
Pid
893
Project Name
Bronx Animal Care Center
Description
Bronx Animal Care Center & Veterinary Clinic is a new 50,000 SF facility that will be housing admissions, adoptions, medical services, and boarding for approximately 70 dogs, 140 cats, 30 rabbits and 20 animals or other species. In addition to the animal housing, the Bronx Animal Care Center will include a wildlife area to rehabilitate wild birds, academic partnership for youth, and enhanced senior services. Site work will include yards to facilitate dog adoptions, covered exercise runs, courtyards, and parking for staff, visitors, and center vehicles, as well as site lighting and low maintenance planting throughout. The building and associated landscape are to achieve LEED Silver standards or higher.
Category
Health and Hospitals
Managing Agency
DDC
Client Agency
Health
Current Phase
Construction Procurement
Design Start
2019-06-20T00:00:00.000
Budget Forecast
92103000.00
Latest Budget Changes
250000.00
Total Budget Changes
24815617.00
Forecast Completion
2025-02-15T00:00:00.000
Latest Schedule Changes
32
Total Schedule Changes
110
Queensboro Bridge Roadway Replacement over East River
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 594 • Project Name: Queensboro Bridge Roadway Replacement over East River
Date Reported As Of
2022-04-01T00:00:00.000
Pid
594
Project Name
Queensboro Bridge Roadway Replacement over East River
Description
This project includes the replacement of the upper roadway's deck on the main bridge along with steel repairs, fire standpipes, and lighting upgrades.
Category
Bridges, Streets and Roadways
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2015-04-09T00:00:00.000
Budget Forecast
364535769.00
Latest Budget Changes
-18497245.00
Total Budget Changes
8567339.67
Forecast Completion
2024-03-13T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1970
FUEL TANK & SUMP REPLACEMENTS - QUEENS
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 898 • Project Name: FUEL TANK & SUMP REPLACEMENTS - QUEENS
Date Reported As Of
2022-04-01T00:00:00.000
Pid
898
Project Name
FUEL TANK & SUMP REPLACEMENTS - QUEENS
Description
CITYWIDE FUEL TANK REPLACEMENT PROGRAM FOR NEW 2015 EPA PETROLEUM BULK STORAGE REGULATIONS
Category
Industrial Development
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Design
Design Start
2019-07-16T00:00:00.000
Budget Forecast
25350000.00
Latest Budget Changes
0.00
Total Budget Changes
-1850000.00
Forecast Completion
2025-06-29T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
663
Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 112 • Project Name: Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Date Reported As Of
2022-04-01T00:00:00.000
Pid
112
Project Name
Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Description
Repair abutments, piers, approaches, and steel superstructure located in Pelham Bay, Bronx; replace reinforced concrete deck.
Category
Bridges, Streets and Roadways
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
1995-01-17T00:00:00.000
Budget Forecast
82262363.00
Latest Budget Changes
-6413908.00
Total Budget Changes
20945057.00
Forecast Completion
2022-07-23T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1592
Hannah Street Pumping Station Construction
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 364 • Project Name: Hannah Street Pumping Station Construction
Date Reported As Of
2022-04-01T00:00:00.000
Pid
364
Project Name
Hannah Street Pumping Station Construction
Description
This project will reconstruct the Hannah St. Pumping Station, the largest City-owned wastewater collection and pumping station on Staten Island. Built in 1977, the facility has numerous deficiencies, needing a comprehensive upgrade.
Category
Wastewater Treatment
Borough
Staten Island
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2012-08-03T00:00:00.000
Budget Forecast
102992162.23
Latest Budget Changes
0.00
Total Budget Changes
67909196.80
Forecast Completion
2025-08-22T00:00:00.000
Latest Schedule Changes
443
Total Schedule Changes
3238
Brooklyn Public School 676 New Construction
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1100 • Project Name: Brooklyn Public School 676 New Construction
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1100
Project Name
Brooklyn Public School 676 New Construction
Description
NEW SCHOOL
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2020-08-12T00:00:00.000
Budget Forecast
92786690.00
Latest Budget Changes
0.00
Total Budget Changes
1339880.00
Forecast Completion
2024-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
0
Bronx Public School 077 Addition
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1101 • Project Name: Bronx Public School 077 Addition
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1101
Project Name
Bronx Public School 077 Addition
Description
ADDITION / EXISTING SCHOOL RENOVATION WORK (PHASE I) / DEMOLITION (PHASE II)
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2019-09-25T00:00:00.000
Budget Forecast
86862349.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2024-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
0
Reconstruction Of Arthur Kill Road, Phase I
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 741 • Project Name: Reconstruction Of Arthur Kill Road, Phase I
Date Reported As Of
2022-04-01T00:00:00.000
Pid
741
Project Name
Reconstruction Of Arthur Kill Road, Phase I
Description
Reconstruction of Arthur Kill Rd from Clark Avenue to Richmond Avenue including widening of roadway
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2016-12-16T00:00:00.000
Budget Forecast
50406000.00
Latest Budget Changes
2163000.00
Total Budget Changes
22503000.00
Forecast Completion
2025-10-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1415
Queens Public School 472 New Construction
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1099 • Project Name: Queens Public School 472 New Construction
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1099
Project Name
Queens Public School 472 New Construction
Description
NEW SCHOOL
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2019-01-07T00:00:00.000
Budget Forecast
251284250.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2025-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
0
Network Infrastructure Refresh Program
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 863 • Project Name: Network Infrastructure Refresh Program
Date Reported As Of
2022-04-01T00:00:00.000
Pid
863
Project Name
Network Infrastructure Refresh Program
Description
This project has a two-fold basis: 1) The ongoing Network Refresh which is needed to replace aging, end-of-life, end-of-support equipment across the NYC H+H. 2) Networking capacity needed to support the Electronic Medical Records system.
Category
Health and Hospitals, IT
Managing Agency
HHC
Client Agency
H+H
Current Phase
IT
Budget Forecast
0.00
Latest Budget Changes
0.00
Total Budget Changes
180514000.00
Storm Mitigation Loan Program at Hunts Point
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 672 • Project Name: Storm Mitigation Loan Program at Hunts Point
Date Reported As Of
2022-04-01T00:00:00.000
Pid
672
Project Name
Storm Mitigation Loan Program at Hunts Point
Description
SMLP portion for Hunts Point WWTP as part of the New York City Wastewater Resiliency Program.
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2018-04-16T00:00:00.000
Budget Forecast
70261761.84
Latest Budget Changes
9379600.47
Total Budget Changes
20080597.79
Forecast Completion
2023-02-17T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1091
New 40th Precinct
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 634 • Project Name: New 40th Precinct
Date Reported As Of
2022-04-01T00:00:00.000
Pid
634
Project Name
New 40th Precinct
Description
Design and build a new Police Precinct with full basement totaling 43,000 sq. ft. on an existing City owned property in the Bronx.
Category
Public Safety and Criminal Justice
Borough
Bronx
Managing Agency
DDC
Client Agency
Police
Current Phase
Construction
Design Start
2014-09-30T00:00:00.000
Budget Forecast
91274000.00
Latest Budget Changes
10321000.00
Total Budget Changes
26020000.00
Forecast Completion
2022-11-09T00:00:00.000
Latest Schedule Changes
14
Total Schedule Changes
711
East River Esplanade Stabilization and Reconstruction Phase 3
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 973 • Project Name: East River Esplanade Stabilization and Reconstruction Phase 3
Date Reported As Of
2022-04-01T00:00:00.000
Pid
973
Project Name
East River Esplanade Stabilization and Reconstruction Phase 3
Description
This project will stabilize and reconstruct portions of the East River Esplanade from East 62nd Street to East 63rd Street, at East 76th Street, and from East 90th Street to East 94th Street.
Category
Parks
Managing Agency
DPR
Client Agency
DPR
Current Phase
Design
Design Start
2019-02-01T00:00:00.000
Budget Forecast
65038645.26
Latest Budget Changes
0.00
Total Budget Changes
3616645.26
Forecast Completion
2024-11-23T00:00:00.000
Latest Schedule Changes
61
Total Schedule Changes
612
Bergen Avenue Street Reconstruction
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 170 • Project Name: Bergen Avenue Street Reconstruction
Date Reported As Of
2022-04-01T00:00:00.000
Pid
170
Project Name
Bergen Avenue Street Reconstruction
Description
Reconstruction of Bergen Avenue Area, including Storm Sewers, Water Mains, Street Lighting, Traffic Signal Work, and reconstruction of new outfall at East Mill Basin.
Category
Streets and Roadways
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction
Design Start
2012-12-03T00:00:00.000
Budget Forecast
79864000.00
Latest Budget Changes
-1638000.00
Total Budget Changes
45837000.00
Forecast Completion
2023-06-24T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
-388
79th St Boat Basin
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 862 • Project Name: 79th St Boat Basin
Date Reported As Of
2022-04-01T00:00:00.000
Pid
862
Project Name
79th St Boat Basin
Description
Reconstruction of bulkhead and piers at 79th St Boat Basin on behalf of NYCDPR .
Category
Parks
Managing Agency
EDC
Client Agency
DPR
Current Phase
Design
Design Start
2019-06-13T00:00:00.000
Budget Forecast
89219175.00
Latest Budget Changes
0.00
Total Budget Changes
-1131246.67
Forecast Completion
2025-09-08T00:00:00.000
Latest Schedule Changes
181
Total Schedule Changes
1036