Capital Projects

All major infrastructure and information technology projects with a budget of $25 million or more that are currently active (in the design, procurement, or construction phase).

City Government Mayor's Office of Operations (OPS) Dataset n7gv-k5yt 16 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
Storm Sewer Outlet In 224Th St
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 784 • Project Name: Storm Sewer Outlet In 224Th St
Date Reported As Of
2022-04-01T00:00:00.000
Pid
784
Project Name
Storm Sewer Outlet In 224Th St
Description
Installation of storm sewers at 224th St and 149th Ave and along the access road through Idlewild Parks known as Springfield Lane (Spine Farmers Blvd)
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2016-01-04T00:00:00.000
Budget Forecast
157088000.00
Latest Budget Changes
48534000.00
Total Budget Changes
155854000.00
Forecast Completion
2026-05-17T00:00:00.000
Latest Schedule Changes
92
Total Schedule Changes
1238
Combined Sewer In 70Th Street, Queens
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 788 • Project Name: Combined Sewer In 70Th Street, Queens
Date Reported As Of
2022-04-01T00:00:00.000
Pid
788
Project Name
Combined Sewer In 70Th Street, Queens
Description
COMBINED SEWER IN 70TH STREET, QUEENS
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2016-08-31T00:00:00.000
Budget Forecast
124773000.00
Latest Budget Changes
1339000.00
Total Budget Changes
94201000.00
Forecast Completion
2023-08-10T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1155
Fort Totten Infrastructure Upgrade
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1154 • Project Name: Fort Totten Infrastructure Upgrade
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1154
Project Name
Fort Totten Infrastructure Upgrade
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
FDNY
Current Phase
Design
Design Start
2021-05-06T00:00:00.000
Budget Forecast
57786000.00
Latest Budget Changes
0.00
Total Budget Changes
100000.00
Forecast Completion
2025-10-13T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
318
RECONSTRUCTION OF FRONT STREET, MANHATTAN
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1012 • Project Name: RECONSTRUCTION OF FRONT STREET, MANHATTAN
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1012
Project Name
RECONSTRUCTION OF FRONT STREET, MANHATTAN
Description
Reconstruction of Front Street, Manhattan
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction
Design Start
2015-07-31T00:00:00.000
Budget Forecast
31066000.00
Latest Budget Changes
-13000.00
Total Budget Changes
6153000.00
Forecast Completion
2023-10-13T00:00:00.000
Latest Schedule Changes
484
Total Schedule Changes
484
Gilboa Dam Reconstruction, Phase V
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 456 • Project Name: Gilboa Dam Reconstruction, Phase V
Date Reported As Of
2022-04-01T00:00:00.000
Pid
456
Project Name
Gilboa Dam Reconstruction, Phase V
Description
This is the final phase of the Gilboa Dam reconstruction project and includes reforestation, final site stabilization and wetlands mitigation measures.
Category
Water Supply
Borough
Upstate
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2020-12-30T00:00:00.000
Budget Forecast
31929026.00
Latest Budget Changes
-6400000.00
Total Budget Changes
-3079490.00
Forecast Completion
2025-07-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
503
253 Broadway NYC. Fire Alarm Raplacement
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 850 • Project Name: 253 Broadway NYC. Fire Alarm Raplacement
Date Reported As Of
2022-04-01T00:00:00.000
Pid
850
Project Name
253 Broadway NYC. Fire Alarm Raplacement
Description
Installation of new building wide fire alarm and sprinkler distribution for 253 Broadway The PW357FIRE project has been divided into two phases. • Phase 1 - Fire alarm core to meet the PW77LYA project LPC office renovation - currently under construction • Phase 2 – Fire alarm branches, sprinkler system branches, and BMS – currently under bid package review phase
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Construction
Design Start
2018-01-22T00:00:00.000
Budget Forecast
49531000.00
Latest Budget Changes
5264000.00
Total Budget Changes
17827000.00
Forecast Completion
2026-12-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1553
Tompkinsville Esplanade
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 963 • Project Name: Tompkinsville Esplanade
Date Reported As Of
2022-04-01T00:00:00.000
Pid
963
Project Name
Tompkinsville Esplanade
Description
Esplanade from Stapleton to the Lighthouse Museum and Pier for DOT Dockbuilders.
Category
Parks
Managing Agency
EDC
Client Agency
EDC
Current Phase
Design
Design Start
2019-07-01T00:00:00.000
Budget Forecast
161572069.00
Latest Budget Changes
10000000.00
Total Budget Changes
10582596.00
Forecast Completion
2025-10-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
944
RECONSTRUCTION OF QUEENS BLVD - PHASE 3
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1152 • Project Name: RECONSTRUCTION OF QUEENS BLVD - PHASE 3
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1152
Project Name
RECONSTRUCTION OF QUEENS BLVD - PHASE 3
Description
Vision Zero - Queens Boulevard - Segment 3: Eliot Avenue to Yellowstone Boulevard. Variety of safety and streetscape improvements including partial street reconstruction and resurfacing to address roadway conditions.
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2018-04-26T00:00:00.000
Budget Forecast
99344000.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Total Schedule Changes
0
80 CENTRE ST.- FIRE ALARMS/SPRINKLERS
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1174 • Project Name: 80 CENTRE ST.- FIRE ALARMS/SPRINKLERS
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1174
Project Name
80 CENTRE ST.- FIRE ALARMS/SPRINKLERS
Description
Fire Alarm and Sprinklers Upgrade
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Design
Design Start
2021-07-26T00:00:00.000
Budget Forecast
44469000.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2026-09-11T00:00:00.000
Latest Schedule Changes
172
Total Schedule Changes
340
Bainbridge Avenue Trunk Water Main
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 454 • Project Name: Bainbridge Avenue Trunk Water Main
Date Reported As Of
2022-04-01T00:00:00.000
Pid
454
Project Name
Bainbridge Avenue Trunk Water Main
Description
Replacement of Trunk Water Main in Bainbridge Avenue Between Gunhill Road and Holly Lane and in Jerome Avenue Between Holly Lane and E233th Street, etc. Also, New 36" WM in West Burnside Avenue & Phelan Place
Category
Water Supply
Borough
Bronx
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2014-03-17T00:00:00.000
Budget Forecast
69710000.00
Latest Budget Changes
625000.00
Total Budget Changes
25547000.00
Forecast Completion
2023-06-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1687
Coastal Resiliency Area 1 - East 23Rd St. To Montg
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 773 • Project Name: Coastal Resiliency Area 1 - East 23Rd St. To Montg
Date Reported As Of
2022-04-01T00:00:00.000
Pid
773
Project Name
Coastal Resiliency Area 1 - East 23Rd St. To Montg
Description
East Side Coastal Resiliency - Montgomery Street to East 15th Street, Manhattan
Category
Industrial Development, Parks
Managing Agency
DDC
Client Agency
Parks & Recreation
Current Phase
Construction
Design Start
2016-04-27T00:00:00.000
Budget Forecast
92660363.63
Latest Budget Changes
0.00
Total Budget Changes
-418193636.37
Forecast Completion
2026-08-15T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
836
49th Avenue Bridge Replacement
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 131 • Project Name: 49th Avenue Bridge Replacement
Date Reported As Of
2022-04-01T00:00:00.000
Pid
131
Project Name
49th Avenue Bridge Replacement
Description
Replace the 49th Avenue bridge over Long Island Railroad and Amtrak in Hunters Point, Queens.
Category
Bridges, Streets and Roadways
Borough
Queens
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-08-15T00:00:00.000
Budget Forecast
113934419.00
Latest Budget Changes
-104713600.00
Total Budget Changes
32902419.00
Forecast Completion
2027-04-05T00:00:00.000
Latest Schedule Changes
21
Total Schedule Changes
1449
FUEL TANK REPLACEMENT - 71
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 935 • Project Name: FUEL TANK REPLACEMENT - 71
Date Reported As Of
2022-04-01T00:00:00.000
Pid
935
Project Name
FUEL TANK REPLACEMENT - 71
Description
By Notice To Proceed letter dated September 21, 2018, the New York City Department of Design and Construction (“DDC”) directed PMS Construction Management Corp. (“PMS”) to commence work on Capis ID PW348-71, Contract No. 20191404531 CM/Design/Build for the Replacement and Upgrade of Petroleum Storage Tanks for the Borough of Manhattan. The contract was awarded for a maximum fee of $28,026,750.00 and was partially registered by the Comptroller on September 21, 2018 in the amount of $4,885,000.00. The term of the contract is 1,095 consecutive calendar days from September 21, 2018. Contract termination date is September 19, 2021.
Category
Industrial Development
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Construction
Design Start
2018-10-02T00:00:00.000
Budget Forecast
32709000.00
Latest Budget Changes
0.00
Total Budget Changes
3444000.00
Forecast Completion
2024-03-20T00:00:00.000
Latest Schedule Changes
366
Total Schedule Changes
548
Rego Park New Facility
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1145 • Project Name: Rego Park New Facility
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1145
Project Name
Rego Park New Facility
Description
New Library for Rego Park
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
Libraries-QBPL
Current Phase
Design
Design Start
2019-04-11T00:00:00.000
Budget Forecast
41511000.00
Latest Budget Changes
200000.00
Total Budget Changes
535000.00
Forecast Completion
2026-03-07T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
474
Brooklyn Bridge - Approach Arches Rehabilitation
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 584 • Project Name: Brooklyn Bridge - Approach Arches Rehabilitation
Date Reported As Of
2022-04-01T00:00:00.000
Pid
584
Project Name
Brooklyn Bridge - Approach Arches Rehabilitation
Description
Rehabilitate approach arches and towers of Brooklyn Bridge. Including masonry cleaning, masonry repairs, repointing, rehabilition of transverse walls, new infill walls of the approach arch blocks. Clean and repoint the tower masonry, reinforce the gothic arches of the towers, and rehabilitate the tower tops.
Category
Bridges
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2016-04-13T00:00:00.000
Budget Forecast
347633300.00
Latest Budget Changes
127724000.00
Total Budget Changes
33135732.10
Forecast Completion
2024-02-20T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1908
Battery Park Underpass Emergency Relief Betterments
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 540 • Project Name: Battery Park Underpass Emergency Relief Betterments
Date Reported As Of
2022-04-01T00:00:00.000
Pid
540
Project Name
Battery Park Underpass Emergency Relief Betterments
Description
Resiliency betterments for Battery Park and West Street underpasses.
Category
Bridges
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2018-04-01T00:00:00.000
Budget Forecast
56984167.00
Latest Budget Changes
1940638.00
Total Budget Changes
47923308.00
Forecast Completion
2024-11-27T00:00:00.000
Latest Schedule Changes
30
Total Schedule Changes
1197
SOUTH BROOKLYN CROSSTOWN SBS
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 843 • Project Name: SOUTH BROOKLYN CROSSTOWN SBS
Date Reported As Of
2022-04-01T00:00:00.000
Pid
843
Project Name
SOUTH BROOKLYN CROSSTOWN SBS
Description
The construction of Southern Brooklyn Crosstown Select Bus Service (SBS)
Category
Industrial Development
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2018-07-17T00:00:00.000
Budget Forecast
86214000.00
Latest Budget Changes
150000.00
Total Budget Changes
29789000.00
Forecast Completion
2026-08-18T00:00:00.000
Latest Schedule Changes
153
Total Schedule Changes
819
NEW 48" TRUNK WATER MAIN IN E 233 STREET
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 998 • Project Name: NEW 48" TRUNK WATER MAIN IN E 233 STREET
Date Reported As Of
2022-04-01T00:00:00.000
Pid
998
Project Name
NEW 48" TRUNK WATER MAIN IN E 233 STREET
Description
New 48" Trunk Water Main in E 233rd Street between Bronxwood Avenue & Baychester Avenue, etc.
Category
Water Supply
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2015-10-01T00:00:00.000
Budget Forecast
33905000.00
Latest Budget Changes
74000.00
Total Budget Changes
1077000.00
Forecast Completion
2025-02-24T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1796
New Westchester Square
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1147 • Project Name: New Westchester Square
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1147
Project Name
New Westchester Square
Description
DDC Constructability comments anticipated by 5/31/17. Anticipated Construction Budget shortfall of $600k. Funding required to submit initial Construction CP.
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
Libraries-NYPL
Current Phase
Construction Procurement
Design Start
2013-05-13T00:00:00.000
Budget Forecast
36429630.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2026-02-28T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
471
SEELY STREET OVER PROSPECT AVENUE BIN: 2244470
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1119 • Project Name: SEELY STREET OVER PROSPECT AVENUE BIN: 2244470
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1119
Project Name
SEELY STREET OVER PROSPECT AVENUE BIN: 2244470
Description
Rehabilitation of Seeley Street bridge over Prospect Avenue
Category
Bridges
Managing Agency
DOT
Client Agency
n/a
Current Phase
Design
Design Start
2019-11-12T00:00:00.000
Budget Forecast
30709037.00
Latest Budget Changes
-512230.00
Total Budget Changes
0.00
Forecast Completion
2027-10-03T00:00:00.000
Latest Schedule Changes
27
Total Schedule Changes
253
Reconstruction of Power Distribution at Wards Island WWTP
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 453 • Project Name: Reconstruction of Power Distribution at Wards Island WWTP
Date Reported As Of
2022-04-01T00:00:00.000
Pid
453
Project Name
Reconstruction of Power Distribution at Wards Island WWTP
Description
Upgrades significant portions of the electrical distribution infrastructure including 3 power center installations, 15 motor control centers, 6 automatic transfer switches and 20 transformers throughout the plant
Category
Wastewater Treatment
Borough
Manhattan
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2019-06-04T00:00:00.000
Budget Forecast
130373506.22
Latest Budget Changes
3787765.00
Total Budget Changes
33489860.26
Forecast Completion
2027-09-04T00:00:00.000
Latest Schedule Changes
305
Total Schedule Changes
1147
WM REPLMT EAST NEW YORK AVE
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 991 • Project Name: WM REPLMT EAST NEW YORK AVE
Date Reported As Of
2022-04-01T00:00:00.000
Pid
991
Project Name
WM REPLMT EAST NEW YORK AVE
Description
Trunk Water Main replacement in East New York Avenue between Howard Avenue and Pacific Street; Jamaica Avenue between Herkimer Street and Vermont Street; and Atlantic Avenue between Van Sinderen Avenue and Pennsylvania Avenue.
Category
Water Supply
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2015-02-16T00:00:00.000
Budget Forecast
101963000.00
Latest Budget Changes
12000000.00
Total Budget Changes
29337000.00
Forecast Completion
2024-09-09T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
913
Queens Public School 343 New Construction
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1111 • Project Name: Queens Public School 343 New Construction
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1111
Project Name
Queens Public School 343 New Construction
Description
NEW SCHOOL
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2020-03-03T00:00:00.000
Budget Forecast
70167105.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2023-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
0
Union Turnpike over Cross Island Parkway
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 932 • Project Name: Union Turnpike over Cross Island Parkway
Date Reported As Of
2022-04-01T00:00:00.000
Pid
932
Project Name
Union Turnpike over Cross Island Parkway
Description
Rehabilitation of Union Turnpike Bridge over Cross Island Parkway
Category
Bridges
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2019-09-06T00:00:00.000
Budget Forecast
64425695.00
Latest Budget Changes
-2856083.00
Total Budget Changes
3378281.00
Forecast Completion
2028-12-02T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
834
Primary Treatment Improvement at Wards Island WWTP
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 452 • Project Name: Primary Treatment Improvement at Wards Island WWTP
Date Reported As Of
2022-04-01T00:00:00.000
Pid
452
Project Name
Primary Treatment Improvement at Wards Island WWTP
Description
Replacement of collector drives, scum trough dipping weirs and dump valves for ten primary settling tanks. Also included are Influent channel mixing and seal water system for the primary sludge pumps and concrete repairs.
Category
Wastewater Treatment
Borough
Manhattan
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction Procurement
Design Start
2017-11-06T00:00:00.000
Budget Forecast
106205187.75
Latest Budget Changes
531024.50
Total Budget Changes
99651290.98
Forecast Completion
2026-09-22T00:00:00.000
Latest Schedule Changes
94
Total Schedule Changes
2142
UNION TURNPIKE CENTER MEDIAN REPLACEMENT
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 986 • Project Name: UNION TURNPIKE CENTER MEDIAN REPLACEMENT
Date Reported As Of
2022-04-01T00:00:00.000
Pid
986
Project Name
UNION TURNPIKE CENTER MEDIAN REPLACEMENT
Description
Union Turnpike Center Median Replacement from Hollis Court Blvd to 226th Street, Borough of Queens
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction Procurement
Design Start
2019-05-23T00:00:00.000
Budget Forecast
50000000.00
Latest Budget Changes
20231000.00
Total Budget Changes
23766000.00
Forecast Completion
2024-09-10T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
341
WOODHAVEN BLVD QUEENS BLVD BIN# 2248159
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1128 • Project Name: WOODHAVEN BLVD QUEENS BLVD BIN# 2248159
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1128
Project Name
WOODHAVEN BLVD QUEENS BLVD BIN# 2248159
Description
This bridge is a two span concrete encased structure, 153.3 feet wide, 75 feet long and carries a total of 9 lanes of traffic. The bridge itself is an integral part of the Woodhaven Blvd. subway station structure owned and operated by the MTA. The superstructure consists of concrete encased steel stringers framing into concrete encased steel columns which are also used to serve as the retaining wall holding up Queens Blvd. service road.
Category
Bridges
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2018-10-10T00:00:00.000
Budget Forecast
65231241.00
Latest Budget Changes
115000.00
Total Budget Changes
2052000.00
Forecast Completion
2027-05-03T00:00:00.000
Latest Schedule Changes
26
Total Schedule Changes
932
NEW UTRECH LIBRARY MAJOR RENOVATIONS
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 841 • Project Name: NEW UTRECH LIBRARY MAJOR RENOVATIONS
Date Reported As Of
2022-04-01T00:00:00.000
Pid
841
Project Name
NEW UTRECH LIBRARY MAJOR RENOVATIONS
Description
New Utrech branch library is a comprehensive interior and exterior renovation which includes new fire alarm/ BMS, new interior layout, new HVAC, new roof, exterior rehabilitation and landscape.
Category
Libraries
Managing Agency
DDC
Client Agency
Libraries-BPL
Current Phase
Design
Design Start
2018-06-27T00:00:00.000
Budget Forecast
26658000.00
Latest Budget Changes
0.00
Total Budget Changes
290000.00
Forecast Completion
2026-11-27T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1188
Emergency Communications Transformation Program (ECTP) Upgrades and Enhancements
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 267 • Project Name: Emergency Communications Transformation Program (ECTP) Upgrades and Enhancements
Date Reported As Of
2022-04-01T00:00:00.000
Pid
267
Project Name
Emergency Communications Transformation Program (ECTP) Upgrades and Enhancements
Description
Upgrade and enhancement of emergency technology infrastructure to improve interoperability and coordination among public safety agencies and improve call processing time to decrease overall response times.
Category
IT
Borough
Citywide
Managing Agency
DOITT
Client Agency
FDNY, NYPD
Current Phase
IT
Budget Forecast
2312235952.36
Latest Budget Changes
-624063.25
Total Budget Changes
73735148.87
Forecast Completion
2023-03-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2252
DBCD South Site Cultural Fit-Out
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 484 • Project Name: DBCD South Site Cultural Fit-Out
Date Reported As Of
2022-04-01T00:00:00.000
Pid
484
Project Name
DBCD South Site Cultural Fit-Out
Description
Interior fit-out of the south site cultural unit.
Category
Arts and Culture
Borough
Brooklyn
Managing Agency
EDC
Client Agency
DCLA
Current Phase
Construction
Design Start
2014-12-01T00:00:00.000
Budget Forecast
51070000.00
Latest Budget Changes
0.00
Total Budget Changes
36789601.16
Forecast Completion
2022-12-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1706
New 40th Precinct
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 634 • Project Name: New 40th Precinct
Date Reported As Of
2022-04-01T00:00:00.000
Pid
634
Project Name
New 40th Precinct
Description
Design and build a new Police Precinct with full basement totaling 43,000 sq. ft. on an existing City owned property in the Bronx.
Category
Public Safety and Criminal Justice
Borough
Bronx
Managing Agency
DDC
Client Agency
Police
Current Phase
Construction
Design Start
2014-09-30T00:00:00.000
Budget Forecast
91274000.00
Latest Budget Changes
10321000.00
Total Budget Changes
26020000.00
Forecast Completion
2022-11-09T00:00:00.000
Latest Schedule Changes
14
Total Schedule Changes
711
Bronx Public School 108 Addition
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1109 • Project Name: Bronx Public School 108 Addition
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1109
Project Name
Bronx Public School 108 Addition
Description
ADDITION
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2020-01-17T00:00:00.000
Budget Forecast
86927350.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2024-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
0
DELANCEY STREET SAFETY IMPROVEMENTS
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 983 • Project Name: DELANCEY STREET SAFETY IMPROVEMENTS
Date Reported As Of
2022-04-01T00:00:00.000
Pid
983
Project Name
DELANCEY STREET SAFETY IMPROVEMENTS
Description
DELANCEY STREET SAFETY IMPROVEMENTS
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2017-07-19T00:00:00.000
Budget Forecast
56381000.00
Latest Budget Changes
0.00
Total Budget Changes
20937000.00
Forecast Completion
2026-10-23T00:00:00.000
Latest Schedule Changes
123
Total Schedule Changes
1217
Brooklyn Public School 253 Addition
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1110 • Project Name: Brooklyn Public School 253 Addition
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1110
Project Name
Brooklyn Public School 253 Addition
Description
ADDITION
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2020-03-09T00:00:00.000
Budget Forecast
75767435.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2024-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
0
DOH Public Health Lab
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 909 • Project Name: DOH Public Health Lab
Date Reported As Of
2022-04-01T00:00:00.000
Pid
909
Project Name
DOH Public Health Lab
Description
The construction of an approximately 230,000 sq ft municipal Public Health Lab building for DOHMH.
Category
Health and Hospitals
Managing Agency
EDC
Client Agency
DOHMH
Current Phase
Construction Procurement
Design Start
2019-01-01T00:00:00.000
Budget Forecast
633132280.00
Latest Budget Changes
19334959.71
Total Budget Changes
19334959.71
Forecast Completion
2025-01-01T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1
Queens Public School 032 Addition
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1108 • Project Name: Queens Public School 032 Addition
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1108
Project Name
Queens Public School 032 Addition
Description
ADDITION
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2020-02-24T00:00:00.000
Budget Forecast
67965151.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2024-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
0
Queensboro Bridge Roadway Replacement over East River
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 594 • Project Name: Queensboro Bridge Roadway Replacement over East River
Date Reported As Of
2022-04-01T00:00:00.000
Pid
594
Project Name
Queensboro Bridge Roadway Replacement over East River
Description
This project includes the replacement of the upper roadway's deck on the main bridge along with steel repairs, fire standpipes, and lighting upgrades.
Category
Bridges, Streets and Roadways
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2015-04-09T00:00:00.000
Budget Forecast
364535769.00
Latest Budget Changes
-18497245.00
Total Budget Changes
8567339.67
Forecast Completion
2024-03-13T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1970
Oakwood Beach WWTP Headworks Improvements
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 450 • Project Name: Oakwood Beach WWTP Headworks Improvements
Date Reported As Of
2022-04-01T00:00:00.000
Pid
450
Project Name
Oakwood Beach WWTP Headworks Improvements
Description
Replacement of six bar screens, grit bin vibrator, six ring flushing pumps, six main sewage pumps and assoc. piping/valves and motor control center, replacement of four exhaust fans, gas and oxygen detectors and a 15 KVA transformer
Category
Wastewater Treatment
Borough
Staten Island
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2015-12-23T00:00:00.000
Budget Forecast
83229440.00
Latest Budget Changes
0.00
Total Budget Changes
31867440.00
Forecast Completion
2029-08-03T00:00:00.000
Latest Schedule Changes
1021
Total Schedule Changes
2857
150 ST SPINE: PHASE II TRUNK SEWER AT BERGEN BASIN
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 999 • Project Name: 150 ST SPINE: PHASE II TRUNK SEWER AT BERGEN BASIN
Date Reported As Of
2022-04-01T00:00:00.000
Pid
999
Project Name
150 ST SPINE: PHASE II TRUNK SEWER AT BERGEN BASIN
Description
Southeast Queens 150th Street Spine, Phase II - Installation of a new double barrel trunk storm sewer that will run through JFK airport; approximately 1,000 feet east of Bergen Basin, to the north side of the Belt Parkway at Inwood Street and 150th Street
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2020-03-02T00:00:00.000
Budget Forecast
47307000.00
Latest Budget Changes
-283000.00
Total Budget Changes
-158027000.00
Forecast Completion
2026-08-20T00:00:00.000
Latest Schedule Changes
92
Total Schedule Changes
646
Bronx Public School 468 New Construction
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1106 • Project Name: Bronx Public School 468 New Construction
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1106
Project Name
Bronx Public School 468 New Construction
Description
NEW SCHOOL
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2020-01-16T00:00:00.000
Budget Forecast
80833865.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2024-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
0
RECONST. OF COLUMBIA ST., PH II/BED-768B/SEK002321
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 845 • Project Name: RECONST. OF COLUMBIA ST., PH II/BED-768B/SEK002321
Date Reported As Of
2022-04-01T00:00:00.000
Pid
845
Project Name
RECONST. OF COLUMBIA ST., PH II/BED-768B/SEK002321
Description
Roadway reconstruction including new sewers, water main, street lighting and traffic signals: Columbia Street south of Hamilton Avenue.
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2019-07-01T00:00:00.000
Budget Forecast
120604000.00
Latest Budget Changes
3660000.00
Total Budget Changes
6730000.00
Forecast Completion
2025-07-14T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
972
WESTBOURNE - DUNBAR ROADWAYS/BULKHEADS, QNS
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 981 • Project Name: WESTBOURNE - DUNBAR ROADWAYS/BULKHEADS, QNS
Date Reported As Of
2022-04-01T00:00:00.000
Pid
981
Project Name
WESTBOURNE - DUNBAR ROADWAYS/BULKHEADS, QNS
Description
PRELIMINARY AND FINAL DESIGN SERVICES FOR RECONSTRUCTION OF WESTBOURNE NORTON DRIVE. BOROUGH OF QUEENS
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2016-12-15T00:00:00.000
Budget Forecast
60672000.00
Latest Budget Changes
-651000.00
Total Budget Changes
47223000.00
Forecast Completion
2029-09-26T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1840
Throgs Neck Pumping Station Rehabilitation and Improvements
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 722 • Project Name: Throgs Neck Pumping Station Rehabilitation and Improvements
Date Reported As Of
2022-04-01T00:00:00.000
Pid
722
Project Name
Throgs Neck Pumping Station Rehabilitation and Improvements
Description
Throgs Neck Pumping Station Rehabilitation and Improvements
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2018-06-30T00:00:00.000
Budget Forecast
67400071.25
Latest Budget Changes
184.06
Total Budget Changes
25708336.86
Forecast Completion
2025-12-16T00:00:00.000
Latest Schedule Changes
509
Total Schedule Changes
1306
Storm Mitigation Loan Program at Bowery Bay
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 671 • Project Name: Storm Mitigation Loan Program at Bowery Bay
Date Reported As Of
2022-04-01T00:00:00.000
Pid
671
Project Name
Storm Mitigation Loan Program at Bowery Bay
Description
SMLP portion for Bowery Bay WWTP as part of the New York City Wastewater Resiliency Program.
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2018-04-30T00:00:00.000
Budget Forecast
37775009.87
Latest Budget Changes
-115187.08
Total Budget Changes
-19623216.41
Forecast Completion
2022-09-01T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1026
Metropolitan Avenue Bridge over CSX Transport
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 556 • Project Name: Metropolitan Avenue Bridge over CSX Transport
Date Reported As Of
2022-04-01T00:00:00.000
Pid
556
Project Name
Metropolitan Avenue Bridge over CSX Transport
Description
Replace/Rehab the Metropolitan Avenue bridge over CSX Transport, Queens.
Category
Bridges, Streets and Roadways
Borough
Queens
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2018-04-16T00:00:00.000
Budget Forecast
71376394.00
Latest Budget Changes
-925000.00
Total Budget Changes
4699394.00
Forecast Completion
2029-07-16T00:00:00.000
Latest Schedule Changes
199
Total Schedule Changes
2027
FUEL TANK REPLACEMENT
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 851 • Project Name: FUEL TANK REPLACEMENT
Date Reported As Of
2022-04-01T00:00:00.000
Pid
851
Project Name
FUEL TANK REPLACEMENT
Description
The scope of work consists of providing all necessary construction management, design, and r.onstruction services required to perform ail phases of the project: Surveying, tank testing, investigation, design, construction, and construction management for the closure, removal, upgrade, or replacement of petroieum product storage tanks at various City owned sites. This work must comply with all local, state, nnd federal laws nnd regulations governing tanks and associated work. The general scope of work for tank replacement includes: File NYSDEC PBS application; mobilization; securing all required NYC agency approvals & permits; site survey; geophysical survey; drilling for laboratory soil and groundwater samples; crane & rigging; saw cutting; demo & disposal of old tanks, piping, and concrete vaults; dewatering· of excavation; tank bottom sludge removal & disposal; remove/transfer/dispose product; laboratory analysis of soil and groundwater; excavate, remove, dispose incidental contaminated soil; install shoring, new tanks and tan·k sumps, piping, monitoring and leak detection system, overfill protection and alarms, electrical wiring; construction of concrete slabs and block piers; backfill excavation; resurfacing; demobilization; performance of a closeout investigation and the preparation and filing of appropriate reports; obtaining FDNY and DOB closeout documents; preparing "As-built" drawings.
Category
Industrial Development
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Construction
Design Start
2017-10-30T00:00:00.000
Budget Forecast
31294000.00
Latest Budget Changes
0.00
Total Budget Changes
207000.00
Forecast Completion
2025-04-14T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1278
Brooklyn Supreme Court Fire Alarm System Upgrade
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 510 • Project Name: Brooklyn Supreme Court Fire Alarm System Upgrade
Date Reported As Of
2022-04-01T00:00:00.000
Pid
510
Project Name
Brooklyn Supreme Court Fire Alarm System Upgrade
Description
Brooklyn Supreme Court, Fire Alarm, Sprinkler, 360 Adams Street - New addressable fire detection and alarm system and new sprinkler system.
Category
Public Safety and Criminal Justice
Borough
Brooklyn
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Design
Design Start
2017-03-31T00:00:00.000
Budget Forecast
90193000.00
Latest Budget Changes
32000.00
Total Budget Changes
47003000.00
Forecast Completion
2026-06-30T00:00:00.000
Latest Schedule Changes
92
Total Schedule Changes
1533
Power Distribution at Bowery Bay WWTP
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 522 • Project Name: Power Distribution at Bowery Bay WWTP
Date Reported As Of
2022-04-01T00:00:00.000
Pid
522
Project Name
Power Distribution at Bowery Bay WWTP
Description
Power Distribution at Bowery Bay WWTP.
Category
Wastewater Treatment
Borough
Queens
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2015-11-13T00:00:00.000
Budget Forecast
68873764.13
Latest Budget Changes
0.00
Total Budget Changes
24235381.01
Forecast Completion
2024-03-29T00:00:00.000
Latest Schedule Changes
427
Total Schedule Changes
1684
RED HOOK INTEGRATED FLOOD PROTECTION SYSTEM
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 985 • Project Name: RED HOOK INTEGRATED FLOOD PROTECTION SYSTEM
Date Reported As Of
2022-04-01T00:00:00.000
Pid
985
Project Name
RED HOOK INTEGRATED FLOOD PROTECTION SYSTEM
Description
Reconstruction of Beard Street in the Red Hook neighborhood of Brooklyn, including raising the streets, reconstruction of roadway, curbs and sidewalk, and installing a new bulkhead and floodwall along the waterfront. The reconstruction/raising for Beard Street will cover two blocks (Van Brunt St. to Dwight St).
Category
Public Safety and Criminal Justice
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2019-08-17T00:00:00.000
Budget Forecast
100955000.00
Latest Budget Changes
1469000.00
Total Budget Changes
86623000.00
Forecast Completion
2025-09-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1172
Queens Public School 489 Annex
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1107 • Project Name: Queens Public School 489 Annex
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1107
Project Name
Queens Public School 489 Annex
Description
NEW SCHOOL
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2019-12-16T00:00:00.000
Budget Forecast
79171750.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2024-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
0