Capital Projects

All major infrastructure and information technology projects with a budget of $25 million or more that are currently active (in the design, procurement, or construction phase).

City Government Mayor's Office of Operations (OPS) Dataset n7gv-k5yt 16 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
Reconstruct Final Settling System Equipment at Port Richmond
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 947 • Project Name: Reconstruct Final Settling System Equipment at Port Richmond
Date Reported As Of
2022-04-01T00:00:00.000
Pid
947
Project Name
Reconstruct Final Settling System Equipment at Port Richmond
Description
Rehabilitation of the Final Settling Tanks at Port Richomnd Wastewater Resources Recovery Facility.
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2021-11-16T00:00:00.000
Budget Forecast
128435659.00
Latest Budget Changes
-16464341.00
Total Budget Changes
30972687.00
Forecast Completion
2028-06-17T00:00:00.000
Latest Schedule Changes
26
Total Schedule Changes
205
The Reconstruction of The Lower Catskill Aqueduct
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 667 • Project Name: The Reconstruction of The Lower Catskill Aqueduct
Date Reported As Of
2022-04-01T00:00:00.000
Pid
667
Project Name
The Reconstruction of The Lower Catskill Aqueduct
Description
Reconstruction of Aqueduct structures; Replacement of mechanical equipment; cleaning the aqueduct interior & rehabilitation & repair of cracks & leaks. All relevent assessments, investigations, piloting, plans and reports.
Category
Water Supply
Borough
Citywide
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2019-04-15T00:00:00.000
Budget Forecast
249460845.00
Latest Budget Changes
5000000.00
Total Budget Changes
-65760729.00
Forecast Completion
2027-11-27T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1421
Fort Totten Infrastructure Upgrade
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1154 • Project Name: Fort Totten Infrastructure Upgrade
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1154
Project Name
Fort Totten Infrastructure Upgrade
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
FDNY
Current Phase
Design
Design Start
2021-05-06T00:00:00.000
Budget Forecast
57786000.00
Latest Budget Changes
0.00
Total Budget Changes
100000.00
Forecast Completion
2025-10-13T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
318
FUEL TANK REPLACEMENT
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 851 • Project Name: FUEL TANK REPLACEMENT
Date Reported As Of
2022-04-01T00:00:00.000
Pid
851
Project Name
FUEL TANK REPLACEMENT
Description
The scope of work consists of providing all necessary construction management, design, and r.onstruction services required to perform ail phases of the project: Surveying, tank testing, investigation, design, construction, and construction management for the closure, removal, upgrade, or replacement of petroieum product storage tanks at various City owned sites. This work must comply with all local, state, nnd federal laws nnd regulations governing tanks and associated work. The general scope of work for tank replacement includes: File NYSDEC PBS application; mobilization; securing all required NYC agency approvals & permits; site survey; geophysical survey; drilling for laboratory soil and groundwater samples; crane & rigging; saw cutting; demo & disposal of old tanks, piping, and concrete vaults; dewatering· of excavation; tank bottom sludge removal & disposal; remove/transfer/dispose product; laboratory analysis of soil and groundwater; excavate, remove, dispose incidental contaminated soil; install shoring, new tanks and tan·k sumps, piping, monitoring and leak detection system, overfill protection and alarms, electrical wiring; construction of concrete slabs and block piers; backfill excavation; resurfacing; demobilization; performance of a closeout investigation and the preparation and filing of appropriate reports; obtaining FDNY and DOB closeout documents; preparing "As-built" drawings.
Category
Industrial Development
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Construction
Design Start
2017-10-30T00:00:00.000
Budget Forecast
31294000.00
Latest Budget Changes
0.00
Total Budget Changes
207000.00
Forecast Completion
2025-04-14T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1278
RECONSTRUCTION OF ROSEDALE AREA, PHASE 2
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1011 • Project Name: RECONSTRUCTION OF ROSEDALE AREA, PHASE 2
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1011
Project Name
RECONSTRUCTION OF ROSEDALE AREA, PHASE 2
Description
RECONSTRUCTION OF STREETS IN ROSEDALE AREA - PHASE 2
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2018-06-07T00:00:00.000
Budget Forecast
50547000.00
Latest Budget Changes
1710000.00
Total Budget Changes
61291000.00
Forecast Completion
2026-07-15T00:00:00.000
Latest Schedule Changes
23
Total Schedule Changes
829
Replacement of The Digester at The Hunts Point WWTP
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 580 • Project Name: Replacement of The Digester at The Hunts Point WWTP
Date Reported As Of
2022-04-01T00:00:00.000
Pid
580
Project Name
Replacement of The Digester at The Hunts Point WWTP
Description
Construction of New Anaerobic Digesters
Category
Wastewater Treatment
Borough
Bronx
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2017-10-22T00:00:00.000
Budget Forecast
393773004.14
Latest Budget Changes
-64880897.86
Total Budget Changes
72852004.14
Forecast Completion
2026-04-04T00:00:00.000
Latest Schedule Changes
87
Total Schedule Changes
1355
BBJ Queens Garage - Construction of new multi-level Garage with Community Space
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1156 • Project Name: BBJ Queens Garage - Construction of new multi-level Garage with Community Space
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1156
Project Name
BBJ Queens Garage - Construction of new multi-level Garage with Community Space
Description
BBJ Queens Garage - Construction of new multi-level Garage with Community Space
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
Corrections
Current Phase
Design
Design Start
2021-03-25T00:00:00.000
Budget Forecast
95611000.00
Latest Budget Changes
-356000.00
Total Budget Changes
1314000.00
Forecast Completion
2021-10-11T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
547
150th Street Spine: Phase II - DOT Van Wyck Expressway - Trunk Combined Sewer
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1202 • Project Name: 150th Street Spine: Phase II - DOT Van Wyck Expressway - Trunk Combined Sewer
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1202
Project Name
150th Street Spine: Phase II - DOT Van Wyck Expressway - Trunk Combined Sewer
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2020-03-02T00:00:00.000
Budget Forecast
139368000.00
Latest Budget Changes
0.00
Total Budget Changes
-676000.00
Forecast Completion
2026-05-01T00:00:00.000
Latest Schedule Changes
188
Total Schedule Changes
-194
RECONSTRUCTION OF QUEENS BLVD - PHASE 2
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 619 • Project Name: RECONSTRUCTION OF QUEENS BLVD - PHASE 2
Date Reported As Of
2022-04-01T00:00:00.000
Pid
619
Project Name
RECONSTRUCTION OF QUEENS BLVD - PHASE 2
Description
Vision Zero - Queens Boulevard - Segment 2: 73rd Street to Eliot Avenue. Variety of safety and streetscape improvements including partial street reconstruction and resurfacing to address roadway conditions
Category
Industrial Development
Borough
Queens
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2016-10-26T00:00:00.000
Budget Forecast
85043000.00
Latest Budget Changes
800000.00
Total Budget Changes
14201000.00
Forecast Completion
2029-08-13T00:00:00.000
Latest Schedule Changes
-31
Total Schedule Changes
2315
Bellevue Medical Center Priority Mitigation Projects
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 545 • Project Name: Bellevue Medical Center Priority Mitigation Projects
Date Reported As Of
2022-04-01T00:00:00.000
Pid
545
Project Name
Bellevue Medical Center Priority Mitigation Projects
Description
Priority mitigation projects for the repair/restoration and hazard mitigation for Bellevue Hospital, damaged during Superstorm Sandy
Category
Health and Hospitals
Borough
Manhattan
Managing Agency
EDC
Client Agency
H+H
Current Phase
Construction
Design Start
2014-01-01T00:00:00.000
Budget Forecast
45792288.00
Latest Budget Changes
211063.00
Total Budget Changes
0.00
Forecast Completion
2023-06-30T00:00:00.000
Latest Schedule Changes
381
Total Schedule Changes
1854
EMS Station 17 - New Facility
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1153 • Project Name: EMS Station 17 - New Facility
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1153
Project Name
EMS Station 17 - New Facility
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
Fire
Current Phase
Design
Design Start
2019-01-18T00:00:00.000
Budget Forecast
43914000.00
Latest Budget Changes
12388000.00
Total Budget Changes
13113000.00
Forecast Completion
2024-08-19T00:00:00.000
Latest Schedule Changes
72
Total Schedule Changes
434
80 CENTRE ST.- FIRE ALARMS/SPRINKLERS
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1174 • Project Name: 80 CENTRE ST.- FIRE ALARMS/SPRINKLERS
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1174
Project Name
80 CENTRE ST.- FIRE ALARMS/SPRINKLERS
Description
Fire Alarm and Sprinklers Upgrade
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Design
Design Start
2021-07-26T00:00:00.000
Budget Forecast
44469000.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2026-09-11T00:00:00.000
Latest Schedule Changes
172
Total Schedule Changes
340
Oakwood Beach WWTP Sludge Thickening Improvements
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 449 • Project Name: Oakwood Beach WWTP Sludge Thickening Improvements
Date Reported As Of
2022-04-01T00:00:00.000
Pid
449
Project Name
Oakwood Beach WWTP Sludge Thickening Improvements
Description
Replacement of thickener pumps and associated controls/piping, digested sludge pumps, sludge mixing pumps, sludge recirculation pumps, spray water pumps, and seal water pumps
Category
Wastewater Treatment
Borough
Staten Island
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2018-08-02T00:00:00.000
Budget Forecast
87880194.11
Latest Budget Changes
0.00
Total Budget Changes
57138101.30
Forecast Completion
2026-10-18T00:00:00.000
Latest Schedule Changes
92
Total Schedule Changes
3241
Grand Concourse Metro North Railroad Bridge Construction
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 120 • Project Name: Grand Concourse Metro North Railroad Bridge Construction
Date Reported As Of
2022-04-01T00:00:00.000
Pid
120
Project Name
Grand Concourse Metro North Railroad Bridge Construction
Description
Repair the existing bridge and separate the NYCDOT and NYCT components. Includes new steel plate girders, concrete deck, pedestals, backwalls, sidewalks, and bridge railing.
Category
Bridges
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2000-02-14T00:00:00.000
Budget Forecast
73341117.00
Latest Budget Changes
-4575562.00
Total Budget Changes
22682117.00
Forecast Completion
2023-01-16T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
836
Broadway Bridge over Harlem River Replacement
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 106 • Project Name: Broadway Bridge over Harlem River Replacement
Date Reported As Of
2022-04-01T00:00:00.000
Pid
106
Project Name
Broadway Bridge over Harlem River Replacement
Description
Replace deteriorated members of lift span superstructure, concrete deck, lift electrical and mechanical systems, and fenders.
Category
Bridges
Borough
Bronx, Manhattan
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2005-04-01T00:00:00.000
Budget Forecast
157492984.00
Latest Budget Changes
-7589535.00
Total Budget Changes
39724388.00
Forecast Completion
2027-04-02T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2797
Brooklyn Civil Court move to 210 Joralemon St
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 509 • Project Name: Brooklyn Civil Court move to 210 Joralemon St
Date Reported As Of
2022-04-01T00:00:00.000
Pid
509
Project Name
Brooklyn Civil Court move to 210 Joralemon St
Category
Public Safety and Criminal Justice
Borough
Brooklyn
Managing Agency
DCAS
Client Agency
DCAS
Total Budget Changes
200931011.96
Total Schedule Changes
1977
Coney Island Hospital CSS Building and Perimeter Flood Protection
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 561 • Project Name: Coney Island Hospital CSS Building and Perimeter Flood Protection
Date Reported As Of
2022-04-01T00:00:00.000
Pid
561
Project Name
Coney Island Hospital CSS Building and Perimeter Flood Protection
Description
Renovation of CIH to advance the City’s resiliency plan, repair damages, and protect the hospital from future disasters.
Category
Health and Hospitals
Borough
Brooklyn
Managing Agency
EDC
Client Agency
H+H
Current Phase
Construction
Design Start
2016-02-01T00:00:00.000
Budget Forecast
695449514.00
Latest Budget Changes
9597645.00
Total Budget Changes
30635879.93
Forecast Completion
2023-12-31T00:00:00.000
Latest Schedule Changes
139
Total Schedule Changes
1243
253 Broadway NYC. Fire Alarm Raplacement
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 850 • Project Name: 253 Broadway NYC. Fire Alarm Raplacement
Date Reported As Of
2022-04-01T00:00:00.000
Pid
850
Project Name
253 Broadway NYC. Fire Alarm Raplacement
Description
Installation of new building wide fire alarm and sprinkler distribution for 253 Broadway The PW357FIRE project has been divided into two phases. • Phase 1 - Fire alarm core to meet the PW77LYA project LPC office renovation - currently under construction • Phase 2 – Fire alarm branches, sprinkler system branches, and BMS – currently under bid package review phase
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Construction
Design Start
2018-01-22T00:00:00.000
Budget Forecast
49531000.00
Latest Budget Changes
5264000.00
Total Budget Changes
17827000.00
Forecast Completion
2026-12-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1553
North River WWTP Primary Treatment Improvements
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 945 • Project Name: North River WWTP Primary Treatment Improvements
Date Reported As Of
2022-04-01T00:00:00.000
Pid
945
Project Name
North River WWTP Primary Treatment Improvements
Description
Rehabilitation of the Primary Settling Tanks at North River Wastewater Resources Recovery Facility.
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2021-05-17T00:00:00.000
Budget Forecast
200316583.00
Latest Budget Changes
17182221.20
Total Budget Changes
35891899.00
Forecast Completion
2028-05-20T00:00:00.000
Latest Schedule Changes
145
Total Schedule Changes
121
Reconstruction of Beach Channel Drive -- Phase B
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1151 • Project Name: Reconstruction of Beach Channel Drive -- Phase B
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1151
Project Name
Reconstruction of Beach Channel Drive -- Phase B
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2021-04-15T00:00:00.000
Budget Forecast
42592000.00
Latest Budget Changes
82000.00
Total Budget Changes
642000.00
Forecast Completion
2028-09-01T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
0
RECONSTRUCTION OF QUEENS BLVD - PHASE 3
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1152 • Project Name: RECONSTRUCTION OF QUEENS BLVD - PHASE 3
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1152
Project Name
RECONSTRUCTION OF QUEENS BLVD - PHASE 3
Description
Vision Zero - Queens Boulevard - Segment 3: Eliot Avenue to Yellowstone Boulevard. Variety of safety and streetscape improvements including partial street reconstruction and resurfacing to address roadway conditions.
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2018-04-26T00:00:00.000
Budget Forecast
99344000.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Total Schedule Changes
0
Jerome Reservoir and Aqueduct Rehabilitation
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 448 • Project Name: Jerome Reservoir and Aqueduct Rehabilitation
Date Reported As Of
2022-04-01T00:00:00.000
Pid
448
Project Name
Jerome Reservoir and Aqueduct Rehabilitation
Description
Improvements to: fencing, vegetation, roadway, drainage, ext. above-ground retaining walls. Including repair of dam inlet archway & wingwall, re-pointing of stones & reinforcement of east reservoir wall, & leakage/seepage protection within OCA.
Category
Water Supply
Borough
Bronx
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2016-02-24T00:00:00.000
Budget Forecast
57255623.09
Latest Budget Changes
0.00
Total Budget Changes
-833277.14
Forecast Completion
2026-12-29T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2363
Combined Sewer And Wm Work In 71 Street, Queens
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 789 • Project Name: Combined Sewer And Wm Work In 71 Street, Queens
Date Reported As Of
2022-04-01T00:00:00.000
Pid
789
Project Name
Combined Sewer And Wm Work In 71 Street, Queens
Description
Replacement of combined sewer in 71st Street between Juniper Boulevard South and Queens Midtown Expressway, etc.
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2018-09-10T00:00:00.000
Budget Forecast
73613000.00
Latest Budget Changes
6400000.00
Total Budget Changes
27172000.00
Forecast Completion
2026-10-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1889
GI - GRAVESEND BAY CSO - PHASE III
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1199 • Project Name: GI - GRAVESEND BAY CSO - PHASE III
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1199
Project Name
GI - GRAVESEND BAY CSO - PHASE III
Description
GREEN INFRASTRUCTURE IN OH-015 GRAVESEND BAY CSO PH 3
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2017-08-01T00:00:00.000
Budget Forecast
42742000.00
Latest Budget Changes
2136000.00
Total Budget Changes
-372000.00
Forecast Completion
2025-06-11T00:00:00.000
Latest Schedule Changes
28
Total Schedule Changes
189
FUEL TANK REPLACEMENT
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1005 • Project Name: FUEL TANK REPLACEMENT
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1005
Project Name
FUEL TANK REPLACEMENT
Description
FUEL TANK REPLACEMENT
Category
Industrial Development
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Construction
Design Start
2018-04-25T00:00:00.000
Budget Forecast
25520000.00
Latest Budget Changes
150000.00
Total Budget Changes
-6429000.00
Forecast Completion
2024-10-04T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
914
East 174th Street over Sheridan Expressway - Amtrak
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 701 • Project Name: East 174th Street over Sheridan Expressway - Amtrak
Date Reported As Of
2022-04-01T00:00:00.000
Pid
701
Project Name
East 174th Street over Sheridan Expressway - Amtrak
Description
Repair the East 174th Street bridge over Sheridan Expressway/ AMTRAK, the Bronx
Category
Bridges
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2018-08-16T00:00:00.000
Budget Forecast
140939882.00
Latest Budget Changes
-515000.00
Total Budget Changes
5146882.00
Forecast Completion
2029-12-13T00:00:00.000
Latest Schedule Changes
-112
Total Schedule Changes
1431
Roma and Hett Avenue Storm and Sanitary Sewer Installation
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 206 • Project Name: Roma and Hett Avenue Storm and Sanitary Sewer Installation
Date Reported As Of
2022-04-01T00:00:00.000
Pid
206
Project Name
Roma and Hett Avenue Storm and Sanitary Sewer Installation
Description
Installation of Storm, Sanitary Sewers in the following Streets:=================================1- Cedar Grove Avenue between Ebbitts Street and new Dorp Lane.2- Milton Avenue between Ebbitts Street and new Dorp Lane.3- Finley Avenue between Ebbitts Street and new Dorp Lane.4- Roma Avenue between Ebbitts Street and new Dorp Lane.5- Hett Avenue between Ebbitts Street and new Dorp Lane.6- Marine Way between Cedar Grove and Milton Avenue7- Beacon Avenue between Roma Avenue and Milton Avenue.8- Dustan Avenue between Marine way and Milton Avenue.9- Garibaldi Avenue between Roma Avenue and Cedar Grove Avenue.10- Cedar Grove Court between Cedar Grove Avenue and Dustan Street.11- Topping Street between Cedar Grove Avenue and Dustan Street.12- Center Way between Cedar Grove Avenue and Dustan Street.13- Neptune Street between Cedar Grove Avenue and Dustan Street.14- Seafoam Street between Cedar Grove Avenue and Dustan Street.15- Waterside Street between Cedar Grove Avenue and Dustan Street.16- Maple Terrace between Cedar Grove Avenue and Dustan Street.17- Herman Street between Cedar Grove Avenue and Dustan Street.18- Neutral Avenue between Cedar Grove Avenue and Dustan Street.19- Milbank Drive between Cedar Grove Avenue and Dustan Street.
Category
Sewers
Borough
Staten Island
Managing Agency
DDC
Client Agency
Trans. & Env. Protection
Current Phase
Construction
Design Start
2014-10-15T00:00:00.000
Budget Forecast
94020000.00
Latest Budget Changes
4400000.00
Total Budget Changes
62973000.00
Forecast Completion
2023-10-04T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
-8
MULTI-SITE PEDESTRIAN SAFETY PHASE 5
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1004 • Project Name: MULTI-SITE PEDESTRIAN SAFETY PHASE 5
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1004
Project Name
MULTI-SITE PEDESTRIAN SAFETY PHASE 5
Description
PEDESTRIAN SAFETY GEOMETRIC IMPROVEMENTS AT VARIOUS SPECIFIED LOCATIONS, CITYWIDE
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction
Design Start
2017-08-01T00:00:00.000
Budget Forecast
26189000.00
Latest Budget Changes
-30000.00
Total Budget Changes
-4087000.00
Forecast Completion
2024-06-01T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1126
Owls Head WWTP Final Settling System Rehabilitation
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 946 • Project Name: Owls Head WWTP Final Settling System Rehabilitation
Date Reported As Of
2022-04-01T00:00:00.000
Pid
946
Project Name
Owls Head WWTP Final Settling System Rehabilitation
Description
Rehabilitation of the Final Settling Tanks at Owls Head Wastewater Resources Recovery Facility.
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2021-11-09T00:00:00.000
Budget Forecast
208757740.00
Latest Budget Changes
-4042260.00
Total Budget Changes
-3573164.00
Forecast Completion
2029-05-25T00:00:00.000
Latest Schedule Changes
322
Total Schedule Changes
345
South Bronx East-West Crosstown SBS
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1008 • Project Name: South Bronx East-West Crosstown SBS
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1008
Project Name
South Bronx East-West Crosstown SBS
Description
The South Bronx Crosstown SBS capital project (BRT) will add bus pads and construct bus bulbs, curb and median extensions, and pedestrian islands for enhanced pedestrian safety and access improvements.
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2019-07-01T00:00:00.000
Budget Forecast
53718000.00
Latest Budget Changes
100000.00
Total Budget Changes
3130000.00
Forecast Completion
2026-11-03T00:00:00.000
Latest Schedule Changes
112
Total Schedule Changes
626
Croton Above Ground Structure And Landscaping
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 747 • Project Name: Croton Above Ground Structure And Landscaping
Date Reported As Of
2022-04-01T00:00:00.000
Pid
747
Project Name
Croton Above Ground Structure And Landscaping
Description
The new Mosholu Golf Course Club House, together with fifty-five Driving Range Tee Boxes and ten-acres of re-landscaping comprise the phase IV and final of the vast DEP Croton Water Treatment Plant project, currently under construction in Van Cortlandt Park in the Bronx. Through a multifunctional design strategy the project reinstates the pre-existing golf program and facility, creates civic space for community use and ensures security for a multi-billion dollar public works facility.
Category
Industrial Development
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2012-05-23T00:00:00.000
Budget Forecast
132780000.00
Latest Budget Changes
25336000.00
Total Budget Changes
75117000.00
Forecast Completion
2023-02-23T00:00:00.000
Latest Schedule Changes
22
Total Schedule Changes
897
SAN & STRM SEWER, WM IN CONEY ISLAND AREA, PH 4
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1009 • Project Name: SAN & STRM SEWER, WM IN CONEY ISLAND AREA, PH 4
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1009
Project Name
SAN & STRM SEWER, WM IN CONEY ISLAND AREA, PH 4
Description
Storm, Sanitary Sewers & Water Mains in Coney Island Area - Phase 04, Brooklyn
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2019-07-25T00:00:00.000
Budget Forecast
29669000.00
Latest Budget Changes
50000.00
Total Budget Changes
1984000.00
Forecast Completion
2027-02-07T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1431
Rego Park New Facility
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1145 • Project Name: Rego Park New Facility
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1145
Project Name
Rego Park New Facility
Description
New Library for Rego Park
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
Libraries-QBPL
Current Phase
Design
Design Start
2019-04-11T00:00:00.000
Budget Forecast
41511000.00
Latest Budget Changes
200000.00
Total Budget Changes
535000.00
Forecast Completion
2026-03-07T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
474
New Westchester Square
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1147 • Project Name: New Westchester Square
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1147
Project Name
New Westchester Square
Description
DDC Constructability comments anticipated by 5/31/17. Anticipated Construction Budget shortfall of $600k. Funding required to submit initial Construction CP.
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
Libraries-NYPL
Current Phase
Construction Procurement
Design Start
2013-05-13T00:00:00.000
Budget Forecast
36429630.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2026-02-28T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
471
Lower Concourse Initiative
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 575 • Project Name: Lower Concourse Initiative
Date Reported As Of
2022-04-01T00:00:00.000
Pid
575
Project Name
Lower Concourse Initiative
Description
The Project will improve the roadways and pedestrian facilities. The Project will consist of roadway reconstruction within Exterior Street between East 138th Street and East 150th Street.
Category
Industrial Development
Borough
Bronx
Managing Agency
EDC
Client Agency
EDC
Current Phase
Construction
Design Start
2017-04-01T00:00:00.000
Budget Forecast
84520367.00
Latest Budget Changes
0.00
Total Budget Changes
-5100000.00
Forecast Completion
2023-06-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
730
HIGH LEVEL STM SEWERS IN GOWANUS CANAL AREA-PH II
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 849 • Project Name: HIGH LEVEL STM SEWERS IN GOWANUS CANAL AREA-PH II
Date Reported As Of
2022-04-01T00:00:00.000
Pid
849
Project Name
HIGH LEVEL STM SEWERS IN GOWANUS CANAL AREA-PH II
Description
High Level Storm and Combine Sewer installation and Water Main replacement in Gowanus Canal Area Phase-2, Brooklyn.
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2016-09-30T00:00:00.000
Budget Forecast
42105000.00
Latest Budget Changes
1404000.00
Total Budget Changes
8657000.00
Forecast Completion
2022-11-23T00:00:00.000
Latest Schedule Changes
210
Total Schedule Changes
813
Reconstruction of the Port Jervis Wastewater Treatment Plant
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 444 • Project Name: Reconstruction of the Port Jervis Wastewater Treatment Plant
Date Reported As Of
2022-04-01T00:00:00.000
Pid
444
Project Name
Reconstruction of the Port Jervis Wastewater Treatment Plant
Description
Reconstruction of the Port Jervis WWTP as required based on the effluent limits proposed by the Delaware River Basin Commission (DRBC)
Category
Wastewater Treatment
Borough
Port Jervis
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2014-06-17T00:00:00.000
Budget Forecast
60924311.99
Latest Budget Changes
0.00
Total Budget Changes
9428438.55
Forecast Completion
2026-10-04T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2445
150 ST SPINE: PHASE II TRUNK SEWER AT BERGEN BASIN
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 999 • Project Name: 150 ST SPINE: PHASE II TRUNK SEWER AT BERGEN BASIN
Date Reported As Of
2022-04-01T00:00:00.000
Pid
999
Project Name
150 ST SPINE: PHASE II TRUNK SEWER AT BERGEN BASIN
Description
Southeast Queens 150th Street Spine, Phase II - Installation of a new double barrel trunk storm sewer that will run through JFK airport; approximately 1,000 feet east of Bergen Basin, to the north side of the Belt Parkway at Inwood Street and 150th Street
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2020-03-02T00:00:00.000
Budget Forecast
47307000.00
Latest Budget Changes
-283000.00
Total Budget Changes
-158027000.00
Forecast Completion
2026-08-20T00:00:00.000
Latest Schedule Changes
92
Total Schedule Changes
646
Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 112 • Project Name: Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Date Reported As Of
2022-04-01T00:00:00.000
Pid
112
Project Name
Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Description
Repair abutments, piers, approaches, and steel superstructure located in Pelham Bay, Bronx; replace reinforced concrete deck.
Category
Bridges, Streets and Roadways
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
1995-01-17T00:00:00.000
Budget Forecast
82262363.00
Latest Budget Changes
-6413908.00
Total Budget Changes
20945057.00
Forecast Completion
2022-07-23T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1592
33rd Street West of 11th Avenue (Hudson Yards)
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1043 • Project Name: 33rd Street West of 11th Avenue (Hudson Yards)
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1043
Project Name
33rd Street West of 11th Avenue (Hudson Yards)
Category
Bridges
Managing Agency
DOT
Client Agency
EDC
Current Phase
Design
Design Start
2017-04-01T00:00:00.000
Budget Forecast
100000104.00
Latest Budget Changes
0.00
Total Budget Changes
-1399960.00
Forecast Completion
2029-01-11T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
611
Bronx River CSO Reduction
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 943 • Project Name: Bronx River CSO Reduction
Date Reported As Of
2022-04-01T00:00:00.000
Pid
943
Project Name
Bronx River CSO Reduction
Description
The project will provide hydraulic relief to Outfalls HP-007 and HP-009 by creating new sewers parallel to the existing combined sewers. It will also provide floatables control at Outfall HP-011 by replacing Regulator 5.
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
WWC
Current Phase
Design
Design Start
2020-04-16T00:00:00.000
Budget Forecast
184348203.00
Latest Budget Changes
0.00
Total Budget Changes
1210235.00
Forecast Completion
2028-12-14T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
-712
Fort Greene Park Entrances, Paths, Plaza and Drainage Infrastructure Reconstruction
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1218 • Category: Parks
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1218
Project Name
Fort Greene Park Entrances, Paths, Plaza and Drainage Infrastructure Reconstruction
Description
This project will reconstruct the entrances, paths, plaza and drainage infrastructure at Fort Greene Park.
Category
Parks
Managing Agency
DPR
Client Agency
DPR
Current Phase
Design
Design Start
2021-02-22T00:00:00.000
Budget Forecast
29284800.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2024-11-23T00:00:00.000
Total Schedule Changes
417
RECONSTRUCTION OF E 177 STREET/DEVOE AVENUE
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 623 • Project Name: RECONSTRUCTION OF E 177 STREET/DEVOE AVENUE
Date Reported As Of
2022-04-01T00:00:00.000
Pid
623
Project Name
RECONSTRUCTION OF E 177 STREET/DEVOE AVENUE
Description
Road Reconstruction, Water Main and Combined Sewer Work E 177th Street from Devoe Ave to Bronx Park Ave East Tremont Ave from Bronx Park Ave to Boston Rd Devoe Ave from E 177th Street to East Tremont Ave
Category
Industrial Development, Streets and Roadways
Borough
Bronx
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2009-09-03T00:00:00.000
Budget Forecast
49935000.00
Latest Budget Changes
22987000.00
Total Budget Changes
25050000.00
Forecast Completion
2025-09-26T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1839
Combined Sewer In 70Th Street, Queens
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 788 • Project Name: Combined Sewer In 70Th Street, Queens
Date Reported As Of
2022-04-01T00:00:00.000
Pid
788
Project Name
Combined Sewer In 70Th Street, Queens
Description
COMBINED SEWER IN 70TH STREET, QUEENS
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2016-08-31T00:00:00.000
Budget Forecast
124773000.00
Latest Budget Changes
1339000.00
Total Budget Changes
94201000.00
Forecast Completion
2023-08-10T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1155
Henry Hudson Parkway over Amtrak (Northbound)
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 592 • Project Name: Henry Hudson Parkway over Amtrak (Northbound)
Date Reported As Of
2022-04-01T00:00:00.000
Pid
592
Project Name
Henry Hudson Parkway over Amtrak (Northbound)
Description
Replace the Ramp to northbound Henry Hudson Parkway over Amtrak in Manhattan.
Category
Bridges
Borough
Manhattan
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2020-01-02T00:00:00.000
Budget Forecast
53551625.00
Latest Budget Changes
-500000.00
Total Budget Changes
500625.00
Forecast Completion
2029-07-01T00:00:00.000
Latest Schedule Changes
45
Total Schedule Changes
1693
SEELY STREET OVER PROSPECT AVENUE BIN: 2244470
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1119 • Project Name: SEELY STREET OVER PROSPECT AVENUE BIN: 2244470
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1119
Project Name
SEELY STREET OVER PROSPECT AVENUE BIN: 2244470
Description
Rehabilitation of Seeley Street bridge over Prospect Avenue
Category
Bridges
Managing Agency
DOT
Client Agency
n/a
Current Phase
Design
Design Start
2019-11-12T00:00:00.000
Budget Forecast
30709037.00
Latest Budget Changes
-512230.00
Total Budget Changes
0.00
Forecast Completion
2027-10-03T00:00:00.000
Latest Schedule Changes
27
Total Schedule Changes
253
Metropolitan Avenue Bridge over CSX Transport
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 556 • Project Name: Metropolitan Avenue Bridge over CSX Transport
Date Reported As Of
2022-04-01T00:00:00.000
Pid
556
Project Name
Metropolitan Avenue Bridge over CSX Transport
Description
Replace/Rehab the Metropolitan Avenue bridge over CSX Transport, Queens.
Category
Bridges, Streets and Roadways
Borough
Queens
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2018-04-16T00:00:00.000
Budget Forecast
71376394.00
Latest Budget Changes
-925000.00
Total Budget Changes
4699394.00
Forecast Completion
2029-07-16T00:00:00.000
Latest Schedule Changes
199
Total Schedule Changes
2027
Reconstruction Of Primary Tanks at Bowery Bay WPCP
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 942 • Project Name: Reconstruction Of Primary Tanks at Bowery Bay WPCP
Date Reported As Of
2022-04-01T00:00:00.000
Pid
942
Project Name
Reconstruction Of Primary Tanks at Bowery Bay WPCP
Description
Reconstruction Of Primary Tanks at Bowery Bay WPCP
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2019-09-27T00:00:00.000
Budget Forecast
128275608.00
Latest Budget Changes
0.00
Total Budget Changes
74442173.00
Forecast Completion
2027-07-09T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
636
Harlem River Drive Ramp Reconstruction (George Washington Bridge)
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 708 • Project Name: Harlem River Drive Ramp Reconstruction (George Washington Bridge)
Date Reported As Of
2022-04-01T00:00:00.000
Pid
708
Project Name
Harlem River Drive Ramp Reconstruction (George Washington Bridge)
Description
Repair the Harlem River Drive Ramp to George Washington Bridge over Harlem River Drive Southbound (Trans-Manhattan Expressway), Manhattan
Category
Bridges, Streets and Roadways
Borough
Manhattan
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2019-02-07T00:00:00.000
Budget Forecast
429792546.00
Latest Budget Changes
-290000.00
Total Budget Changes
-3711870.00
Forecast Completion
2034-08-03T00:00:00.000
Latest Schedule Changes
25
Total Schedule Changes
2697
Manhattan Greenway: East Midtown
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 859 • Project Name: Manhattan Greenway: East Midtown
Date Reported As Of
2022-04-01T00:00:00.000
Pid
859
Project Name
Manhattan Greenway: East Midtown
Description
The East Midtown Waterfront Greenway project involves the creation of a waterfront esplanade between East 53rd and East 59th Streets.
Category
Parks
Managing Agency
EDC
Client Agency
EDC
Current Phase
Construction
Design Start
2017-10-01T00:00:00.000
Budget Forecast
154840000.00
Latest Budget Changes
18840000.00
Total Budget Changes
24840000.00
Forecast Completion
2023-12-31T00:00:00.000
Latest Schedule Changes
122
Total Schedule Changes
487