Capital Projects

All major infrastructure and information technology projects with a budget of $25 million or more that are currently active (in the design, procurement, or construction phase).

City Government Mayor's Office of Operations (OPS) Dataset n7gv-k5yt 16 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
Bronx Sanitation Garage Rehabilitation: Community District 6
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 971 • Project Name: Bronx Sanitation Garage Rehabilitation: Community District 6
Date Reported As Of
2022-04-01T00:00:00.000
Pid
971
Project Name
Bronx Sanitation Garage Rehabilitation: Community District 6
Description
Rehabilitation of garage, broom garage and salt shed that serves Bronx Community Disrtict 6 located at 800 East 176th Street, Bronx.
Category
Sanitation
Managing Agency
DSNY
Client Agency
DSNY
Current Phase
Design
Design Start
2017-06-20T00:00:00.000
Budget Forecast
39941681.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2027-06-30T00:00:00.000
Latest Schedule Changes
365
Total Schedule Changes
913
Coastal Resiliency Area 1 - East 23rd St. to Montg
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1169 • Project Name: Coastal Resiliency Area 1 - East 23rd St. to Montg
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1169
Project Name
Coastal Resiliency Area 1 - East 23rd St. to Montg
Description
East Side Coastal Resiliency - Montgomery Street to East 15th Street, Manhattan
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Parks & Recreation
Current Phase
Construction Procurement
Design Start
2016-04-27T00:00:00.000
Budget Forecast
1328351541.76
Latest Budget Changes
0.00
Total Budget Changes
0.76
Supreme Courthouse Fire Alarm/ Protection Upgrade
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 837 • Project Name: Supreme Courthouse Fire Alarm/ Protection Upgrade
Date Reported As Of
2022-04-01T00:00:00.000
Pid
837
Project Name
Supreme Courthouse Fire Alarm/ Protection Upgrade
Description
Bronx Supreme Court, Fire Alarm, Sprinkler, 851 Grand Concourse - Replace the existing fire alarm system and install a new sprinkler system.
Category
Public Safety and Criminal Justice
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Design
Design Start
2018-07-11T00:00:00.000
Budget Forecast
80366000.00
Latest Budget Changes
-350000.00
Total Budget Changes
37248610.00
Forecast Completion
2027-01-15T00:00:00.000
Latest Schedule Changes
121
Total Schedule Changes
1319
East 174th Street over Sheridan Expressway - Amtrak
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 701 • Project Name: East 174th Street over Sheridan Expressway - Amtrak
Date Reported As Of
2022-04-01T00:00:00.000
Pid
701
Project Name
East 174th Street over Sheridan Expressway - Amtrak
Description
Repair the East 174th Street bridge over Sheridan Expressway/ AMTRAK, the Bronx
Category
Bridges
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2018-08-16T00:00:00.000
Budget Forecast
140939882.00
Latest Budget Changes
-515000.00
Total Budget Changes
5146882.00
Forecast Completion
2029-12-13T00:00:00.000
Latest Schedule Changes
-112
Total Schedule Changes
1431
Dumbo and Vinegar Hill Area Roadway Reconstruction and Renovation
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 193 • Project Name: Dumbo and Vinegar Hill Area Roadway Reconstruction and Renovation
Date Reported As Of
2022-04-01T00:00:00.000
Pid
193
Project Name
Dumbo and Vinegar Hill Area Roadway Reconstruction and Renovation
Description
Reconstruction DUMBO/Vinegar Hill Area including Trunk and Distribution water main replacement; Installation of HLSS and Combined Sewer replacement; Restoration of Belgian block in Water Street; Street lighting and Traffic Signal work.
Category
Streets and Roadways
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction
Design Start
2012-06-07T00:00:00.000
Budget Forecast
130410000.00
Latest Budget Changes
930000.00
Total Budget Changes
96724000.00
Forecast Completion
2024-06-04T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
3253
Queens PS 206 New Construction
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 970 • Project Name: Queens PS 206 New Construction
Date Reported As Of
2022-04-01T00:00:00.000
Pid
970
Project Name
Queens PS 206 New Construction
Description
ADDITION
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2018-09-10T00:00:00.000
Budget Forecast
54584235.00
Latest Budget Changes
0.00
Total Budget Changes
2268625.00
Forecast Completion
2023-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
365
STM & SAN SWR, WILLET PT BLVD WHITESTONE AREA, PH2
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 651 • Project Name: STM & SAN SWR, WILLET PT BLVD WHITESTONE AREA, PH2
Date Reported As Of
2022-04-01T00:00:00.000
Pid
651
Project Name
STM & SAN SWR, WILLET PT BLVD WHITESTONE AREA, PH2
Description
Installation of Storm sewers, Sanitary sewers, & Water mains in Whitestone Area.
Category
Sewers
Borough
Queens
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2013-03-15T00:00:00.000
Budget Forecast
109091000.00
Latest Budget Changes
0.00
Total Budget Changes
41243000.00
Forecast Completion
2022-09-15T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
642
Brooklyn P.S. at 4302 4TH AVE
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 949 • Project Name: Brooklyn P.S. at 4302 4TH AVE
Date Reported As Of
2022-04-01T00:00:00.000
Pid
949
Project Name
Brooklyn P.S. at 4302 4TH AVE
Description
NEW SCHOOL (PHASE II)
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2017-11-17T00:00:00.000
Budget Forecast
66058403.00
Latest Budget Changes
0.00
Total Budget Changes
-221356.00
Forecast Completion
2023-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
365
Cunningham Park Garage Reconstruction
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1019 • Project Name: Cunningham Park Garage Reconstruction
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1019
Project Name
Cunningham Park Garage Reconstruction
Description
This project will reconstruct the garage in Cunningham Park.
Category
Parks
Managing Agency
DPR
Client Agency
DPR
Current Phase
Construction Procurement
Design Start
2018-11-19T00:00:00.000
Budget Forecast
27060000.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2024-07-29T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
703
RECONSTRUCTION OF SOUTH JAMAICA AREA (SEQ200562)
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1163 • Project Name: RECONSTRUCTION OF SOUTH JAMAICA AREA (SEQ200562)
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1163
Project Name
RECONSTRUCTION OF SOUTH JAMAICA AREA (SEQ200562)
Description
Total reconstruction of two street grids in South Jamaica approximately bounded by Sutphin Boulevard, 109th Avenue, 155th Street and Linden Boulevard, and by 157th Street, 111th Avenue, Beddell Street and 116th Avenue.
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2014-02-04T00:00:00.000
Budget Forecast
57023000.00
Latest Budget Changes
637000.00
Total Budget Changes
1360000.00
Forecast Completion
2027-01-11T00:00:00.000
Latest Schedule Changes
336
Total Schedule Changes
366
P.S. 163 - BRONX New Construction
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1219 • Project Name: P.S. 163 - BRONX New Construction
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1219
Project Name
P.S. 163 - BRONX New Construction
Description
NEW SCHOOL / DEMOLITION OF EXISTING X163 BUILDING
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction Procurement
Design Start
2019-12-06T00:00:00.000
Budget Forecast
105558715.00
Latest Budget Changes
-7624613.00
Total Budget Changes
-6925988.00
Forecast Completion
2024-12-13T00:00:00.000
Latest Schedule Changes
101
Total Schedule Changes
0
Far Rockaway New Facility
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 730 • Project Name: Far Rockaway New Facility
Date Reported As Of
2022-04-01T00:00:00.000
Pid
730
Project Name
Far Rockaway New Facility
Description
Construction of a new 18,000 sq.ft. Branch employing the latest technology and sustainable design.
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
Libraries-QBPL
Current Phase
Construction
Design Start
2012-01-10T00:00:00.000
Budget Forecast
39531557.09
Latest Budget Changes
0.00
Total Budget Changes
-623757.91
Forecast Completion
2022-05-30T00:00:00.000
Latest Schedule Changes
14
Total Schedule Changes
-78
Rehab Of Queens District 11/13 Sanitation Garage
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 770 • Project Name: Rehab Of Queens District 11/13 Sanitation Garage
Date Reported As Of
2022-04-01T00:00:00.000
Pid
770
Project Name
Rehab Of Queens District 11/13 Sanitation Garage
Description
The Department of Sanitation of the City of New York (DSNY) is planning to rehabilitate Queens Districts 11 and 13 garage. The renovation serving both districts is to extend the useful life of the facility through rehabilitation of the building structure and systems. The renovation includes: Extensive structural work that includes the replacement of reinforced concrete slabs and stiffening of the existing steel frame, select replacement of building MEP systems, including BMS systems, architectural renovation of the entire building, study and implementation of deep energy conservation measures (DECMs), and site work which includes new landscape work and replacement of sidewalks and driveways. Rehabilitation is required to meet LEED Silver requirements.
Category
Sanitation
Borough
Queens
Managing Agency
DDC
Client Agency
Sanitation
Current Phase
Design
Design Start
2017-03-06T00:00:00.000
Budget Forecast
73161000.00
Latest Budget Changes
544000.00
Total Budget Changes
36221000.00
Forecast Completion
2026-06-12T00:00:00.000
Latest Schedule Changes
164
Total Schedule Changes
1521
Reconstruction of the Ashokan Headworks
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 834 • Project Name: Reconstruction of the Ashokan Headworks
Date Reported As Of
2022-04-01T00:00:00.000
Pid
834
Project Name
Reconstruction of the Ashokan Headworks
Description
CAT-213
Category
Water Supply
Borough
Upstate
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2020-08-07T00:00:00.000
Budget Forecast
333066831.75
Latest Budget Changes
13832112.00
Total Budget Changes
41950858.00
Forecast Completion
2027-11-04T00:00:00.000
Latest Schedule Changes
11
Total Schedule Changes
-67
Gilboa Dam Reconstruction, Phase IV
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 406 • Project Name: Gilboa Dam Reconstruction, Phase IV
Date Reported As Of
2022-04-01T00:00:00.000
Pid
406
Project Name
Gilboa Dam Reconstruction, Phase IV
Description
This project will rehabilitate the mechanics and the architecture of the Shandaken Tunnel Intake Chamber, which includes the replacement of gates and general site improvements.
Category
Water Supply
Borough
Upstate
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2008-12-01T00:00:00.000
Budget Forecast
72960489.85
Latest Budget Changes
-111745.70
Total Budget Changes
33535991.20
Forecast Completion
2022-08-29T00:00:00.000
Latest Schedule Changes
-3
Total Schedule Changes
1684
New York State Pavilion Observation Towers Reconstruction
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1018 • Project Name: New York State Pavilion Observation Towers Reconstruction
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1018
Project Name
New York State Pavilion Observation Towers Reconstruction
Description
This project will reconstruct portions of the New York State Pavilion Observation Towers in Flushing Meadows Corona Park.
Category
Parks
Managing Agency
DPR
Client Agency
DPR
Current Phase
Construction
Design Start
2015-09-21T00:00:00.000
Budget Forecast
28779000.00
Latest Budget Changes
0.00
Total Budget Changes
1000.00
Forecast Completion
2022-07-01T00:00:00.000
Latest Schedule Changes
123
Total Schedule Changes
772
BBJ Queens Garage - Construction of new multi-level Garage with Community Space
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1156 • Project Name: BBJ Queens Garage - Construction of new multi-level Garage with Community Space
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1156
Project Name
BBJ Queens Garage - Construction of new multi-level Garage with Community Space
Description
BBJ Queens Garage - Construction of new multi-level Garage with Community Space
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
Corrections
Current Phase
Design
Design Start
2021-03-25T00:00:00.000
Budget Forecast
95611000.00
Latest Budget Changes
-356000.00
Total Budget Changes
1314000.00
Forecast Completion
2021-10-11T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
547
Brooklyn Public School 730 New Construction
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 876 • Project Name: Brooklyn Public School 730 New Construction
Date Reported As Of
2022-04-01T00:00:00.000
Pid
876
Project Name
Brooklyn Public School 730 New Construction
Description
NEW SCHOOL
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2018-01-26T00:00:00.000
Budget Forecast
66249461.00
Latest Budget Changes
0.00
Total Budget Changes
6379885.00
Forecast Completion
2023-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
730
New 40th Precinct
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 634 • Project Name: New 40th Precinct
Date Reported As Of
2022-04-01T00:00:00.000
Pid
634
Project Name
New 40th Precinct
Description
Design and build a new Police Precinct with full basement totaling 43,000 sq. ft. on an existing City owned property in the Bronx.
Category
Public Safety and Criminal Justice
Borough
Bronx
Managing Agency
DDC
Client Agency
Police
Current Phase
Construction
Design Start
2014-09-30T00:00:00.000
Budget Forecast
91274000.00
Latest Budget Changes
10321000.00
Total Budget Changes
26020000.00
Forecast Completion
2022-11-09T00:00:00.000
Latest Schedule Changes
14
Total Schedule Changes
711
West 35th Street over Amtrak
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 696 • Project Name: West 35th Street over Amtrak
Date Reported As Of
2022-04-01T00:00:00.000
Pid
696
Project Name
West 35th Street over Amtrak
Description
Repair the West 35th Street bridge over Amtrak, Manhattan
Category
Bridges
Borough
Manhattan
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2018-11-21T00:00:00.000
Budget Forecast
32671034.00
Latest Budget Changes
-500000.00
Total Budget Changes
-621966.00
Forecast Completion
2030-12-10T00:00:00.000
Latest Schedule Changes
988
Total Schedule Changes
2846
150th Street Spine: Phase II - DOT Van Wyck Expressway - Trunk Combined Sewer
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1202 • Project Name: 150th Street Spine: Phase II - DOT Van Wyck Expressway - Trunk Combined Sewer
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1202
Project Name
150th Street Spine: Phase II - DOT Van Wyck Expressway - Trunk Combined Sewer
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2020-03-02T00:00:00.000
Budget Forecast
139368000.00
Latest Budget Changes
0.00
Total Budget Changes
-676000.00
Forecast Completion
2026-05-01T00:00:00.000
Latest Schedule Changes
188
Total Schedule Changes
-194
STM & SAN SWR, N.B. WHITESTONE EXPWY SERV RD, PH 3
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 652 • Project Name: STM & SAN SWR, N.B. WHITESTONE EXPWY SERV RD, PH 3
Date Reported As Of
2022-04-01T00:00:00.000
Pid
652
Project Name
STM & SAN SWR, N.B. WHITESTONE EXPWY SERV RD, PH 3
Description
Installation of Storm sewers, Sanitary sewers, & Water mains in Whitestone Area-Phase 3
Category
Sewers
Borough
Queens
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2016-07-15T00:00:00.000
Budget Forecast
76746000.00
Latest Budget Changes
155000.00
Total Budget Changes
15468000.00
Forecast Completion
2024-08-21T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
684
Alley Pond Environmental Center Reconstruction
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1017 • Project Name: Alley Pond Environmental Center Reconstruction
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1017
Project Name
Alley Pond Environmental Center Reconstruction
Description
This project will demolish and construct a new environmental center in Alley Pond Park.
Category
Parks
Managing Agency
DPR
Client Agency
DPR
Current Phase
Construction
Design Start
2010-02-24T00:00:00.000
Budget Forecast
31987000.00
Latest Budget Changes
0.00
Total Budget Changes
1641000.00
Forecast Completion
2022-07-29T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
556
Revenue Cycle Implementation
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 723 • Project Name: Revenue Cycle Implementation
Date Reported As Of
2022-04-01T00:00:00.000
Pid
723
Project Name
Revenue Cycle Implementation
Description
The Epic Revenue Cycle system will be enterprise-wide and help increase revenue (by proper billing of services provided) in addition to ensuring patient safety and improved patient care, a top priority in workflows.
Category
Health and Hospitals, IT
Borough
Citywide
Managing Agency
HHC
Client Agency
H+H
Current Phase
IT
Budget Forecast
289117990.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2022-12-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1279
Fort Totten Infrastructure Upgrade
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1154 • Project Name: Fort Totten Infrastructure Upgrade
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1154
Project Name
Fort Totten Infrastructure Upgrade
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
FDNY
Current Phase
Design
Design Start
2021-05-06T00:00:00.000
Budget Forecast
57786000.00
Latest Budget Changes
0.00
Total Budget Changes
100000.00
Forecast Completion
2025-10-13T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
318
Queens IS at 47-10 Barnett Avenue Addition
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 967 • Project Name: Queens IS at 47-10 Barnett Avenue Addition
Date Reported As Of
2022-04-01T00:00:00.000
Pid
967
Project Name
Queens IS at 47-10 Barnett Avenue Addition
Description
NEW SCHOOL
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2018-07-02T00:00:00.000
Budget Forecast
95408495.00
Latest Budget Changes
0.00
Total Budget Changes
3206657.00
Forecast Completion
2023-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
365
Bronx Animal Care Center
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 893 • Project Name: Bronx Animal Care Center
Date Reported As Of
2022-04-01T00:00:00.000
Pid
893
Project Name
Bronx Animal Care Center
Description
Bronx Animal Care Center & Veterinary Clinic is a new 50,000 SF facility that will be housing admissions, adoptions, medical services, and boarding for approximately 70 dogs, 140 cats, 30 rabbits and 20 animals or other species. In addition to the animal housing, the Bronx Animal Care Center will include a wildlife area to rehabilitate wild birds, academic partnership for youth, and enhanced senior services. Site work will include yards to facilitate dog adoptions, covered exercise runs, courtyards, and parking for staff, visitors, and center vehicles, as well as site lighting and low maintenance planting throughout. The building and associated landscape are to achieve LEED Silver standards or higher.
Category
Health and Hospitals
Managing Agency
DDC
Client Agency
Health
Current Phase
Construction Procurement
Design Start
2019-06-20T00:00:00.000
Budget Forecast
92103000.00
Latest Budget Changes
250000.00
Total Budget Changes
24815617.00
Forecast Completion
2025-02-15T00:00:00.000
Latest Schedule Changes
32
Total Schedule Changes
110
12th Avenue Accessibility Improvements
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1158 • Project Name: 12th Avenue Accessibility Improvements
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1158
Project Name
12th Avenue Accessibility Improvements
Description
12TH AVENUE ACCESSIBILITY IMPROVEMENTS
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2020-03-02T00:00:00.000
Budget Forecast
109491000.00
Latest Budget Changes
51571000.00
Total Budget Changes
51571000.00
Forecast Completion
2027-01-06T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
-98
WATERMAIN REPLACEMENT IN ORIENTAL BLVD, BROOKLYN
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1165 • Project Name: WATERMAIN REPLACEMENT IN ORIENTAL BLVD, BROOKLYN
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1165
Project Name
WATERMAIN REPLACEMENT IN ORIENTAL BLVD, BROOKLYN
Description
WATERMAIN REPLACEMENT IN ORIENTAL BLVD, BROOKLYN
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction Procurement
Design Start
2017-02-15T00:00:00.000
Budget Forecast
52382000.00
Latest Budget Changes
1498000.00
Total Budget Changes
3715000.00
Forecast Completion
2023-08-28T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
443
Brooklyn Bridge - Approach Arches Rehabilitation
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 584 • Project Name: Brooklyn Bridge - Approach Arches Rehabilitation
Date Reported As Of
2022-04-01T00:00:00.000
Pid
584
Project Name
Brooklyn Bridge - Approach Arches Rehabilitation
Description
Rehabilitate approach arches and towers of Brooklyn Bridge. Including masonry cleaning, masonry repairs, repointing, rehabilition of transverse walls, new infill walls of the approach arch blocks. Clean and repoint the tower masonry, reinforce the gothic arches of the towers, and rehabilitate the tower tops.
Category
Bridges
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2016-04-13T00:00:00.000
Budget Forecast
347633300.00
Latest Budget Changes
127724000.00
Total Budget Changes
33135732.10
Forecast Completion
2024-02-20T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1908
4Th Ave. Safety Improvements Phase II-Vision Zero
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 833 • Project Name: 4Th Ave. Safety Improvements Phase II-Vision Zero
Date Reported As Of
2022-04-01T00:00:00.000
Pid
833
Project Name
4Th Ave. Safety Improvements Phase II-Vision Zero
Description
4TH AVENUE SAFETY IMPROVEMENTS PHASE II - VISION ZERO GREAT STREETS
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction
Design Start
2017-06-01T00:00:00.000
Budget Forecast
62857000.00
Latest Budget Changes
1000000.00
Total Budget Changes
-11525000.00
Forecast Completion
2024-06-17T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1106
Freshkills South Park Synthetic Turf Fields and Landscape Construction
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1016 • Project Name: Freshkills South Park Synthetic Turf Fields and Landscape Construction
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1016
Project Name
Freshkills South Park Synthetic Turf Fields and Landscape Construction
Description
This project will construct synthetic turf athletic fields, roadways, a parking lot with associated landscaping and stormwater management, multi-use and pedestrian paths, benches, signage, fencing, and lighting, and restore woodlands and wetlands.
Category
Parks
Managing Agency
DPR
Client Agency
DPR
Current Phase
Design
Design Start
2016-11-30T00:00:00.000
Budget Forecast
39111000.00
Latest Budget Changes
0.00
Total Budget Changes
1436858.72
Forecast Completion
2025-05-17T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1309
Park Avenue Tunnel (Murray Hill)
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 536 • Project Name: Park Avenue Tunnel (Murray Hill)
Date Reported As Of
2022-04-01T00:00:00.000
Pid
536
Project Name
Park Avenue Tunnel (Murray Hill)
Description
Repair Park Avenue tunnel, located in Midtown, Manhattan.
Category
Bridges
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2006-08-01T00:00:00.000
Budget Forecast
46396271.00
Latest Budget Changes
-6440696.00
Total Budget Changes
-17773389.61
Forecast Completion
2022-08-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1568
Gilboa Dam Reconstruction, Phase III
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 405 • Project Name: Gilboa Dam Reconstruction, Phase III
Date Reported As Of
2022-04-01T00:00:00.000
Pid
405
Project Name
Gilboa Dam Reconstruction, Phase III
Description
Gilboa Dam Reconstruction Project includes construction of a new low level outlet (LLO) consisting of 2,000 feet of tunneling , an access shaft, oulet structure and gate valve controls.
Category
Water Supply
Borough
Upstate
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2004-03-18T00:00:00.000
Budget Forecast
199070771.81
Latest Budget Changes
0.00
Total Budget Changes
10376533.49
Forecast Completion
2022-12-12T00:00:00.000
Latest Schedule Changes
72
Total Schedule Changes
1113
Reconstruction of Beach Channel Drive -- Phase B
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1151 • Project Name: Reconstruction of Beach Channel Drive -- Phase B
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1151
Project Name
Reconstruction of Beach Channel Drive -- Phase B
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2021-04-15T00:00:00.000
Budget Forecast
42592000.00
Latest Budget Changes
82000.00
Total Budget Changes
642000.00
Forecast Completion
2028-09-01T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
0
Hillview Reservoir Flow Control Improvements
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 670 • Project Name: Hillview Reservoir Flow Control Improvements
Date Reported As Of
2022-04-01T00:00:00.000
Pid
670
Project Name
Hillview Reservoir Flow Control Improvements
Description
This project provides improvements to the existing structures and mechanical flow control systems at Hillview Reservoir.
Category
Water Supply
Borough
City of Yonkers
Managing Agency
DEP
Client Agency
BWS
Current Phase
Design
Design Start
2020-04-13T00:00:00.000
Budget Forecast
318659349.82
Latest Budget Changes
-11800.00
Total Budget Changes
-11397050.18
Forecast Completion
2033-01-02T00:00:00.000
Latest Schedule Changes
211
Total Schedule Changes
254
Riverside Drive/West 158th Street Bridge Rehabilitation
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 113 • Project Name: Riverside Drive/West 158th Street Bridge Rehabilitation
Date Reported As Of
2022-04-01T00:00:00.000
Pid
113
Project Name
Riverside Drive/West 158th Street Bridge Rehabilitation
Description
Replace deck of the Riverside Drive viaduct/ bridge over West 158th Street.
Category
Bridges, Streets and Roadways
Borough
Manhattan
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2014-10-22T00:00:00.000
Budget Forecast
153137026.00
Latest Budget Changes
8229000.00
Total Budget Changes
96922794.00
Forecast Completion
2023-07-15T00:00:00.000
Latest Schedule Changes
-90
Total Schedule Changes
2152
Wyckoff Avenue Street Reconstruction
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 191 • Project Name: Wyckoff Avenue Street Reconstruction
Date Reported As Of
2022-04-01T00:00:00.000
Pid
191
Project Name
Wyckoff Avenue Street Reconstruction
Description
Reconstruction of Wyckoff Avenue from Flushing Avenue to Cooper Avenue, in the Boroughs of Brooklyn and Queens..
Category
Streets and Roadways
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Trans. & Env. Protection
Current Phase
Design
Design Start
2017-03-29T00:00:00.000
Budget Forecast
76517000.00
Latest Budget Changes
2525000.00
Total Budget Changes
43926000.00
Forecast Completion
2028-03-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
226
Henry Hudson Parkway over Amtrak (Northbound)
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 592 • Project Name: Henry Hudson Parkway over Amtrak (Northbound)
Date Reported As Of
2022-04-01T00:00:00.000
Pid
592
Project Name
Henry Hudson Parkway over Amtrak (Northbound)
Description
Replace the Ramp to northbound Henry Hudson Parkway over Amtrak in Manhattan.
Category
Bridges
Borough
Manhattan
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2020-01-02T00:00:00.000
Budget Forecast
53551625.00
Latest Budget Changes
-500000.00
Total Budget Changes
500625.00
Forecast Completion
2029-07-01T00:00:00.000
Latest Schedule Changes
45
Total Schedule Changes
1693
RECONSTRUCTION OF QUEENS BLVD - PHASE 3
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1152 • Project Name: RECONSTRUCTION OF QUEENS BLVD - PHASE 3
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1152
Project Name
RECONSTRUCTION OF QUEENS BLVD - PHASE 3
Description
Vision Zero - Queens Boulevard - Segment 3: Eliot Avenue to Yellowstone Boulevard. Variety of safety and streetscape improvements including partial street reconstruction and resurfacing to address roadway conditions.
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2018-04-26T00:00:00.000
Budget Forecast
99344000.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Total Schedule Changes
0
EMS Station 17 - New Facility
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1153 • Project Name: EMS Station 17 - New Facility
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1153
Project Name
EMS Station 17 - New Facility
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
Fire
Current Phase
Design
Design Start
2019-01-18T00:00:00.000
Budget Forecast
43914000.00
Latest Budget Changes
12388000.00
Total Budget Changes
13113000.00
Forecast Completion
2024-08-19T00:00:00.000
Latest Schedule Changes
72
Total Schedule Changes
434
New Westchester Square
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1147 • Project Name: New Westchester Square
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1147
Project Name
New Westchester Square
Description
DDC Constructability comments anticipated by 5/31/17. Anticipated Construction Budget shortfall of $600k. Funding required to submit initial Construction CP.
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
Libraries-NYPL
Current Phase
Construction Procurement
Design Start
2013-05-13T00:00:00.000
Budget Forecast
36429630.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2026-02-28T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
471
Tompkinsville Esplanade
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 963 • Project Name: Tompkinsville Esplanade
Date Reported As Of
2022-04-01T00:00:00.000
Pid
963
Project Name
Tompkinsville Esplanade
Description
Esplanade from Stapleton to the Lighthouse Museum and Pier for DOT Dockbuilders.
Category
Parks
Managing Agency
EDC
Client Agency
EDC
Current Phase
Design
Design Start
2019-07-01T00:00:00.000
Budget Forecast
161572069.00
Latest Budget Changes
10000000.00
Total Budget Changes
10582596.00
Forecast Completion
2025-10-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
944
Grant Park Construction
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1015 • Project Name: Grant Park Construction
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1015
Project Name
Grant Park Construction
Description
This project will construct Grant Park, including converting the roadbed to recreational space.
Category
Parks
Managing Agency
DPR
Client Agency
DPR
Current Phase
Construction Procurement
Design Start
2019-05-29T00:00:00.000
Budget Forecast
32590000.00
Latest Budget Changes
0.00
Total Budget Changes
1489000.00
Forecast Completion
2025-01-27T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
612
Network Infrastructure Refresh Program
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 863 • Project Name: Network Infrastructure Refresh Program
Date Reported As Of
2022-04-01T00:00:00.000
Pid
863
Project Name
Network Infrastructure Refresh Program
Description
This project has a two-fold basis: 1) The ongoing Network Refresh which is needed to replace aging, end-of-life, end-of-support equipment across the NYC H+H. 2) Networking capacity needed to support the Electronic Medical Records system.
Category
Health and Hospitals, IT
Managing Agency
HHC
Client Agency
H+H
Current Phase
IT
Budget Forecast
0.00
Latest Budget Changes
0.00
Total Budget Changes
180514000.00
New Stapleton Waterfront: Phases 2 and 3
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 962 • Project Name: New Stapleton Waterfront: Phases 2 and 3
Date Reported As Of
2022-04-01T00:00:00.000
Pid
962
Project Name
New Stapleton Waterfront: Phases 2 and 3
Description
Mixed-use residential community on Staten Island's North Shore.
Category
Industrial Development
Managing Agency
EDC
Client Agency
EDC
Current Phase
Design
Design Start
2015-09-30T00:00:00.000
Budget Forecast
199142346.00
Latest Budget Changes
13852532.00
Total Budget Changes
100733778.00
Forecast Completion
2026-12-02T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
913
Croton Above Ground Structure And Landscaping
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 747 • Project Name: Croton Above Ground Structure And Landscaping
Date Reported As Of
2022-04-01T00:00:00.000
Pid
747
Project Name
Croton Above Ground Structure And Landscaping
Description
The new Mosholu Golf Course Club House, together with fifty-five Driving Range Tee Boxes and ten-acres of re-landscaping comprise the phase IV and final of the vast DEP Croton Water Treatment Plant project, currently under construction in Van Cortlandt Park in the Bronx. Through a multifunctional design strategy the project reinstates the pre-existing golf program and facility, creates civic space for community use and ensures security for a multi-billion dollar public works facility.
Category
Industrial Development
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2012-05-23T00:00:00.000
Budget Forecast
132780000.00
Latest Budget Changes
25336000.00
Total Budget Changes
75117000.00
Forecast Completion
2023-02-23T00:00:00.000
Latest Schedule Changes
22
Total Schedule Changes
897
Electronic Medical Records Upgrade
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 403 • Project Name: Electronic Medical Records Upgrade
Date Reported As Of
2022-04-01T00:00:00.000
Pid
403
Project Name
Electronic Medical Records Upgrade
Description
The EPIC - EMR Program: Electronic Medical Records (EMR) System - a single enterprise-wide EMR to meet the needs of HHC's expansive size and improve patient care will replace the legacy EMR - QuadraMed, which is over 25 years old.
Category
Health and Hospitals, IT
Borough
Citywide
Managing Agency
HHC
Client Agency
H+H
Current Phase
IT
Budget Forecast
764063231.00
Latest Budget Changes
0.00
Total Budget Changes
15184947.00
Forecast Completion
2022-12-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2032
NYCF Homeport 2
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1022 • Project Name: NYCF Homeport 2
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1022
Project Name
NYCF Homeport 2
Description
Development, design, and construction of NYC Ferry Homeport II within Atlantic Basin.
Category
Ferries
Managing Agency
EDC
Client Agency
EDC
Current Phase
Construction Procurement
Design Start
2020-02-01T00:00:00.000
Budget Forecast
116220834.00
Latest Budget Changes
51220834.00
Total Budget Changes
51220834.00
Forecast Completion
2024-09-29T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
153
SAFE ROUTES TO SCHOOL MANHATTAN
Date Reported As Of: 2022-04-01T00:00:00.000 • Pid: 1181 • Project Name: SAFE ROUTES TO SCHOOL MANHATTAN
Date Reported As Of
2022-04-01T00:00:00.000
Pid
1181
Project Name
SAFE ROUTES TO SCHOOL MANHATTAN
Description
SAFE ROUTES TO SCHOOLS - MANHATTAN
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2018-06-25T00:00:00.000
Budget Forecast
45246000.00
Latest Budget Changes
400000.00
Total Budget Changes
7175000.00
Forecast Completion
2025-07-09T00:00:00.000
Latest Schedule Changes
76
Total Schedule Changes
505