Capital Projects

All major infrastructure and information technology projects with a budget of $25 million or more that are currently active (in the design, procurement, or construction phase).

City Government Mayor's Office of Operations (OPS) Dataset n7gv-k5yt 16 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
TRAVIS AVENUE WIDENING
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 1240 • Project Name: TRAVIS AVENUE WIDENING
Date Reported As Of
2021-12-01T00:00:00.000
Pid
1240
Project Name
TRAVIS AVENUE WIDENING
Description
TRAVIS AVENUE WIDENING
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2015-01-15T00:00:00.000
Budget Forecast
85587000.00
Total Budget Changes
50000.00
Forecast Completion
2024-12-27T00:00:00.000
Total Schedule Changes
1029
New 116Th Pct
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 762 • Project Name: New 116Th Pct
Date Reported As Of
2021-12-01T00:00:00.000
Pid
762
Project Name
New 116Th Pct
Description
Construction of a new precinct station house facility and associated site work for the new 116th Precinct.
Category
Public Safety and Criminal Justice
Managing Agency
DDC
Client Agency
Police
Current Phase
Construction
Design Start
2017-09-14T00:00:00.000
Budget Forecast
110640000.00
Latest Budget Changes
0.00
Total Budget Changes
33852900.86
Forecast Completion
2023-12-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
727
City Tunnel No.3, Stage 2 in Queens and Brooklyn, Construction of Shaft 17B and 18B
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 1042 • Category: Water Supply
Date Reported As Of
2021-12-01T00:00:00.000
Pid
1042
Project Name
City Tunnel No.3, Stage 2 in Queens and Brooklyn, Construction of Shaft 17B and 18B
Description
Contract C547A is for the construction of two shafts (17B-1 and 18B-1) on City Tunnel No. 3 (CT3), Stage 2 in Queens and Brooklyn
Category
Water Supply
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2019-01-30T00:00:00.000
Budget Forecast
438180571.59
Latest Budget Changes
-3583488.46
Total Budget Changes
3150108.42
Forecast Completion
2027-01-24T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
119
Brooklyn Civil Court move to 210 Joralemon St
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 509 • Project Name: Brooklyn Civil Court move to 210 Joralemon St
Date Reported As Of
2021-12-01T00:00:00.000
Pid
509
Project Name
Brooklyn Civil Court move to 210 Joralemon St
Description
Relocation of Brooklyn Civil and Housing Court to 210 Joralemon St
Category
Public Safety and Criminal Justice
Borough
Brooklyn
Managing Agency
DCAS
Client Agency
DCAS
Current Phase
Construction
Design Start
2016-07-27T00:00:00.000
Budget Forecast
254101000.00
Latest Budget Changes
2658000.00
Total Budget Changes
200931011.96
Forecast Completion
2025-01-03T00:00:00.000
Latest Schedule Changes
-28
Total Schedule Changes
1977
FUEL TANK REPLACEMENT
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 851 • Project Name: FUEL TANK REPLACEMENT
Date Reported As Of
2021-12-01T00:00:00.000
Pid
851
Project Name
FUEL TANK REPLACEMENT
Description
The scope of work consists of providing all necessary construction management, design, and r.onstruction services required to perform ail phases of the project: Surveying, tank testing, investigation, design, construction, and construction management for the closure, removal, upgrade, or replacement of petroieum product storage tanks at various City owned sites. This work must comply with all local, state, nnd federal laws nnd regulations governing tanks and associated work. The general scope of work for tank replacement includes: File NYSDEC PBS application; mobilization; securing all required NYC agency approvals & permits; site survey; geophysical survey; drilling for laboratory soil and groundwater samples; crane & rigging; saw cutting; demo & disposal of old tanks, piping, and concrete vaults; dewatering· of excavation; tank bottom sludge removal & disposal; remove/transfer/dispose product; laboratory analysis of soil and groundwater; excavate, remove, dispose incidental contaminated soil; install shoring, new tanks and tan·k sumps, piping, monitoring and leak detection system, overfill protection and alarms, electrical wiring; construction of concrete slabs and block piers; backfill excavation; resurfacing; demobilization; performance of a closeout investigation and the preparation and filing of appropriate reports; obtaining FDNY and DOB closeout documents; preparing "As-built" drawings.
Category
Industrial Development
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Construction
Design Start
2017-10-30T00:00:00.000
Budget Forecast
31294000.00
Latest Budget Changes
200000.00
Total Budget Changes
207000.00
Forecast Completion
2025-04-14T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1278
Far Rockaway New Facility
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 730 • Project Name: Far Rockaway New Facility
Date Reported As Of
2021-12-01T00:00:00.000
Pid
730
Project Name
Far Rockaway New Facility
Description
Construction of a new 18,000 sq.ft. Branch employing the latest technology and sustainable design.
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
Libraries-QBPL
Current Phase
Construction
Design Start
2012-01-10T00:00:00.000
Budget Forecast
39531557.09
Latest Budget Changes
1.09
Total Budget Changes
-623757.91
Forecast Completion
2022-05-16T00:00:00.000
Latest Schedule Changes
138
Total Schedule Changes
-78
Union Turnpike over Cross Island Parkway
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 932 • Project Name: Union Turnpike over Cross Island Parkway
Date Reported As Of
2021-12-01T00:00:00.000
Pid
932
Project Name
Union Turnpike over Cross Island Parkway
Description
Rehabilitation of Union Turnpike Bridge over Cross Island Parkway
Category
Bridges
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2019-09-06T00:00:00.000
Budget Forecast
67281778.00
Latest Budget Changes
900000.00
Total Budget Changes
3378281.00
Forecast Completion
2028-12-02T00:00:00.000
Latest Schedule Changes
90
Total Schedule Changes
834
80 CENTRE ST.- FIRE ALARMS/SPRINKLERS
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 1174 • Project Name: 80 CENTRE ST.- FIRE ALARMS/SPRINKLERS
Date Reported As Of
2021-12-01T00:00:00.000
Pid
1174
Project Name
80 CENTRE ST.- FIRE ALARMS/SPRINKLERS
Description
Fire Alarm and Sprinklers Upgrade
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Design
Design Start
2021-07-26T00:00:00.000
Budget Forecast
44469000.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2026-03-23T00:00:00.000
Total Schedule Changes
340
CITYWIDE RESILENCY MEASURES-Lower Manhattan Two Bridges
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 1187 • Project Name: CITYWIDE RESILENCY MEASURES-Lower Manhattan Two Bridges
Date Reported As Of
2021-12-01T00:00:00.000
Pid
1187
Project Name
CITYWIDE RESILENCY MEASURES-Lower Manhattan Two Bridges
Description
Installation of Brooklyn Bridge - Montgomery Coastal Resilience from Robert F. Wagner Sr. Place to Montgomery Street
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Mayors Office of Resiliency (MOR)
Current Phase
Construction Procurement
Design Start
2019-02-22T00:00:00.000
Budget Forecast
528495000.00
Latest Budget Changes
28668000.00
Total Budget Changes
34901000.00
Forecast Completion
2026-05-14T00:00:00.000
Total Schedule Changes
161
Pelham Parkway Bridge Reconstruction over Hutchinson Parkway
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 506 • Project Name: Pelham Parkway Bridge Reconstruction over Hutchinson Parkway
Date Reported As Of
2021-12-01T00:00:00.000
Pid
506
Project Name
Pelham Parkway Bridge Reconstruction over Hutchinson Parkway
Description
Replace/Rehab the Pelham Parkway bridge over Hutchinson River Parkway, Bronx.
Category
Bridges, Streets and Roadways
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-11-08T00:00:00.000
Budget Forecast
59687530.00
Latest Budget Changes
539052.00
Total Budget Changes
10338071.57
Forecast Completion
2028-01-12T00:00:00.000
Latest Schedule Changes
-24
Total Schedule Changes
1934
Next Generation 911 Program
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 1035 • Project Name: Next Generation 911 Program
Date Reported As Of
2021-12-01T00:00:00.000
Pid
1035
Project Name
Next Generation 911 Program
Description
The goal of this program is to replace the current end of life analog system with an Emergency Response System that meets the latest Public Safety standards and regulations in compliance with NENA standards.
Category
IT, Public Safety and Criminal Justice
Managing Agency
DOITT
Client Agency
NYPD & FDNY
Current Phase
IT
Budget Forecast
279671960.27
Latest Budget Changes
17601708.57
Total Budget Changes
30123504.48
Forecast Completion
2024-12-31T00:00:00.000
Latest Schedule Changes
1558
Total Schedule Changes
1558
Coastal Resiliency – Project Area 2
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 1170 • Project Name: Coastal Resiliency – Project Area 2
Date Reported As Of
2021-12-01T00:00:00.000
Pid
1170
Project Name
Coastal Resiliency – Project Area 2
Description
INSTALLATION OF EAST SIDE COASTAL RESILIENCY (ESCR) PROJECT AREA 2 FROM EAST 15TH STREET TO EAST 25TH STREET
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Parks & Recreation
Current Phase
Construction
Design Start
2016-04-27T00:00:00.000
Budget Forecast
223136000.00
Latest Budget Changes
6239000.00
Total Budget Changes
448000.00
Forecast Completion
2024-10-13T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
0
Raise Shorelines Citywide
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 689 • Project Name: Raise Shorelines Citywide
Date Reported As Of
2021-12-01T00:00:00.000
Pid
689
Project Name
Raise Shorelines Citywide
Description
The design and construction of shoreline reconstruction projects necessary to provide Citywide protection from future flooding caused by elevated seal elvels.
Category
Industrial Development
Borough
Citywide
Managing Agency
EDC
Client Agency
ORR
Current Phase
Design
Design Start
2017-08-01T00:00:00.000
Budget Forecast
60422410.00
Latest Budget Changes
-28730516.86
Total Budget Changes
0.00
Forecast Completion
2023-06-30T00:00:00.000
Latest Schedule Changes
181
Total Schedule Changes
639
Hannah Street Pumping Station Construction
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 364 • Project Name: Hannah Street Pumping Station Construction
Date Reported As Of
2021-12-01T00:00:00.000
Pid
364
Project Name
Hannah Street Pumping Station Construction
Description
This project will reconstruct the Hannah St. Pumping Station, the largest City-owned wastewater collection and pumping station on Staten Island. Built in 1977, the facility has numerous deficiencies, needing a comprehensive upgrade.
Category
Wastewater Treatment
Borough
Staten Island
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2012-10-01T00:00:00.000
Budget Forecast
102992162.23
Latest Budget Changes
0.00
Total Budget Changes
67909196.80
Forecast Completion
2024-06-05T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
3238
150Th St Spine Phase 1 Storm Sewer At Bergen Basin
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 791 • Project Name: 150Th St Spine Phase 1 Storm Sewer At Bergen Basin
Date Reported As Of
2021-12-01T00:00:00.000
Pid
791
Project Name
150Th St Spine Phase 1 Storm Sewer At Bergen Basin
Description
SOUTHEAST QUEENS 150TH STREET SPINE, PHASE 1. TRUNK STORM SEWER AND OUTFALL AT BERGEN BASIN FOR THE 150TH STREET TRUNK SEWER WHICH SHARES AN OUTFALL WITH THE GUY R BREWER TRUNK SEWER
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2019-07-23T00:00:00.000
Budget Forecast
142511000.00
Latest Budget Changes
-290000.00
Total Budget Changes
101452000.00
Forecast Completion
2025-11-03T00:00:00.000
Latest Schedule Changes
126
Total Schedule Changes
753
Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 112 • Project Name: Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Date Reported As Of
2021-12-01T00:00:00.000
Pid
112
Project Name
Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Description
Repair abutments, piers, approaches, and steel superstructure located in Pelham Bay, Bronx; replace reinforced concrete deck.
Category
Bridges, Streets and Roadways
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
1995-01-17T00:00:00.000
Budget Forecast
88676271.00
Latest Budget Changes
6504821.00
Total Budget Changes
20945057.00
Forecast Completion
2022-07-23T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1592
HIGH LEVEL STM SEWERS IN GOWANUS CANAL AREA-PH II
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 849 • Project Name: HIGH LEVEL STM SEWERS IN GOWANUS CANAL AREA-PH II
Date Reported As Of
2021-12-01T00:00:00.000
Pid
849
Project Name
HIGH LEVEL STM SEWERS IN GOWANUS CANAL AREA-PH II
Description
High Level Storm and Combine Sewer installation and Water Main replacement in Gowanus Canal Area Phase-2, Brooklyn.
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2016-09-30T00:00:00.000
Budget Forecast
40701000.00
Latest Budget Changes
687000.00
Total Budget Changes
8657000.00
Forecast Completion
2022-04-27T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
813
5th Avenue Bridge Reconstruction over LIRR and Sea Beach, Brooklyn
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 504 • Project Name: 5th Avenue Bridge Reconstruction over LIRR and Sea Beach, Brooklyn
Date Reported As Of
2021-12-01T00:00:00.000
Pid
504
Project Name
5th Avenue Bridge Reconstruction over LIRR and Sea Beach, Brooklyn
Description
Replace the 5th Avenue Bridge over LIRR & Sea Beach, Brooklyn.
Category
Bridges
Borough
Brooklyn
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-11-30T00:00:00.000
Budget Forecast
74525379.00
Latest Budget Changes
-460001.00
Total Budget Changes
36577693.00
Forecast Completion
2027-12-03T00:00:00.000
Latest Schedule Changes
211
Total Schedule Changes
969
Headworks Improvements at Tallman Island
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 906 • Project Name: Headworks Improvements at Tallman Island
Date Reported As Of
2021-12-01T00:00:00.000
Pid
906
Project Name
Headworks Improvements at Tallman Island
Description
Headworks Improvements
Category
Industrial Development
Managing Agency
DEP
Client Agency
WWC
Current Phase
Design
Design Start
2019-07-07T00:00:00.000
Budget Forecast
52030751.00
Latest Budget Changes
4575000.00
Total Budget Changes
19975649.96
Forecast Completion
2026-11-05T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
586
Coastal Resiliency Area 1 - East 23rd St. to Montg
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 1169 • Project Name: Coastal Resiliency Area 1 - East 23rd St. to Montg
Date Reported As Of
2021-12-01T00:00:00.000
Pid
1169
Project Name
Coastal Resiliency Area 1 - East 23rd St. to Montg
Description
East Side Coastal Resiliency - Montgomery Street to East 15th Street, Manhattan
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Parks & Recreation
Current Phase
Construction Procurement
Design Start
2016-04-27T00:00:00.000
Budget Forecast
1328351541.76
Latest Budget Changes
0.76
Total Budget Changes
0.76
Michaelis-Bayswater Park Reconstruction
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 1032 • Project Name: Michaelis-Bayswater Park Reconstruction
Date Reported As Of
2021-12-01T00:00:00.000
Pid
1032
Project Name
Michaelis-Bayswater Park Reconstruction
Description
This project will reconstruct Michaelis-Bayswater Park.
Category
Parks
Managing Agency
DPR
Client Agency
DPR
Current Phase
Design
Design Start
2018-10-29T00:00:00.000
Budget Forecast
57346000.00
Latest Budget Changes
4640069.66
Total Budget Changes
4849393.61
Forecast Completion
2025-03-23T00:00:00.000
Total Schedule Changes
280
Throgs Neck Pumping Station Rehabilitation and Improvements
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 722 • Project Name: Throgs Neck Pumping Station Rehabilitation and Improvements
Date Reported As Of
2021-12-01T00:00:00.000
Pid
722
Project Name
Throgs Neck Pumping Station Rehabilitation and Improvements
Description
Throgs Neck Pumping Station Rehabilitation and Improvements
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction Procurement
Design Start
2018-06-30T00:00:00.000
Budget Forecast
67399887.19
Latest Budget Changes
1524779.00
Total Budget Changes
25708336.86
Forecast Completion
2024-07-25T00:00:00.000
Latest Schedule Changes
63
Total Schedule Changes
1306
Coastal Resiliency -- Parallel Conveyances
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 1171 • Project Name: Coastal Resiliency -- Parallel Conveyances
Date Reported As Of
2021-12-01T00:00:00.000
Pid
1171
Project Name
Coastal Resiliency -- Parallel Conveyances
Description
Coastal Resiliency -- Parallel Conveyances
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Parks & Recreation
Current Phase
Construction Procurement
Design Start
2016-04-27T00:00:00.000
Budget Forecast
167831000.00
Latest Budget Changes
52000.00
Total Budget Changes
32327000.00
Forecast Completion
2026-06-11T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
92
West Tremont Avenue over Metro North Railroad
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 503 • Project Name: West Tremont Avenue over Metro North Railroad
Date Reported As Of
2021-12-01T00:00:00.000
Pid
503
Project Name
West Tremont Avenue over Metro North Railroad
Description
Replace/Rehab the West Tremont Avenue bridge over the Metro North line, located in the Bronx.
Category
Bridges
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2018-01-16T00:00:00.000
Budget Forecast
85056088.00
Latest Budget Changes
-59999.00
Total Budget Changes
37794543.00
Forecast Completion
2026-11-11T00:00:00.000
Latest Schedule Changes
146
Total Schedule Changes
1253
Lower Manhattan Coastal Resiliency (LMCR): Battery
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 1223 • Project Name: Lower Manhattan Coastal Resiliency (LMCR): Battery
Date Reported As Of
2021-12-01T00:00:00.000
Pid
1223
Project Name
Lower Manhattan Coastal Resiliency (LMCR): Battery
Description
Implementation of coastal resiliency measures to protect Battery Park and adjacent upland neighborhoods from storm surges and sea level rise.
Category
Parks
Managing Agency
EDC
Client Agency
City Hall
Current Phase
Design
Design Start
2020-12-01T00:00:00.000
Budget Forecast
165700000.00
Total Budget Changes
0.00
Forecast Completion
2025-04-30T00:00:00.000
Total Schedule Changes
-29
SOUTHEAST QUEENS PRIORITY GRIDS - GROUP 2
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 847 • Project Name: SOUTHEAST QUEENS PRIORITY GRIDS - GROUP 2
Date Reported As Of
2021-12-01T00:00:00.000
Pid
847
Project Name
SOUTHEAST QUEENS PRIORITY GRIDS - GROUP 2
Description
SOUTHEAST QUEENS PRIORITY GRIDS - GROUP 2
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2018-10-09T00:00:00.000
Budget Forecast
32453000.00
Latest Budget Changes
-10000.00
Total Budget Changes
14480000.00
Forecast Completion
2028-02-29T00:00:00.000
Latest Schedule Changes
-366
Total Schedule Changes
1630
Replacement of The Digester at The Hunts Point WWTP
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 580 • Project Name: Replacement of The Digester at The Hunts Point WWTP
Date Reported As Of
2021-12-01T00:00:00.000
Pid
580
Project Name
Replacement of The Digester at The Hunts Point WWTP
Description
Construction of New Anaerobic Digesters
Category
Wastewater Treatment
Borough
Bronx
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction Procurement
Design Start
2017-10-22T00:00:00.000
Budget Forecast
458653902.00
Latest Budget Changes
0.00
Total Budget Changes
72852004.14
Forecast Completion
2026-01-07T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1355
Bergen Avenue Street Reconstruction
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 170 • Project Name: Bergen Avenue Street Reconstruction
Date Reported As Of
2021-12-01T00:00:00.000
Pid
170
Project Name
Bergen Avenue Street Reconstruction
Description
Reconstruction of Bergen Avenue Area, including Storm Sewers, Water Mains, Street Lighting, Traffic Signal Work, and reconstruction of new outfall at East Mill Basin.
Category
Streets and Roadways
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction
Design Start
2012-12-03T00:00:00.000
Budget Forecast
81502000.00
Latest Budget Changes
-435000.00
Total Budget Changes
45837000.00
Forecast Completion
2023-06-24T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
-388
FUEL TANK & SUMP REPLACEMENTS - BRONX
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 901 • Project Name: FUEL TANK & SUMP REPLACEMENTS - BRONX
Date Reported As Of
2021-12-01T00:00:00.000
Pid
901
Project Name
FUEL TANK & SUMP REPLACEMENTS - BRONX
Description
CITYWIDE FUEL TANK REPLACEMENT PROGRAM FOR NEW 2015 EPA PETROLEUM BULK STORAGE REGULATIONS
Category
Industrial Development
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Construction
Design Start
2019-08-20T00:00:00.000
Budget Forecast
25316000.00
Latest Budget Changes
0.00
Total Budget Changes
-1834000.00
Forecast Completion
2025-01-22T00:00:00.000
Latest Schedule Changes
20
Total Schedule Changes
663
Metropolitan Hospital Perimeter Flood Protection
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 562 • Project Name: Metropolitan Hospital Perimeter Flood Protection
Date Reported As Of
2021-12-01T00:00:00.000
Pid
562
Project Name
Metropolitan Hospital Perimeter Flood Protection
Description
Flood mitigation system to protect Metropolitan's campus from future flooding due and sea level rise
Category
Industrial Development
Borough
Manhattan
Managing Agency
EDC
Client Agency
H+H
Current Phase
Construction Procurement
Design Start
2016-12-01T00:00:00.000
Budget Forecast
111118294.00
Latest Budget Changes
9286435.00
Total Budget Changes
27046705.00
Forecast Completion
2027-04-02T00:00:00.000
Latest Schedule Changes
-127
Total Schedule Changes
1452
Flushing Meadows Corona Park World's Fair Marina Reconstruction (Hurricane Sandy)
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 1031 • Category: Parks
Date Reported As Of
2021-12-01T00:00:00.000
Pid
1031
Project Name
Flushing Meadows Corona Park World's Fair Marina Reconstruction (Hurricane Sandy)
Description
This project will reconstruct the deteriorated fixed piers, floating docks, bulkhead, and related components, including Sandy-damaged elements.
Category
Parks
Managing Agency
DPR
Client Agency
DPR
Current Phase
Design
Design Start
2017-08-15T00:00:00.000
Budget Forecast
48487000.00
Latest Budget Changes
0.00
Total Budget Changes
4947362.68
Forecast Completion
2025-03-23T00:00:00.000
Latest Schedule Changes
147
Total Schedule Changes
708
Queens Botanical Garden Educ Bldg Renovation
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 1167 • Project Name: Queens Botanical Garden Educ Bldg Renovation
Date Reported As Of
2021-12-01T00:00:00.000
Pid
1167
Project Name
Queens Botanical Garden Educ Bldg Renovation
Description
New education building at Queens Botanical Garden (QBG). Design and construction of a new 14,500 SF building to provide year-round programming and educational spaces to serve students, children, community gardeners, and others. The New Education Building will add six new teaching spaces, including four classrooms, a teaching kitchen and a teaching greenhouse where educators will be able to grow and maintain plants for educational purposes. Ideally, the four regular classrooms will be able to opened up into one large space to accommodate larger training programs.
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
Cultural Affairs
Current Phase
Design
Design Start
2019-06-18T00:00:00.000
Budget Forecast
28686000.00
Latest Budget Changes
0.00
Total Budget Changes
905000.00
Forecast Completion
2025-04-11T00:00:00.000
Latest Schedule Changes
154
Total Schedule Changes
357
FDR Rehabilitation, Northbound (East 42nd to 49th Streets)
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 502 • Project Name: FDR Rehabilitation, Northbound (East 42nd to 49th Streets)
Date Reported As Of
2021-12-01T00:00:00.000
Pid
502
Project Name
FDR Rehabilitation, Northbound (East 42nd to 49th Streets)
Description
Repair the northbound FDR from East 42nd to 49th Streets.
Category
Bridges
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2016-08-30T00:00:00.000
Budget Forecast
63030178.00
Latest Budget Changes
-36000000.00
Total Budget Changes
-2802822.00
Forecast Completion
2029-02-12T00:00:00.000
Latest Schedule Changes
30
Total Schedule Changes
1816
P.S./I.S. @ 3761 10TH AVENUE - Manhattan
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 1222 • Project Name: P.S./I.S. @ 3761 10TH AVENUE - Manhattan
Date Reported As Of
2021-12-01T00:00:00.000
Pid
1222
Project Name
P.S./I.S. @ 3761 10TH AVENUE - Manhattan
Description
NEW SCHOOL
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Design
Design Start
2021-03-24T00:00:00.000
Budget Forecast
133550326.00
Total Budget Changes
9539089.00
Forecast Completion
2024-09-03T00:00:00.000
Total Schedule Changes
0
WATERMAIN REPLACEMENT IN ORIENTAL BLVD, BROOKLYN
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 1165 • Project Name: WATERMAIN REPLACEMENT IN ORIENTAL BLVD, BROOKLYN
Date Reported As Of
2021-12-01T00:00:00.000
Pid
1165
Project Name
WATERMAIN REPLACEMENT IN ORIENTAL BLVD, BROOKLYN
Description
WATERMAIN REPLACEMENT IN ORIENTAL BLVD, BROOKLYN
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction Procurement
Design Start
2017-02-15T00:00:00.000
Budget Forecast
50884000.00
Latest Budget Changes
6952000.00
Total Budget Changes
3715000.00
Forecast Completion
2023-08-28T00:00:00.000
Latest Schedule Changes
57
Total Schedule Changes
443
Storm Sanitary Sewer Repl Springfield Gardens
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 790 • Project Name: Storm Sanitary Sewer Repl Springfield Gardens
Date Reported As Of
2021-12-01T00:00:00.000
Pid
790
Project Name
Storm Sanitary Sewer Repl Springfield Gardens
Description
SPRINGFIELD GARDENS RECONSTRUCTION PHASE 5; STORM AND SANITARY SEWER EXTENSIONS AND UPGRADES AND WATER MAIN REPLACEMENT IN 146TH AVENUE BETWEEN 153RD PLACE AND 159TH STREET, ETC, BOROUGH OF QUEENS (HWQ662G)
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2018-05-09T00:00:00.000
Budget Forecast
112247000.00
Latest Budget Changes
-1161000.00
Total Budget Changes
35414000.00
Forecast Completion
2026-03-25T00:00:00.000
Latest Schedule Changes
126
Total Schedule Changes
1097
STM & SAN SWR, N.B. WHITESTONE EXPWY SERV RD, PH 3
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 652 • Project Name: STM & SAN SWR, N.B. WHITESTONE EXPWY SERV RD, PH 3
Date Reported As Of
2021-12-01T00:00:00.000
Pid
652
Project Name
STM & SAN SWR, N.B. WHITESTONE EXPWY SERV RD, PH 3
Description
Installation of Storm sewers, Sanitary sewers, & Water mains in Whitestone Area-Phase 3
Category
Sewers
Borough
Queens
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2016-07-15T00:00:00.000
Budget Forecast
76591000.00
Latest Budget Changes
-306000.00
Total Budget Changes
15468000.00
Forecast Completion
2024-08-21T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
684
Construction Of Sanitary Sewers, Storm Sewers (Bm
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 760 • Project Name: Construction Of Sanitary Sewers, Storm Sewers (Bm
Date Reported As Of
2021-12-01T00:00:00.000
Pid
760
Project Name
Construction Of Sanitary Sewers, Storm Sewers (Bm
Description
Construction of storm sewers, sanitary sewers, water mains and Best Management Practice (BMP) NC-16 in Mason Avenue area, Borough of Staten Island.
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2016-08-29T00:00:00.000
Budget Forecast
61593000.00
Latest Budget Changes
-33000.00
Total Budget Changes
37691000.00
Forecast Completion
2023-06-26T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
595
DBCD South Site Cultural Fit-Out
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 484 • Project Name: DBCD South Site Cultural Fit-Out
Date Reported As Of
2021-12-01T00:00:00.000
Pid
484
Project Name
DBCD South Site Cultural Fit-Out
Description
Interior fit-out of the south site cultural unit.
Category
Arts and Culture
Borough
Brooklyn
Managing Agency
EDC
Client Agency
DCLA
Current Phase
Construction
Design Start
2014-12-01T00:00:00.000
Budget Forecast
51070000.00
Latest Budget Changes
0.00
Total Budget Changes
36789601.16
Forecast Completion
2022-12-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1706
West 59th Street Marine Transfer Station Construction, Phase 2
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 347 • Project Name: West 59th Street Marine Transfer Station Construction, Phase 2
Date Reported As Of
2021-12-01T00:00:00.000
Pid
347
Project Name
West 59th Street Marine Transfer Station Construction, Phase 2
Description
Project 2 Scope: Refurbishment of the existing pier building including: repair of existing pier structure including pile caps and fendering; construction of new emergency generator, electrical, mechanical, fire pump and fire valve rooms; new exit passageway construction and existing exit passageway refurbishment; re-arrangement and refurbishment of the Operations Building interiors; replacement of fire suppression system throughout the entire pier structure; mechanical, electrical and plumbing system upgrades; refurbishment and painting the existing pier interior steel framing and wall/roof surfaces; recoating the structure's exterior cladding systems including metal wall and roof panel system and translucent panel wall cladding system.
Category
Sanitation
Borough
Manhattan
Managing Agency
DDC
Client Agency
Sanitation
Current Phase
Construction
Design Start
2012-01-17T00:00:00.000
Budget Forecast
93915288.23
Latest Budget Changes
-93915288.23
Total Budget Changes
126753576.46
Forecast Completion
2022-02-28T00:00:00.000
Latest Schedule Changes
185
Total Schedule Changes
1949
12th Avenue Accessibility Improvements
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 1158 • Project Name: 12th Avenue Accessibility Improvements
Date Reported As Of
2021-12-01T00:00:00.000
Pid
1158
Project Name
12th Avenue Accessibility Improvements
Description
12TH AVENUE ACCESSIBILITY IMPROVEMENTS
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2020-03-02T00:00:00.000
Budget Forecast
57920000.00
Latest Budget Changes
0.00
Total Budget Changes
51571000.00
Forecast Completion
2027-01-06T00:00:00.000
Total Schedule Changes
-98
RECONST. OF COLUMBIA ST., PH II/BED-768B/SEK002321
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 845 • Project Name: RECONST. OF COLUMBIA ST., PH II/BED-768B/SEK002321
Date Reported As Of
2021-12-01T00:00:00.000
Pid
845
Project Name
RECONST. OF COLUMBIA ST., PH II/BED-768B/SEK002321
Description
Roadway reconstruction including new sewers, water main, street lighting and traffic signals: Columbia Street south of Hamilton Avenue.
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2019-07-01T00:00:00.000
Budget Forecast
116944000.00
Latest Budget Changes
280000.00
Total Budget Changes
6730000.00
Forecast Completion
2025-07-14T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
972
Queens Public School 169 Addition
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 1028 • Project Name: Queens Public School 169 Addition
Date Reported As Of
2021-12-01T00:00:00.000
Pid
1028
Project Name
Queens Public School 169 Addition
Description
ADDITION / WORK IN SUPPORT OF ADDITION / FIRE ALARM SYSTEM
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2019-01-29T00:00:00.000
Budget Forecast
89707695.00
Latest Budget Changes
0.00
Total Budget Changes
5307201.00
Forecast Completion
2024-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
366
Storm Mitigation Loan Program at Hunts Point
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 672 • Project Name: Storm Mitigation Loan Program at Hunts Point
Date Reported As Of
2021-12-01T00:00:00.000
Pid
672
Project Name
Storm Mitigation Loan Program at Hunts Point
Description
SMLP portion for Hunts Point WWTP as part of the New York City Wastewater Resiliency Program.
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2018-04-16T00:00:00.000
Budget Forecast
60882161.37
Latest Budget Changes
8375603.18
Total Budget Changes
20080597.79
Forecast Completion
2023-02-17T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1091
P.S. 96 - QUEENS Addition
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 1221 • Project Name: P.S. 96 - QUEENS Addition
Date Reported As Of
2021-12-01T00:00:00.000
Pid
1221
Project Name
P.S. 96 - QUEENS Addition
Description
ADDITION
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Design
Design Start
2021-02-26T00:00:00.000
Budget Forecast
75688643.00
Total Budget Changes
-3902865.00
Forecast Completion
2024-09-03T00:00:00.000
Total Schedule Changes
0
Storm Mitigation Loan Program at Red Hook
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 721 • Project Name: Storm Mitigation Loan Program at Red Hook
Date Reported As Of
2021-12-01T00:00:00.000
Pid
721
Project Name
Storm Mitigation Loan Program at Red Hook
Description
SMLP portion for Red Hook WWTP as part of the New York City Wastewater Resiliency Program.
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2018-11-01T00:00:00.000
Budget Forecast
39124845.02
Latest Budget Changes
3559224.90
Total Budget Changes
13549422.97
Forecast Completion
2022-09-01T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
921
FUEL TANK & SUMP REPLACEMENTS - MANHATTAN/S.I.
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 900 • Project Name: FUEL TANK & SUMP REPLACEMENTS - MANHATTAN/S.I.
Date Reported As Of
2021-12-01T00:00:00.000
Pid
900
Project Name
FUEL TANK & SUMP REPLACEMENTS - MANHATTAN/S.I.
Description
CITYWIDE FUEL TANK REPLACEMENT PROGRAM FOR NEW 2015 EPA PETROLEUM BULK STORAGE REGULATIONS
Category
Industrial Development
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Design
Design Start
2019-07-17T00:00:00.000
Budget Forecast
25246000.00
Latest Budget Changes
0.00
Total Budget Changes
-1754000.00
Forecast Completion
2025-06-29T00:00:00.000
Latest Schedule Changes
178
Total Schedule Changes
663
Queensboro Bridge Roadway Replacement over East River
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 594 • Project Name: Queensboro Bridge Roadway Replacement over East River
Date Reported As Of
2021-12-01T00:00:00.000
Pid
594
Project Name
Queensboro Bridge Roadway Replacement over East River
Description
This project includes the replacement of the upper roadway's deck on the main bridge along with steel repairs, fire standpipes, and lighting upgrades.
Category
Bridges, Streets and Roadways
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2015-04-09T00:00:00.000
Budget Forecast
383033014.00
Latest Budget Changes
24026048.00
Total Budget Changes
8567339.67
Forecast Completion
2024-03-13T00:00:00.000
Latest Schedule Changes
89
Total Schedule Changes
1970
Catskill Aqueduct Repair and Rehabilitation
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 478 • Project Name: Catskill Aqueduct Repair and Rehabilitation
Date Reported As Of
2021-12-01T00:00:00.000
Pid
478
Project Name
Catskill Aqueduct Repair and Rehabilitation
Description
Project to ensure the reliability of the 74 mile upper Catskill Aqueduct, including replacement of mechanical components, leak mitigation, and biofilm removal/condition assessment.
Category
Water Supply
Borough
Citywide
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2015-06-19T00:00:00.000
Budget Forecast
267212023.00
Latest Budget Changes
0.00
Total Budget Changes
9642889.68
Forecast Completion
2022-08-01T00:00:00.000
Latest Schedule Changes
365
Total Schedule Changes
1517
RECONSTRUCTION OF QUEENS BLVD - PHASE 2
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 619 • Project Name: RECONSTRUCTION OF QUEENS BLVD - PHASE 2
Date Reported As Of
2021-12-01T00:00:00.000
Pid
619
Project Name
RECONSTRUCTION OF QUEENS BLVD - PHASE 2
Description
Vision Zero - Queens Boulevard - Segment 2: 73rd Street to Eliot Avenue. Variety of safety and streetscape improvements including partial street reconstruction and resurfacing to address roadway conditions
Category
Industrial Development
Borough
Queens
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2016-10-26T00:00:00.000
Budget Forecast
84243000.00
Latest Budget Changes
5000.00
Total Budget Changes
14201000.00
Forecast Completion
2029-09-13T00:00:00.000
Latest Schedule Changes
366
Total Schedule Changes
2315