Capital Projects

All major infrastructure and information technology projects with a budget of $25 million or more that are currently active (in the design, procurement, or construction phase).

City Government Mayor's Office of Operations (OPS) Dataset n7gv-k5yt 16 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
Installation of Dechlorination System at Hunts Point WRRF
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 1094 • Project Name: Installation of Dechlorination System at Hunts Point WRRF
Date Reported As Of
2021-12-01T00:00:00.000
Pid
1094
Project Name
Installation of Dechlorination System at Hunts Point WRRF
Description
Install a Dechlorination System, replace the existing chlorination system including chemical storage tanks, metering pumps, electrical distribution equipment and upgrade the HVAC within the existing Chlorination Building.
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2021-05-25T00:00:00.000
Budget Forecast
34679510.00
Latest Budget Changes
-76511.00
Total Budget Changes
-6856021.00
Forecast Completion
2028-05-20T00:00:00.000
Latest Schedule Changes
325
Total Schedule Changes
-9
MULTI-SITE PEDESTRIAN SAFETY PHASE 5
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 1004 • Project Name: MULTI-SITE PEDESTRIAN SAFETY PHASE 5
Date Reported As Of
2021-12-01T00:00:00.000
Pid
1004
Project Name
MULTI-SITE PEDESTRIAN SAFETY PHASE 5
Description
PEDESTRIAN SAFETY GEOMETRIC IMPROVEMENTS AT VARIOUS SPECIFIED LOCATIONS, CITYWIDE
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction
Design Start
2017-08-01T00:00:00.000
Budget Forecast
26219000.00
Latest Budget Changes
150000.00
Total Budget Changes
-4087000.00
Forecast Completion
2024-06-01T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1126
HIGH LEVEL STM SEWERS IN GOWANUS CANAL AREA-PH II
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 849 • Project Name: HIGH LEVEL STM SEWERS IN GOWANUS CANAL AREA-PH II
Date Reported As Of
2021-12-01T00:00:00.000
Pid
849
Project Name
HIGH LEVEL STM SEWERS IN GOWANUS CANAL AREA-PH II
Description
High Level Storm and Combine Sewer installation and Water Main replacement in Gowanus Canal Area Phase-2, Brooklyn.
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2016-09-30T00:00:00.000
Budget Forecast
40701000.00
Latest Budget Changes
687000.00
Total Budget Changes
8657000.00
Forecast Completion
2022-04-27T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
813
150 ST SPINE: PHASE II TRUNK SEWER AT BERGEN BASIN
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 999 • Project Name: 150 ST SPINE: PHASE II TRUNK SEWER AT BERGEN BASIN
Date Reported As Of
2021-12-01T00:00:00.000
Pid
999
Project Name
150 ST SPINE: PHASE II TRUNK SEWER AT BERGEN BASIN
Description
Southeast Queens 150th Street Spine, Phase II - Installation of a new double barrel trunk storm sewer that will run through JFK airport; approximately 1,000 feet east of Bergen Basin, to the north side of the Belt Parkway at Inwood Street and 150th Street
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2020-03-02T00:00:00.000
Budget Forecast
47590000.00
Latest Budget Changes
0.00
Total Budget Changes
-158027000.00
Forecast Completion
2026-05-20T00:00:00.000
Latest Schedule Changes
121
Total Schedule Changes
646
Coler Specialty Hospital Priority Mitigation Projects
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 544 • Project Name: Coler Specialty Hospital Priority Mitigation Projects
Date Reported As Of
2021-12-01T00:00:00.000
Pid
544
Project Name
Coler Specialty Hospital Priority Mitigation Projects
Description
The priority mitigation projects at Coler include key critical mitigation projects to improve the resiliency of the campus.
Category
Health and Hospitals
Borough
Manhattan
Managing Agency
EDC
Client Agency
H+H
Current Phase
Construction
Design Start
2014-09-01T00:00:00.000
Budget Forecast
24246640.00
Latest Budget Changes
2716986.00
Total Budget Changes
0.00
Forecast Completion
2023-03-01T00:00:00.000
Latest Schedule Changes
60
Total Schedule Changes
2085
SOUTHEAST QUEENS PRIORITY GRIDS - GROUP 2
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 847 • Project Name: SOUTHEAST QUEENS PRIORITY GRIDS - GROUP 2
Date Reported As Of
2021-12-01T00:00:00.000
Pid
847
Project Name
SOUTHEAST QUEENS PRIORITY GRIDS - GROUP 2
Description
SOUTHEAST QUEENS PRIORITY GRIDS - GROUP 2
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2018-10-09T00:00:00.000
Budget Forecast
32453000.00
Latest Budget Changes
-10000.00
Total Budget Changes
14480000.00
Forecast Completion
2028-02-29T00:00:00.000
Latest Schedule Changes
-366
Total Schedule Changes
1630
Studio Museum in Harlem New Building
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 896 • Project Name: Studio Museum in Harlem New Building
Date Reported As Of
2021-12-01T00:00:00.000
Pid
896
Project Name
Studio Museum in Harlem New Building
Description
The Project will combine two adjacent lots on 125th Street: the sculpture court, City-owned lot 11, and the Museum building on lot 9, owned by the Museum. Existing structures on both lots will be demolished for the new, six story 82,000sf City owned building.
Category
Arts and Culture
Managing Agency
DDC
Client Agency
Cultural Affairs
Current Phase
Construction
Design Start
2018-09-25T00:00:00.000
Budget Forecast
58931000.00
Latest Budget Changes
0.00
Total Budget Changes
-190000.00
Forecast Completion
2024-06-30T00:00:00.000
Latest Schedule Changes
583
Total Schedule Changes
856
Gilboa Dam Reconstruction, Phase III
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 405 • Project Name: Gilboa Dam Reconstruction, Phase III
Date Reported As Of
2021-12-01T00:00:00.000
Pid
405
Project Name
Gilboa Dam Reconstruction, Phase III
Description
Gilboa Dam Reconstruction Project includes construction of a new low level outlet (LLO) consisting of 2,000 feet of tunneling , an access shaft, oulet structure and gate valve controls.
Category
Water Supply
Borough
Upstate
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2004-03-18T00:00:00.000
Budget Forecast
199070771.81
Latest Budget Changes
-7599346.86
Total Budget Changes
10376533.49
Forecast Completion
2022-10-01T00:00:00.000
Latest Schedule Changes
90
Total Schedule Changes
1113
RECONSTRUCTION OF QUEENS BLVD - PHASE 2
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 619 • Project Name: RECONSTRUCTION OF QUEENS BLVD - PHASE 2
Date Reported As Of
2021-12-01T00:00:00.000
Pid
619
Project Name
RECONSTRUCTION OF QUEENS BLVD - PHASE 2
Description
Vision Zero - Queens Boulevard - Segment 2: 73rd Street to Eliot Avenue. Variety of safety and streetscape improvements including partial street reconstruction and resurfacing to address roadway conditions
Category
Industrial Development
Borough
Queens
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2016-10-26T00:00:00.000
Budget Forecast
84243000.00
Latest Budget Changes
5000.00
Total Budget Changes
14201000.00
Forecast Completion
2029-09-13T00:00:00.000
Latest Schedule Changes
366
Total Schedule Changes
2315
NEW 48" TRUNK WATER MAIN IN E 233 STREET
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 998 • Project Name: NEW 48" TRUNK WATER MAIN IN E 233 STREET
Date Reported As Of
2021-12-01T00:00:00.000
Pid
998
Project Name
NEW 48" TRUNK WATER MAIN IN E 233 STREET
Description
New 48" Trunk Water Main in E 233rd Street between Bronxwood Avenue & Baychester Avenue, etc.
Category
Water Supply
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2015-10-01T00:00:00.000
Budget Forecast
33831000.00
Latest Budget Changes
248000.00
Total Budget Changes
1077000.00
Forecast Completion
2025-02-24T00:00:00.000
Latest Schedule Changes
350
Total Schedule Changes
1796
Shore Road Bridge over Hutchinson River
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 541 • Project Name: Shore Road Bridge over Hutchinson River
Date Reported As Of
2021-12-01T00:00:00.000
Pid
541
Project Name
Shore Road Bridge over Hutchinson River
Description
Replace the Shore Road Bridge over the Hutchinson River with a new bridge.
Category
Bridges, Streets and Roadways
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-06-30T00:00:00.000
Budget Forecast
332185852.00
Latest Budget Changes
8810109.00
Total Budget Changes
-19049921.84
Forecast Completion
2029-03-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1477
Henry Hudson Parkway over Amtrak (Northbound)
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 592 • Project Name: Henry Hudson Parkway over Amtrak (Northbound)
Date Reported As Of
2021-12-01T00:00:00.000
Pid
592
Project Name
Henry Hudson Parkway over Amtrak (Northbound)
Description
Replace the Ramp to northbound Henry Hudson Parkway over Amtrak in Manhattan.
Category
Bridges
Borough
Manhattan
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2020-01-02T00:00:00.000
Budget Forecast
54051625.00
Latest Budget Changes
0.00
Total Budget Changes
500625.00
Forecast Completion
2029-05-17T00:00:00.000
Latest Schedule Changes
-194
Total Schedule Changes
1693
Pier 42 and East River Park Connector Program
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 1085 • Project Name: Pier 42 and East River Park Connector Program
Date Reported As Of
2021-12-01T00:00:00.000
Pid
1085
Project Name
Pier 42 and East River Park Connector Program
Description
Abatement, demolition, and replacement of shed with an upland park on Pier 42 in Manhattan.
Category
Parks
Managing Agency
EDC
Client Agency
DPR
Current Phase
Construction
Design Start
2017-06-01T00:00:00.000
Budget Forecast
60115737.00
Latest Budget Changes
0.00
Total Budget Changes
100000.00
Forecast Completion
2023-08-31T00:00:00.000
Latest Schedule Changes
153
Total Schedule Changes
214
SUNSET PARK NORTH BK WATERFRONT GREENWAY
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 1176 • Project Name: SUNSET PARK NORTH BK WATERFRONT GREENWAY
Date Reported As Of
2021-12-01T00:00:00.000
Pid
1176
Project Name
SUNSET PARK NORTH BK WATERFRONT GREENWAY
Description
Reconstruction of Sunset Park North Section of the Brooklyn Waterfront Greenway.
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2018-09-06T00:00:00.000
Budget Forecast
26661000.00
Latest Budget Changes
710000.00
Total Budget Changes
20345000.00
Forecast Completion
2024-07-13T00:00:00.000
Latest Schedule Changes
120
Total Schedule Changes
1096
Douglaston New Facility
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 960 • Project Name: Douglaston New Facility
Date Reported As Of
2021-12-01T00:00:00.000
Pid
960
Project Name
Douglaston New Facility
Description
New library facility for the Douglaston/Little Neck community.
Category
Libraries
Managing Agency
DDC
Client Agency
Libraries-QBPL
Current Phase
Design
Design Start
2019-11-20T00:00:00.000
Budget Forecast
30399000.00
Latest Budget Changes
4881000.00
Total Budget Changes
5348000.00
Forecast Completion
2026-10-05T00:00:00.000
Total Schedule Changes
244
New water main work in 7th avenue between 14th street and 34th street, and other locations as shown on page 3 of attached CPI
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 1178 • Category: Streets and Roadways
Date Reported As Of
2021-12-01T00:00:00.000
Pid
1178
Project Name
New water main work in 7th avenue between 14th street and 34th street, and other locations as shown on page 3 of attached CPI
Description
Distribution water main replacement along 7th Avenue between 14th Street and 34th Street
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2021-05-03T00:00:00.000
Budget Forecast
69718000.00
Latest Budget Changes
0.00
Total Budget Changes
1335000.00
Forecast Completion
2026-08-26T00:00:00.000
Total Schedule Changes
181
Wyckoff Avenue Street Reconstruction
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 191 • Project Name: Wyckoff Avenue Street Reconstruction
Date Reported As Of
2021-12-01T00:00:00.000
Pid
191
Project Name
Wyckoff Avenue Street Reconstruction
Description
Reconstruction of Wyckoff Avenue from Flushing Avenue to Cooper Avenue, in the Boroughs of Brooklyn and Queens..
Category
Streets and Roadways
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Trans. & Env. Protection
Current Phase
Design
Design Start
2017-03-29T00:00:00.000
Budget Forecast
73992000.00
Latest Budget Changes
0.00
Total Budget Changes
43926000.00
Forecast Completion
2028-03-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
226
Flushing Meadows Corona Park Electrical Vault Reconstruction (Hurricane Sandy)
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 1083 • Project Name: Flushing Meadows Corona Park Electrical Vault Reconstruction (Hurricane Sandy)
Date Reported As Of
2021-12-01T00:00:00.000
Pid
1083
Project Name
Flushing Meadows Corona Park Electrical Vault Reconstruction (Hurricane Sandy)
Description
This project will reconstruct the electrical vaults in Flushing Meadows Corona Park that were damaged by Hurricane Sandy.
Category
Parks
Managing Agency
DPR
Client Agency
DPR
Current Phase
Design
Design Start
2019-08-21T00:00:00.000
Budget Forecast
59527909.00
Latest Budget Changes
95000.00
Total Budget Changes
-3555909.00
Battery Park Underpass Emergency Relief Betterments
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 540 • Project Name: Battery Park Underpass Emergency Relief Betterments
Date Reported As Of
2021-12-01T00:00:00.000
Pid
540
Project Name
Battery Park Underpass Emergency Relief Betterments
Description
Resiliency betterments for Battery Park and West Street underpasses.
Category
Bridges
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2018-04-01T00:00:00.000
Budget Forecast
55043529.00
Latest Budget Changes
-11670141.00
Total Budget Changes
47923308.00
Forecast Completion
2024-10-28T00:00:00.000
Latest Schedule Changes
182
Total Schedule Changes
1197
Riverside Drive/West 158th Street Bridge Rehabilitation
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 113 • Project Name: Riverside Drive/West 158th Street Bridge Rehabilitation
Date Reported As Of
2021-12-01T00:00:00.000
Pid
113
Project Name
Riverside Drive/West 158th Street Bridge Rehabilitation
Description
Replace deck of the Riverside Drive viaduct/ bridge over West 158th Street.
Category
Bridges, Streets and Roadways
Borough
Manhattan
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2014-10-22T00:00:00.000
Budget Forecast
144908026.00
Latest Budget Changes
9223686.00
Total Budget Changes
96922794.00
Forecast Completion
2023-10-13T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2152
GREENWICH STREET RECONSTRUCTION
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 1175 • Project Name: GREENWICH STREET RECONSTRUCTION
Date Reported As Of
2021-12-01T00:00:00.000
Pid
1175
Project Name
GREENWICH STREET RECONSTRUCTION
Description
RECONSTRUCTION OF GREENWICH STREET FROM BARCLAY STREET TO CHAMBERS STREET, MANHATTAN
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction
Design Start
2018-04-25T00:00:00.000
Budget Forecast
35696000.00
Latest Budget Changes
3894000.00
Total Budget Changes
4449000.00
Forecast Completion
2024-11-06T00:00:00.000
Latest Schedule Changes
-1
Total Schedule Changes
-1
Croton Above Ground Structure And Landscaping
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 747 • Project Name: Croton Above Ground Structure And Landscaping
Date Reported As Of
2021-12-01T00:00:00.000
Pid
747
Project Name
Croton Above Ground Structure And Landscaping
Description
The new Mosholu Golf Course Club House, together with fifty-five Driving Range Tee Boxes and ten-acres of re-landscaping comprise the phase IV and final of the vast DEP Croton Water Treatment Plant project, currently under construction in Van Cortlandt Park in the Bronx. Through a multifunctional design strategy the project reinstates the pre-existing golf program and facility, creates civic space for community use and ensures security for a multi-billion dollar public works facility.
Category
Industrial Development
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2012-05-23T00:00:00.000
Budget Forecast
107444000.00
Latest Budget Changes
0.00
Total Budget Changes
75117000.00
Forecast Completion
2023-02-01T00:00:00.000
Latest Schedule Changes
161
Total Schedule Changes
897
Porpoise Bridge In Flushing Meadows-Corona Park
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 749 • Project Name: Porpoise Bridge In Flushing Meadows-Corona Park
Date Reported As Of
2021-12-01T00:00:00.000
Pid
749
Project Name
Porpoise Bridge In Flushing Meadows-Corona Park
Description
Feasibility Study for the repair and or restoration for Porpoise (Tide Gate) Bridge in Flushing Meadows Corona Park.
Category
Bridges
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2017-09-18T00:00:00.000
Budget Forecast
63979000.00
Latest Budget Changes
1054000.00
Total Budget Changes
82000.00
Forecast Completion
2026-04-06T00:00:00.000
Latest Schedule Changes
113
Total Schedule Changes
1110
Boston Road Bridge Over Hutchinson River Rehabilitation
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 539 • Project Name: Boston Road Bridge Over Hutchinson River Rehabilitation
Date Reported As Of
2021-12-01T00:00:00.000
Pid
539
Project Name
Boston Road Bridge Over Hutchinson River Rehabilitation
Description
Rehabilitation of Boston Road Bridge over Hutchinson River, located in the Bornx.
Category
Bridges, Streets and Roadways
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction Procurement
Design Start
2018-04-16T00:00:00.000
Budget Forecast
84001814.00
Latest Budget Changes
1500000.00
Total Budget Changes
49309814.00
Forecast Completion
2025-11-02T00:00:00.000
Latest Schedule Changes
257
Total Schedule Changes
803
Central Park Light Infrastructure
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 586 • Project Name: Central Park Light Infrastructure
Date Reported As Of
2021-12-01T00:00:00.000
Pid
586
Project Name
Central Park Light Infrastructure
Description
Install, remove, and furnish equipment for electrical work associated with traffic signals, lighting, and distribution systems in Central Park, Manhattan.
Category
Parks, Streets and Roadways
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2016-04-29T00:00:00.000
Budget Forecast
40815476.00
Latest Budget Changes
750000.00
Total Budget Changes
-3323649.60
Forecast Completion
2022-06-20T00:00:00.000
Latest Schedule Changes
1098
Total Schedule Changes
1535
SAN & STRM SEWER, WM IN CONEY ISLAND AREA, PH 4
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 1009 • Project Name: SAN & STRM SEWER, WM IN CONEY ISLAND AREA, PH 4
Date Reported As Of
2021-12-01T00:00:00.000
Pid
1009
Project Name
SAN & STRM SEWER, WM IN CONEY ISLAND AREA, PH 4
Description
Storm, Sanitary Sewers & Water Mains in Coney Island Area - Phase 04, Brooklyn
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2019-07-25T00:00:00.000
Budget Forecast
29619000.00
Latest Budget Changes
170000.00
Total Budget Changes
1984000.00
Forecast Completion
2027-02-07T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1431
Staten Island 1 & 3 Garage Construction & Rehab
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 769 • Project Name: Staten Island 1 & 3 Garage Construction & Rehab
Date Reported As Of
2021-12-01T00:00:00.000
Pid
769
Project Name
Staten Island 1 & 3 Garage Construction & Rehab
Description
The Department of Sanitation of the City of New York (DSNY) is planning to develop a Staten Island Districts 1 and 3 campus that will include a new garage serving both districts and renovation of the existing Borough Repair Shop. The site is to be reconfigured with new grading and drainage, new covered salt storage, new outdoor fueling, new household special waste collection, outdoor DSNY truck parking and a new force main sanitary line to connect to the NYC DEP sewer.
Category
Sanitation
Borough
Staten Island
Managing Agency
DDC
Client Agency
Sanitation
Current Phase
Construction
Design Start
2017-07-14T00:00:00.000
Budget Forecast
190154000.00
Latest Budget Changes
2946000.00
Total Budget Changes
68555000.00
Forecast Completion
2023-09-01T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
406
Pelham Bay Equestrian Park over Amtrak
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 703 • Project Name: Pelham Bay Equestrian Park over Amtrak
Date Reported As Of
2021-12-01T00:00:00.000
Pid
703
Project Name
Pelham Bay Equestrian Park over Amtrak
Description
Replace/Rehab the Pelham Bay Equestrian Park bridge over Amtrak, the Bronx
Category
Bridges
Borough
Bronx
Managing Agency
DOT
Client Agency
DPR
Current Phase
Design
Design Start
2019-01-30T00:00:00.000
Budget Forecast
41466997.00
Latest Budget Changes
-362000.00
Total Budget Changes
137997.00
Forecast Completion
2026-08-24T00:00:00.000
Latest Schedule Changes
99
Total Schedule Changes
1029
East River Esplanade Stabilization and Reconstruction Phase 2
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 1082 • Project Name: East River Esplanade Stabilization and Reconstruction Phase 2
Date Reported As Of
2021-12-01T00:00:00.000
Pid
1082
Project Name
East River Esplanade Stabilization and Reconstruction Phase 2
Description
This project will stabilize and reconstruct portions of the East River Esplanade.
Category
Parks
Managing Agency
DPR
Client Agency
DPR
Current Phase
Design
Design Start
2019-02-01T00:00:00.000
Budget Forecast
29475000.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2024-09-23T00:00:00.000
Total Schedule Changes
156
Bush Terminal Development Site Preparation
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 1086 • Project Name: Bush Terminal Development Site Preparation
Date Reported As Of
2021-12-01T00:00:00.000
Pid
1086
Project Name
Bush Terminal Development Site Preparation
Description
Sitework (including but not limited to: excavation, utility, and bulkhead work) at Bush Terminal in preparation of the Steiner Studio campus.
Category
Industrial Development
Managing Agency
EDC
Client Agency
EDC
Current Phase
Design
Design Start
2021-03-01T00:00:00.000
Budget Forecast
29000000.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2024-06-30T00:00:00.000
Latest Schedule Changes
182
Total Schedule Changes
517
80 CENTRE ST.- FIRE ALARMS/SPRINKLERS
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 1174 • Project Name: 80 CENTRE ST.- FIRE ALARMS/SPRINKLERS
Date Reported As Of
2021-12-01T00:00:00.000
Pid
1174
Project Name
80 CENTRE ST.- FIRE ALARMS/SPRINKLERS
Description
Fire Alarm and Sprinklers Upgrade
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Design
Design Start
2021-07-26T00:00:00.000
Budget Forecast
44469000.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2026-03-23T00:00:00.000
Total Schedule Changes
340
Staten Island 3 Garage - HVAC Replacement
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 1179 • Project Name: Staten Island 3 Garage - HVAC Replacement
Date Reported As Of
2021-12-01T00:00:00.000
Pid
1179
Project Name
Staten Island 3 Garage - HVAC Replacement
Description
Replacement of HVAC System and Roof at Staten Island District 3 DSNY Garage and Boro Repair Shop
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
Sanitation
Current Phase
Construction
Design Start
2017-07-14T00:00:00.000
Budget Forecast
25216000.00
Latest Budget Changes
-28000.00
Total Budget Changes
460000.00
Forecast Completion
2022-07-01T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
409
Next Generation Data Platform Re-Architecture
Date Reported As Of: 2021-12-01T00:00:00.000 • Pid: 1224 • Project Name: Next Generation Data Platform Re-Architecture
Date Reported As Of
2021-12-01T00:00:00.000
Pid
1224
Project Name
Next Generation Data Platform Re-Architecture
Description
Comprehensive modernization of existing end-of-life DataShare and DataBridge platforms to guarantee DoITT can maintain ongoing support, evolution, and growth of the DoITT agency-integration and data-sharing eco-system
Category
IT
Managing Agency
DOITT
Client Agency
DoITT
Current Phase
IT
Budget Forecast
92807744.77
Total Budget Changes
0.40
Forecast Completion
2024-06-30T00:00:00.000
Total Schedule Changes
304
Carl Schurz Park Promenade over FDR (East 81st to 90th Streets)
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 537 • Project Name: Carl Schurz Park Promenade over FDR (East 81st to 90th Streets)
Date Reported As Of
2021-07-01T00:00:00.000
Pid
537
Project Name
Carl Schurz Park Promenade over FDR (East 81st to 90th Streets)
Description
Replace the Promenade over FDR Drive between East 81st to 90th Streets in Manhattan.
Category
Bridges
Borough
Manhattan
Managing Agency
DOT
Client Agency
DOT, DPR
Current Phase
Design
Design Start
2017-05-30T00:00:00.000
Budget Forecast
116552421.00
Latest Budget Changes
-197350000.00
Total Budget Changes
-197139579.00
Forecast Completion
2028-12-16T00:00:00.000
Latest Schedule Changes
49
Total Schedule Changes
1571
Electronic Medical Records Upgrade
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 403 • Project Name: Electronic Medical Records Upgrade
Date Reported As Of
2021-07-01T00:00:00.000
Pid
403
Project Name
Electronic Medical Records Upgrade
Description
The EPIC - EMR Program: Electronic Medical Records (EMR) System - a single enterprise-wide EMR to meet the needs of HHC's expansive size and improve patient care will replace the legacy EMR - QuadraMed, which is over 25 years old.
Category
Health and Hospitals, IT
Borough
Citywide
Managing Agency
HHC
Client Agency
H+H
Current Phase
IT
Budget Forecast
764063231.00
Latest Budget Changes
0.00
Total Budget Changes
15184947.00
Forecast Completion
2022-12-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2032
Bronx Animal Care Center
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 893 • Project Name: Bronx Animal Care Center
Date Reported As Of
2021-07-01T00:00:00.000
Pid
893
Project Name
Bronx Animal Care Center
Description
Bronx Animal Care Center & Veterinary Clinic is a new 50,000 SF facility that will be housing admissions, adoptions, medical services, and boarding for approximately 70 dogs, 140 cats, 30 rabbits and 20 animals or other species. In addition to the animal housing, the Bronx Animal Care Center will include a wildlife area to rehabilitate wild birds, academic partnership for youth, and enhanced senior services. Site work will include yards to facilitate dog adoptions, covered exercise runs, courtyards, and parking for staff, visitors, and center vehicles, as well as site lighting and low maintenance planting throughout. The building and associated landscape are to achieve LEED Silver standards or higher.
Category
Health and Hospitals
Managing Agency
DDC
Client Agency
Health
Current Phase
Design
Design Start
2019-06-20T00:00:00.000
Budget Forecast
91453000.00
Latest Budget Changes
22078000.00
Total Budget Changes
24815617.00
Forecast Completion
2025-01-14T00:00:00.000
Latest Schedule Changes
319
Total Schedule Changes
110
Coastal Resiliency -- Parallel Conveyances
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 1171 • Project Name: Coastal Resiliency -- Parallel Conveyances
Date Reported As Of
2021-07-01T00:00:00.000
Pid
1171
Project Name
Coastal Resiliency -- Parallel Conveyances
Description
Coastal Resiliency -- Parallel Conveyances
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Parks & Recreation
Current Phase
Construction Procurement
Design Start
2016-04-27T00:00:00.000
Budget Forecast
167779000.00
Total Budget Changes
32327000.00
Forecast Completion
2026-06-11T00:00:00.000
Total Schedule Changes
92
New Storm Sewer N Conduit Av-Baisley Blvd
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 792 • Project Name: New Storm Sewer N Conduit Av-Baisley Blvd
Date Reported As Of
2021-07-01T00:00:00.000
Pid
792
Project Name
New Storm Sewer N Conduit Av-Baisley Blvd
Description
Storm, Sanitary and Water Mains work in North Conduit between Baisley Blvd and Guy Brewer Blvd, South Queens
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2018-07-30T00:00:00.000
Budget Forecast
113711000.00
Latest Budget Changes
1647000.00
Total Budget Changes
31711000.00
Forecast Completion
2026-05-22T00:00:00.000
Latest Schedule Changes
616
Total Schedule Changes
1619
Bronx Sanitation Garage Rehabilitation: Community District 12
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 956 • Project Name: Bronx Sanitation Garage Rehabilitation: Community District 12
Date Reported As Of
2021-07-01T00:00:00.000
Pid
956
Project Name
Bronx Sanitation Garage Rehabilitation: Community District 12
Description
Rehabilitation of garage that serves Bronx Community District 12 located at 1635 East 233rd Street, Bronx.
Category
Sanitation
Managing Agency
DSNY
Client Agency
DSNY
Current Phase
Design
Design Start
2017-11-01T00:00:00.000
Budget Forecast
57376185.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2026-07-31T00:00:00.000
Latest Schedule Changes
365
Total Schedule Changes
1064
RECONST. OF COLUMBIA ST., PH II/BED-768B/SEK002321
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 845 • Project Name: RECONST. OF COLUMBIA ST., PH II/BED-768B/SEK002321
Date Reported As Of
2021-07-01T00:00:00.000
Pid
845
Project Name
RECONST. OF COLUMBIA ST., PH II/BED-768B/SEK002321
Description
Roadway reconstruction including new sewers, water main, street lighting and traffic signals: Columbia Street south of Hamilton Avenue.
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2019-07-01T00:00:00.000
Budget Forecast
116664000.00
Latest Budget Changes
2790000.00
Total Budget Changes
6730000.00
Forecast Completion
2025-07-14T00:00:00.000
Latest Schedule Changes
365
Total Schedule Changes
972
Park Avenue Tunnel (Murray Hill)
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 536 • Project Name: Park Avenue Tunnel (Murray Hill)
Date Reported As Of
2021-07-01T00:00:00.000
Pid
536
Project Name
Park Avenue Tunnel (Murray Hill)
Description
Repair Park Avenue tunnel, located in Midtown, Manhattan.
Category
Bridges
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2006-08-01T00:00:00.000
Budget Forecast
48301028.00
Latest Budget Changes
-229000.00
Total Budget Changes
-17773389.61
Forecast Completion
2022-08-03T00:00:00.000
Latest Schedule Changes
421
Total Schedule Changes
1568
TLC - NEW OFFICE FACILITY - 24-55 BQE WEST
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 665 • Project Name: TLC - NEW OFFICE FACILITY - 24-55 BQE WEST
Date Reported As Of
2021-07-01T00:00:00.000
Pid
665
Project Name
TLC - NEW OFFICE FACILITY - 24-55 BQE WEST
Description
Replace existing administration wing; provide new parking and new inspection lane within the facility.
Category
Other Government Facilities
Borough
Queens
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Construction
Design Start
2015-09-15T00:00:00.000
Budget Forecast
152358000.00
Latest Budget Changes
72377000.00
Total Budget Changes
75370000.00
Forecast Completion
2025-03-24T00:00:00.000
Latest Schedule Changes
400
Total Schedule Changes
1248
HILL DR (TERRACE BR) OVER PROSPECT PARK LAKE BIN 2244120
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 1073 • Project Name: HILL DR (TERRACE BR) OVER PROSPECT PARK LAKE BIN 2244120
Date Reported As Of
2021-07-01T00:00:00.000
Pid
1073
Project Name
HILL DR (TERRACE BR) OVER PROSPECT PARK LAKE BIN 2244120
Category
Bridges
Managing Agency
DOT
Client Agency
NYC Parks
Current Phase
Design
Design Start
2020-01-06T00:00:00.000
Budget Forecast
28153244.00
Latest Budget Changes
-883000.00
Total Budget Changes
-785268.00
Forecast Completion
2027-12-14T00:00:00.000
Latest Schedule Changes
190
Total Schedule Changes
636
Coastal Resiliency – Project Area 2
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 1170 • Project Name: Coastal Resiliency – Project Area 2
Date Reported As Of
2021-07-01T00:00:00.000
Pid
1170
Project Name
Coastal Resiliency – Project Area 2
Description
INSTALLATION OF EAST SIDE COASTAL RESILIENCY (ESCR) PROJECT AREA 2 FROM EAST 15TH STREET TO EAST 25TH STREET
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Parks & Recreation
Current Phase
Construction
Design Start
2016-04-27T00:00:00.000
Budget Forecast
216897000.00
Total Budget Changes
448000.00
Forecast Completion
2024-10-13T00:00:00.000
Total Schedule Changes
0
253 Broadway Landmark's Space Renovations
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 639 • Project Name: 253 Broadway Landmark's Space Renovations
Date Reported As Of
2021-07-01T00:00:00.000
Pid
639
Project Name
253 Broadway Landmark's Space Renovations
Description
Renovate 4 floors of the building to create new office space for the Landmarks Preservation Commission, including new hearing room.
Category
Other Government Facilities
Borough
Manhattan
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Construction
Design Start
2013-01-23T00:00:00.000
Budget Forecast
66994000.00
Latest Budget Changes
-6938000.00
Total Budget Changes
35010000.00
Forecast Completion
2022-08-31T00:00:00.000
Latest Schedule Changes
551
Total Schedule Changes
1696
Storm Mitigation Loan Program at Hunts Point
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 672 • Project Name: Storm Mitigation Loan Program at Hunts Point
Date Reported As Of
2021-07-01T00:00:00.000
Pid
672
Project Name
Storm Mitigation Loan Program at Hunts Point
Description
SMLP portion for Hunts Point WRRF as part of the New York City Wastewater Resiliency Program.
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2018-04-16T00:00:00.000
Budget Forecast
52506558.19
Latest Budget Changes
0.00
Total Budget Changes
20080597.79
Forecast Completion
2023-02-17T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1091
UNION TURNPIKE CENTER MEDIAN REPLACEMENT
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 986 • Project Name: UNION TURNPIKE CENTER MEDIAN REPLACEMENT
Date Reported As Of
2021-07-01T00:00:00.000
Pid
986
Project Name
UNION TURNPIKE CENTER MEDIAN REPLACEMENT
Description
Union Turnpike Center Median Replacement from Hollis Court Blvd to 226th Street, Borough of Queens
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2019-05-23T00:00:00.000
Budget Forecast
27919000.00
Latest Budget Changes
1687000.00
Total Budget Changes
23766000.00
Forecast Completion
2024-09-13T00:00:00.000
Latest Schedule Changes
365
Total Schedule Changes
341
Mobile Radios
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 1079 • Project Name: Mobile Radios
Date Reported As Of
2021-07-01T00:00:00.000
Pid
1079
Project Name
Mobile Radios
Category
Public Safety and Criminal Justice
Managing Agency
FDNY
Current Phase
IT
Total Budget Changes
-8074214.27
Total Schedule Changes
0
Brooklyn P.S. at 4302 4TH AVE
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 949 • Project Name: Brooklyn P.S. at 4302 4TH AVE
Date Reported As Of
2021-07-01T00:00:00.000
Pid
949
Project Name
Brooklyn P.S. at 4302 4TH AVE
Description
NEW SCHOOL (PHASE II)
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2017-11-17T00:00:00.000
Budget Forecast
66058403.00
Latest Budget Changes
0.00
Total Budget Changes
-221356.00
Forecast Completion
2023-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
365
Grand Street Bridge over Newtown Creek
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 534 • Project Name: Grand Street Bridge over Newtown Creek
Date Reported As Of
2021-07-01T00:00:00.000
Pid
534
Project Name
Grand Street Bridge over Newtown Creek
Description
Replace the existing structure (swing-type bridge) with a new bridge; located between Gardner Avenue in Brooklyn and 47th Street in Queens.
Category
Bridges, Streets and Roadways
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2019-06-17T00:00:00.000
Budget Forecast
140136744.00
Latest Budget Changes
-966000.00
Total Budget Changes
160682490.00
Forecast Completion
2029-08-22T00:00:00.000
Latest Schedule Changes
-2
Total Schedule Changes
1645