Capital Projects

All major infrastructure and information technology projects with a budget of $25 million or more that are currently active (in the design, procurement, or construction phase).

City Government Mayor's Office of Operations (OPS) Dataset n7gv-k5yt 16 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
Coney Island Area, Phase 3A
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 516 • Project Name: Coney Island Area, Phase 3A
Date Reported As Of
2023-01-01T00:00:00.000
Pid
516
Project Name
Coney Island Area, Phase 3A
Description
Reconstruction of Storm and Sanitary sewer, Trunk and distribution water main in Coney Island area - Phase 3A, Borough of Brooklyn
Category
Industrial Development
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2014-03-17T00:00:00.000
Budget Forecast
63426000.00
Latest Budget Changes
0.00
Total Budget Changes
25273000.00
Forecast Completion
2023-11-27T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1215
West Tremont Avenue over Metro North Railroad
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 503 • Project Name: West Tremont Avenue over Metro North Railroad
Date Reported As Of
2023-01-01T00:00:00.000
Pid
503
Project Name
West Tremont Avenue over Metro North Railroad
Description
Replace/Rehab the West Tremont Avenue bridge over the Metro North line, located in the Bronx.
Category
Bridges
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2018-01-16T00:00:00.000
Budget Forecast
91785543.00
Latest Budget Changes
-564000.00
Total Budget Changes
37794543.00
Forecast Completion
2027-10-04T00:00:00.000
Latest Schedule Changes
57
Total Schedule Changes
1253
5th Avenue Bridge Reconstruction over LIRR and Sea Beach, Brooklyn
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 504 • Project Name: 5th Avenue Bridge Reconstruction over LIRR and Sea Beach, Brooklyn
Date Reported As Of
2023-01-01T00:00:00.000
Pid
504
Project Name
5th Avenue Bridge Reconstruction over LIRR and Sea Beach, Brooklyn
Description
Replace the 5th Avenue Bridge over LIRR & Sea Beach, Brooklyn.
Category
Bridges
Borough
Brooklyn
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction Procurement
Design Start
2017-11-30T00:00:00.000
Budget Forecast
83778580.00
Latest Budget Changes
-2732781.00
Total Budget Changes
36577693.00
Forecast Completion
2027-07-01T00:00:00.000
Latest Schedule Changes
-135
Total Schedule Changes
969
2nd Avenue Watermain Trunk Construction
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 388 • Project Name: 2nd Avenue Watermain Trunk Construction
Date Reported As Of
2023-01-01T00:00:00.000
Pid
388
Project Name
2nd Avenue Watermain Trunk Construction
Description
Trunk and Distribution Main Connection to shaft 32B in 2nd Ave., etc., together with all work incidental thereto, Borough of Manhattan. 2nd Avenue from East 33rd Street to East 37th Street
Category
Water Supply
Borough
Manhattan
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2013-09-30T00:00:00.000
Budget Forecast
52942000.00
Latest Budget Changes
0.00
Total Budget Changes
-7266000.00
Forecast Completion
2023-07-27T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2113
Oakwood Beach WWTP Headworks Improvements
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 450 • Project Name: Oakwood Beach WWTP Headworks Improvements
Date Reported As Of
2023-01-01T00:00:00.000
Pid
450
Project Name
Oakwood Beach WWTP Headworks Improvements
Description
Replacement of six bar screens, grit bin vibrator, six ring flushing pumps, six main sewage pumps and assoc. piping/valves and motor control center, replacement of four exhaust fans, gas and oxygen detectors and a 15 KVA transformer
Category
Wastewater Treatment
Borough
Staten Island
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2023-02-01T00:00:00.000
Budget Forecast
83229440.00
Latest Budget Changes
0.00
Total Budget Changes
31867440.00
Forecast Completion
2029-04-25T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2857
20th Avenue Storm and Sanitary Sewer Construction
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 432 • Project Name: 20th Avenue Storm and Sanitary Sewer Construction
Date Reported As Of
2023-01-01T00:00:00.000
Pid
432
Project Name
20th Avenue Storm and Sanitary Sewer Construction
Description
Storm and sanitary sewers in 20th Ave between 126th Street and U.S. Bulkhead Line, etc. Water main works.
Category
Sewers
Borough
Queens
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2012-07-10T00:00:00.000
Budget Forecast
141866000.00
Latest Budget Changes
-10000.00
Total Budget Changes
117177000.00
Forecast Completion
2023-06-19T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2180
Metropolitan Hospital Perimeter Flood Protection
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 562 • Project Name: Metropolitan Hospital Perimeter Flood Protection
Date Reported As Of
2023-01-01T00:00:00.000
Pid
562
Project Name
Metropolitan Hospital Perimeter Flood Protection
Description
Flood mitigation system to protect Metropolitan's campus from future flooding due and sea level rise
Category
Industrial Development
Borough
Manhattan
Managing Agency
EDC
Client Agency
H+H
Current Phase
Construction
Design Start
2016-12-01T00:00:00.000
Budget Forecast
108206086.00
Latest Budget Changes
0.00
Total Budget Changes
27046705.00
Forecast Completion
2024-11-21T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1452
Pelham Parkway Bridge Reconstruction over Hutchinson Parkway
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 506 • Project Name: Pelham Parkway Bridge Reconstruction over Hutchinson Parkway
Date Reported As Of
2023-01-01T00:00:00.000
Pid
506
Project Name
Pelham Parkway Bridge Reconstruction over Hutchinson Parkway
Description
Replace/Rehab the Pelham Parkway bridge over Hutchinson River Parkway, Bronx.
Category
Bridges, Streets and Roadways
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-11-08T00:00:00.000
Budget Forecast
67133092.00
Latest Budget Changes
350000.00
Total Budget Changes
10338071.57
Forecast Completion
2029-08-15T00:00:00.000
Latest Schedule Changes
60
Total Schedule Changes
1934
Bronx Sanitation Garage Construction: Community District 9, 10, 11
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 573 • Project Name: Bronx Sanitation Garage Construction: Community District 9, 10, 11
Date Reported As Of
2023-01-01T00:00:00.000
Pid
573
Project Name
Bronx Sanitation Garage Construction: Community District 9, 10, 11
Description
Construction of new Sanitation garage facility to serve Bronx community districts 9, 10, and 11 to be located at Zerega Avenue in the Bronx
Category
Sanitation
Borough
Bronx
Managing Agency
DSNY
Client Agency
DSNY
Current Phase
Design
Design Start
2017-08-01T00:00:00.000
Budget Forecast
561433662.56
Latest Budget Changes
219638662.56
Total Budget Changes
268983862.56
Forecast Completion
2031-10-01T00:00:00.000
Latest Schedule Changes
458
Total Schedule Changes
1919
Reconstruction of the Ashokan Headworks
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 834 • Project Name: Reconstruction of the Ashokan Headworks
Date Reported As Of
2023-01-01T00:00:00.000
Pid
834
Project Name
Reconstruction of the Ashokan Headworks
Description
CAT-213
Category
Water Supply
Borough
Upstate
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2020-08-07T00:00:00.000
Budget Forecast
343303864.75
Latest Budget Changes
26871269.00
Total Budget Changes
41950858.00
Forecast Completion
2028-09-01T00:00:00.000
Latest Schedule Changes
138
Total Schedule Changes
-67
SOUTH BROOKLYN CROSSTOWN SBS
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 843 • Project Name: SOUTH BROOKLYN CROSSTOWN SBS
Date Reported As Of
2023-01-01T00:00:00.000
Pid
843
Project Name
SOUTH BROOKLYN CROSSTOWN SBS
Description
The construction of Southern Brooklyn Crosstown Select Bus Service (SBS)
Category
Industrial Development
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction Procurement
Design Start
2018-07-17T00:00:00.000
Budget Forecast
111598000.00
Latest Budget Changes
20513000.00
Total Budget Changes
29789000.00
Forecast Completion
2026-10-29T00:00:00.000
Latest Schedule Changes
42
Total Schedule Changes
819
Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 112 • Project Name: Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Date Reported As Of
2023-01-01T00:00:00.000
Pid
112
Project Name
Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Description
Repair abutments, piers, approaches, and steel superstructure located in Pelham Bay, Bronx; replace reinforced concrete deck.
Category
Bridges, Streets and Roadways
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
1995-01-17T00:00:00.000
Budget Forecast
79204057.00
Latest Budget Changes
471000.00
Total Budget Changes
20945057.00
Forecast Completion
2023-07-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1592
49th Avenue Bridge Replacement
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 131 • Project Name: 49th Avenue Bridge Replacement
Date Reported As Of
2023-01-01T00:00:00.000
Pid
131
Project Name
49th Avenue Bridge Replacement
Description
Replace the 49th Avenue bridge over Long Island Railroad and Amtrak in Hunters Point, Queens.
Category
Bridges, Streets and Roadways
Borough
Queens
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-08-15T00:00:00.000
Budget Forecast
114154419.00
Latest Budget Changes
530000.00
Total Budget Changes
32902419.00
Forecast Completion
2028-10-16T00:00:00.000
Latest Schedule Changes
100
Total Schedule Changes
1449
Grand Concourse Metro North Railroad Bridge Construction
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 120 • Project Name: Grand Concourse Metro North Railroad Bridge Construction
Date Reported As Of
2023-01-01T00:00:00.000
Pid
120
Project Name
Grand Concourse Metro North Railroad Bridge Construction
Description
Repair the existing bridge and separate the NYCDOT and NYCT components. Includes new steel plate girders, concrete deck, pedestals, backwalls, sidewalks, and bridge railing.
Category
Bridges
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2000-02-14T00:00:00.000
Budget Forecast
72968117.00
Latest Budget Changes
-532000.00
Total Budget Changes
22682117.00
Forecast Completion
2023-01-16T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
836
Lower Concourse Initiative
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 575 • Project Name: Lower Concourse Initiative
Date Reported As Of
2023-01-01T00:00:00.000
Pid
575
Project Name
Lower Concourse Initiative
Description
The Project will improve the roadways and pedestrian facilities. The Project will consist of roadway reconstruction within Exterior Street between East 138th Street and East 150th Street.
Category
Industrial Development
Borough
Bronx
Managing Agency
EDC
Client Agency
EDC
Current Phase
Construction
Design Start
2017-04-01T00:00:00.000
Budget Forecast
79420367.00
Latest Budget Changes
-5100000.00
Total Budget Changes
-5100000.00
Forecast Completion
2023-09-01T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
730
Primary Treatment Improvement at Wards Island WWTP
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 452 • Project Name: Primary Treatment Improvement at Wards Island WWTP
Date Reported As Of
2023-01-01T00:00:00.000
Pid
452
Project Name
Primary Treatment Improvement at Wards Island WWTP
Description
Replacement of collector drives, scum trough dipping weirs and dump valves for ten primary settling tanks. Also included are Influent channel mixing and seal water system for the primary sludge pumps and concrete repairs.
Category
Wastewater Treatment
Borough
Manhattan
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2017-11-06T00:00:00.000
Budget Forecast
146107921.98
Latest Budget Changes
2277592.62
Total Budget Changes
99651290.98
Forecast Completion
2027-04-09T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2142
253 Broadway NYC. Fire Alarm Raplacement
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 850 • Project Name: 253 Broadway NYC. Fire Alarm Raplacement
Date Reported As Of
2023-01-01T00:00:00.000
Pid
850
Project Name
253 Broadway NYC. Fire Alarm Raplacement
Description
Installation of new building wide fire alarm and sprinkler distribution for 253 Broadway The PW357FIRE project has been divided into two phases. • Phase 1 - Fire alarm core to meet the PW77LYA project LPC office renovation - currently under construction • Phase 2 – Fire alarm branches, sprinkler system branches, and BMS – currently under bid package review phase
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Construction
Design Start
2018-01-22T00:00:00.000
Budget Forecast
57169000.00
Latest Budget Changes
0.00
Total Budget Changes
17827000.00
Forecast Completion
2026-12-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1553
Brooklyn Civil Court move to 210 Joralemon St
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 509 • Project Name: Brooklyn Civil Court move to 210 Joralemon St
Date Reported As Of
2023-01-01T00:00:00.000
Pid
509
Project Name
Brooklyn Civil Court move to 210 Joralemon St
Description
Relocation of Brooklyn Civil and Housing Court to 210 Joralemon St
Category
Public Safety and Criminal Justice
Borough
Brooklyn
Managing Agency
DCAS
Client Agency
DCAS
Current Phase
Construction
Design Start
2016-07-27T00:00:00.000
Budget Forecast
281430011.96
Latest Budget Changes
0.00
Total Budget Changes
200931011.96
Forecast Completion
2026-03-31T00:00:00.000
Latest Schedule Changes
301
Total Schedule Changes
1977
Central Park Light Infrastructure
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 586 • Project Name: Central Park Light Infrastructure
Date Reported As Of
2023-01-01T00:00:00.000
Pid
586
Project Name
Central Park Light Infrastructure
Description
Install, remove, and furnish equipment for electrical work associated with traffic signals, lighting, and distribution systems in Central Park, Manhattan.
Category
Parks, Streets and Roadways
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2016-04-29T00:00:00.000
Budget Forecast
39055476.00
Latest Budget Changes
-715712.00
Total Budget Changes
-3323649.60
Forecast Completion
2023-08-31T00:00:00.000
Latest Schedule Changes
62
Total Schedule Changes
1535
Bergen Avenue Street Reconstruction
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 170 • Project Name: Bergen Avenue Street Reconstruction
Date Reported As Of
2023-01-01T00:00:00.000
Pid
170
Project Name
Bergen Avenue Street Reconstruction
Description
Reconstruction of Bergen Avenue Area, including Storm Sewers, Water Mains, Street Lighting, Traffic Signal Work, and reconstruction of new outfall at East Mill Basin.
Category
Streets and Roadways
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction
Design Start
2012-12-03T00:00:00.000
Budget Forecast
79564000.00
Latest Budget Changes
0.00
Total Budget Changes
45837000.00
Forecast Completion
2023-06-24T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
-388
North River Wastewater Treatment Plant Cogeneration and Electrification
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 423 • Project Name: North River Wastewater Treatment Plant Cogeneration and Electrification
Date Reported As Of
2023-01-01T00:00:00.000
Pid
423
Project Name
North River Wastewater Treatment Plant Cogeneration and Electrification
Description
This project will replace the 10 existing pump and blower engines with electric motors for the main sewage pumps and a new cogeneration facility consisting of 5 new dual fuel engines and electrical service distribution upgrades.
Category
Wastewater Treatment
Borough
New York
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2013-07-01T00:00:00.000
Budget Forecast
287224972.88
Latest Budget Changes
1560089.01
Total Budget Changes
134242052.88
Forecast Completion
2024-01-13T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1712
Replacement of The Digester at The Hunts Point WWTP
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 580 • Project Name: Replacement of The Digester at The Hunts Point WWTP
Date Reported As Of
2023-01-01T00:00:00.000
Pid
580
Project Name
Replacement of The Digester at The Hunts Point WWTP
Description
Construction of New Anaerobic Digesters
Category
Wastewater Treatment
Borough
Bronx
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2017-10-22T00:00:00.000
Budget Forecast
393773004.14
Latest Budget Changes
0.00
Total Budget Changes
72852004.14
Forecast Completion
2026-04-04T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1355
Hannah Street Pumping Station Construction
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 364 • Project Name: Hannah Street Pumping Station Construction
Date Reported As Of
2023-01-01T00:00:00.000
Pid
364
Project Name
Hannah Street Pumping Station Construction
Description
This project will reconstruct the Hannah St. Pumping Station, the largest City-owned wastewater collection and pumping station on Staten Island. Built in 1977, the facility has numerous deficiencies, needing a comprehensive upgrade.
Category
Wastewater Treatment
Borough
Staten Island
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2012-08-03T00:00:00.000
Budget Forecast
109709196.80
Latest Budget Changes
6717034.57
Total Budget Changes
67909196.80
Forecast Completion
2026-06-23T00:00:00.000
Latest Schedule Changes
174
Total Schedule Changes
3238
Reconstruction of Power Distribution at Wards Island WWTP
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 453 • Project Name: Reconstruction of Power Distribution at Wards Island WWTP
Date Reported As Of
2023-01-01T00:00:00.000
Pid
453
Project Name
Reconstruction of Power Distribution at Wards Island WWTP
Description
Upgrades significant portions of the electrical distribution infrastructure including 3 power center installations, 15 motor control centers, 6 automatic transfer switches and 20 transformers throughout the plant
Category
Wastewater Treatment
Borough
Manhattan
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2019-06-04T00:00:00.000
Budget Forecast
149106268.26
Latest Budget Changes
0.00
Total Budget Changes
33489860.26
Forecast Completion
2028-03-04T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1147
Electronic Medical Records Upgrade
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 403 • Project Name: Electronic Medical Records Upgrade
Date Reported As Of
2023-01-01T00:00:00.000
Pid
403
Project Name
Electronic Medical Records Upgrade
Description
The EPIC - EMR Program: Electronic Medical Records (EMR) System - a single enterprise-wide EMR to meet the needs of HHC's expansive size and improve patient care will replace the legacy EMR - QuadraMed, which is over 25 years old.
Category
Health and Hospitals, IT
Borough
Citywide
Managing Agency
HHC
Client Agency
H+H
Current Phase
IT
Budget Forecast
764063231.00
Latest Budget Changes
0.00
Total Budget Changes
15184947.00
Forecast Completion
2023-12-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2032
Brooklyn Bridge - Approach Arches Rehabilitation
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 584 • Project Name: Brooklyn Bridge - Approach Arches Rehabilitation
Date Reported As Of
2023-01-01T00:00:00.000
Pid
584
Project Name
Brooklyn Bridge - Approach Arches Rehabilitation
Description
Rehabilitate approach arches and towers of Brooklyn Bridge. Including masonry cleaning, masonry repairs, repointing, rehabilition of transverse walls, new infill walls of the approach arch blocks. Clean and repoint the tower masonry, reinforce the gothic arches of the towers, and rehabilitate the tower tops.
Category
Bridges
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2016-04-13T00:00:00.000
Budget Forecast
333382674.00
Latest Budget Changes
-103247000.00
Total Budget Changes
33135732.10
Forecast Completion
2024-02-20T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1908
Investigation and Remediation of Corrosion in Water Tunnel Facilities
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 457 • Project Name: Investigation and Remediation of Corrosion in Water Tunnel Facilities
Date Reported As Of
2023-01-01T00:00:00.000
Pid
457
Project Name
Investigation and Remediation of Corrosion in Water Tunnel Facilities
Description
Design Services for Investigation and Remediation of Corrosion in Water Tunnel Facilities
Category
Water Supply
Borough
Citywide
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2022-07-12T00:00:00.000
Budget Forecast
56020208.84
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2029-05-31T00:00:00.000
Latest Schedule Changes
335
Total Schedule Changes
335
Emergency Communications Transformation Program (ECTP) Upgrades and Enhancements
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 267 • Project Name: Emergency Communications Transformation Program (ECTP) Upgrades and Enhancements
Date Reported As Of
2023-01-01T00:00:00.000
Pid
267
Project Name
Emergency Communications Transformation Program (ECTP) Upgrades and Enhancements
Description
Upgrade and enhancement of emergency technology infrastructure to improve interoperability and coordination among public safety agencies and improve call processing time to decrease overall response times.
Category
IT
Borough
Citywide
Managing Agency
DOITT
Client Agency
FDNY, NYPD
Current Phase
IT
Budget Forecast
2325426529.98
Latest Budget Changes
-1174838.83
Total Budget Changes
73735148.87
Forecast Completion
2024-03-01T00:00:00.000
Latest Schedule Changes
337
Total Schedule Changes
2252
Roosevelt Avenue Bridge Superstructure and Substructure Repairs
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 101 • Project Name: Roosevelt Avenue Bridge Superstructure and Substructure Repairs
Date Reported As Of
2023-01-01T00:00:00.000
Pid
101
Project Name
Roosevelt Avenue Bridge Superstructure and Substructure Repairs
Description
Repair the bridge superstructure and substructure and install a new concrete-filled steel grid deck.
Category
Bridges
Borough
Queens
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2003-03-10T00:00:00.000
Budget Forecast
147182213.00
Latest Budget Changes
-14677352.00
Total Budget Changes
23798213.00
Forecast Completion
2023-08-07T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2003
Bainbridge Avenue Trunk Water Main
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 454 • Project Name: Bainbridge Avenue Trunk Water Main
Date Reported As Of
2023-01-01T00:00:00.000
Pid
454
Project Name
Bainbridge Avenue Trunk Water Main
Description
Replacement of Trunk Water Main in Bainbridge Avenue Between Gunhill Road and Holly Lane and in Jerome Avenue Between Holly Lane and E233th Street, etc. Also, New 36" WM in West Burnside Avenue & Phelan Place
Category
Water Supply
Borough
Bronx
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2014-03-17T00:00:00.000
Budget Forecast
72349000.00
Latest Budget Changes
400000.00
Total Budget Changes
25547000.00
Forecast Completion
2023-06-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1687
Ped Safety Upgrades on Atlantic Avenue, Phase 2
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 519 • Project Name: Ped Safety Upgrades on Atlantic Avenue, Phase 2
Date Reported As Of
2023-01-01T00:00:00.000
Pid
519
Project Name
Ped Safety Upgrades on Atlantic Avenue, Phase 2
Description
PED. SAFETY UPGRADES ON ATLANTIC AVE - PH 2, BROOKLYN
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction
Design Start
2016-08-04T00:00:00.000
Budget Forecast
40012000.00
Latest Budget Changes
0.00
Total Budget Changes
10136496.00
Forecast Completion
2024-05-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1400
Williamsburg Bridge Miscellaneous Repairs and Painting
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 599 • Project Name: Williamsburg Bridge Miscellaneous Repairs and Painting
Date Reported As Of
2023-01-01T00:00:00.000
Pid
599
Project Name
Williamsburg Bridge Miscellaneous Repairs and Painting
Description
Scope includes paint the south side of the bridge, repair flags and structural steel, evaluate PP20 Bearings, evaluate tension rods at mid-span of the bridge, repair bridge cables and suspenders, replace modular joint, investigate the feasibility of additional clearance at towers, and resurface bridge decks with new waterproofing membrane.
Category
Bridges
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2018-08-15T00:00:00.000
Budget Forecast
222766947.00
Latest Budget Changes
-5306459.00
Total Budget Changes
52784947.00
Forecast Completion
2025-12-03T00:00:00.000
Latest Schedule Changes
-197
Total Schedule Changes
362
Riverside Drive/West 158th Street Bridge Rehabilitation
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 113 • Project Name: Riverside Drive/West 158th Street Bridge Rehabilitation
Date Reported As Of
2023-01-01T00:00:00.000
Pid
113
Project Name
Riverside Drive/West 158th Street Bridge Rehabilitation
Description
Replace deck of the Riverside Drive viaduct/ bridge over West 158th Street.
Category
Bridges, Streets and Roadways
Borough
Manhattan
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2014-10-22T00:00:00.000
Budget Forecast
151628794.00
Latest Budget Changes
7058936.00
Total Budget Changes
96922794.00
Forecast Completion
2025-05-21T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2152
RECONSTRUCTION OF QUEENS BLVD - PHASE 1
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 618 • Project Name: RECONSTRUCTION OF QUEENS BLVD - PHASE 1
Date Reported As Of
2023-01-01T00:00:00.000
Pid
618
Project Name
RECONSTRUCTION OF QUEENS BLVD - PHASE 1
Description
Vision Zero - Queens Boulevard - Segment 1: Roosevelt Avenue to 73rd Street. Variety of safety and streetscape improvements including partial street reconstruction and resurfacing to address roadway conditions
Category
Industrial Development
Borough
Queens
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2016-08-11T00:00:00.000
Budget Forecast
251711000.00
Latest Budget Changes
0.00
Total Budget Changes
176245000.00
Forecast Completion
2029-02-01T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1906
Gilboa Dam Reconstruction, Phase V
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 456 • Project Name: Gilboa Dam Reconstruction, Phase V
Date Reported As Of
2023-01-01T00:00:00.000
Pid
456
Project Name
Gilboa Dam Reconstruction, Phase V
Description
This is the final phase of the Gilboa Dam reconstruction project and includes reforestation, final site stabilization and wetlands mitigation measures.
Category
Water Supply
Borough
Upstate
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2020-12-30T00:00:00.000
Budget Forecast
36492236.00
Latest Budget Changes
-246464.00
Total Budget Changes
-3079490.00
Forecast Completion
2026-04-16T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
503
Replacement of the Esopus & Route 28A Railroad Bridges
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 443 • Project Name: Replacement of the Esopus & Route 28A Railroad Bridges
Date Reported As Of
2023-01-01T00:00:00.000
Pid
443
Project Name
Replacement of the Esopus & Route 28A Railroad Bridges
Description
Replacement of the Esopus & Route 28A Railroad Bridges
Category
Bridges
Borough
Olive
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2016-10-11T00:00:00.000
Budget Forecast
51873522.24
Latest Budget Changes
663242.28
Total Budget Changes
-50461071.35
Forecast Completion
2025-11-09T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
714
Carl Schurz Park Promenade over FDR (East 81st to 90th Streets)
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 537 • Project Name: Carl Schurz Park Promenade over FDR (East 81st to 90th Streets)
Date Reported As Of
2023-01-01T00:00:00.000
Pid
537
Project Name
Carl Schurz Park Promenade over FDR (East 81st to 90th Streets)
Description
Replace the Promenade over FDR Drive between East 81st to 90th Streets in Manhattan.
Category
Bridges
Borough
Manhattan
Managing Agency
DOT
Client Agency
DOT, DPR
Current Phase
Design
Design Start
2017-05-30T00:00:00.000
Budget Forecast
115852421.00
Latest Budget Changes
115852421.00
Total Budget Changes
-197139579.00
Forecast Completion
2030-02-18T00:00:00.000
Latest Schedule Changes
141
Total Schedule Changes
1571
Power Distribution at Bowery Bay WWTP
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 522 • Project Name: Power Distribution at Bowery Bay WWTP
Date Reported As Of
2023-01-01T00:00:00.000
Pid
522
Project Name
Power Distribution at Bowery Bay WWTP
Description
Power Distribution at Bowery Bay WWTP.
Category
Wastewater Treatment
Borough
Queens
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2015-11-13T00:00:00.000
Budget Forecast
69734919.01
Latest Budget Changes
861154.88
Total Budget Changes
24235381.01
Forecast Completion
2025-07-22T00:00:00.000
Latest Schedule Changes
210
Total Schedule Changes
1684
GI - GRAVESEND BAY CSO - PHASE III
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 1199 • Project Name: GI - GRAVESEND BAY CSO - PHASE III
Date Reported As Of
2023-01-01T00:00:00.000
Pid
1199
Project Name
GI - GRAVESEND BAY CSO - PHASE III
Description
GREEN INFRASTRUCTURE IN OH-015 GRAVESEND BAY CSO PH 3
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2017-08-01T00:00:00.000
Budget Forecast
49132000.00
Latest Budget Changes
0.00
Total Budget Changes
-372000.00
Forecast Completion
2025-11-19T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
189
STM & SAN SWR, WILLET PT BLVD WHITESTONE AREA, PH2
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 651 • Project Name: STM & SAN SWR, WILLET PT BLVD WHITESTONE AREA, PH2
Date Reported As Of
2023-01-01T00:00:00.000
Pid
651
Project Name
STM & SAN SWR, WILLET PT BLVD WHITESTONE AREA, PH2
Description
Installation of Storm sewers, Sanitary sewers, & Water mains in Whitestone Area.
Category
Sewers
Borough
Queens
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2013-03-15T00:00:00.000
Budget Forecast
110525000.00
Latest Budget Changes
0.00
Total Budget Changes
41243000.00
Forecast Completion
2023-05-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
642
Madison Avenue Bridge Reconstruction
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 114 • Project Name: Madison Avenue Bridge Reconstruction
Date Reported As Of
2023-01-01T00:00:00.000
Pid
114
Project Name
Madison Avenue Bridge Reconstruction
Description
Replace the electrical and mechanical systems of the Madison Avenue Bridge.
Category
Bridges
Borough
Manhattan, Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2011-02-14T00:00:00.000
Budget Forecast
56546302.00
Latest Budget Changes
1121903.00
Total Budget Changes
2036997.00
Forecast Completion
2023-01-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1628
Park Avenue Tunnel (Murray Hill)
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 536 • Project Name: Park Avenue Tunnel (Murray Hill)
Date Reported As Of
2023-01-01T00:00:00.000
Pid
536
Project Name
Park Avenue Tunnel (Murray Hill)
Description
Repair Park Avenue tunnel, located in Midtown, Manhattan.
Category
Bridges
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2006-08-01T00:00:00.000
Budget Forecast
46066272.00
Latest Budget Changes
3041858.00
Total Budget Changes
-17773389.61
Forecast Completion
2023-05-02T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1568
Catskill Aqueduct Repair and Rehabilitation
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 478 • Project Name: Catskill Aqueduct Repair and Rehabilitation
Date Reported As Of
2023-01-01T00:00:00.000
Pid
478
Project Name
Catskill Aqueduct Repair and Rehabilitation
Description
Project to ensure the reliability of the 74 mile upper Catskill Aqueduct, including replacement of mechanical components, leak mitigation, and biofilm removal/condition assessment.
Category
Water Supply
Borough
Citywide
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2015-06-19T00:00:00.000
Budget Forecast
237517401.68
Latest Budget Changes
-4752101.50
Total Budget Changes
9642889.68
Forecast Completion
2022-11-30T00:00:00.000
Latest Schedule Changes
15
Total Schedule Changes
1517
Grand Concourse Reconstruction, Phase 4 (Great Streets)
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 476 • Project Name: Grand Concourse Reconstruction, Phase 4 (Great Streets)
Date Reported As Of
2023-01-01T00:00:00.000
Pid
476
Project Name
Grand Concourse Reconstruction, Phase 4 (Great Streets)
Description
RECONSTRUCTION OF GRAND CONCOURSE FROM E 175 ST TO EAST FORDHAM RD- PHASE 4, BX
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction
Design Start
2016-07-19T00:00:00.000
Budget Forecast
96108000.00
Latest Budget Changes
0.00
Total Budget Changes
57634000.00
Forecast Completion
2023-06-13T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1448
Shore Road Bridge over Hutchinson River
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 541 • Project Name: Shore Road Bridge over Hutchinson River
Date Reported As Of
2023-01-01T00:00:00.000
Pid
541
Project Name
Shore Road Bridge over Hutchinson River
Description
Replace the Shore Road Bridge over the Hutchinson River with a new bridge.
Category
Bridges, Streets and Roadways
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-06-30T00:00:00.000
Budget Forecast
339641078.00
Latest Budget Changes
-1091765.00
Total Budget Changes
-19049921.84
Forecast Completion
2030-01-02T00:00:00.000
Latest Schedule Changes
162
Total Schedule Changes
1477
Boston Road Bridge Over Hutchinson River Rehabilitation
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 539 • Project Name: Boston Road Bridge Over Hutchinson River Rehabilitation
Date Reported As Of
2023-01-01T00:00:00.000
Pid
539
Project Name
Boston Road Bridge Over Hutchinson River Rehabilitation
Description
Rehabilitation of Boston Road Bridge over Hutchinson River, located in the Bornx.
Category
Bridges, Streets and Roadways
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction Procurement
Design Start
2018-04-16T00:00:00.000
Budget Forecast
88359814.00
Latest Budget Changes
10880806.00
Total Budget Changes
49309814.00
Forecast Completion
2026-05-26T00:00:00.000
Latest Schedule Changes
110
Total Schedule Changes
803
Storm Mitigation Loan Program at Bowery Bay
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 671 • Project Name: Storm Mitigation Loan Program at Bowery Bay
Date Reported As Of
2023-01-01T00:00:00.000
Pid
671
Project Name
Storm Mitigation Loan Program at Bowery Bay
Description
SMLP portion for Bowery Bay WWTP as part of the New York City Wastewater Resiliency Program.
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2018-04-30T00:00:00.000
Budget Forecast
38312242.41
Latest Budget Changes
0.00
Total Budget Changes
-19623216.41
Forecast Completion
2023-09-11T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1026
Gilboa Dam Reconstruction, Phase III
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 405 • Project Name: Gilboa Dam Reconstruction, Phase III
Date Reported As Of
2023-01-01T00:00:00.000
Pid
405
Project Name
Gilboa Dam Reconstruction, Phase III
Description
Gilboa Dam Reconstruction Project includes construction of a new low level outlet (LLO) consisting of 2,000 feet of tunneling , an access shaft, oulet structure and gate valve controls.
Category
Water Supply
Borough
Upstate
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2004-03-18T00:00:00.000
Budget Forecast
199398344.49
Latest Budget Changes
-1313992.21
Total Budget Changes
10376533.49
Forecast Completion
2023-06-15T00:00:00.000
Latest Schedule Changes
81
Total Schedule Changes
1113
Reconstruction of the Port Jervis Wastewater Treatment Plant
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 444 • Project Name: Reconstruction of the Port Jervis Wastewater Treatment Plant
Date Reported As Of
2023-01-01T00:00:00.000
Pid
444
Project Name
Reconstruction of the Port Jervis Wastewater Treatment Plant
Description
Reconstruction of the Port Jervis WWTP as required based on the effluent limits proposed by the Delaware River Basin Commission (DRBC)
Category
Wastewater Treatment
Borough
Port Jervis
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2014-06-17T00:00:00.000
Budget Forecast
60624916.55
Latest Budget Changes
0.00
Total Budget Changes
9428438.55
Forecast Completion
2026-10-04T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2445
Studio Museum in Harlem New Building
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 896 • Project Name: Studio Museum in Harlem New Building
Date Reported As Of
2023-01-01T00:00:00.000
Pid
896
Project Name
Studio Museum in Harlem New Building
Description
The Project will combine two adjacent lots on 125th Street: the sculpture court, City-owned lot 11, and the Museum building on lot 9, owned by the Museum. Existing structures on both lots will be demolished for the new, six story 82,000sf City owned building.
Category
Arts and Culture
Managing Agency
DDC
Client Agency
Cultural Affairs
Current Phase
Construction
Design Start
2018-09-25T00:00:00.000
Budget Forecast
59141000.00
Latest Budget Changes
0.00
Total Budget Changes
-190000.00
Forecast Completion
2024-06-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
856