Capital Projects

All major infrastructure and information technology projects with a budget of $25 million or more that are currently active (in the design, procurement, or construction phase).

City Government Mayor's Office of Operations (OPS) Dataset n7gv-k5yt 16 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
Reconstruct Main Sewage Pump Controls at Port Richmond WWTP
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 948 • Project Name: Reconstruct Main Sewage Pump Controls at Port Richmond WWTP
Date Reported As Of
2021-07-01T00:00:00.000
Pid
948
Project Name
Reconstruct Main Sewage Pump Controls at Port Richmond WWTP
Description
Reconstruction of main sewage pumps and ancillary components including suction valves, suction piping, seal water system, pressure gauges, suction header, etc. New MSP's should meet the new design parameter of N+2 redundancy during wet weather flow
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2019-09-03T00:00:00.000
Budget Forecast
48220341.39
Latest Budget Changes
210273.00
Total Budget Changes
26923720.62
Forecast Completion
2026-04-26T00:00:00.000
Latest Schedule Changes
62
Total Schedule Changes
516
Pelham Bay Equestrian Park over Amtrak
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 703 • Project Name: Pelham Bay Equestrian Park over Amtrak
Date Reported As Of
2021-07-01T00:00:00.000
Pid
703
Project Name
Pelham Bay Equestrian Park over Amtrak
Description
Replace/Rehab the Pelham Bay Equestrian Park bridge over Amtrak, the Bronx
Category
Bridges
Borough
Bronx
Managing Agency
DOT
Client Agency
DPR
Current Phase
Design
Design Start
2019-01-30T00:00:00.000
Budget Forecast
41828997.00
Latest Budget Changes
-500000.00
Total Budget Changes
137997.00
Forecast Completion
2026-05-17T00:00:00.000
Latest Schedule Changes
-687
Total Schedule Changes
1029
253 Broadway NYC. Fire Alarm Raplacement
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 850 • Project Name: 253 Broadway NYC. Fire Alarm Raplacement
Date Reported As Of
2021-07-01T00:00:00.000
Pid
850
Project Name
253 Broadway NYC. Fire Alarm Raplacement
Description
Installation of new building wide fire alarm and sprinkler distribution for 253 Broadway The PW357FIRE project has been divided into two phases. � Phase 1 - Fire alarm core to meet the PW77LYA project LPC office renovation - currently under construction � Phase 2 � Fire alarm branches, sprinkler system branches, and BMS � currently under bid package review phase
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Construction
Design Start
2018-01-22T00:00:00.000
Budget Forecast
31917000.00
Latest Budget Changes
2283000.00
Total Budget Changes
17827000.00
Forecast Completion
2026-12-31T00:00:00.000
Latest Schedule Changes
1701
Total Schedule Changes
1553
New York State Pavilion Observation Towers Reconstruction
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 1018 • Project Name: New York State Pavilion Observation Towers Reconstruction
Date Reported As Of
2021-07-01T00:00:00.000
Pid
1018
Project Name
New York State Pavilion Observation Towers Reconstruction
Description
This project will reconstruct portions of the New York State Pavilion Observation Towers in Flushing Meadows Corona Park.
Category
Parks
Managing Agency
DPR
Client Agency
DPR
Current Phase
Construction
Design Start
2015-09-21T00:00:00.000
Budget Forecast
28778000.00
Latest Budget Changes
0.00
Total Budget Changes
1000.00
Forecast Completion
2022-02-28T00:00:00.000
Latest Schedule Changes
223
Total Schedule Changes
772
Kensico Eastview Connection Tunnel Construction
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 554 • Project Name: Kensico Eastview Connection Tunnel Construction
Date Reported As Of
2021-07-01T00:00:00.000
Pid
554
Project Name
Kensico Eastview Connection Tunnel Construction
Description
A new 2+ mile, 27-ft internal diameter tunnel between Kensico and the Cat-Del UV Facility. The tunnel will include a new screen chamber and rehab of existing intake, and will provide critical redundancy to the Delaware Aqueduct in this area.
Category
Water Supply
Borough
Valhalla
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2017-08-01T00:00:00.000
Budget Forecast
1902139633.60
Latest Budget Changes
0.00
Total Budget Changes
881770648.00
Forecast Completion
2031-05-17T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
3132
Cunningham Park Garage Reconstruction
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 1019 • Project Name: Cunningham Park Garage Reconstruction
Date Reported As Of
2021-07-01T00:00:00.000
Pid
1019
Project Name
Cunningham Park Garage Reconstruction
Description
This project will reconstruct the garage in Cunningham Park.
Category
Parks
Managing Agency
DPR
Client Agency
DPR
Current Phase
Construction Procurement
Design Start
2018-11-19T00:00:00.000
Budget Forecast
27060000.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2023-08-30T00:00:00.000
Latest Schedule Changes
95
Total Schedule Changes
703
Brooklyn Public School 322 New Construction
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 1104 • Project Name: Brooklyn Public School 322 New Construction
Date Reported As Of
2021-07-01T00:00:00.000
Pid
1104
Project Name
Brooklyn Public School 322 New Construction
Description
NEW SCHOOL
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction Procurement
Design Start
2020-06-04T00:00:00.000
Budget Forecast
85395900.00
Total Budget Changes
0.00
Forecast Completion
2024-09-03T00:00:00.000
Total Schedule Changes
0
East 180th Street over Metro North Railroad (Harrison Line)
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 811 • Project Name: East 180th Street over Metro North Railroad (Harrison Line)
Date Reported As Of
2021-07-01T00:00:00.000
Pid
811
Project Name
East 180th Street over Metro North Railroad (Harrison Line)
Description
Rehabilitation of East 180th Street Bridge over Metro North Railroad, the Bronx
Category
Bridges
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2017-02-06T00:00:00.000
Budget Forecast
36999378.00
Latest Budget Changes
-2350000.00
Total Budget Changes
4194366.00
Forecast Completion
2023-10-26T00:00:00.000
Latest Schedule Changes
10
Total Schedule Changes
664
Red Hook Recreation Area Track 1, Soccer Fields 3-5, and Ballfields 1-4 Reconstruction
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 974 • Category: Parks
Date Reported As Of
2021-07-01T00:00:00.000
Pid
974
Project Name
Red Hook Recreation Area Track 1, Soccer Fields 3-5, and Ballfields 1-4 Reconstruction
Description
This project will reconstruct the track & field and convert three soccer fields and four ballfields from natural turf to synthetic turf at Red Hook Recreation Area.
Category
Parks
Managing Agency
DPR
Client Agency
DPR
Current Phase
Construction
Design Start
2017-11-01T00:00:00.000
Budget Forecast
68712000.00
Latest Budget Changes
0.00
Total Budget Changes
-10555000.00
Forecast Completion
2023-01-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1082
Gilboa Dam Reconstruction, Phase IV
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 406 • Project Name: Gilboa Dam Reconstruction, Phase IV
Date Reported As Of
2021-07-01T00:00:00.000
Pid
406
Project Name
Gilboa Dam Reconstruction, Phase IV
Description
This project will rehabilitate the mechanics and the architecture of the Shandaken Tunnel Intake Chamber, which includes the replacement of gates and general site improvements.
Category
Water Supply
Borough
Upstate
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2008-12-01T00:00:00.000
Budget Forecast
72818170.00
Latest Budget Changes
3038.10
Total Budget Changes
33535991.20
Forecast Completion
2022-02-15T00:00:00.000
Latest Schedule Changes
-1
Total Schedule Changes
1684
Alley Pond Environmental Center Reconstruction
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 1017 • Project Name: Alley Pond Environmental Center Reconstruction
Date Reported As Of
2021-07-01T00:00:00.000
Pid
1017
Project Name
Alley Pond Environmental Center Reconstruction
Description
This project will demolish and construct a new environmental center in Alley Pond Park.
Category
Parks
Managing Agency
DPR
Client Agency
DPR
Current Phase
Construction
Design Start
2010-02-24T00:00:00.000
Budget Forecast
30497000.00
Latest Budget Changes
-1000.00
Total Budget Changes
1641000.00
Forecast Completion
2022-07-29T00:00:00.000
Latest Schedule Changes
227
Total Schedule Changes
556
EASTERN PARKWAY LIBRARY MAJOR RENOVATIONS
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 1191 • Project Name: EASTERN PARKWAY LIBRARY MAJOR RENOVATIONS
Date Reported As Of
2021-07-01T00:00:00.000
Pid
1191
Project Name
EASTERN PARKWAY LIBRARY MAJOR RENOVATIONS
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
Libraries-BPL
Current Phase
Design
Design Start
2018-06-28T00:00:00.000
Budget Forecast
35381000.00
Total Budget Changes
493000.00
Forecast Completion
2024-12-08T00:00:00.000
Total Schedule Changes
389
Construction of Gowanus CSO retention FAC Superfund Site
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 550 • Project Name: Construction of Gowanus CSO retention FAC Superfund Site
Date Reported As Of
2021-07-01T00:00:00.000
Pid
550
Project Name
Construction of Gowanus CSO retention FAC Superfund Site
Description
CSO Facilities, bulkheads, pilots and other requirements to comply with Gowanus Canal Superfund Adminstrative Orders
Category
Industrial Development
Borough
Brooklyn
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction Procurement
Design Start
2017-11-22T00:00:00.000
Budget Forecast
1547300000.00
Latest Budget Changes
-11000000.00
Total Budget Changes
432995114.00
Forecast Completion
2031-11-25T00:00:00.000
Latest Schedule Changes
141
Total Schedule Changes
1086
BROWNSVILLE LIBRARY MAJOR RENOVATIONS
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 977 • Project Name: BROWNSVILLE LIBRARY MAJOR RENOVATIONS
Date Reported As Of
2021-07-01T00:00:00.000
Pid
977
Project Name
BROWNSVILLE LIBRARY MAJOR RENOVATIONS
Description
The Brownsville Library is a comprehensive interior/exterior renovation and addition which includes new fire alarm/BMS, new interior layout, new HVAC, new accessible restrooms, exterior rehabilitation and landscape.
Category
Libraries
Managing Agency
DDC
Client Agency
Libraries-BPL
Current Phase
Design
Design Start
2018-07-27T00:00:00.000
Budget Forecast
32015000.00
Latest Budget Changes
6513000.00
Total Budget Changes
6752000.00
Forecast Completion
2026-01-02T00:00:00.000
Latest Schedule Changes
368
Total Schedule Changes
916
Bellevue Medical Center Priority Mitigation Projects
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 545 • Project Name: Bellevue Medical Center Priority Mitigation Projects
Date Reported As Of
2021-07-01T00:00:00.000
Pid
545
Project Name
Bellevue Medical Center Priority Mitigation Projects
Description
Priority mitigation projects for the repair/restoration and hazard mitigation for Bellevue Hospital, damaged during Superstorm Sandy
Category
Health and Hospitals
Borough
Manhattan
Managing Agency
EDC
Client Agency
H+H
Current Phase
Construction
Design Start
2014-01-01T00:00:00.000
Budget Forecast
46807309.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2022-04-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1854
Bronx Public School 077 Addition
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 1101 • Project Name: Bronx Public School 077 Addition
Date Reported As Of
2021-07-01T00:00:00.000
Pid
1101
Project Name
Bronx Public School 077 Addition
Description
ADDITION / EXISTING SCHOOL RENOVATION WORK (PHASE I) / DEMOLITION (PHASE II)
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2019-09-25T00:00:00.000
Budget Forecast
86862349.00
Total Budget Changes
0.00
Forecast Completion
2024-09-03T00:00:00.000
Total Schedule Changes
0
Harlem River Drive Ramp Reconstruction (George Washington Bridge)
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 708 • Project Name: Harlem River Drive Ramp Reconstruction (George Washington Bridge)
Date Reported As Of
2021-07-01T00:00:00.000
Pid
708
Project Name
Harlem River Drive Ramp Reconstruction (George Washington Bridge)
Description
Repair the Harlem River Drive Ramp to George Washington Bridge over Harlem River Drive Southbound (Trans-Manhattan Expressway), Manhattan
Category
Bridges, Streets and Roadways
Borough
Manhattan
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2019-02-07T00:00:00.000
Budget Forecast
430082546.00
Latest Budget Changes
-500000.00
Total Budget Changes
-3711870.00
Forecast Completion
2033-07-08T00:00:00.000
Latest Schedule Changes
1614
Total Schedule Changes
2697
New Ferry Boat Construction
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 94 • Project Name: New Ferry Boat Construction
Date Reported As Of
2021-07-01T00:00:00.000
Pid
94
Project Name
New Ferry Boat Construction
Description
Replace one Barberi class boat and the John F. Kennedy boat which are approaching the end of their useful lives with new Staten Island ferries. Replacement is needed to continue reliable service.
Category
Ferries
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2014-09-15T00:00:00.000
Budget Forecast
23683112.00
Latest Budget Changes
-343567411.00
Total Budget Changes
-238419180.00
Forecast Completion
2021-12-06T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
549
Bronx Public School 469 New Construction
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 1102 • Project Name: Bronx Public School 469 New Construction
Date Reported As Of
2021-07-01T00:00:00.000
Pid
1102
Project Name
Bronx Public School 469 New Construction
Description
NEW SCHOOL
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction Procurement
Design Start
2020-03-13T00:00:00.000
Budget Forecast
81015110.00
Total Budget Changes
-505800.00
Forecast Completion
2024-09-03T00:00:00.000
Total Schedule Changes
0
Coler Specialty Hospital Priority Mitigation Projects
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 544 • Project Name: Coler Specialty Hospital Priority Mitigation Projects
Date Reported As Of
2021-07-01T00:00:00.000
Pid
544
Project Name
Coler Specialty Hospital Priority Mitigation Projects
Description
The priority mitigation projects at Coler include key critical mitigation projects to improve the resiliency of the campus.
Category
Health and Hospitals
Borough
Manhattan
Managing Agency
EDC
Client Agency
H+H
Current Phase
Construction
Design Start
2014-09-01T00:00:00.000
Budget Forecast
21529654.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2022-12-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2085
HIGH LEVEL STM SEWERS IN GOWANUS CANAL AREA-PH II
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 849 • Project Name: HIGH LEVEL STM SEWERS IN GOWANUS CANAL AREA-PH II
Date Reported As Of
2021-07-01T00:00:00.000
Pid
849
Project Name
HIGH LEVEL STM SEWERS IN GOWANUS CANAL AREA-PH II
Description
High Level Storm and Combine Sewer installation and Water Main replacement in Gowanus Canal Area Phase-2, Brooklyn.
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2016-09-30T00:00:00.000
Budget Forecast
40014000.00
Latest Budget Changes
5431000.00
Total Budget Changes
8657000.00
Forecast Completion
2022-04-27T00:00:00.000
Latest Schedule Changes
210
Total Schedule Changes
813
Brkyln District 17/18 Garage: HVAC Replacement
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 1190 • Project Name: Brkyln District 17/18 Garage: HVAC Replacement
Date Reported As Of
2021-07-01T00:00:00.000
Pid
1190
Project Name
Brkyln District 17/18 Garage: HVAC Replacement
Description
Roof andThe project for which services are required is the rehabilitation of the Brooklyn Districts 17 and 18 Sanitation Garage, located at 10502 Avenue D, Brooklyn, NY 11236. Block: 8136/Lot: 1. The 159,500 total gross square foot, masonry-veneered and steel framed facility is located in eastern Brooklyn at the intersection of the Avenue D and the 105th St. This building was completed in 1991 and was last renovated in 1998. The main objective of this project is to extend the useful life of this facility through rehabilitation of the building Roofing, and HVAC systems and adding a Solar Ready Systems. The rehabilitation shall include the following: replacement of the roof (membrane, select areas of decking, select roof drains and domes, select skylights and coordination for future solar panel locations), structural work (stiffening of the existing structural steel frame, supports for new HVAC equipment and solar panels and select parapet replacement), select replacement of building systems (electrical, fire protection and HVAC (including BMS)), building expansion joints and architectural renovation of the entire building to repair water damage. The funding for solar program provided by DCAS. Scope of Work: The rehabilitation shall include the following: replacement of the roof (membrane, select areas of decking, select roof drains and domes, select skylights and coordination for future solar panel locations), structural work (stiffening of the existing structural steel frame, supports for new HVAC equipment and solar panels and select parapet replacement), select replacement of building systems (electrical, fire protection and HVAC (including BMS)),
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
Sanitation
Current Phase
Construction Procurement
Design Start
2017-05-11T00:00:00.000
Budget Forecast
34158000.00
Total Budget Changes
-709000.00
Forecast Completion
2024-06-30T00:00:00.000
Total Schedule Changes
123
Combined Sewer In 70Th Street, Queens
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 788 • Project Name: Combined Sewer In 70Th Street, Queens
Date Reported As Of
2021-07-01T00:00:00.000
Pid
788
Project Name
Combined Sewer In 70Th Street, Queens
Description
COMBINED SEWER IN 70TH STREET, QUEENS
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2016-08-31T00:00:00.000
Budget Forecast
123425000.00
Latest Budget Changes
3725000.00
Total Budget Changes
94201000.00
Forecast Completion
2023-08-10T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1155
Gilboa Dam Reconstruction, Phase III
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 405 • Project Name: Gilboa Dam Reconstruction, Phase III
Date Reported As Of
2021-07-01T00:00:00.000
Pid
405
Project Name
Gilboa Dam Reconstruction, Phase III
Description
Gilboa Dam Reconstruction Project includes construction of a new low level outlet (LLO) consisting of 2,000 feet of tunneling, an access shaft, oulet structure and gate valve controls.
Category
Water Supply
Borough
Upstate
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2004-03-18T00:00:00.000
Budget Forecast
206670118.67
Latest Budget Changes
325604.46
Total Budget Changes
10376533.49
Forecast Completion
2022-07-03T00:00:00.000
Latest Schedule Changes
48
Total Schedule Changes
1113
Freshkills South Park Synthetic Turf Fields and Landscape Construction
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 1016 • Project Name: Freshkills South Park Synthetic Turf Fields and Landscape Construction
Date Reported As Of
2021-07-01T00:00:00.000
Pid
1016
Project Name
Freshkills South Park Synthetic Turf Fields and Landscape Construction
Description
This project will construct synthetic turf athletic fields, roadways, a parking lot with associated landscaping and stormwater management, multi-use and pedestrian paths, benches, signage, fencing, and lighting, and restore woodlands and wetlands.
Category
Parks
Managing Agency
DPR
Client Agency
DPR
Current Phase
Design
Design Start
2016-11-30T00:00:00.000
Budget Forecast
39111000.00
Latest Budget Changes
1165413.72
Total Budget Changes
1436858.72
Forecast Completion
2024-04-17T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1309
Shore Road Bridge over Hutchinson River
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 541 • Project Name: Shore Road Bridge over Hutchinson River
Date Reported As Of
2021-07-01T00:00:00.000
Pid
541
Project Name
Shore Road Bridge over Hutchinson River
Description
Replace the Shore Road Bridge over the Hutchinson River with a new bridge.
Category
Bridges, Streets and Roadways
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-06-30T00:00:00.000
Budget Forecast
323375743.00
Latest Budget Changes
-750000.00
Total Budget Changes
-19049921.84
Forecast Completion
2029-03-31T00:00:00.000
Latest Schedule Changes
-106
Total Schedule Changes
1477
Queens Public School 472 New Construction
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 1099 • Project Name: Queens Public School 472 New Construction
Date Reported As Of
2021-07-01T00:00:00.000
Pid
1099
Project Name
Queens Public School 472 New Construction
Description
NEW SCHOOL
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2019-01-07T00:00:00.000
Budget Forecast
251284250.00
Total Budget Changes
0.00
Forecast Completion
2025-09-03T00:00:00.000
Total Schedule Changes
0
North River WWTP Primary Treatment Improvements
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 945 • Project Name: North River WWTP Primary Treatment Improvements
Date Reported As Of
2021-07-01T00:00:00.000
Pid
945
Project Name
North River WWTP Primary Treatment Improvements
Description
Rehabilitation of the Primary Settling Tanks at North River Wastewater Resources Recovery Facility.
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2021-05-17T00:00:00.000
Budget Forecast
165300000.00
Latest Budget Changes
0.00
Total Budget Changes
35891899.00
Forecast Completion
2027-11-25T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
121
Brooklyn Public School 676 New Construction
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 1100 • Project Name: Brooklyn Public School 676 New Construction
Date Reported As Of
2021-07-01T00:00:00.000
Pid
1100
Project Name
Brooklyn Public School 676 New Construction
Description
NEW SCHOOL
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2020-08-12T00:00:00.000
Budget Forecast
92786690.00
Total Budget Changes
1339880.00
Forecast Completion
2024-09-03T00:00:00.000
Total Schedule Changes
0
Staten Island 1 & 3 Garage Construction & Rehab
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 769 • Project Name: Staten Island 1 & 3 Garage Construction & Rehab
Date Reported As Of
2021-07-01T00:00:00.000
Pid
769
Project Name
Staten Island 1 & 3 Garage Construction & Rehab
Description
The Department of Sanitation of the City of New York (DSNY) is planning to develop a Staten Island Districts 1 and 3 campus that will include a new garage serving both districts and renovation of the existing Borough Repair Shop. The site is to be reconfigured with new grading and drainage, new covered salt storage, new outdoor fueling, new household special waste collection, outdoor DSNY truck parking and a new force main sanitary line to connect to the NYC DEP sewer.
Category
Sanitation
Borough
Staten Island
Managing Agency
DDC
Client Agency
Sanitation
Current Phase
Construction
Design Start
2017-07-14T00:00:00.000
Budget Forecast
187208000.00
Latest Budget Changes
4073000.00
Total Budget Changes
68555000.00
Forecast Completion
2023-09-01T00:00:00.000
Latest Schedule Changes
-178
Total Schedule Changes
406
Wyckoff Avenue Street Reconstruction
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 191 • Project Name: Wyckoff Avenue Street Reconstruction
Date Reported As Of
2021-07-01T00:00:00.000
Pid
191
Project Name
Wyckoff Avenue Street Reconstruction
Description
Reconstruction of Wyckoff Avenue from Flushing Avenue to Cooper Avenue, in the Boroughs of Brooklyn and Queens..
Category
Streets and Roadways
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Trans. & Env. Protection
Current Phase
Design
Design Start
2017-03-29T00:00:00.000
Budget Forecast
73992000.00
Latest Budget Changes
-83000.00
Total Budget Changes
43926000.00
Forecast Completion
2028-03-30T00:00:00.000
Latest Schedule Changes
1828
Total Schedule Changes
226
Battery Park Underpass Emergency Relief Betterments
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 540 • Project Name: Battery Park Underpass Emergency Relief Betterments
Date Reported As Of
2021-07-01T00:00:00.000
Pid
540
Project Name
Battery Park Underpass Emergency Relief Betterments
Description
Resiliency betterments for Battery Park and West Street underpasses.
Category
Bridges
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2018-04-01T00:00:00.000
Budget Forecast
66713670.00
Latest Budget Changes
46593141.00
Total Budget Changes
47923308.00
Forecast Completion
2024-04-29T00:00:00.000
Latest Schedule Changes
761
Total Schedule Changes
1197
Riverside Drive/West 158th Street Bridge Rehabilitation
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 113 • Project Name: Riverside Drive/West 158th Street Bridge Rehabilitation
Date Reported As Of
2021-07-01T00:00:00.000
Pid
113
Project Name
Riverside Drive/West 158th Street Bridge Rehabilitation
Description
Replace deck of the Riverside Drive viaduct/ bridge over West 158th Street.
Category
Bridges, Streets and Roadways
Borough
Manhattan
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2014-10-22T00:00:00.000
Budget Forecast
135684340.00
Latest Budget Changes
-18000.00
Total Budget Changes
96922794.00
Forecast Completion
2023-10-13T00:00:00.000
Latest Schedule Changes
473
Total Schedule Changes
2152
Rehab Of Queens District 11/13 Sanitation Garage
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 770 • Project Name: Rehab Of Queens District 11/13 Sanitation Garage
Date Reported As Of
2021-07-01T00:00:00.000
Pid
770
Project Name
Rehab Of Queens District 11/13 Sanitation Garage
Description
The Department of Sanitation of the City of New York (DSNY) is planning to rehabilitate Queens Districts 11 and 13 garage. The renovation serving both districts is to extend the useful life of the facility through rehabilitation of the building structure and systems. The renovation includes: Extensive structural work that includes the replacement of reinforced concrete slabs and stiffening of the existing steel frame, select replacement of building MEP systems, including BMS systems, architectural renovation of the entire building, study and implementation of deep energy conservation measures (DECMs), and site work which includes new landscape work and replacement of sidewalks and driveways. Rehabilitation is required to meet LEED Silver requirements.
Category
Sanitation
Borough
Queens
Managing Agency
DDC
Client Agency
Sanitation
Current Phase
Design
Design Start
2017-03-06T00:00:00.000
Budget Forecast
72557000.00
Latest Budget Changes
4463000.00
Total Budget Changes
36221000.00
Forecast Completion
2025-06-30T00:00:00.000
Latest Schedule Changes
730
Total Schedule Changes
1521
Douglaston New Facility
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 960 • Project Name: Douglaston New Facility
Date Reported As Of
2021-07-01T00:00:00.000
Pid
960
Project Name
Douglaston New Facility
Category
Libraries
Managing Agency
DDC
Client Agency
Libraries-QBPL
Total Budget Changes
5348000.00
Total Schedule Changes
244
CITYWIDE RESILENCY MEASURES-Lower Manhattan Two Bridges
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 1187 • Project Name: CITYWIDE RESILENCY MEASURES-Lower Manhattan Two Bridges
Date Reported As Of
2021-07-01T00:00:00.000
Pid
1187
Project Name
CITYWIDE RESILENCY MEASURES-Lower Manhattan Two Bridges
Description
Installation of Brooklyn Bridge - Montgomery Coastal Resilience from Robert F. Wagner Sr. Place to Montgomery Street
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Mayors Office of Resiliency (MOR)
Current Phase
Design
Design Start
2019-02-22T00:00:00.000
Budget Forecast
499827000.00
Total Budget Changes
34901000.00
Total Schedule Changes
161
Hillview Reservoir Flow Control Improvements
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 670 • Project Name: Hillview Reservoir Flow Control Improvements
Date Reported As Of
2021-07-01T00:00:00.000
Pid
670
Project Name
Hillview Reservoir Flow Control Improvements
Description
This project provides improvements to the existing structures and mechanical flow control systems at Hillview Reservoir.
Category
Water Supply
Borough
City of Yonkers
Managing Agency
DEP
Client Agency
BWS
Current Phase
Design
Design Start
2020-04-13T00:00:00.000
Budget Forecast
318720000.00
Latest Budget Changes
43595196.64
Total Budget Changes
-11397050.18
Forecast Completion
2032-01-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
254
Boston Road Bridge Over Hutchinson River Rehabilitation
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 539 • Project Name: Boston Road Bridge Over Hutchinson River Rehabilitation
Date Reported As Of
2021-07-01T00:00:00.000
Pid
539
Project Name
Boston Road Bridge Over Hutchinson River Rehabilitation
Description
Rehabilitation of Boston Road Bridge over Hutchinson River, located in the Bornx.
Category
Bridges, Streets and Roadways
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2018-04-16T00:00:00.000
Budget Forecast
82501814.00
Latest Budget Changes
1302000.00
Total Budget Changes
49309814.00
Forecast Completion
2025-02-18T00:00:00.000
Latest Schedule Changes
25
Total Schedule Changes
803
Bronx Animal Care Center
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 893 • Project Name: Bronx Animal Care Center
Date Reported As Of
2021-07-01T00:00:00.000
Pid
893
Project Name
Bronx Animal Care Center
Description
Bronx Animal Care Center & Veterinary Clinic is a new 50,000 SF facility that will be housing admissions, adoptions, medical services, and boarding for approximately 70 dogs, 140 cats, 30 rabbits and 20 animals or other species. In addition to the animal housing, the Bronx Animal Care Center will include a wildlife area to rehabilitate wild birds, academic partnership for youth, and enhanced senior services. Site work will include yards to facilitate dog adoptions, covered exercise runs, courtyards, and parking for staff, visitors, and center vehicles, as well as site lighting and low maintenance planting throughout. The building and associated landscape are to achieve LEED Silver standards or higher.
Category
Health and Hospitals
Managing Agency
DDC
Client Agency
Health
Current Phase
Design
Design Start
2019-06-20T00:00:00.000
Budget Forecast
91453000.00
Latest Budget Changes
22078000.00
Total Budget Changes
24815617.00
Forecast Completion
2025-01-14T00:00:00.000
Latest Schedule Changes
319
Total Schedule Changes
110
West 33rd Street
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 861 • Project Name: West 33rd Street
Date Reported As Of
2021-07-01T00:00:00.000
Pid
861
Project Name
West 33rd Street
Description
Regrading and reconstruction of 33rd Street Viaduct between 11th and 12th Avenue..
Category
Streets and Roadways
Managing Agency
EDC
Client Agency
DOT
Current Phase
Design
Design Start
2018-09-01T00:00:00.000
Budget Forecast
100000000.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2025-11-29T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1736
NYPD Firearms and Tactics Facility
Date Reported As Of: 2021-07-01T00:00:00.000 • Pid: 1194 • Project Name: NYPD Firearms and Tactics Facility
Date Reported As Of
2021-07-01T00:00:00.000
Pid
1194
Project Name
NYPD Firearms and Tactics Facility
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
Police
Current Phase
Design
Design Start
2018-09-18T00:00:00.000
Budget Forecast
281500000.00
Total Budget Changes
3365000.00
Forecast Completion
2026-11-24T00:00:00.000
Total Schedule Changes
328
Carl Schurz Park Promenade over FDR (East 81st to 90th Streets)
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 537 • Project Name: Carl Schurz Park Promenade over FDR (East 81st to 90th Streets)
Date Reported As Of
2021-03-01T00:00:00.000
Pid
537
Project Name
Carl Schurz Park Promenade over FDR (East 81st to 90th Streets)
Category
Bridges
Borough
Manhattan
Managing Agency
DOT
Client Agency
DOT, DPR
Total Budget Changes
-197139579.00
Total Schedule Changes
1571
Electronic Medical Records Upgrade
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 403 • Project Name: Electronic Medical Records Upgrade
Date Reported As Of
2021-03-01T00:00:00.000
Pid
403
Project Name
Electronic Medical Records Upgrade
Description
The EPIC - EMR Program: Electronic Medical Records (EMR) System - a single enterprise-wide EMR to meet the needs of HHC's expansive size and improve patient care will replace the legacy EMR - QuadraMed, which is over 25 years old.
Category
Health and Hospitals, IT
Borough
Citywide
Managing Agency
HHC
Client Agency
H+H
Current Phase
IT
Budget Forecast
764063231.00
Latest Budget Changes
0.00
Total Budget Changes
15184947.00
Forecast Completion
2022-12-31T00:00:00.000
Latest Schedule Changes
580
Total Schedule Changes
2032
Park Avenue Tunnel (Murray Hill)
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 536 • Project Name: Park Avenue Tunnel (Murray Hill)
Date Reported As Of
2021-03-01T00:00:00.000
Pid
536
Project Name
Park Avenue Tunnel (Murray Hill)
Category
Bridges
Managing Agency
DOT
Client Agency
DOT
Total Budget Changes
-17773389.61
Total Schedule Changes
1568
CSO Hutchinson River Disinfection Facility
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 944 • Project Name: CSO Hutchinson River Disinfection Facility
Date Reported As Of
2021-03-01T00:00:00.000
Pid
944
Project Name
CSO Hutchinson River Disinfection Facility
Description
Construction of disinfection/de-chlorination facility thru 14'x10' conduit ~ 1,650' long, with detention times of 5 min/30 sec, for a design flow rate of 300 MGD for seasonal operation (May-Oct). Floatables control for 100 MGD will also be provided.
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2020-09-23T00:00:00.000
Budget Forecast
227079862.00
Latest Budget Changes
-778642.00
Total Budget Changes
-24577348.00
Forecast Completion
2030-11-22T00:00:00.000
Latest Schedule Changes
83
Total Schedule Changes
894
Reconstruction Of Arthur Kill Road, Phase I
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 741 • Project Name: Reconstruction Of Arthur Kill Road, Phase I
Date Reported As Of
2021-03-01T00:00:00.000
Pid
741
Project Name
Reconstruction Of Arthur Kill Road, Phase I
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Total Budget Changes
22503000.00
Total Schedule Changes
1415
West 79th Street over Amtrak and Rotunda Complex Rehabilitation
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 801 • Project Name: West 79th Street over Amtrak and Rotunda Complex Rehabilitation
Date Reported As Of
2021-03-01T00:00:00.000
Pid
801
Project Name
West 79th Street over Amtrak and Rotunda Complex Rehabilitation
Category
Bridges, Streets and Roadways
Borough
Manhattan
Managing Agency
DOT
Client Agency
DOT, DPR
Total Budget Changes
-51088528.00
Total Schedule Changes
604
Reconstruction of the West and North Docks at the OH WWTP
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 720 • Project Name: Reconstruction of the West and North Docks at the OH WWTP
Date Reported As Of
2021-03-01T00:00:00.000
Pid
720
Project Name
Reconstruction of the West and North Docks at the OH WWTP
Description
RECONSTRUCTION OF SEA WALL AND DOCK AT OWLS HEAD WWTP
Category
Wastewater Treatment
Borough
Brooklyn
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2017-08-18T00:00:00.000
Budget Forecast
63402555.40
Latest Budget Changes
803347.23
Total Budget Changes
10985726.80
Forecast Completion
2023-02-22T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1389
Brooklyn Public School 730 New Construction
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 876 • Project Name: Brooklyn Public School 730 New Construction
Date Reported As Of
2021-03-01T00:00:00.000
Pid
876
Project Name
Brooklyn Public School 730 New Construction
Description
NEW SCHOOL
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2018-01-26T00:00:00.000
Budget Forecast
66249461.00
Latest Budget Changes
0.00
Total Budget Changes
6379885.00
Forecast Completion
2022-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
730
Grant Park Construction
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 1015 • Project Name: Grant Park Construction
Date Reported As Of
2021-03-01T00:00:00.000
Pid
1015
Project Name
Grant Park Construction
Description
This project will construct Grant Park, including converting the roadbed to recreational space.
Category
Parks
Managing Agency
DPR
Client Agency
DPR
Current Phase
Construction Procurement
Design Start
2019-05-29T00:00:00.000
Budget Forecast
32590000.00
Latest Budget Changes
0.00
Total Budget Changes
1489000.00
Forecast Completion
2024-02-08T00:00:00.000
Latest Schedule Changes
46
Total Schedule Changes
612