All major infrastructure and information technology projects with a budget of $25 million or more that are currently active (in the design, procurement, or construction phase).
City GovernmentMayor's Office of Operations (OPS)
Dataset n7gv-k5yt
16 fields
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 522 • Project Name: Power Distribution at Bowery Bay WWTP
Date Reported As Of
2021-03-01T00:00:00.000
Pid
522
Project Name
Power Distribution at Bowery Bay WWTP
Description
Power Distribution at Bowery Bay WWTP.
Category
Wastewater Treatment
Borough
Queens
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2015-11-13T00:00:00.000
Budget Forecast
68873764.13
Latest Budget Changes
0.00
Total Budget Changes
24235381.01
Forecast Completion
2023-01-27T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1684
2nd Avenue Watermain Trunk Construction
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 388 • Project Name: 2nd Avenue Watermain Trunk Construction
Date Reported As Of
2021-03-01T00:00:00.000
Pid
388
Project Name
2nd Avenue Watermain Trunk Construction
Category
Water Supply
Borough
Manhattan
Managing Agency
DDC
Client Agency
Environmental Protection
Total Budget Changes
-7266000.00
Total Schedule Changes
2113
NYCF Homeport 2
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 1022 • Project Name: NYCF Homeport 2
Date Reported As Of
2021-03-01T00:00:00.000
Pid
1022
Project Name
NYCF Homeport 2
Description
Development, design, and construction of NYC Ferry Homeport II within Atlantic Basin.
Category
Ferries
Managing Agency
EDC
Client Agency
EDC
Current Phase
Design
Design Start
2020-02-01T00:00:00.000
Budget Forecast
65000000.00
Latest Budget Changes
0.00
Total Budget Changes
51220834.00
Forecast Completion
2023-09-17T00:00:00.000
Latest Schedule Changes
201
Total Schedule Changes
153
SUNSET PARK GOWANUS CONNECTOR, BK
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 979 • Project Name: SUNSET PARK GOWANUS CONNECTOR, BK
Date Reported As Of
2021-03-01T00:00:00.000
Pid
979
Project Name
SUNSET PARK GOWANUS CONNECTOR, BK
Category
Parks, Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Total Budget Changes
-16441000.00
Total Schedule Changes
445
Roosevelt Avenue Bridge Superstructure and Substructure Repairs
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 101 • Project Name: Roosevelt Avenue Bridge Superstructure and Substructure Repairs
Date Reported As Of
2021-03-01T00:00:00.000
Pid
101
Project Name
Roosevelt Avenue Bridge Superstructure and Substructure Repairs
Category
Bridges
Borough
Queens
Managing Agency
DOT
Client Agency
DOT
Total Budget Changes
23798213.00
Total Schedule Changes
2003
Bronx Sanitation Garage Rehabilitation: Community District 12
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 956 • Project Name: Bronx Sanitation Garage Rehabilitation: Community District 12
Date Reported As Of
2021-03-01T00:00:00.000
Pid
956
Project Name
Bronx Sanitation Garage Rehabilitation: Community District 12
Description
Rehabilitation of garage that serves Bronx Community District 12 located at 1635 East 233rd Street, Bronx.
Category
Sanitation
Managing Agency
DSNY
Client Agency
DSNY
Current Phase
Design
Design Start
2017-11-01T00:00:00.000
Budget Forecast
57376185.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2025-07-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1064
Ped Safety Upgrades on Atlantic Avenue, Phase 2
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 519 • Project Name: Ped Safety Upgrades on Atlantic Avenue, Phase 2
Date Reported As Of
2021-03-01T00:00:00.000
Pid
519
Project Name
Ped Safety Upgrades on Atlantic Avenue, Phase 2
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Total Budget Changes
10136496.00
Total Schedule Changes
1400
BROWNSVILLE LIBRARY MAJOR RENOVATIONS
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 977 • Project Name: BROWNSVILLE LIBRARY MAJOR RENOVATIONS
Date Reported As Of
2021-03-01T00:00:00.000
Pid
977
Project Name
BROWNSVILLE LIBRARY MAJOR RENOVATIONS
Category
Libraries
Managing Agency
DDC
Client Agency
Libraries-BPL
Total Budget Changes
6752000.00
Total Schedule Changes
916
TRENCH RESTORATION BROOKLYN
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 855 • Project Name: TRENCH RESTORATION BROOKLYN
Date Reported As Of
2021-03-01T00:00:00.000
Pid
855
Project Name
TRENCH RESTORATION BROOKLYN
Category
Industrial Development
Managing Agency
DDC
Client Agency
Transportation
Total Budget Changes
6536000.00
Total Schedule Changes
1467
150Th St Spine Phase 1 Storm Sewer At Bergen Basin
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 791 • Project Name: 150Th St Spine Phase 1 Storm Sewer At Bergen Basin
Date Reported As Of
2021-03-01T00:00:00.000
Pid
791
Project Name
150Th St Spine Phase 1 Storm Sewer At Bergen Basin
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Total Budget Changes
101452000.00
Total Schedule Changes
753
Pelham Parkway Roadway Reconstruction, Phase 2
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 180 • Project Name: Pelham Parkway Roadway Reconstruction, Phase 2
Date Reported As Of
2021-03-01T00:00:00.000
Pid
180
Project Name
Pelham Parkway Roadway Reconstruction, Phase 2
Category
Streets and Roadways
Borough
Bronx
Managing Agency
DDC
Client Agency
Transportation
Total Budget Changes
125164000.00
Total Schedule Changes
2869
Coney Island Area, Phase 3A
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 516 • Project Name: Coney Island Area, Phase 3A
Date Reported As Of
2021-03-01T00:00:00.000
Pid
516
Project Name
Coney Island Area, Phase 3A
Category
Industrial Development
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Environmental Protection
Total Budget Changes
25273000.00
Total Schedule Changes
1215
Harlem River Drive Ramp Reconstruction (George Washington Bridge)
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 708 • Project Name: Harlem River Drive Ramp Reconstruction (George Washington Bridge)
Date Reported As Of
2021-03-01T00:00:00.000
Pid
708
Project Name
Harlem River Drive Ramp Reconstruction (George Washington Bridge)
Category
Bridges, Streets and Roadways
Borough
Manhattan
Managing Agency
DOT
Client Agency
DOT
Total Budget Changes
-3711870.00
Total Schedule Changes
2697
Cunningham Park Garage Reconstruction
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 1019 • Project Name: Cunningham Park Garage Reconstruction
Date Reported As Of
2021-03-01T00:00:00.000
Pid
1019
Project Name
Cunningham Park Garage Reconstruction
Description
This project will reconstruct the garage in Cunningham Park.
Category
Parks
Managing Agency
DPR
Client Agency
DPR
Current Phase
Construction Procurement
Design Start
2018-11-19T00:00:00.000
Budget Forecast
27060000.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2023-05-27T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
703
Asphalt Plant, 30-01 Harper St, Queens Demo/Cons
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 840 • Project Name: Asphalt Plant, 30-01 Harper St, Queens Demo/Cons
Date Reported As Of
2021-03-01T00:00:00.000
Pid
840
Project Name
Asphalt Plant, 30-01 Harper St, Queens Demo/Cons
Category
Industrial Development
Managing Agency
DDC
Client Agency
Transportation
Total Budget Changes
55883745.00
Total Schedule Changes
1211
Brooklyn Supreme Court Fire Alarm System Upgrade
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 510 • Project Name: Brooklyn Supreme Court Fire Alarm System Upgrade
Date Reported As Of
2021-03-01T00:00:00.000
Pid
510
Project Name
Brooklyn Supreme Court Fire Alarm System Upgrade
Category
Public Safety and Criminal Justice
Borough
Brooklyn
Managing Agency
DDC
Client Agency
DCAS
Total Budget Changes
47003000.00
Total Schedule Changes
1533
Orchard Beach Pavilion
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 858 • Project Name: Orchard Beach Pavilion
Date Reported As Of
2021-03-01T00:00:00.000
Pid
858
Project Name
Orchard Beach Pavilion
Description
The restoration of the existing landmarked Orchard Beach Pavilion (located in Bronx, NY) which includes the construction of an ADA ramp at the main entrance of the Pavilion to improve accessibility to the beach passageway.
Category
Parks
Managing Agency
EDC
Client Agency
DPR
Current Phase
Design
Design Start
2018-11-30T00:00:00.000
Budget Forecast
60000000.00
Latest Budget Changes
0.00
Total Budget Changes
35628847.00
Forecast Completion
2024-06-02T00:00:00.000
Latest Schedule Changes
640
Total Schedule Changes
942
Flatbush Avenue Trunk Watermain Replacement
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 370 • Project Name: Flatbush Avenue Trunk Watermain Replacement
Date Reported As Of
2021-03-01T00:00:00.000
Pid
370
Project Name
Flatbush Avenue Trunk Watermain Replacement
Category
Wastewater Treatment
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Environmental Protection
Total Budget Changes
39272000.00
Total Schedule Changes
2266
FUEL TANK & SUMP REPLACEMENTS - MANHATTAN/S.I.
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 900 • Project Name: FUEL TANK & SUMP REPLACEMENTS - MANHATTAN/S.I.
Date Reported As Of
2021-03-01T00:00:00.000
Pid
900
Project Name
FUEL TANK & SUMP REPLACEMENTS - MANHATTAN/S.I.
Category
Industrial Development
Managing Agency
DDC
Client Agency
DCAS
Total Budget Changes
-1754000.00
Total Schedule Changes
663
Coastal Resiliency Area 1 - East 23Rd St. To Montg
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 773 • Project Name: Coastal Resiliency Area 1 - East 23Rd St. To Montg
Date Reported As Of
2021-03-01T00:00:00.000
Pid
773
Project Name
Coastal Resiliency Area 1 - East 23Rd St. To Montg
Category
Industrial Development, Parks
Managing Agency
DDC
Client Agency
Parks & Recreation
Total Budget Changes
-418193636.37
Total Schedule Changes
836
New York State Pavilion Observation Towers Reconstruction
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 1018 • Project Name: New York State Pavilion Observation Towers Reconstruction
Date Reported As Of
2021-03-01T00:00:00.000
Pid
1018
Project Name
New York State Pavilion Observation Towers Reconstruction
Description
This project will reconstruct portions of the New York State Pavilion Observation Towers in Flushing Meadows Corona Park.
Category
Parks
Managing Agency
DPR
Client Agency
DPR
Current Phase
Construction
Design Start
2015-09-21T00:00:00.000
Budget Forecast
28778000.00
Latest Budget Changes
0.00
Total Budget Changes
1000.00
Forecast Completion
2021-07-20T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
772
Supreme Courthouse Fire Alarm/ Protection Upgrade
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 837 • Project Name: Supreme Courthouse Fire Alarm/ Protection Upgrade
Date Reported As Of
2021-03-01T00:00:00.000
Pid
837
Project Name
Supreme Courthouse Fire Alarm/ Protection Upgrade
Category
Public Safety and Criminal Justice
Managing Agency
DDC
Client Agency
DCAS
Total Budget Changes
37248610.00
Total Schedule Changes
1319
Brooklyn Civil Court move to 210 Joralemon St
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 509 • Project Name: Brooklyn Civil Court move to 210 Joralemon St
Date Reported As Of
2021-03-01T00:00:00.000
Pid
509
Project Name
Brooklyn Civil Court move to 210 Joralemon St
Description
Relocation of Brooklyn Civil and Housing Court to 210 Joralemon St
Category
Public Safety and Criminal Justice
Borough
Brooklyn
Managing Agency
DCAS
Client Agency
DCAS
Current Phase
Construction Procurement
Design Start
2016-07-27T00:00:00.000
Budget Forecast
251443000.00
Latest Budget Changes
0.00
Total Budget Changes
200931011.96
Forecast Completion
2024-08-01T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1977
Brooklyn P.S. at 4302 4TH AVE
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 949 • Project Name: Brooklyn P.S. at 4302 4TH AVE
Date Reported As Of
2021-03-01T00:00:00.000
Pid
949
Project Name
Brooklyn P.S. at 4302 4TH AVE
Description
NEW SCHOOL (PHASE II)
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2017-11-17T00:00:00.000
Budget Forecast
66058403.00
Latest Budget Changes
0.00
Total Budget Changes
-221356.00
Forecast Completion
2023-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
365
Croton Above Ground Structure And Landscaping
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 747 • Project Name: Croton Above Ground Structure And Landscaping
Date Reported As Of
2021-03-01T00:00:00.000
Pid
747
Project Name
Croton Above Ground Structure And Landscaping
Category
Industrial Development
Managing Agency
DDC
Client Agency
Environmental Protection
Total Budget Changes
75117000.00
Total Schedule Changes
897
Pelham Parkway Bridge Reconstruction over Hutchinson Parkway
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 506 • Project Name: Pelham Parkway Bridge Reconstruction over Hutchinson Parkway
Date Reported As Of
2021-03-01T00:00:00.000
Pid
506
Project Name
Pelham Parkway Bridge Reconstruction over Hutchinson Parkway
Category
Bridges, Streets and Roadways
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Total Budget Changes
10338071.57
Total Schedule Changes
1934
FUEL TANK & SUMP REPLACEMENTS - QUEENS
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 898 • Project Name: FUEL TANK & SUMP REPLACEMENTS - QUEENS
Date Reported As Of
2021-03-01T00:00:00.000
Pid
898
Project Name
FUEL TANK & SUMP REPLACEMENTS - QUEENS
Category
Industrial Development
Managing Agency
DDC
Client Agency
DCAS
Total Budget Changes
-1850000.00
Total Schedule Changes
663
Hannah Street Pumping Station Construction
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 364 • Project Name: Hannah Street Pumping Station Construction
Date Reported As Of
2021-03-01T00:00:00.000
Pid
364
Project Name
Hannah Street Pumping Station Construction
Description
This project will reconstruct the Hannah St. Pumping Station, the largest City-owned wastewater collection and pumping station on Staten Island. Built in 1977, the facility has numerous deficiencies, needing a comprehensive upgrade.
Category
Wastewater Treatment
Borough
Staten Island
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2012-10-01T00:00:00.000
Budget Forecast
102992162.23
Latest Budget Changes
-984794.00
Total Budget Changes
67909196.80
Forecast Completion
2024-06-05T00:00:00.000
Latest Schedule Changes
394
Total Schedule Changes
3238
5th Avenue Bridge Reconstruction over LIRR and Sea Beach, Brooklyn
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 504 • Project Name: 5th Avenue Bridge Reconstruction over LIRR and Sea Beach, Brooklyn
Date Reported As Of
2021-03-01T00:00:00.000
Pid
504
Project Name
5th Avenue Bridge Reconstruction over LIRR and Sea Beach, Brooklyn
Category
Bridges
Borough
Brooklyn
Managing Agency
DOT
Client Agency
DOT
Total Budget Changes
36577693.00
Total Schedule Changes
969
Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 112 • Project Name: Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Date Reported As Of
2021-03-01T00:00:00.000
Pid
112
Project Name
Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Category
Bridges, Streets and Roadways
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Total Budget Changes
20945057.00
Total Schedule Changes
1592
Alley Pond Environmental Center Reconstruction
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 1017 • Project Name: Alley Pond Environmental Center Reconstruction
Date Reported As Of
2021-03-01T00:00:00.000
Pid
1017
Project Name
Alley Pond Environmental Center Reconstruction
Description
This project will demolish and construct a new environmental center in Alley Pond Park.
Category
Parks
Managing Agency
DPR
Client Agency
DPR
Current Phase
Construction
Design Start
2010-02-24T00:00:00.000
Budget Forecast
30498000.00
Latest Budget Changes
32000.00
Total Budget Changes
1641000.00
Forecast Completion
2021-12-14T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
556
West Tremont Avenue over Metro North Railroad
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 503 • Project Name: West Tremont Avenue over Metro North Railroad
Date Reported As Of
2021-03-01T00:00:00.000
Pid
503
Project Name
West Tremont Avenue over Metro North Railroad
Category
Bridges
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Total Budget Changes
37794543.00
Total Schedule Changes
1253
Reconstruct Main Sewage Pump Controls at Port Richmond WWTP
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 948 • Project Name: Reconstruct Main Sewage Pump Controls at Port Richmond WWTP
Date Reported As Of
2021-03-01T00:00:00.000
Pid
948
Project Name
Reconstruct Main Sewage Pump Controls at Port Richmond WWTP
Description
Reconstruction of main sewage pumps and ancillary components including suction valves, suction piping, seal water system, pressure gauges, suction header, etc. New MSP's should meet the new design parameter of N+2 redundancy during wet weather flow
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2019-09-03T00:00:00.000
Budget Forecast
48010068.39
Latest Budget Changes
0.00
Total Budget Changes
26923720.62
Forecast Completion
2026-02-23T00:00:00.000
Latest Schedule Changes
90
Total Schedule Changes
516
FUEL TANK REPLACEMENT
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 851 • Project Name: FUEL TANK REPLACEMENT
Date Reported As Of
2021-03-01T00:00:00.000
Pid
851
Project Name
FUEL TANK REPLACEMENT
Category
Industrial Development
Managing Agency
DDC
Client Agency
DCAS
Total Budget Changes
207000.00
Total Schedule Changes
1278
Reconstruction of the Ashokan Headworks
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 834 • Project Name: Reconstruction of the Ashokan Headworks
Date Reported As Of
2021-03-01T00:00:00.000
Pid
834
Project Name
Reconstruction of the Ashokan Headworks
Description
CAT-213FAC Reconstruction of the Ashokan Reservoir Headworks. This Contract is for design services. The Headworks include the Upper and Lower Gate Chambers, the Screen Chamber and inter-connecting aquedcuts.
Category
Water Supply
Borough
Upstate
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2020-09-15T00:00:00.000
Budget Forecast
311610618.75
Latest Budget Changes
-9064365.00
Total Budget Changes
41950858.00
Forecast Completion
2031-12-21T00:00:00.000
Latest Schedule Changes
1063
Total Schedule Changes
-67
Bergen Avenue Street Reconstruction
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 170 • Project Name: Bergen Avenue Street Reconstruction
Date Reported As Of
2021-03-01T00:00:00.000
Pid
170
Project Name
Bergen Avenue Street Reconstruction
Category
Streets and Roadways
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Transportation
Total Budget Changes
45837000.00
Total Schedule Changes
-388
FDR Rehabilitation, Northbound (East 42nd to 49th Streets)
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 502 • Project Name: FDR Rehabilitation, Northbound (East 42nd to 49th Streets)
Date Reported As Of
2021-03-01T00:00:00.000
Pid
502
Project Name
FDR Rehabilitation, Northbound (East 42nd to 49th Streets)
Category
Bridges
Managing Agency
DOT
Client Agency
DOT
Total Budget Changes
-2802822.00
Total Schedule Changes
1816
Freshkills South Park Synthetic Turf Fields and Landscape Construction
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 1016 • Project Name: Freshkills South Park Synthetic Turf Fields and Landscape Construction
Date Reported As Of
2021-03-01T00:00:00.000
Pid
1016
Project Name
Freshkills South Park Synthetic Turf Fields and Landscape Construction
Description
This project will construct synthetic turf athletic fields, roadways, a parking lot with associated landscaping and stormwater management, multi-use and pedestrian paths, benches, signage, fencing, and lighting, and restore woodlands and wetlands.
Category
Parks
Managing Agency
DPR
Client Agency
DPR
Current Phase
Design
Design Start
2016-11-30T00:00:00.000
Budget Forecast
37945586.28
Latest Budget Changes
130500.00
Total Budget Changes
1436858.72
Forecast Completion
2024-04-17T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1309
Red Hook Recreation Area Track 1, Soccer Fields 3-5, and Ballfields 1-4 Reconstruction
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 974 • Category: Parks
Date Reported As Of
2021-03-01T00:00:00.000
Pid
974
Project Name
Red Hook Recreation Area Track 1, Soccer Fields 3-5, and Ballfields 1-4 Reconstruction
Description
This project will reconstruct the track & field and convert three soccer fields and four ballfields from natural turf to synthetic turf at Red Hook Recreation Area.
Category
Parks
Managing Agency
DPR
Client Agency
DPR
Current Phase
Construction
Design Start
2017-11-01T00:00:00.000
Budget Forecast
68712000.00
Latest Budget Changes
-7216000.00
Total Budget Changes
-10555000.00
Forecast Completion
2023-01-03T00:00:00.000
Latest Schedule Changes
-11
Total Schedule Changes
1082
DBCD South Site Cultural Fit-Out
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 484 • Project Name: DBCD South Site Cultural Fit-Out
Date Reported As Of
2021-03-01T00:00:00.000
Pid
484
Project Name
DBCD South Site Cultural Fit-Out
Description
Interior fit-out of the south site cultural unit.
Category
Arts and Culture
Borough
Brooklyn
Managing Agency
EDC
Client Agency
DCLA
Current Phase
Construction
Design Start
2014-12-01T00:00:00.000
Budget Forecast
51070000.00
Latest Budget Changes
0.00
Total Budget Changes
36789601.16
Forecast Completion
2022-12-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1706
West 59th Street Marine Transfer Station Construction, Phase 2
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 347 • Project Name: West 59th Street Marine Transfer Station Construction, Phase 2
Date Reported As Of
2021-03-01T00:00:00.000
Pid
347
Project Name
West 59th Street Marine Transfer Station Construction, Phase 2
Category
Sanitation
Borough
Manhattan
Managing Agency
DDC
Client Agency
Sanitation
Total Budget Changes
126753576.46
Total Schedule Changes
1949
Studio Museum in Harlem New Building
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 896 • Project Name: Studio Museum in Harlem New Building
Date Reported As Of
2021-03-01T00:00:00.000
Pid
896
Project Name
Studio Museum in Harlem New Building
Category
Arts and Culture
Managing Agency
DDC
Client Agency
Cultural Affairs
Total Budget Changes
-190000.00
Total Schedule Changes
856
Catskill Aqueduct Repair and Rehabilitation
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 478 • Project Name: Catskill Aqueduct Repair and Rehabilitation
Date Reported As Of
2021-03-01T00:00:00.000
Pid
478
Project Name
Catskill Aqueduct Repair and Rehabilitation
Description
Project to ensure the reliability of the 74 mile upper Catskill Aqueduct, including replacement of mechanical components, leak mitigation, and biofilm removal/condition assessment.
Category
Water Supply
Borough
Citywide
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2015-06-19T00:00:00.000
Budget Forecast
254516352.02
Latest Budget Changes
6983309.50
Total Budget Changes
9642889.68
Forecast Completion
2022-08-01T00:00:00.000
Latest Schedule Changes
61
Total Schedule Changes
1517
New 116Th Pct
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 762 • Project Name: New 116Th Pct
Date Reported As Of
2021-03-01T00:00:00.000
Pid
762
Project Name
New 116Th Pct
Category
Public Safety and Criminal Justice
Managing Agency
DDC
Client Agency
Police
Total Budget Changes
33852900.86
Total Schedule Changes
727
4Th Ave. Safety Improvements Phase II-Vision Zero
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 833 • Project Name: 4Th Ave. Safety Improvements Phase II-Vision Zero
Date Reported As Of
2021-03-01T00:00:00.000
Pid
833
Project Name
4Th Ave. Safety Improvements Phase II-Vision Zero
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Total Budget Changes
-11525000.00
Total Schedule Changes
1106
Grant Park Construction
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 1015 • Project Name: Grant Park Construction
Date Reported As Of
2021-03-01T00:00:00.000
Pid
1015
Project Name
Grant Park Construction
Description
This project will construct Grant Park, including converting the roadbed to recreational space.
Category
Parks
Managing Agency
DPR
Client Agency
DPR
Current Phase
Construction Procurement
Design Start
2019-05-29T00:00:00.000
Budget Forecast
32590000.00
Latest Budget Changes
0.00
Total Budget Changes
1489000.00
Forecast Completion
2024-02-08T00:00:00.000
Latest Schedule Changes
46
Total Schedule Changes
612
East 174th Street over Sheridan Expressway - Amtrak
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 701 • Project Name: East 174th Street over Sheridan Expressway - Amtrak
Date Reported As Of
2021-03-01T00:00:00.000
Pid
701
Project Name
East 174th Street over Sheridan Expressway - Amtrak
Category
Bridges
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Total Budget Changes
5146882.00
Total Schedule Changes
1431
Raise Shorelines Citywide
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 689 • Project Name: Raise Shorelines Citywide
Date Reported As Of
2021-03-01T00:00:00.000
Pid
689
Project Name
Raise Shorelines Citywide
Description
The design and construction of shoreline reconstruction projects necessary to provide Citywide protection from future flooding caused by elevated seal elvels.
Category
Industrial Development
Borough
Citywide
Managing Agency
EDC
Client Agency
ORR
Current Phase
Design
Design Start
2017-08-01T00:00:00.000
Budget Forecast
89152926.86
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2022-12-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
639
Upgrades At Brooklyn Animal Shelter
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 750 • Project Name: Upgrades At Brooklyn Animal Shelter
Date Reported As Of
2021-03-01T00:00:00.000
Pid
750
Project Name
Upgrades At Brooklyn Animal Shelter
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
Health
Total Budget Changes
21288000.00
Total Schedule Changes
1355
Storm Sanitary Sewer Repl Springfield Gardens
Date Reported As Of: 2021-03-01T00:00:00.000 • Pid: 790 • Project Name: Storm Sanitary Sewer Repl Springfield Gardens