Capital Projects

All major infrastructure and information technology projects with a budget of $25 million or more that are currently active (in the design, procurement, or construction phase).

City Government Mayor's Office of Operations (OPS) Dataset n7gv-k5yt 16 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
Supreme Courthouse Fire Alarm/ Protection Upgrade
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 837 • Project Name: Supreme Courthouse Fire Alarm/ Protection Upgrade
Date Reported As Of
2020-10-01T00:00:00.000
Pid
837
Project Name
Supreme Courthouse Fire Alarm/ Protection Upgrade
Category
Public Safety and Criminal Justice
Managing Agency
DDC
Client Agency
DCAS
Total Budget Changes
37248610.00
Total Schedule Changes
1319
Tompkinsville Esplanade
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 963 • Project Name: Tompkinsville Esplanade
Date Reported As Of
2020-10-01T00:00:00.000
Pid
963
Project Name
Tompkinsville Esplanade
Description
Esplanade from Stapleton to the Lighthouse Museum and Pier for DOT Dockbuilders.
Category
Parks
Managing Agency
EDC
Client Agency
EDC
Current Phase
Design
Design Start
2019-07-01T00:00:00.000
Budget Forecast
151572069.00
Latest Budget Changes
0.00
Total Budget Changes
10582596.00
Forecast Completion
2022-12-30T00:00:00.000
Latest Schedule Changes
-213
Total Schedule Changes
944
Far Rockaway New Facility
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 730 • Project Name: Far Rockaway New Facility
Date Reported As Of
2020-10-01T00:00:00.000
Pid
730
Project Name
Far Rockaway New Facility
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
Libraries-QBPL
Total Budget Changes
-623757.91
Total Schedule Changes
-78
5th Avenue Bridge Reconstruction over LIRR and Sea Beach, Brooklyn
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 504 • Project Name: 5th Avenue Bridge Reconstruction over LIRR and Sea Beach, Brooklyn
Date Reported As Of
2020-10-01T00:00:00.000
Pid
504
Project Name
5th Avenue Bridge Reconstruction over LIRR and Sea Beach, Brooklyn
Description
Replace the 5th Avenue Bridge over LIRR & Sea Beach, Brooklyn.
Category
Bridges
Borough
Brooklyn
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-11-30T00:00:00.000
Budget Forecast
80817380.00
Latest Budget Changes
2922557.00
Total Budget Changes
36577693.00
Forecast Completion
2027-01-16T00:00:00.000
Latest Schedule Changes
88
Total Schedule Changes
969
Broadway Bridge over Harlem River Replacement
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 106 • Project Name: Broadway Bridge over Harlem River Replacement
Date Reported As Of
2020-10-01T00:00:00.000
Pid
106
Project Name
Broadway Bridge over Harlem River Replacement
Description
Replace deteriorated members of lift span superstructure, concrete deck, lift electrical and mechanical systems, and fenders.
Category
Bridges
Borough
Bronx, Manhattan
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2005-04-01T00:00:00.000
Budget Forecast
184818519.00
Latest Budget Changes
-140000.00
Total Budget Changes
39724388.00
Forecast Completion
2023-02-01T00:00:00.000
Latest Schedule Changes
562
Total Schedule Changes
2797
East River Esplanade Stabilization and Reconstruction Phase 3
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 973 • Project Name: East River Esplanade Stabilization and Reconstruction Phase 3
Date Reported As Of
2020-10-01T00:00:00.000
Pid
973
Project Name
East River Esplanade Stabilization and Reconstruction Phase 3
Description
This project will stabilize and reconstruct portions of the East River Esplanade from East 62nd Street to East 63rd Street, at East 76th Street, and from East 90th Street to East 94th Street.
Category
Parks
Managing Agency
DPR
Client Agency
DPR
Current Phase
Design
Design Start
2019-02-01T00:00:00.000
Budget Forecast
72647778.13
Latest Budget Changes
0.00
Total Budget Changes
3616645.26
Forecast Completion
2023-06-25T00:00:00.000
Total Schedule Changes
612
Reconstruction Of Arthur Kill Road, Phase I
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 741 • Project Name: Reconstruction Of Arthur Kill Road, Phase I
Date Reported As Of
2020-10-01T00:00:00.000
Pid
741
Project Name
Reconstruction Of Arthur Kill Road, Phase I
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Total Budget Changes
22503000.00
Total Schedule Changes
1415
HIGH LEVEL STM SEWERS IN GOWANUS CANAL AREA-PH II
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 849 • Project Name: HIGH LEVEL STM SEWERS IN GOWANUS CANAL AREA-PH II
Date Reported As Of
2020-10-01T00:00:00.000
Pid
849
Project Name
HIGH LEVEL STM SEWERS IN GOWANUS CANAL AREA-PH II
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Total Budget Changes
8657000.00
Total Schedule Changes
813
Brooklyn Sanitation Garage Construction: Community District 3
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 560 • Project Name: Brooklyn Sanitation Garage Construction: Community District 3
Date Reported As Of
2020-10-01T00:00:00.000
Pid
560
Project Name
Brooklyn Sanitation Garage Construction: Community District 3
Description
Construction of new Sanitation garage facility for services to Brooklyn Community District 3 to be located at Warsoff Place in Brooklyn
Category
Sanitation
Borough
Brooklyn
Managing Agency
DSNY
Client Agency
DSNY
Current Phase
Construction
Design Start
2005-07-25T00:00:00.000
Budget Forecast
204347986.93
Latest Budget Changes
0.00
Total Budget Changes
25603365.00
Forecast Completion
2022-12-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
790
Alley Pond Environmental Center Reconstruction
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 1017 • Project Name: Alley Pond Environmental Center Reconstruction
Date Reported As Of
2020-10-01T00:00:00.000
Pid
1017
Project Name
Alley Pond Environmental Center Reconstruction
Description
This project will demolish and construct a new environmental center in Alley Pond Park.
Category
Parks
Managing Agency
DPR
Client Agency
DPR
Current Phase
Construction
Design Start
2010-02-24T00:00:00.000
Budget Forecast
30466000.00
Latest Budget Changes
0.00
Total Budget Changes
1641000.00
Forecast Completion
2021-12-14T00:00:00.000
Latest Schedule Changes
15
Total Schedule Changes
556
Reconstruction Of Primary Tanks at Bowery Bay WPCP
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 942 • Project Name: Reconstruction Of Primary Tanks at Bowery Bay WPCP
Date Reported As Of
2020-10-01T00:00:00.000
Pid
942
Project Name
Reconstruction Of Primary Tanks at Bowery Bay WPCP
Description
Replacement of Primary Settling Tanks collection system mechanisms and miscellaneous improvements at Bowery Bay WRRF.
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2019-09-27T00:00:00.000
Budget Forecast
99190376.00
Latest Budget Changes
0.00
Total Budget Changes
74442173.00
Forecast Completion
2026-02-17T00:00:00.000
Latest Schedule Changes
63
Total Schedule Changes
636
BROWNSVILLE LIBRARY MAJOR RENOVATIONS
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 977 • Project Name: BROWNSVILLE LIBRARY MAJOR RENOVATIONS
Date Reported As Of
2020-10-01T00:00:00.000
Pid
977
Project Name
BROWNSVILLE LIBRARY MAJOR RENOVATIONS
Category
Libraries
Managing Agency
DDC
Client Agency
Libraries-BPL
Total Budget Changes
6752000.00
Total Schedule Changes
916
Croton Above Ground Structure And Landscaping
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 747 • Project Name: Croton Above Ground Structure And Landscaping
Date Reported As Of
2020-10-01T00:00:00.000
Pid
747
Project Name
Croton Above Ground Structure And Landscaping
Category
Industrial Development
Managing Agency
DDC
Client Agency
Environmental Protection
Total Budget Changes
75117000.00
Total Schedule Changes
897
HILL DR (TERRACE BR) OVER PROSPECT PARK LAKE BIN 2244120
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 1073 • Project Name: HILL DR (TERRACE BR) OVER PROSPECT PARK LAKE BIN 2244120
Date Reported As Of
2020-10-01T00:00:00.000
Pid
1073
Project Name
HILL DR (TERRACE BR) OVER PROSPECT PARK LAKE BIN 2244120
Category
Bridges
Managing Agency
DOT
Client Agency
NYC Parks
Current Phase
Design
Design Start
2020-01-06T00:00:00.000
Budget Forecast
29036244.00
Total Budget Changes
-785268.00
Forecast Completion
2027-06-07T00:00:00.000
Total Schedule Changes
636
Porpoise Bridge In Flushing Meadows-Corona Park
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 749 • Project Name: Porpoise Bridge In Flushing Meadows-Corona Park
Date Reported As Of
2020-10-01T00:00:00.000
Pid
749
Project Name
Porpoise Bridge In Flushing Meadows-Corona Park
Category
Bridges
Managing Agency
DDC
Client Agency
Transportation
Total Budget Changes
82000.00
Total Schedule Changes
1110
Asphalt Plant, 30-01 Harper St, Queens Demo/Cons
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 840 • Project Name: Asphalt Plant, 30-01 Harper St, Queens Demo/Cons
Date Reported As Of
2020-10-01T00:00:00.000
Pid
840
Project Name
Asphalt Plant, 30-01 Harper St, Queens Demo/Cons
Category
Industrial Development
Managing Agency
DDC
Client Agency
Transportation
Total Budget Changes
55883745.00
Total Schedule Changes
1211
Pelham Parkway Bridge Reconstruction over Hutchinson Parkway
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 506 • Project Name: Pelham Parkway Bridge Reconstruction over Hutchinson Parkway
Date Reported As Of
2020-10-01T00:00:00.000
Pid
506
Project Name
Pelham Parkway Bridge Reconstruction over Hutchinson Parkway
Description
Replace/Rehab the Pelham Parkway bridge over Hutchinson River Parkway, Bronx.
Category
Bridges, Streets and Roadways
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-05-30T00:00:00.000
Budget Forecast
57348478.00
Latest Budget Changes
350000.00
Total Budget Changes
10338071.57
Forecast Completion
2028-02-02T00:00:00.000
Latest Schedule Changes
226
Total Schedule Changes
1934
Dumbo and Vinegar Hill Area Roadway Reconstruction and Renovation
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 193 • Project Name: Dumbo and Vinegar Hill Area Roadway Reconstruction and Renovation
Date Reported As Of
2020-10-01T00:00:00.000
Pid
193
Project Name
Dumbo and Vinegar Hill Area Roadway Reconstruction and Renovation
Category
Streets and Roadways
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Transportation
Total Budget Changes
96724000.00
Total Schedule Changes
3253
New Stapleton Waterfront: Phases 2 and 3
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 962 • Project Name: New Stapleton Waterfront: Phases 2 and 3
Date Reported As Of
2020-10-01T00:00:00.000
Pid
962
Project Name
New Stapleton Waterfront: Phases 2 and 3
Description
Mixed-use residential community on Staten Island's North Shore.
Category
Industrial Development
Managing Agency
EDC
Client Agency
EDC
Current Phase
Design
Design Start
2015-09-30T00:00:00.000
Budget Forecast
98407645.00
Latest Budget Changes
0.00
Total Budget Changes
100733778.00
Forecast Completion
2026-05-01T00:00:00.000
Latest Schedule Changes
546
Total Schedule Changes
913
Upgrades At Brooklyn Animal Shelter
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 750 • Project Name: Upgrades At Brooklyn Animal Shelter
Date Reported As Of
2020-10-01T00:00:00.000
Pid
750
Project Name
Upgrades At Brooklyn Animal Shelter
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
Health
Total Budget Changes
21288000.00
Total Schedule Changes
1355
FUEL TANK & SUMP REPLACEMENTS - BROOKLYN
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 899 • Project Name: FUEL TANK & SUMP REPLACEMENTS - BROOKLYN
Date Reported As Of
2020-10-01T00:00:00.000
Pid
899
Project Name
FUEL TANK & SUMP REPLACEMENTS - BROOKLYN
Category
Industrial Development
Managing Agency
DDC
Client Agency
DCAS
Total Budget Changes
-1940000.00
Total Schedule Changes
663
Orchard Beach Pavilion
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 858 • Project Name: Orchard Beach Pavilion
Date Reported As Of
2020-10-01T00:00:00.000
Pid
858
Project Name
Orchard Beach Pavilion
Description
The restoration of the existing landmarked Orchard Beach Pavilion (located in Bronx, NY) which includes the construction of an ADA ramp at the main entrance of the Pavilion to improve accessibility to the beach passageway.
Category
Parks
Managing Agency
EDC
Client Agency
DPR
Current Phase
Design
Design Start
2018-11-30T00:00:00.000
Budget Forecast
60000000.00
Latest Budget Changes
0.00
Total Budget Changes
35628847.00
Forecast Completion
2022-09-01T00:00:00.000
Latest Schedule Changes
-275
Total Schedule Changes
942
Shore Road Bridge over Hutchinson River
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 541 • Project Name: Shore Road Bridge over Hutchinson River
Date Reported As Of
2020-10-01T00:00:00.000
Pid
541
Project Name
Shore Road Bridge over Hutchinson River
Description
Replace the Shore Road Bridge over the Hutchinson River with a new bridge.
Category
Bridges, Streets and Roadways
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-06-30T00:00:00.000
Budget Forecast
324125743.00
Latest Budget Changes
4731000.00
Total Budget Changes
-19049921.84
Forecast Completion
2029-07-15T00:00:00.000
Latest Schedule Changes
101
Total Schedule Changes
1477
Headworks Improvements at Tallman Island
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 906 • Project Name: Headworks Improvements at Tallman Island
Date Reported As Of
2020-10-01T00:00:00.000
Pid
906
Project Name
Headworks Improvements at Tallman Island
Description
Headworks Improvements
Category
Industrial Development
Managing Agency
DEP
Client Agency
WWC
Current Phase
Design
Design Start
2019-07-07T00:00:00.000
Budget Forecast
42150751.00
Latest Budget Changes
177779.00
Total Budget Changes
19975649.96
Forecast Completion
2025-08-05T00:00:00.000
Latest Schedule Changes
235
Total Schedule Changes
586
Reconstruction Of Trinity Pl
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 755 • Project Name: Reconstruction Of Trinity Pl
Date Reported As Of
2020-10-01T00:00:00.000
Pid
755
Project Name
Reconstruction Of Trinity Pl
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Total Budget Changes
13224000.00
Total Schedule Changes
730
South Bronx East-West Crosstown SBS
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 1008 • Project Name: South Bronx East-West Crosstown SBS
Date Reported As Of
2020-10-01T00:00:00.000
Pid
1008
Project Name
South Bronx East-West Crosstown SBS
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Total Budget Changes
3130000.00
Total Schedule Changes
626
FUEL TANK & SUMP REPLACEMENTS - QUEENS
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 898 • Project Name: FUEL TANK & SUMP REPLACEMENTS - QUEENS
Date Reported As Of
2020-10-01T00:00:00.000
Pid
898
Project Name
FUEL TANK & SUMP REPLACEMENTS - QUEENS
Category
Industrial Development
Managing Agency
DDC
Client Agency
DCAS
Total Budget Changes
-1850000.00
Total Schedule Changes
663
Construction Of Sanitary Sewers, Storm Sewers (Bm
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 760 • Project Name: Construction Of Sanitary Sewers, Storm Sewers (Bm
Date Reported As Of
2020-10-01T00:00:00.000
Pid
760
Project Name
Construction Of Sanitary Sewers, Storm Sewers (Bm
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Total Budget Changes
37691000.00
Total Schedule Changes
595
Studio Museum in Harlem New Building
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 896 • Project Name: Studio Museum in Harlem New Building
Date Reported As Of
2020-10-01T00:00:00.000
Pid
896
Project Name
Studio Museum in Harlem New Building
Category
Arts and Culture
Managing Agency
DDC
Client Agency
Cultural Affairs
Total Budget Changes
-190000.00
Total Schedule Changes
856
Power Distribution Improvements at Tallman Island
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 907 • Project Name: Power Distribution Improvements at Tallman Island
Date Reported As Of
2020-10-01T00:00:00.000
Pid
907
Project Name
Power Distribution Improvements at Tallman Island
Description
Power Distribution Improvements
Category
Industrial Development
Managing Agency
DEP
Client Agency
WWC
Current Phase
Design
Design Start
2019-05-31T00:00:00.000
Budget Forecast
59036622.00
Latest Budget Changes
256804.00
Total Budget Changes
10926063.83
Forecast Completion
2025-12-02T00:00:00.000
Latest Schedule Changes
241
Total Schedule Changes
651
FUEL TANK REPLACEMENT - 71
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 935 • Project Name: FUEL TANK REPLACEMENT - 71
Date Reported As Of
2020-10-01T00:00:00.000
Pid
935
Project Name
FUEL TANK REPLACEMENT - 71
Category
Industrial Development
Managing Agency
DDC
Client Agency
DCAS
Total Budget Changes
3444000.00
Total Schedule Changes
548
New 116Th Pct
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 762 • Project Name: New 116Th Pct
Date Reported As Of
2020-10-01T00:00:00.000
Pid
762
Project Name
New 116Th Pct
Category
Public Safety and Criminal Justice
Managing Agency
DDC
Client Agency
Police
Total Budget Changes
33852900.86
Total Schedule Changes
727
Gilboa Dam Reconstruction, Phase IV
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 406 • Project Name: Gilboa Dam Reconstruction, Phase IV
Date Reported As Of
2020-10-01T00:00:00.000
Pid
406
Project Name
Gilboa Dam Reconstruction, Phase IV
Description
This project will rehabilitate the mechanics and the architecture of the Shandaken Tunnel Intake Chamber, which includes the replacement of gates and general site improvements.
Category
Water Supply
Borough
Upstate
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2008-12-01T00:00:00.000
Budget Forecast
72000604.60
Latest Budget Changes
912144.70
Total Budget Changes
33535991.20
Forecast Completion
2021-11-24T00:00:00.000
Latest Schedule Changes
168
Total Schedule Changes
1684
33rd Street West of 11th Avenue (Hudson Yards)
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 1043 • Project Name: 33rd Street West of 11th Avenue (Hudson Yards)
Date Reported As Of
2020-10-01T00:00:00.000
Pid
1043
Project Name
33rd Street West of 11th Avenue (Hudson Yards)
Category
Bridges
Managing Agency
DOT
Client Agency
EDC
Current Phase
Design
Budget Forecast
100000104.00
Total Budget Changes
-1399960.00
Total Schedule Changes
611
Water Main Replacement In 222 Street, Queens
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 768 • Project Name: Water Main Replacement In 222 Street, Queens
Date Reported As Of
2020-10-01T00:00:00.000
Pid
768
Project Name
Water Main Replacement In 222 Street, Queens
Category
Water Supply
Managing Agency
DDC
Client Agency
Environmental Protection
Total Budget Changes
7195000.00
Total Schedule Changes
2236
NEW UTRECH LIBRARY MAJOR RENOVATIONS
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 841 • Project Name: NEW UTRECH LIBRARY MAJOR RENOVATIONS
Date Reported As Of
2020-10-01T00:00:00.000
Pid
841
Project Name
NEW UTRECH LIBRARY MAJOR RENOVATIONS
Category
Libraries
Managing Agency
DDC
Client Agency
Libraries-BPL
Total Budget Changes
290000.00
Total Schedule Changes
1188
SAN & STRM SEWER, WM IN CONEY ISLAND AREA, PH 4
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 1009 • Project Name: SAN & STRM SEWER, WM IN CONEY ISLAND AREA, PH 4
Date Reported As Of
2020-10-01T00:00:00.000
Pid
1009
Project Name
SAN & STRM SEWER, WM IN CONEY ISLAND AREA, PH 4
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Total Budget Changes
1984000.00
Total Schedule Changes
1431
SUNSET PARK GOWANUS CONNECTOR, BK
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 979 • Project Name: SUNSET PARK GOWANUS CONNECTOR, BK
Date Reported As Of
2020-10-01T00:00:00.000
Pid
979
Project Name
SUNSET PARK GOWANUS CONNECTOR, BK
Category
Parks, Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Total Budget Changes
-16441000.00
Total Schedule Changes
445
Grant Park Construction
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 1015 • Project Name: Grant Park Construction
Date Reported As Of
2020-10-01T00:00:00.000
Pid
1015
Project Name
Grant Park Construction
Description
This project will construct Grant Park, including converting the roadbed to recreational space.
Category
Parks
Managing Agency
DPR
Client Agency
DPR
Current Phase
Design
Design Start
2019-05-29T00:00:00.000
Budget Forecast
32590000.00
Latest Budget Changes
1489000.00
Total Budget Changes
1489000.00
Forecast Completion
2023-12-24T00:00:00.000
Total Schedule Changes
612
City Tunnel No.3, Stage 2 in Queens and Brooklyn, Construction of Shaft 17B and 18B
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 1042 • Category: Water Supply
Date Reported As Of
2020-10-01T00:00:00.000
Pid
1042
Project Name
City Tunnel No.3, Stage 2 in Queens and Brooklyn, Construction of Shaft 17B and 18B
Description
Contract C547A is for the construction of two shafts (17B-1 and 18B-1) on City Tunnel No. 3 (CT3), Stage 2 in Queens and Brooklyn
Category
Water Supply
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2019-01-30T00:00:00.000
Budget Forecast
443063583.00
Total Budget Changes
3150108.42
Forecast Completion
2027-01-11T00:00:00.000
Total Schedule Changes
119
RECONSTRUCTION OF FRONT STREET, MANHATTAN
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 1012 • Project Name: RECONSTRUCTION OF FRONT STREET, MANHATTAN
Date Reported As Of
2020-10-01T00:00:00.000
Pid
1012
Project Name
RECONSTRUCTION OF FRONT STREET, MANHATTAN
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Total Budget Changes
6153000.00
Total Schedule Changes
484
FUEL TANK REPLACEMENT
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 1005 • Project Name: FUEL TANK REPLACEMENT
Date Reported As Of
2020-10-01T00:00:00.000
Pid
1005
Project Name
FUEL TANK REPLACEMENT
Category
Industrial Development
Managing Agency
DDC
Client Agency
DCAS
Total Budget Changes
-6429000.00
Total Schedule Changes
914
Staten Island 1 & 3 Garage Construction & Rehab
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 769 • Project Name: Staten Island 1 & 3 Garage Construction & Rehab
Date Reported As Of
2020-10-01T00:00:00.000
Pid
769
Project Name
Staten Island 1 & 3 Garage Construction & Rehab
Category
Sanitation
Borough
Staten Island
Managing Agency
DDC
Client Agency
Sanitation
Total Budget Changes
68555000.00
Total Schedule Changes
406
Bronx Animal Care Center
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 893 • Project Name: Bronx Animal Care Center
Date Reported As Of
2020-10-01T00:00:00.000
Pid
893
Project Name
Bronx Animal Care Center
Category
Health and Hospitals
Managing Agency
DDC
Client Agency
Health
Total Budget Changes
24815617.00
Total Schedule Changes
110
Electronic Medical Records Upgrade
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 403 • Project Name: Electronic Medical Records Upgrade
Date Reported As Of
2020-10-01T00:00:00.000
Pid
403
Project Name
Electronic Medical Records Upgrade
Description
The EPIC - EMR Program: Electronic Medical Records (EMR) System - a single enterprise-wide EMR to meet the needs of HHC's expansive size and improve patient care will replace the legacy EMR - QuadraMed, which is over 25 years old.
Category
Health and Hospitals, IT
Borough
Citywide
Managing Agency
HHC
Client Agency
H+H
Current Phase
IT
Budget Forecast
764063231.00
Latest Budget Changes
0.00
Total Budget Changes
15184947.00
Forecast Completion
2021-05-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2032
Belt System - Cross Island over 115th Avenue/Dutch Broadway
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 558 • Project Name: Belt System - Cross Island over 115th Avenue/Dutch Broadway
Date Reported As Of
2020-10-01T00:00:00.000
Pid
558
Project Name
Belt System - Cross Island over 115th Avenue/Dutch Broadway
Description
Repair the Cross Island bridge over 115th Avenue/Dutch Broadway, Queens.
Category
Bridges
Borough
Queens
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-10-03T00:00:00.000
Budget Forecast
25843171.00
Latest Budget Changes
6346546.00
Total Budget Changes
17528706.00
Total Schedule Changes
1845
Rehab Of Queens District 11/13 Sanitation Garage
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 770 • Project Name: Rehab Of Queens District 11/13 Sanitation Garage
Date Reported As Of
2020-10-01T00:00:00.000
Pid
770
Project Name
Rehab Of Queens District 11/13 Sanitation Garage
Category
Sanitation
Borough
Queens
Managing Agency
DDC
Client Agency
Sanitation
Total Budget Changes
36221000.00
Total Schedule Changes
1521
FUEL TANK & SUMP REPLACEMENTS - MANHATTAN/S.I.
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 900 • Project Name: FUEL TANK & SUMP REPLACEMENTS - MANHATTAN/S.I.
Date Reported As Of
2020-10-01T00:00:00.000
Pid
900
Project Name
FUEL TANK & SUMP REPLACEMENTS - MANHATTAN/S.I.
Category
Industrial Development
Managing Agency
DDC
Client Agency
DCAS
Total Budget Changes
-1754000.00
Total Schedule Changes
663
Next Generation 911 Program
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 1035 • Project Name: Next Generation 911 Program
Date Reported As Of
2020-10-01T00:00:00.000
Pid
1035
Project Name
Next Generation 911 Program
Description
The goal of this program is to replace the current end of life analog system with an Emergency Response System that meets the latest Public Safety standards and regulations in compliance with NENA standards.
Category
IT, Public Safety and Criminal Justice
Managing Agency
DOITT
Client Agency
NYPD & FDNY
Current Phase
IT
Budget Forecast
274307733.78
Total Budget Changes
30123504.48
Forecast Completion
2024-02-21T00:00:00.000
Total Schedule Changes
1558
GRAND CONCOURSE, PHASE 5
Date Reported As Of: 2020-10-01T00:00:00.000 • Pid: 1013 • Project Name: GRAND CONCOURSE, PHASE 5
Date Reported As Of
2020-10-01T00:00:00.000
Pid
1013
Project Name
GRAND CONCOURSE, PHASE 5
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Total Budget Changes
26673000.00
Total Schedule Changes
729