Capital Projects

All major infrastructure and information technology projects with a budget of $25 million or more that are currently active (in the design, procurement, or construction phase).

City Government Mayor's Office of Operations (OPS) Dataset n7gv-k5yt 16 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
Central Park Light Infrastructure
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 586 • Project Name: Central Park Light Infrastructure
Date Reported As Of
2023-01-01T00:00:00.000
Pid
586
Project Name
Central Park Light Infrastructure
Description
Install, remove, and furnish equipment for electrical work associated with traffic signals, lighting, and distribution systems in Central Park, Manhattan.
Category
Parks, Streets and Roadways
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2016-04-29T00:00:00.000
Budget Forecast
39055476.00
Latest Budget Changes
-715712.00
Total Budget Changes
-3323649.60
Forecast Completion
2023-08-31T00:00:00.000
Latest Schedule Changes
62
Total Schedule Changes
1535
Madison Avenue Bridge Reconstruction
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 114 • Project Name: Madison Avenue Bridge Reconstruction
Date Reported As Of
2023-01-01T00:00:00.000
Pid
114
Project Name
Madison Avenue Bridge Reconstruction
Description
Replace the electrical and mechanical systems of the Madison Avenue Bridge.
Category
Bridges
Borough
Manhattan, Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2011-02-14T00:00:00.000
Budget Forecast
56546302.00
Latest Budget Changes
1121903.00
Total Budget Changes
2036997.00
Forecast Completion
2023-01-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1628
Combined Sewer And Wm Work In 71 Street, Queens
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 789 • Project Name: Combined Sewer And Wm Work In 71 Street, Queens
Date Reported As Of
2023-01-01T00:00:00.000
Pid
789
Project Name
Combined Sewer And Wm Work In 71 Street, Queens
Description
Replacement of combined sewer in 71st Street between Juniper Boulevard South and Queens Midtown Expressway, etc.
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2018-09-10T00:00:00.000
Budget Forecast
76194000.00
Latest Budget Changes
341000.00
Total Budget Changes
27172000.00
Forecast Completion
2028-10-30T00:00:00.000
Latest Schedule Changes
366
Total Schedule Changes
1889
Gilboa Dam Reconstruction, Phase IV
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 406 • Project Name: Gilboa Dam Reconstruction, Phase IV
Date Reported As Of
2023-01-01T00:00:00.000
Pid
406
Project Name
Gilboa Dam Reconstruction, Phase IV
Description
This project will rehabilitate the mechanics and the architecture of the Shandaken Tunnel Intake Chamber, which includes the replacement of gates and general site improvements.
Category
Water Supply
Borough
Upstate
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2008-12-01T00:00:00.000
Budget Forecast
71013192.20
Latest Budget Changes
-33000.00
Total Budget Changes
33535991.20
Forecast Completion
2023-03-27T00:00:00.000
Latest Schedule Changes
120
Total Schedule Changes
1684
New Storm Sewer N Conduit Av-Baisley Blvd
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 792 • Project Name: New Storm Sewer N Conduit Av-Baisley Blvd
Date Reported As Of
2023-01-01T00:00:00.000
Pid
792
Project Name
New Storm Sewer N Conduit Av-Baisley Blvd
Description
Storm, Sanitary and Water Mains work in North Conduit between Baisley Blvd and Guy Brewer Blvd, South Queens
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2018-07-30T00:00:00.000
Budget Forecast
113711000.00
Latest Budget Changes
0.00
Total Budget Changes
31711000.00
Forecast Completion
2029-02-18T00:00:00.000
Latest Schedule Changes
90
Total Schedule Changes
1619
Concourse Village Avenue over Metro North
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 587 • Project Name: Concourse Village Avenue over Metro North
Date Reported As Of
2023-01-01T00:00:00.000
Pid
587
Project Name
Concourse Village Avenue over Metro North
Description
Replace the Concourse Village Avenue bridge over Metro North, Bronx
Category
Bridges
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2019-01-25T00:00:00.000
Budget Forecast
49898190.00
Latest Budget Changes
-239247.00
Total Budget Changes
-186092.37
Forecast Completion
2029-09-28T00:00:00.000
Latest Schedule Changes
210
Total Schedule Changes
1865
Hannah Street Pumping Station Construction
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 364 • Project Name: Hannah Street Pumping Station Construction
Date Reported As Of
2023-01-01T00:00:00.000
Pid
364
Project Name
Hannah Street Pumping Station Construction
Description
This project will reconstruct the Hannah St. Pumping Station, the largest City-owned wastewater collection and pumping station on Staten Island. Built in 1977, the facility has numerous deficiencies, needing a comprehensive upgrade.
Category
Wastewater Treatment
Borough
Staten Island
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2012-08-03T00:00:00.000
Budget Forecast
109709196.80
Latest Budget Changes
6717034.57
Total Budget Changes
67909196.80
Forecast Completion
2026-06-23T00:00:00.000
Latest Schedule Changes
174
Total Schedule Changes
3238
Park Avenue Tunnel (Murray Hill)
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 536 • Project Name: Park Avenue Tunnel (Murray Hill)
Date Reported As Of
2023-01-01T00:00:00.000
Pid
536
Project Name
Park Avenue Tunnel (Murray Hill)
Description
Repair Park Avenue tunnel, located in Midtown, Manhattan.
Category
Bridges
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2006-08-01T00:00:00.000
Budget Forecast
46066272.00
Latest Budget Changes
3041858.00
Total Budget Changes
-17773389.61
Forecast Completion
2023-05-02T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1568
Boston Road Bridge Over Hutchinson River Rehabilitation
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 539 • Project Name: Boston Road Bridge Over Hutchinson River Rehabilitation
Date Reported As Of
2023-01-01T00:00:00.000
Pid
539
Project Name
Boston Road Bridge Over Hutchinson River Rehabilitation
Description
Rehabilitation of Boston Road Bridge over Hutchinson River, located in the Bornx.
Category
Bridges, Streets and Roadways
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction Procurement
Design Start
2018-04-16T00:00:00.000
Budget Forecast
88359814.00
Latest Budget Changes
10880806.00
Total Budget Changes
49309814.00
Forecast Completion
2026-05-26T00:00:00.000
Latest Schedule Changes
110
Total Schedule Changes
803
Williamsburg Bridge Miscellaneous Repairs and Painting
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 599 • Project Name: Williamsburg Bridge Miscellaneous Repairs and Painting
Date Reported As Of
2023-01-01T00:00:00.000
Pid
599
Project Name
Williamsburg Bridge Miscellaneous Repairs and Painting
Description
Scope includes paint the south side of the bridge, repair flags and structural steel, evaluate PP20 Bearings, evaluate tension rods at mid-span of the bridge, repair bridge cables and suspenders, replace modular joint, investigate the feasibility of additional clearance at towers, and resurface bridge decks with new waterproofing membrane.
Category
Bridges
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2018-08-15T00:00:00.000
Budget Forecast
222766947.00
Latest Budget Changes
-5306459.00
Total Budget Changes
52784947.00
Forecast Completion
2025-12-03T00:00:00.000
Latest Schedule Changes
-197
Total Schedule Changes
362
Reconstruction of the Ashokan Headworks
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 834 • Project Name: Reconstruction of the Ashokan Headworks
Date Reported As Of
2023-01-01T00:00:00.000
Pid
834
Project Name
Reconstruction of the Ashokan Headworks
Description
CAT-213
Category
Water Supply
Borough
Upstate
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2020-08-07T00:00:00.000
Budget Forecast
343303864.75
Latest Budget Changes
26871269.00
Total Budget Changes
41950858.00
Forecast Completion
2028-09-01T00:00:00.000
Latest Schedule Changes
138
Total Schedule Changes
-67
Bellevue Medical Center Priority Mitigation Projects
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 545 • Project Name: Bellevue Medical Center Priority Mitigation Projects
Date Reported As Of
2023-01-01T00:00:00.000
Pid
545
Project Name
Bellevue Medical Center Priority Mitigation Projects
Description
Priority mitigation projects for the repair/restoration and hazard mitigation for Bellevue Hospital, damaged during Superstorm Sandy
Category
Health and Hospitals
Borough
Manhattan
Managing Agency
EDC
Client Agency
H+H
Current Phase
Construction
Design Start
2014-01-01T00:00:00.000
Budget Forecast
50941375.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2023-04-28T00:00:00.000
Latest Schedule Changes
-143
Total Schedule Changes
1854
Bruckner Expressway Westchester Creek Bridge Reconstruction
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 97 • Project Name: Bruckner Expressway Westchester Creek Bridge Reconstruction
Date Reported As Of
2023-01-01T00:00:00.000
Pid
97
Project Name
Bruckner Expressway Westchester Creek Bridge Reconstruction
Description
Replace the existing bridge with a new, wider double-leaf bascule bridge in the Bronx.
Category
Bridges, Streets and Roadways
Borough
Bronx
Managing Agency
DOT
Client Agency
DEP, DOT
Current Phase
Construction
Design Start
2012-07-23T00:00:00.000
Budget Forecast
297884658.00
Latest Budget Changes
6225760.00
Total Budget Changes
142277136.00
Forecast Completion
2023-12-27T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2086
Replacement of the Esopus & Route 28A Railroad Bridges
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 443 • Project Name: Replacement of the Esopus & Route 28A Railroad Bridges
Date Reported As Of
2023-01-01T00:00:00.000
Pid
443
Project Name
Replacement of the Esopus & Route 28A Railroad Bridges
Description
Replacement of the Esopus & Route 28A Railroad Bridges
Category
Bridges
Borough
Olive
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2016-10-11T00:00:00.000
Budget Forecast
51873522.24
Latest Budget Changes
663242.28
Total Budget Changes
-50461071.35
Forecast Completion
2025-11-09T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
714
Reconstruction of the Port Jervis Wastewater Treatment Plant
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 444 • Project Name: Reconstruction of the Port Jervis Wastewater Treatment Plant
Date Reported As Of
2023-01-01T00:00:00.000
Pid
444
Project Name
Reconstruction of the Port Jervis Wastewater Treatment Plant
Description
Reconstruction of the Port Jervis WWTP as required based on the effluent limits proposed by the Delaware River Basin Commission (DRBC)
Category
Wastewater Treatment
Borough
Port Jervis
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2014-06-17T00:00:00.000
Budget Forecast
60624916.55
Latest Budget Changes
0.00
Total Budget Changes
9428438.55
Forecast Completion
2026-10-04T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2445
Asphalt Plant, 30-01 Harper St, Queens Demo/Cons
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 840 • Project Name: Asphalt Plant, 30-01 Harper St, Queens Demo/Cons
Date Reported As Of
2023-01-01T00:00:00.000
Pid
840
Project Name
Asphalt Plant, 30-01 Harper St, Queens Demo/Cons
Description
Demolition and rebuild of the existing structures housing the equipment and related facilities necessary for the production, storage and distribution of asphalt at the NYC Harper Street Asphalt Plant facility. All of the existing equipment, storage facilities, and related buildings will be replaced with a new state of the art plant. In addition, the work will involve installing sanitary and storm drainage systems to comply with current government regulatory standard
Category
Industrial Development
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2019-04-03T00:00:00.000
Budget Forecast
96597000.00
Latest Budget Changes
36060000.00
Total Budget Changes
55883745.00
Forecast Completion
2026-10-05T00:00:00.000
Latest Schedule Changes
111
Total Schedule Changes
1211
New Ferry Boat Construction
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 94 • Project Name: New Ferry Boat Construction
Date Reported As Of
2023-01-01T00:00:00.000
Pid
94
Project Name
New Ferry Boat Construction
Description
Replace one Barberi class boat and the John F. Kennedy boat which are approaching the end of their useful lives with new Staten Island ferries. Replacement is needed to continue reliable service.
Category
Ferries
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2014-09-15T00:00:00.000
Budget Forecast
22204190.00
Latest Budget Changes
34000.00
Total Budget Changes
-238419180.00
Total Schedule Changes
549
RECONSTRUCTION OF QUEENS BLVD - PHASE 1
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 618 • Project Name: RECONSTRUCTION OF QUEENS BLVD - PHASE 1
Date Reported As Of
2023-01-01T00:00:00.000
Pid
618
Project Name
RECONSTRUCTION OF QUEENS BLVD - PHASE 1
Description
Vision Zero - Queens Boulevard - Segment 1: Roosevelt Avenue to 73rd Street. Variety of safety and streetscape improvements including partial street reconstruction and resurfacing to address roadway conditions
Category
Industrial Development
Borough
Queens
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2016-08-11T00:00:00.000
Budget Forecast
251711000.00
Latest Budget Changes
0.00
Total Budget Changes
176245000.00
Forecast Completion
2029-02-01T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1906
Shore Road Bridge over Hutchinson River
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 541 • Project Name: Shore Road Bridge over Hutchinson River
Date Reported As Of
2023-01-01T00:00:00.000
Pid
541
Project Name
Shore Road Bridge over Hutchinson River
Description
Replace the Shore Road Bridge over the Hutchinson River with a new bridge.
Category
Bridges, Streets and Roadways
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-06-30T00:00:00.000
Budget Forecast
339641078.00
Latest Budget Changes
-1091765.00
Total Budget Changes
-19049921.84
Forecast Completion
2030-01-02T00:00:00.000
Latest Schedule Changes
162
Total Schedule Changes
1477
Reconstruction of Power Distribution at Wards Island WWTP
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 453 • Project Name: Reconstruction of Power Distribution at Wards Island WWTP
Date Reported As Of
2023-01-01T00:00:00.000
Pid
453
Project Name
Reconstruction of Power Distribution at Wards Island WWTP
Description
Upgrades significant portions of the electrical distribution infrastructure including 3 power center installations, 15 motor control centers, 6 automatic transfer switches and 20 transformers throughout the plant
Category
Wastewater Treatment
Borough
Manhattan
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2019-06-04T00:00:00.000
Budget Forecast
149106268.26
Latest Budget Changes
0.00
Total Budget Changes
33489860.26
Forecast Completion
2028-03-04T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1147
West Tremont Avenue over Metro North Railroad
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 503 • Project Name: West Tremont Avenue over Metro North Railroad
Date Reported As Of
2023-01-01T00:00:00.000
Pid
503
Project Name
West Tremont Avenue over Metro North Railroad
Description
Replace/Rehab the West Tremont Avenue bridge over the Metro North line, located in the Bronx.
Category
Bridges
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2018-01-16T00:00:00.000
Budget Forecast
91785543.00
Latest Budget Changes
-564000.00
Total Budget Changes
37794543.00
Forecast Completion
2027-10-04T00:00:00.000
Latest Schedule Changes
57
Total Schedule Changes
1253
Battery Park Underpass Emergency Relief Betterments
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 540 • Project Name: Battery Park Underpass Emergency Relief Betterments
Date Reported As Of
2023-01-01T00:00:00.000
Pid
540
Project Name
Battery Park Underpass Emergency Relief Betterments
Description
Resiliency betterments for Battery Park and West Street underpasses.
Category
Bridges
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2018-04-01T00:00:00.000
Budget Forecast
66773308.00
Latest Budget Changes
-2398000.00
Total Budget Changes
47923308.00
Forecast Completion
2025-07-09T00:00:00.000
Latest Schedule Changes
171
Total Schedule Changes
1197
RECONSTRUCTION OF QUEENS BLVD - PHASE 2
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 619 • Project Name: RECONSTRUCTION OF QUEENS BLVD - PHASE 2
Date Reported As Of
2023-01-01T00:00:00.000
Pid
619
Project Name
RECONSTRUCTION OF QUEENS BLVD - PHASE 2
Description
Vision Zero - Queens Boulevard - Segment 2: 73rd Street to Eliot Avenue. Variety of safety and streetscape improvements including partial street reconstruction and resurfacing to address roadway conditions
Category
Industrial Development
Borough
Queens
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2016-10-26T00:00:00.000
Budget Forecast
86043000.00
Latest Budget Changes
0.00
Total Budget Changes
14201000.00
Forecast Completion
2029-08-13T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2315
FUEL TANK REPLACEMENT
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 851 • Project Name: FUEL TANK REPLACEMENT
Date Reported As Of
2023-01-01T00:00:00.000
Pid
851
Project Name
FUEL TANK REPLACEMENT
Description
The scope of work consists of providing all necessary construction management, design, and r.onstruction services required to perform ail phases of the project: Surveying, tank testing, investigation, design, construction, and construction management for the closure, removal, upgrade, or replacement of petroieum product storage tanks at various City owned sites. This work must comply with all local, state, nnd federal laws nnd regulations governing tanks and associated work. The general scope of work for tank replacement includes: File NYSDEC PBS application; mobilization; securing all required NYC agency approvals & permits; site survey; geophysical survey; drilling for laboratory soil and groundwater samples; crane & rigging; saw cutting; demo & disposal of old tanks, piping, and concrete vaults; dewatering· of excavation; tank bottom sludge removal & disposal; remove/transfer/dispose product; laboratory analysis of soil and groundwater; excavate, remove, dispose incidental contaminated soil; install shoring, new tanks and tan·k sumps, piping, monitoring and leak detection system, overfill protection and alarms, electrical wiring; construction of concrete slabs and block piers; backfill excavation; resurfacing; demobilization; performance of a closeout investigation and the preparation and filing of appropriate reports; obtaining FDNY and DOB closeout documents; preparing "As-built" drawings.
Category
Industrial Development
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Construction
Design Start
2017-10-30T00:00:00.000
Budget Forecast
31700000.00
Latest Budget Changes
206000.00
Total Budget Changes
207000.00
Forecast Completion
2025-04-14T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1278
West 33rd Street
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 861 • Project Name: West 33rd Street
Date Reported As Of
2023-01-01T00:00:00.000
Pid
861
Project Name
West 33rd Street
Description
Regrading and reconstruction of 33rd Street Viaduct between 11th and 12th Avenue..
Category
Streets and Roadways
Managing Agency
EDC
Client Agency
DOT
Current Phase
Design
Design Start
2018-09-01T00:00:00.000
Budget Forecast
100000000.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2026-11-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1736
Grand Concourse Metro North Railroad Bridge Construction
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 120 • Project Name: Grand Concourse Metro North Railroad Bridge Construction
Date Reported As Of
2023-01-01T00:00:00.000
Pid
120
Project Name
Grand Concourse Metro North Railroad Bridge Construction
Description
Repair the existing bridge and separate the NYCDOT and NYCT components. Includes new steel plate girders, concrete deck, pedestals, backwalls, sidewalks, and bridge railing.
Category
Bridges
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2000-02-14T00:00:00.000
Budget Forecast
72968117.00
Latest Budget Changes
-532000.00
Total Budget Changes
22682117.00
Forecast Completion
2023-01-16T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
836
Broadway Bridge over Harlem River Replacement
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 106 • Project Name: Broadway Bridge over Harlem River Replacement
Date Reported As Of
2023-01-01T00:00:00.000
Pid
106
Project Name
Broadway Bridge over Harlem River Replacement
Description
Replace deteriorated members of lift span superstructure, concrete deck, lift electrical and mechanical systems, and fenders.
Category
Bridges
Borough
Bronx, Manhattan
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2005-04-01T00:00:00.000
Budget Forecast
148960388.00
Latest Budget Changes
-1088222.00
Total Budget Changes
39724388.00
Forecast Completion
2027-04-02T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2797
5th Avenue Bridge Reconstruction over LIRR and Sea Beach, Brooklyn
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 504 • Project Name: 5th Avenue Bridge Reconstruction over LIRR and Sea Beach, Brooklyn
Date Reported As Of
2023-01-01T00:00:00.000
Pid
504
Project Name
5th Avenue Bridge Reconstruction over LIRR and Sea Beach, Brooklyn
Description
Replace the 5th Avenue Bridge over LIRR & Sea Beach, Brooklyn.
Category
Bridges
Borough
Brooklyn
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction Procurement
Design Start
2017-11-30T00:00:00.000
Budget Forecast
83778580.00
Latest Budget Changes
-2732781.00
Total Budget Changes
36577693.00
Forecast Completion
2027-07-01T00:00:00.000
Latest Schedule Changes
-135
Total Schedule Changes
969
Bainbridge Avenue Trunk Water Main
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 454 • Project Name: Bainbridge Avenue Trunk Water Main
Date Reported As Of
2023-01-01T00:00:00.000
Pid
454
Project Name
Bainbridge Avenue Trunk Water Main
Description
Replacement of Trunk Water Main in Bainbridge Avenue Between Gunhill Road and Holly Lane and in Jerome Avenue Between Holly Lane and E233th Street, etc. Also, New 36" WM in West Burnside Avenue & Phelan Place
Category
Water Supply
Borough
Bronx
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2014-03-17T00:00:00.000
Budget Forecast
72349000.00
Latest Budget Changes
400000.00
Total Budget Changes
25547000.00
Forecast Completion
2023-06-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1687
CONSTRUCTION OF BMPs NC 6 AND 15 - SI
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 631 • Project Name: CONSTRUCTION OF BMPs NC 6 AND 15 - SI
Date Reported As Of
2023-01-01T00:00:00.000
Pid
631
Project Name
CONSTRUCTION OF BMPs NC 6 AND 15 - SI
Description
CONSTRUCTION OF BMP’s NC 6 AND 15, STORM AND SANITARY SEWERS INSTALLATION, SI
Category
Industrial Development
Borough
Staten Island
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2017-08-14T00:00:00.000
Budget Forecast
33450000.00
Latest Budget Changes
0.00
Total Budget Changes
1921000.00
Forecast Completion
2024-06-09T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
925
West 59th Street Marine Transfer Station Construction, Phase 2
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 347 • Project Name: West 59th Street Marine Transfer Station Construction, Phase 2
Date Reported As Of
2023-01-01T00:00:00.000
Pid
347
Project Name
West 59th Street Marine Transfer Station Construction, Phase 2
Description
Project 2 Scope: Refurbishment of the existing pier building including: repair of existing pier structure including pile caps and fendering; construction of new emergency generator, electrical, mechanical, fire pump and fire valve rooms; new exit passageway construction and existing exit passageway refurbishment; re-arrangement and refurbishment of the Operations Building interiors; replacement of fire suppression system throughout the entire pier structure; mechanical, electrical and plumbing system upgrades; refurbishment and painting the existing pier interior steel framing and wall/roof surfaces; recoating the structure's exterior cladding systems including metal wall and roof panel system and translucent panel wall cladding system.
Category
Sanitation
Borough
Manhattan
Managing Agency
DDC
Client Agency
Sanitation
Current Phase
Construction
Design Start
2012-01-17T00:00:00.000
Budget Forecast
187830576.46
Latest Budget Changes
0.00
Total Budget Changes
126753576.46
Forecast Completion
2023-05-31T00:00:00.000
Latest Schedule Changes
215
Total Schedule Changes
1949
Flatbush Avenue Trunk Watermain Replacement
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 370 • Project Name: Flatbush Avenue Trunk Watermain Replacement
Date Reported As Of
2023-01-01T00:00:00.000
Pid
370
Project Name
Flatbush Avenue Trunk Watermain Replacement
Description
72" Trunk Water Main and Combined Sewer Replacement in Flatbush Ave. between Sterling Pl. and 8th Ave., etc., Borough of Brooklyn.
Category
Wastewater Treatment
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2014-11-24T00:00:00.000
Budget Forecast
59124000.00
Latest Budget Changes
200000.00
Total Budget Changes
39272000.00
Forecast Completion
2023-09-29T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2266
Pelham Parkway Roadway Reconstruction, Phase 2
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 180 • Project Name: Pelham Parkway Roadway Reconstruction, Phase 2
Date Reported As Of
2023-01-01T00:00:00.000
Pid
180
Project Name
Pelham Parkway Roadway Reconstruction, Phase 2
Description
Pelham Pkwy main road W/B from Bronx River Pkwy to Hutchinson River Pkwy Pelham Pkwy North Service Rd. (S/R) from Bronx Park East to Eastchester Rd. Stillwell Ave from westbound mainline to north service road
Category
Streets and Roadways
Borough
Bronx
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction
Design Start
2002-02-15T00:00:00.000
Budget Forecast
158533000.00
Latest Budget Changes
0.00
Total Budget Changes
125164000.00
Forecast Completion
2023-12-22T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2869
253 Broadway Landmark's Space Renovations
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 639 • Project Name: 253 Broadway Landmark's Space Renovations
Date Reported As Of
2023-01-01T00:00:00.000
Pid
639
Project Name
253 Broadway Landmark's Space Renovations
Description
Renovate 4 floors of the building to create new office space for the Landmarks Preservation Commission, including new hearing room.
Category
Other Government Facilities
Borough
Manhattan
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Construction
Design Start
2013-01-23T00:00:00.000
Budget Forecast
66539000.00
Latest Budget Changes
2431000.00
Total Budget Changes
35010000.00
Forecast Completion
2023-05-31T00:00:00.000
Latest Schedule Changes
151
Total Schedule Changes
1696
Rondout-West Branch Bypass Tunnel Construction Project 2
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 409 • Project Name: Rondout-West Branch Bypass Tunnel Construction Project 2
Date Reported As Of
2023-01-01T00:00:00.000
Pid
409
Project Name
Rondout-West Branch Bypass Tunnel Construction Project 2
Description
To address existing leaks in the Delaware Aqueduct, a 3-mile bypass tunnel will be constructed near the town of Roseton and the existing tunnel will be repaired near the town of Wawarsing.
Category
Water Supply
Borough
Marlboro
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2012-03-23T00:00:00.000
Budget Forecast
908466371.25
Latest Budget Changes
1376538.49
Total Budget Changes
202552329.25
Forecast Completion
2024-11-11T00:00:00.000
Latest Schedule Changes
28
Total Schedule Changes
256
New 40th Precinct
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 634 • Project Name: New 40th Precinct
Date Reported As Of
2023-01-01T00:00:00.000
Pid
634
Project Name
New 40th Precinct
Description
Design and build a new Police Precinct with full basement totaling 43,000 sq. ft. on an existing City owned property in the Bronx.
Category
Public Safety and Criminal Justice
Borough
Bronx
Managing Agency
DDC
Client Agency
Police
Design Start
2014-09-30T00:00:00.000
Budget Forecast
97020000.00
Latest Budget Changes
-1796000.00
Total Budget Changes
26020000.00
Total Schedule Changes
711
GI-OWLS HEAD TRIBUTARY DRAINAGE AREAS, BROOKLYN
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 1200 • Project Name: GI-OWLS HEAD TRIBUTARY DRAINAGE AREAS, BROOKLYN
Date Reported As Of
2023-01-01T00:00:00.000
Pid
1200
Project Name
GI-OWLS HEAD TRIBUTARY DRAINAGE AREAS, BROOKLYN
Description
GREEN INFRASTRUCTURE IN OWLS HEAD TRIBUTARY DRAINAGE AREAS, BROOKLYN
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2019-01-02T00:00:00.000
Budget Forecast
60387000.00
Latest Budget Changes
300000.00
Total Budget Changes
24278000.00
Forecast Completion
2027-07-02T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
396
Electronic Medical Records Upgrade
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 403 • Project Name: Electronic Medical Records Upgrade
Date Reported As Of
2023-01-01T00:00:00.000
Pid
403
Project Name
Electronic Medical Records Upgrade
Description
The EPIC - EMR Program: Electronic Medical Records (EMR) System - a single enterprise-wide EMR to meet the needs of HHC's expansive size and improve patient care will replace the legacy EMR - QuadraMed, which is over 25 years old.
Category
Health and Hospitals, IT
Borough
Citywide
Managing Agency
HHC
Client Agency
H+H
Current Phase
IT
Budget Forecast
764063231.00
Latest Budget Changes
0.00
Total Budget Changes
15184947.00
Forecast Completion
2023-12-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2032
Coler Specialty Hospital Priority Mitigation Projects
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 544 • Project Name: Coler Specialty Hospital Priority Mitigation Projects
Date Reported As Of
2023-01-01T00:00:00.000
Pid
544
Project Name
Coler Specialty Hospital Priority Mitigation Projects
Description
The priority mitigation projects at Coler include key critical mitigation projects to improve the resiliency of the campus.
Category
Health and Hospitals
Borough
Manhattan
Managing Agency
EDC
Client Agency
H+H
Current Phase
Construction
Design Start
2014-09-01T00:00:00.000
Budget Forecast
26776342.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2023-08-17T00:00:00.000
Latest Schedule Changes
17
Total Schedule Changes
2085
DOH Public Health Lab
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 909 • Project Name: DOH Public Health Lab
Date Reported As Of
2023-01-01T00:00:00.000
Pid
909
Project Name
DOH Public Health Lab
Description
The construction of an approximately 230,000 sq ft municipal Public Health Lab building for DOHMH.
Category
Health and Hospitals
Managing Agency
EDC
Client Agency
DOHMH
Current Phase
Construction
Design Start
2019-01-01T00:00:00.000
Budget Forecast
633132280.00
Latest Budget Changes
0.00
Total Budget Changes
19334959.71
Forecast Completion
2025-01-02T00:00:00.000
Latest Schedule Changes
1
Total Schedule Changes
1
49th Avenue Bridge Replacement
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 131 • Project Name: 49th Avenue Bridge Replacement
Date Reported As Of
2023-01-01T00:00:00.000
Pid
131
Project Name
49th Avenue Bridge Replacement
Description
Replace the 49th Avenue bridge over Long Island Railroad and Amtrak in Hunters Point, Queens.
Category
Bridges, Streets and Roadways
Borough
Queens
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-08-15T00:00:00.000
Budget Forecast
114154419.00
Latest Budget Changes
530000.00
Total Budget Changes
32902419.00
Forecast Completion
2028-10-16T00:00:00.000
Latest Schedule Changes
100
Total Schedule Changes
1449
Bergen Avenue Street Reconstruction
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 170 • Project Name: Bergen Avenue Street Reconstruction
Date Reported As Of
2023-01-01T00:00:00.000
Pid
170
Project Name
Bergen Avenue Street Reconstruction
Description
Reconstruction of Bergen Avenue Area, including Storm Sewers, Water Mains, Street Lighting, Traffic Signal Work, and reconstruction of new outfall at East Mill Basin.
Category
Streets and Roadways
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction
Design Start
2012-12-03T00:00:00.000
Budget Forecast
79564000.00
Latest Budget Changes
0.00
Total Budget Changes
45837000.00
Forecast Completion
2023-06-24T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
-388
Gilboa Dam Reconstruction, Phase V
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 456 • Project Name: Gilboa Dam Reconstruction, Phase V
Date Reported As Of
2023-01-01T00:00:00.000
Pid
456
Project Name
Gilboa Dam Reconstruction, Phase V
Description
This is the final phase of the Gilboa Dam reconstruction project and includes reforestation, final site stabilization and wetlands mitigation measures.
Category
Water Supply
Borough
Upstate
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2020-12-30T00:00:00.000
Budget Forecast
36492236.00
Latest Budget Changes
-246464.00
Total Budget Changes
-3079490.00
Forecast Completion
2026-04-16T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
503
Construction of Gowanus CSO retention FAC Superfund Site
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 550 • Project Name: Construction of Gowanus CSO retention FAC Superfund Site
Date Reported As Of
2023-01-01T00:00:00.000
Pid
550
Project Name
Construction of Gowanus CSO retention FAC Superfund Site
Description
CSO Facilities, bulkheads, pilots and other requirements to comply with Gowanus Canal Superfund Adminstrative Orders
Category
Industrial Development
Borough
Brooklyn
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction Procurement
Design Start
2017-11-22T00:00:00.000
Budget Forecast
1547300000.00
Latest Budget Changes
0.00
Total Budget Changes
432995114.00
Forecast Completion
2031-11-25T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1086
Harlem River Drive Ramp Reconstruction (George Washington Bridge)
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 708 • Project Name: Harlem River Drive Ramp Reconstruction (George Washington Bridge)
Date Reported As Of
2023-01-01T00:00:00.000
Pid
708
Project Name
Harlem River Drive Ramp Reconstruction (George Washington Bridge)
Description
Repair the Harlem River Drive Ramp to George Washington Bridge over Harlem River Drive Southbound (Trans-Manhattan Expressway), Manhattan
Category
Bridges, Streets and Roadways
Borough
Manhattan
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2019-02-07T00:00:00.000
Budget Forecast
425871130.00
Latest Budget Changes
-1716416.00
Total Budget Changes
-3711870.00
Forecast Completion
2035-09-02T00:00:00.000
Latest Schedule Changes
140
Total Schedule Changes
2697
Dumbo and Vinegar Hill Area Roadway Reconstruction and Renovation
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 193 • Project Name: Dumbo and Vinegar Hill Area Roadway Reconstruction and Renovation
Date Reported As Of
2023-01-01T00:00:00.000
Pid
193
Project Name
Dumbo and Vinegar Hill Area Roadway Reconstruction and Renovation
Description
Reconstruction DUMBO/Vinegar Hill Area including Trunk and Distribution water main replacement; Installation of HLSS and Combined Sewer replacement; Restoration of Belgian block in Water Street; Street lighting and Traffic Signal work.
Category
Streets and Roadways
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction
Design Start
2012-06-07T00:00:00.000
Budget Forecast
130324000.00
Latest Budget Changes
-1015000.00
Total Budget Changes
96724000.00
Forecast Completion
2024-06-04T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
3253
Roma and Hett Avenue Storm and Sanitary Sewer Installation
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 206 • Project Name: Roma and Hett Avenue Storm and Sanitary Sewer Installation
Date Reported As Of
2023-01-01T00:00:00.000
Pid
206
Project Name
Roma and Hett Avenue Storm and Sanitary Sewer Installation
Description
Installation of Storm, Sanitary Sewers in the following Streets:=================================1- Cedar Grove Avenue between Ebbitts Street and new Dorp Lane.2- Milton Avenue between Ebbitts Street and new Dorp Lane.3- Finley Avenue between Ebbitts Street and new Dorp Lane.4- Roma Avenue between Ebbitts Street and new Dorp Lane.5- Hett Avenue between Ebbitts Street and new Dorp Lane.6- Marine Way between Cedar Grove and Milton Avenue7- Beacon Avenue between Roma Avenue and Milton Avenue.8- Dustan Avenue between Marine way and Milton Avenue.9- Garibaldi Avenue between Roma Avenue and Cedar Grove Avenue.10- Cedar Grove Court between Cedar Grove Avenue and Dustan Street.11- Topping Street between Cedar Grove Avenue and Dustan Street.12- Center Way between Cedar Grove Avenue and Dustan Street.13- Neptune Street between Cedar Grove Avenue and Dustan Street.14- Seafoam Street between Cedar Grove Avenue and Dustan Street.15- Waterside Street between Cedar Grove Avenue and Dustan Street.16- Maple Terrace between Cedar Grove Avenue and Dustan Street.17- Herman Street between Cedar Grove Avenue and Dustan Street.18- Neutral Avenue between Cedar Grove Avenue and Dustan Street.19- Milbank Drive between Cedar Grove Avenue and Dustan Street.
Category
Sewers
Borough
Staten Island
Managing Agency
DDC
Client Agency
Trans. & Env. Protection
Current Phase
Construction
Design Start
2014-10-15T00:00:00.000
Budget Forecast
94191000.00
Latest Budget Changes
0.00
Total Budget Changes
62973000.00
Forecast Completion
2023-12-22T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
-8
Coney Island Area, Phase 3A
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 516 • Project Name: Coney Island Area, Phase 3A
Date Reported As Of
2023-01-01T00:00:00.000
Pid
516
Project Name
Coney Island Area, Phase 3A
Description
Reconstruction of Storm and Sanitary sewer, Trunk and distribution water main in Coney Island area - Phase 3A, Borough of Brooklyn
Category
Industrial Development
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2014-03-17T00:00:00.000
Budget Forecast
63426000.00
Latest Budget Changes
0.00
Total Budget Changes
25273000.00
Forecast Completion
2023-11-27T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1215
STM & SAN SWR, N.B. WHITESTONE EXPWY SERV RD, PH 3
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 652 • Project Name: STM & SAN SWR, N.B. WHITESTONE EXPWY SERV RD, PH 3
Date Reported As Of
2023-01-01T00:00:00.000
Pid
652
Project Name
STM & SAN SWR, N.B. WHITESTONE EXPWY SERV RD, PH 3
Description
Installation of Storm sewers, Sanitary sewers, & Water mains in Whitestone Area-Phase 3
Category
Sewers
Borough
Queens
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2016-07-15T00:00:00.000
Budget Forecast
75390000.00
Latest Budget Changes
0.00
Total Budget Changes
15468000.00
Forecast Completion
2024-08-21T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
684
SUNSET PARK GOWANUS CONNECTOR, BK
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 979 • Project Name: SUNSET PARK GOWANUS CONNECTOR, BK
Date Reported As Of
2023-01-01T00:00:00.000
Pid
979
Project Name
SUNSET PARK GOWANUS CONNECTOR, BK
Description
Sunset Park Gowanus Connector - Brooklyn Waterfront Greenway.
Category
Parks, Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction
Design Start
2017-09-18T00:00:00.000
Budget Forecast
28830000.00
Latest Budget Changes
0.00
Total Budget Changes
-16441000.00
Forecast Completion
2023-09-14T00:00:00.000
Latest Schedule Changes
121
Total Schedule Changes
445