Capital Projects

All major infrastructure and information technology projects with a budget of $25 million or more that are currently active (in the design, procurement, or construction phase).

City Government Mayor's Office of Operations (OPS) Dataset n7gv-k5yt 16 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
Headworks Improvements at Tallman Island
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 906 • Project Name: Headworks Improvements at Tallman Island
Date Reported As Of
2020-05-01T00:00:00.000
Pid
906
Project Name
Headworks Improvements at Tallman Island
Description
Headworks Improvements
Category
Industrial Development
Managing Agency
DEP
Client Agency
WWC
Current Phase
Design
Design Start
2019-07-07T00:00:00.000
Budget Forecast
41972972.00
Latest Budget Changes
-5231506.00
Total Budget Changes
19975649.96
Forecast Completion
2024-12-13T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
586
Queensboro Bridge Roadway Replacement over East River
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 594 • Project Name: Queensboro Bridge Roadway Replacement over East River
Date Reported As Of
2020-05-01T00:00:00.000
Pid
594
Project Name
Queensboro Bridge Roadway Replacement over East River
Description
This project includes the replacement of the upper roadway's deck on the main bridge along with steel repairs, fire standpipes, and lighting upgrades.
Category
Bridges, Streets and Roadways
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2015-04-09T00:00:00.000
Budget Forecast
394447777.00
Latest Budget Changes
-550000.00
Total Budget Changes
8567339.67
Forecast Completion
2022-10-28T00:00:00.000
Latest Schedule Changes
-244
Total Schedule Changes
1970
HIGH LEVEL STM SEWERS IN GOWANUS CANAL AREA-PH II
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 849 • Project Name: HIGH LEVEL STM SEWERS IN GOWANUS CANAL AREA-PH II
Date Reported As Of
2020-05-01T00:00:00.000
Pid
849
Project Name
HIGH LEVEL STM SEWERS IN GOWANUS CANAL AREA-PH II
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Total Budget Changes
8657000.00
Total Schedule Changes
813
Far Rockaway New Facility
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 730 • Project Name: Far Rockaway New Facility
Date Reported As Of
2020-05-01T00:00:00.000
Pid
730
Project Name
Far Rockaway New Facility
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
Libraries-QBPL
Total Budget Changes
-623757.91
Total Schedule Changes
-78
Brooklyn Civil Court move to 210 Joralemon St
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 509 • Project Name: Brooklyn Civil Court move to 210 Joralemon St
Date Reported As Of
2020-05-01T00:00:00.000
Pid
509
Project Name
Brooklyn Civil Court move to 210 Joralemon St
Description
Relocation of Brooklyn Civil and Housing Court to 210 Joralemon St
Category
Public Safety and Criminal Justice
Borough
Brooklyn
Managing Agency
DCAS
Client Agency
DCAS
Current Phase
Construction Procurement
Design Start
2016-07-27T00:00:00.000
Budget Forecast
251443000.00
Latest Budget Changes
0.00
Total Budget Changes
200931011.96
Forecast Completion
2024-02-02T00:00:00.000
Latest Schedule Changes
151
Total Schedule Changes
1977
Broadway Bridge over Harlem River Replacement
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 106 • Project Name: Broadway Bridge over Harlem River Replacement
Date Reported As Of
2020-05-01T00:00:00.000
Pid
106
Project Name
Broadway Bridge over Harlem River Replacement
Description
Replace deteriorated members of lift span superstructure, concrete deck, lift electrical and mechanical systems, and fenders.
Category
Bridges
Borough
Bronx, Manhattan
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2005-04-01T00:00:00.000
Budget Forecast
184958519.00
Latest Budget Changes
35000.00
Total Budget Changes
39724388.00
Forecast Completion
2021-07-19T00:00:00.000
Latest Schedule Changes
-249
Total Schedule Changes
2797
Gilboa Dam Reconstruction, Phase III
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 405 • Project Name: Gilboa Dam Reconstruction, Phase III
Date Reported As Of
2020-05-01T00:00:00.000
Pid
405
Project Name
Gilboa Dam Reconstruction, Phase III
Description
Gilboa Dam Reconstruction Project includes construction of a new low level outlet (LLO) consisting of 2,000 feet of tunneling, an access shaft, oulet structure and gate valve controls.
Category
Water Supply
Borough
Upstate
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2004-03-18T00:00:00.000
Budget Forecast
204633964.18
Latest Budget Changes
10329.87
Total Budget Changes
10376533.49
Forecast Completion
2021-10-18T00:00:00.000
Latest Schedule Changes
101
Total Schedule Changes
1113
Coney Island Hospital CSS Building and Perimeter Flood Protection
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 561 • Project Name: Coney Island Hospital CSS Building and Perimeter Flood Protection
Date Reported As Of
2020-05-01T00:00:00.000
Pid
561
Project Name
Coney Island Hospital CSS Building and Perimeter Flood Protection
Description
Renovation of CIH to advance the City’s resiliency plan, repair damages, and protect the hospital from future disasters.
Category
Health and Hospitals
Borough
Brooklyn
Managing Agency
EDC
Client Agency
H+H
Current Phase
Construction
Design Start
2016-02-01T00:00:00.000
Budget Forecast
683220954.00
Latest Budget Changes
0.00
Total Budget Changes
30635879.93
Forecast Completion
2023-07-31T00:00:00.000
Latest Schedule Changes
122
Total Schedule Changes
1243
Central Park Light Infrastructure
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 586 • Project Name: Central Park Light Infrastructure
Date Reported As Of
2020-05-01T00:00:00.000
Pid
586
Project Name
Central Park Light Infrastructure
Description
Install, remove, and furnish equipment for electrical work associated with traffic signals, lighting, and distribution systems in Central Park, Manhattan.
Category
Parks, Streets and Roadways
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2016-04-29T00:00:00.000
Budget Forecast
43173656.00
Latest Budget Changes
-130000.00
Total Budget Changes
-3323649.60
Total Schedule Changes
1535
Hillview Reservoir Chemical Addition Facilities
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 669 • Project Name: Hillview Reservoir Chemical Addition Facilities
Date Reported As Of
2020-05-01T00:00:00.000
Pid
669
Project Name
Hillview Reservoir Chemical Addition Facilities
Description
This project provides new chemical addition and support facilities at Hillview Reservoir.
Category
Water Supply
Borough
City of Yonkers
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2020-03-17T00:00:00.000
Budget Forecast
412815000.00
Latest Budget Changes
15290000.00
Total Budget Changes
159902202.01
Forecast Completion
2029-01-23T00:00:00.000
Latest Schedule Changes
64
Total Schedule Changes
82
Supreme Courthouse Fire Alarm/ Protection Upgrade
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 837 • Project Name: Supreme Courthouse Fire Alarm/ Protection Upgrade
Date Reported As Of
2020-05-01T00:00:00.000
Pid
837
Project Name
Supreme Courthouse Fire Alarm/ Protection Upgrade
Category
Public Safety and Criminal Justice
Managing Agency
DDC
Client Agency
DCAS
Total Budget Changes
37248610.00
Total Schedule Changes
1319
Ped Safety Upgrades on Atlantic Avenue, Phase 2
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 519 • Project Name: Ped Safety Upgrades on Atlantic Avenue, Phase 2
Date Reported As Of
2020-05-01T00:00:00.000
Pid
519
Project Name
Ped Safety Upgrades on Atlantic Avenue, Phase 2
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Total Budget Changes
10136496.00
Total Schedule Changes
1400
Revenue Cycle Implementation
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 723 • Project Name: Revenue Cycle Implementation
Date Reported As Of
2020-05-01T00:00:00.000
Pid
723
Project Name
Revenue Cycle Implementation
Description
The Epic Revenue Cycle system will be enterprise-wide and help increase revenue (by proper billing of services provided) in addition to ensuring patient safety and improved patient care, a top priority in workflows.
Category
Health and Hospitals, IT
Borough
Citywide
Managing Agency
HHC
Client Agency
H+H
Current Phase
IT
Budget Forecast
289117990.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2021-05-30T00:00:00.000
Latest Schedule Changes
196
Total Schedule Changes
1279
Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 112 • Project Name: Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Date Reported As Of
2020-05-01T00:00:00.000
Pid
112
Project Name
Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Description
Repair abutments, piers, approaches, and steel superstructure located in Pelham Bay, Bronx; replace reinforced concrete deck.
Category
Bridges, Streets and Roadways
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
1995-01-17T00:00:00.000
Budget Forecast
81753674.00
Latest Budget Changes
-425000.00
Total Budget Changes
20945057.00
Total Schedule Changes
1592
Grand Street Bridge over Newtown Creek
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 534 • Project Name: Grand Street Bridge over Newtown Creek
Date Reported As Of
2020-05-01T00:00:00.000
Pid
534
Project Name
Grand Street Bridge over Newtown Creek
Description
Replace the existing structure (swing-type bridge) with a new bridge; located between Gardner Avenue in Brooklyn and 47th Street in Queens.
Category
Bridges, Streets and Roadways
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2019-06-17T00:00:00.000
Budget Forecast
141102744.00
Latest Budget Changes
300000.00
Total Budget Changes
160682490.00
Forecast Completion
2030-06-03T00:00:00.000
Latest Schedule Changes
1280
Total Schedule Changes
1645
UNION TURNPIKE CENTER MEDIAN REPLACEMENT
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 986 • Project Name: UNION TURNPIKE CENTER MEDIAN REPLACEMENT
Date Reported As Of
2020-05-01T00:00:00.000
Pid
986
Project Name
UNION TURNPIKE CENTER MEDIAN REPLACEMENT
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Total Budget Changes
23766000.00
Total Schedule Changes
341
Bronx River CSO Reduction
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 943 • Project Name: Bronx River CSO Reduction
Date Reported As Of
2020-05-01T00:00:00.000
Pid
943
Project Name
Bronx River CSO Reduction
Description
The project will provide hydraulic relief to Outfalls HP-007 and HP-009 by creating new sewers parallel to the existing combined sewers. It will also provide floatables control at Outfall HP-011 by replacing Regulator 5.
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
WWC
Current Phase
Design
Design Start
2020-04-16T00:00:00.000
Budget Forecast
184768403.00
Latest Budget Changes
1630435.00
Total Budget Changes
1210235.00
Forecast Completion
2028-12-13T00:00:00.000
Latest Schedule Changes
-435
Total Schedule Changes
-712
Power Distribution at Bowery Bay WWTP
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 522 • Project Name: Power Distribution at Bowery Bay WWTP
Date Reported As Of
2020-05-01T00:00:00.000
Pid
522
Project Name
Power Distribution at Bowery Bay WWTP
Description
Power Distribution at Bowery Bay WWTP.
Category
Wastewater Treatment
Borough
Queens
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2015-11-13T00:00:00.000
Budget Forecast
68873764.13
Latest Budget Changes
316.47
Total Budget Changes
24235381.01
Forecast Completion
2023-01-27T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1684
Sewer When & Where Seq
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 794 • Project Name: Sewer When & Where Seq
Date Reported As Of
2020-05-01T00:00:00.000
Pid
794
Project Name
Sewer When & Where Seq
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Total Budget Changes
3200000.00
Total Schedule Changes
1377
Reconstruction of Power Distribution at Wards Island WWTP
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 453 • Project Name: Reconstruction of Power Distribution at Wards Island WWTP
Date Reported As Of
2020-05-01T00:00:00.000
Pid
453
Project Name
Reconstruction of Power Distribution at Wards Island WWTP
Description
Upgrades significant portions of the electrical distribution infrastructure including 5 power center installations, 23 motor control centers, 6 automatic transfer switches and 35 transformers throughout the plant, main feeders, breakers
Category
Wastewater Treatment
Borough
Manhattan
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2019-06-04T00:00:00.000
Budget Forecast
126586628.50
Latest Budget Changes
848922.50
Total Budget Changes
33489860.26
Forecast Completion
2025-06-30T00:00:00.000
Latest Schedule Changes
169
Total Schedule Changes
1147
Queens IS at 47-10 Barnett Avenue Addition
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 967 • Project Name: Queens IS at 47-10 Barnett Avenue Addition
Date Reported As Of
2020-05-01T00:00:00.000
Pid
967
Project Name
Queens IS at 47-10 Barnett Avenue Addition
Description
NEW SCHOOL
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2018-07-02T00:00:00.000
Budget Forecast
95408495.00
Latest Budget Changes
0.00
Total Budget Changes
3206657.00
Forecast Completion
2022-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
365
Brooklyn P.S. at 4302 4TH AVE
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 949 • Project Name: Brooklyn P.S. at 4302 4TH AVE
Date Reported As Of
2020-05-01T00:00:00.000
Pid
949
Project Name
Brooklyn P.S. at 4302 4TH AVE
Description
NEW SCHOOL (PHASE II)
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2017-11-17T00:00:00.000
Budget Forecast
66058403.00
Latest Budget Changes
0.00
Total Budget Changes
-221356.00
Forecast Completion
2022-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
365
Throgs Neck Pumping Station Rehabilitation and Improvements
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 722 • Project Name: Throgs Neck Pumping Station Rehabilitation and Improvements
Date Reported As Of
2020-05-01T00:00:00.000
Pid
722
Project Name
Throgs Neck Pumping Station Rehabilitation and Improvements
Description
Throgs Neck Pumping Station Rehabilitation and Improvements
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2018-06-11T00:00:00.000
Budget Forecast
48188239.69
Latest Budget Changes
79592.69
Total Budget Changes
25708336.86
Forecast Completion
2024-01-11T00:00:00.000
Latest Schedule Changes
48
Total Schedule Changes
1306
BROAD CHANNEL BULKHEADS - PH II
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 617 • Project Name: BROAD CHANNEL BULKHEADS - PH II
Date Reported As Of
2020-05-01T00:00:00.000
Pid
617
Project Name
BROAD CHANNEL BULKHEADS - PH II
Category
Industrial Development
Managing Agency
DDC
Client Agency
Transportation
Total Budget Changes
61781000.00
Total Schedule Changes
-74
West 35th Street over Amtrak
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 696 • Project Name: West 35th Street over Amtrak
Date Reported As Of
2020-05-01T00:00:00.000
Pid
696
Project Name
West 35th Street over Amtrak
Description
Repair the West 35th Street bridge over Amtrak, Manhattan
Category
Bridges
Borough
Manhattan
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2018-11-21T00:00:00.000
Budget Forecast
33171034.00
Latest Budget Changes
-500000.00
Total Budget Changes
-621966.00
Total Schedule Changes
2846
DELANCEY STREET SAFETY IMPROVEMENTS
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 983 • Project Name: DELANCEY STREET SAFETY IMPROVEMENTS
Date Reported As Of
2020-05-01T00:00:00.000
Pid
983
Project Name
DELANCEY STREET SAFETY IMPROVEMENTS
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Total Budget Changes
20937000.00
Total Schedule Changes
1217
TLC - NEW OFFICE FACILITY - 24-55 BQE WEST
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 665 • Project Name: TLC - NEW OFFICE FACILITY - 24-55 BQE WEST
Date Reported As Of
2020-05-01T00:00:00.000
Pid
665
Project Name
TLC - NEW OFFICE FACILITY - 24-55 BQE WEST
Category
Other Government Facilities
Borough
Queens
Managing Agency
DDC
Client Agency
DCAS
Total Budget Changes
75370000.00
Total Schedule Changes
1248
Bainbridge Avenue Trunk Water Main
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 454 • Project Name: Bainbridge Avenue Trunk Water Main
Date Reported As Of
2020-05-01T00:00:00.000
Pid
454
Project Name
Bainbridge Avenue Trunk Water Main
Category
Water Supply
Borough
Bronx
Managing Agency
DDC
Client Agency
Environmental Protection
Total Budget Changes
25547000.00
Total Schedule Changes
1687
2nd Avenue Watermain Trunk Construction
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 388 • Project Name: 2nd Avenue Watermain Trunk Construction
Date Reported As Of
2020-05-01T00:00:00.000
Pid
388
Project Name
2nd Avenue Watermain Trunk Construction
Category
Water Supply
Borough
Manhattan
Managing Agency
DDC
Client Agency
Environmental Protection
Total Budget Changes
-7266000.00
Total Schedule Changes
2113
Hillview Reservoir Flow Control Improvements
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 670 • Project Name: Hillview Reservoir Flow Control Improvements
Date Reported As Of
2020-05-01T00:00:00.000
Pid
670
Project Name
Hillview Reservoir Flow Control Improvements
Description
This project provides improvements to the existing structures and mechanical flow control systems at Hillview Reservoir.
Category
Water Supply
Borough
City of Yonkers
Managing Agency
DEP
Client Agency
BWS
Current Phase
Design
Design Start
2020-04-13T00:00:00.000
Budget Forecast
351840000.00
Latest Budget Changes
25075000.00
Total Budget Changes
-11397050.18
Forecast Completion
2032-06-05T00:00:00.000
Latest Schedule Changes
43
Total Schedule Changes
254
Grand Concourse Reconstruction, Phase 4 (Great Streets)
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 476 • Project Name: Grand Concourse Reconstruction, Phase 4 (Great Streets)
Date Reported As Of
2020-05-01T00:00:00.000
Pid
476
Project Name
Grand Concourse Reconstruction, Phase 4 (Great Streets)
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Total Budget Changes
57634000.00
Total Schedule Changes
1448
Manhattan Greenway: East Midtown
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 859 • Project Name: Manhattan Greenway: East Midtown
Date Reported As Of
2020-05-01T00:00:00.000
Pid
859
Project Name
Manhattan Greenway: East Midtown
Description
The East Midtown Waterfront Greenway project involves the creation of a waterfront esplanade between East 53rd and East 59th Streets.
Category
Parks
Managing Agency
EDC
Client Agency
EDC
Current Phase
Construction
Design Start
2017-10-01T00:00:00.000
Budget Forecast
130000000.00
Latest Budget Changes
0.00
Total Budget Changes
24840000.00
Forecast Completion
2022-11-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
487
New Storm Sewer N Conduit Av-Baisley Blvd
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 792 • Project Name: New Storm Sewer N Conduit Av-Baisley Blvd
Date Reported As Of
2020-05-01T00:00:00.000
Pid
792
Project Name
New Storm Sewer N Conduit Av-Baisley Blvd
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Total Budget Changes
31711000.00
Total Schedule Changes
1619
Red Hook Recreation Area Track 1, Soccer Fields 3-5, and Ballfields 1-4 Reconstruction
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 974 • Category: Parks
Date Reported As Of
2020-05-01T00:00:00.000
Pid
974
Project Name
Red Hook Recreation Area Track 1, Soccer Fields 3-5, and Ballfields 1-4 Reconstruction
Description
This project will reconstruct the track & field and convert three soccer fields and four ballfields from natural turf to synthetic turf at Red Hook Recreation Area.
Category
Parks
Managing Agency
DPR
Client Agency
DPR
Current Phase
Construction Procurement
Design Start
2017-11-01T00:00:00.000
Budget Forecast
75928000.00
Latest Budget Changes
-3339000.00
Total Budget Changes
-10555000.00
Forecast Completion
2022-03-18T00:00:00.000
Latest Schedule Changes
81
Total Schedule Changes
1082
RECONSTRUCTION OF ROSEDALE AREA, PHASE 2
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 1011 • Project Name: RECONSTRUCTION OF ROSEDALE AREA, PHASE 2
Date Reported As Of
2020-05-01T00:00:00.000
Pid
1011
Project Name
RECONSTRUCTION OF ROSEDALE AREA, PHASE 2
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Total Budget Changes
61291000.00
Total Schedule Changes
829
Boston Road Bridge Over Hutchinson River Rehabilitation
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 539 • Project Name: Boston Road Bridge Over Hutchinson River Rehabilitation
Date Reported As Of
2020-05-01T00:00:00.000
Pid
539
Project Name
Boston Road Bridge Over Hutchinson River Rehabilitation
Description
Rehabilitation of Boston Road Bridge over Hutchinson River, located in the Bornx.
Category
Bridges, Streets and Roadways
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2018-04-16T00:00:00.000
Budget Forecast
81002092.00
Latest Budget Changes
3320000.00
Total Budget Changes
49309814.00
Forecast Completion
2024-06-25T00:00:00.000
Latest Schedule Changes
42
Total Schedule Changes
803
5th Avenue Bridge Reconstruction over LIRR and Sea Beach, Brooklyn
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 504 • Project Name: 5th Avenue Bridge Reconstruction over LIRR and Sea Beach, Brooklyn
Date Reported As Of
2020-05-01T00:00:00.000
Pid
504
Project Name
5th Avenue Bridge Reconstruction over LIRR and Sea Beach, Brooklyn
Description
Replace the 5th Avenue Bridge over LIRR & Sea Beach, Brooklyn.
Category
Bridges
Borough
Brooklyn
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-11-30T00:00:00.000
Budget Forecast
77894823.00
Latest Budget Changes
25000.00
Total Budget Changes
36577693.00
Forecast Completion
2026-10-20T00:00:00.000
Latest Schedule Changes
268
Total Schedule Changes
969
NEW 48" TRUNK WATER MAIN IN E 233 STREET
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 998 • Project Name: NEW 48" TRUNK WATER MAIN IN E 233 STREET
Date Reported As Of
2020-05-01T00:00:00.000
Pid
998
Project Name
NEW 48" TRUNK WATER MAIN IN E 233 STREET
Category
Water Supply
Managing Agency
DDC
Client Agency
Environmental Protection
Total Budget Changes
1077000.00
Total Schedule Changes
1796
RECONSTRUCTION OF QUEENS BLVD - PHASE 1
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 618 • Project Name: RECONSTRUCTION OF QUEENS BLVD - PHASE 1
Date Reported As Of
2020-05-01T00:00:00.000
Pid
618
Project Name
RECONSTRUCTION OF QUEENS BLVD - PHASE 1
Category
Industrial Development
Borough
Queens
Managing Agency
DDC
Client Agency
Transportation
Total Budget Changes
176245000.00
Total Schedule Changes
1906
Sunset Park Infrastructure
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 574 • Project Name: Sunset Park Infrastructure
Date Reported As Of
2020-05-01T00:00:00.000
Pid
574
Project Name
Sunset Park Infrastructure
Description
This project is construction of infrastructure and streetscape improvements in Sunset Park from 37th to 43rd Streets, between the Gowanus Expressway and the waterfront - to activate the waterfront and promote future development.
Category
Industrial Development
Borough
Brooklyn
Managing Agency
EDC
Client Agency
Mayor's Office
Current Phase
Construction Procurement
Design Start
2016-06-08T00:00:00.000
Budget Forecast
37500000.00
Latest Budget Changes
0.00
Total Budget Changes
31633941.69
Forecast Completion
2023-03-01T00:00:00.000
Latest Schedule Changes
184
Total Schedule Changes
1290
Rondout-West Branch Bypass Tunnel Construction Project 2
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 409 • Project Name: Rondout-West Branch Bypass Tunnel Construction Project 2
Date Reported As Of
2020-05-01T00:00:00.000
Pid
409
Project Name
Rondout-West Branch Bypass Tunnel Construction Project 2
Description
To address existing leaks in the Delaware Aqueduct, a 3-mile bypass tunnel will be constructed near the town of Roseton and the existing tunnel will be repaired near the town of Wawarsing.
Category
Water Supply
Borough
Marlboro
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2012-03-23T00:00:00.000
Budget Forecast
881472816.70
Latest Budget Changes
-938686.30
Total Budget Changes
202552329.25
Forecast Completion
2023-09-26T00:00:00.000
Latest Schedule Changes
20
Total Schedule Changes
256
Storm Mitigation Loan Program at Red Hook
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 721 • Project Name: Storm Mitigation Loan Program at Red Hook
Date Reported As Of
2020-05-01T00:00:00.000
Pid
721
Project Name
Storm Mitigation Loan Program at Red Hook
Description
SMLP portion for Red Hook WRRF as part of the New York City Wastewater Resiliency Program.
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction Procurement
Design Start
2018-11-01T00:00:00.000
Budget Forecast
24483914.27
Latest Budget Changes
514647.10
Total Budget Changes
13549422.97
Forecast Completion
2022-07-05T00:00:00.000
Latest Schedule Changes
57
Total Schedule Changes
921
New York State Pavilion Observation Towers Reconstruction
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 1018 • Project Name: New York State Pavilion Observation Towers Reconstruction
Date Reported As Of
2020-05-01T00:00:00.000
Pid
1018
Project Name
New York State Pavilion Observation Towers Reconstruction
Description
This project will reconstruct portions of the New York State Pavilion Observation Towers in Flushing Meadows Corona Park.
Category
Parks
Managing Agency
DPR
Client Agency
DPR
Current Phase
Construction
Design Start
2015-09-21T00:00:00.000
Budget Forecast
28778000.00
Latest Budget Changes
0.00
Total Budget Changes
1000.00
Forecast Completion
2021-07-20T00:00:00.000
Latest Schedule Changes
91
Total Schedule Changes
772
STM & SAN SWR, WILLET PT BLVD WHITESTONE AREA, PH2
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 651 • Project Name: STM & SAN SWR, WILLET PT BLVD WHITESTONE AREA, PH2
Date Reported As Of
2020-05-01T00:00:00.000
Pid
651
Project Name
STM & SAN SWR, WILLET PT BLVD WHITESTONE AREA, PH2
Category
Sewers
Borough
Queens
Managing Agency
DDC
Client Agency
Environmental Protection
Total Budget Changes
41243000.00
Total Schedule Changes
642
Brooklyn Supreme Court Fire Alarm System Upgrade
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 510 • Project Name: Brooklyn Supreme Court Fire Alarm System Upgrade
Date Reported As Of
2020-05-01T00:00:00.000
Pid
510
Project Name
Brooklyn Supreme Court Fire Alarm System Upgrade
Category
Public Safety and Criminal Justice
Borough
Brooklyn
Managing Agency
DDC
Client Agency
DCAS
Total Budget Changes
47003000.00
Total Schedule Changes
1533
Henry Hudson Parkway over Amtrak (Northbound)
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 592 • Project Name: Henry Hudson Parkway over Amtrak (Northbound)
Date Reported As Of
2020-05-01T00:00:00.000
Pid
592
Project Name
Henry Hudson Parkway over Amtrak (Northbound)
Description
Replace the Ramp to northbound Henry Hudson Parkway over Amtrak in Manhattan.
Category
Bridges
Borough
Manhattan
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2020-01-02T00:00:00.000
Budget Forecast
54051000.00
Latest Budget Changes
500000.00
Total Budget Changes
500625.00
Forecast Completion
2030-02-25T00:00:00.000
Latest Schedule Changes
232
Total Schedule Changes
1693
Oakwood Beach WWTP Headworks Improvements
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 450 • Project Name: Oakwood Beach WWTP Headworks Improvements
Date Reported As Of
2020-05-01T00:00:00.000
Pid
450
Project Name
Oakwood Beach WWTP Headworks Improvements
Description
Replacement of six bar screens, grit bin vibrator, six ring flushing pumps, six main sewage pumps and assoc. piping/valves and motor control center, replacement of four exhaust fans, gas and oxygen detectors and a 15 KVA transformer
Category
Wastewater Treatment
Borough
Staten Island
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction Procurement
Design Start
2015-12-23T00:00:00.000
Budget Forecast
74556528.00
Latest Budget Changes
15437630.00
Total Budget Changes
31867440.00
Forecast Completion
2025-10-16T00:00:00.000
Latest Schedule Changes
422
Total Schedule Changes
2857
Pelham Parkway Roadway Reconstruction, Phase 2
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 180 • Project Name: Pelham Parkway Roadway Reconstruction, Phase 2
Date Reported As Of
2020-05-01T00:00:00.000
Pid
180
Project Name
Pelham Parkway Roadway Reconstruction, Phase 2
Category
Streets and Roadways
Borough
Bronx
Managing Agency
DDC
Client Agency
Transportation
Total Budget Changes
125164000.00
Total Schedule Changes
2869
Roosevelt Avenue Bridge Superstructure and Substructure Repairs
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 101 • Project Name: Roosevelt Avenue Bridge Superstructure and Substructure Repairs
Date Reported As Of
2020-05-01T00:00:00.000
Pid
101
Project Name
Roosevelt Avenue Bridge Superstructure and Substructure Repairs
Description
Repair the bridge superstructure and substructure and install a new concrete-filled steel grid deck.
Category
Bridges
Borough
Queens
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2003-03-10T00:00:00.000
Budget Forecast
119994667.00
Latest Budget Changes
2793000.00
Total Budget Changes
23798213.00
Total Schedule Changes
2003
Replacement of the Esopus & Route 28A Railroad Bridges
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 443 • Project Name: Replacement of the Esopus & Route 28A Railroad Bridges
Date Reported As Of
2020-05-01T00:00:00.000
Pid
443
Project Name
Replacement of the Esopus & Route 28A Railroad Bridges
Description
Replacement of the Esopus Creek Bridge & Route 28A Railroad Bridge
Category
Bridges
Borough
Olive
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction Procurement
Design Start
2016-10-11T00:00:00.000
Budget Forecast
86554947.00
Latest Budget Changes
89842.00
Total Budget Changes
-50461071.35
Forecast Completion
2025-01-01T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
714