All major infrastructure and information technology projects with a budget of $25 million or more that are currently active (in the design, procurement, or construction phase).
City GovernmentMayor's Office of Operations (OPS)
Dataset n7gv-k5yt
16 fields
East 180th Street over Metro North Railroad (Harrison Line)
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 811 • Project Name: East 180th Street over Metro North Railroad (Harrison Line)
Date Reported As Of
2020-05-01T00:00:00.000
Pid
811
Project Name
East 180th Street over Metro North Railroad (Harrison Line)
Description
Rehabilitation of East 180th Street Bridge over Metro North Railroad, the Bronx
Category
Bridges
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction Procurement
Design Start
2017-02-06T00:00:00.000
Budget Forecast
37849378.00
Latest Budget Changes
-1719000.00
Total Budget Changes
4194366.00
Total Schedule Changes
664
Raise Shorelines Citywide
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 689 • Project Name: Raise Shorelines Citywide
Date Reported As Of
2020-05-01T00:00:00.000
Pid
689
Project Name
Raise Shorelines Citywide
Description
The design and construction of shoreline reconstruction projects necessary to provide Citywide protection from future flooding caused by elevated seal elvels.
Category
Industrial Development
Borough
Citywide
Managing Agency
EDC
Client Agency
ORR
Current Phase
Design
Design Start
2017-08-01T00:00:00.000
Budget Forecast
89152926.86
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2022-12-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
639
FUEL TANK REPLACEMENT
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 851 • Project Name: FUEL TANK REPLACEMENT
Date Reported As Of
2020-05-01T00:00:00.000
Pid
851
Project Name
FUEL TANK REPLACEMENT
Category
Industrial Development
Managing Agency
DDC
Client Agency
DCAS
Total Budget Changes
207000.00
Total Schedule Changes
1278
RECONSTRUCTION OF QUEENS BLVD - PHASE 2
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 619 • Project Name: RECONSTRUCTION OF QUEENS BLVD - PHASE 2
Date Reported As Of
2020-05-01T00:00:00.000
Pid
619
Project Name
RECONSTRUCTION OF QUEENS BLVD - PHASE 2
Category
Industrial Development
Borough
Queens
Managing Agency
DDC
Client Agency
Transportation
Total Budget Changes
14201000.00
Total Schedule Changes
2315
Flatbush Avenue Trunk Watermain Replacement
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 370 • Project Name: Flatbush Avenue Trunk Watermain Replacement
Date Reported As Of
2020-05-01T00:00:00.000
Pid
370
Project Name
Flatbush Avenue Trunk Watermain Replacement
Category
Wastewater Treatment
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Environmental Protection
Total Budget Changes
39272000.00
Total Schedule Changes
2266
Reconstruction of the West and North Docks at the OH WWTP
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 720 • Project Name: Reconstruction of the West and North Docks at the OH WWTP
Date Reported As Of
2020-05-01T00:00:00.000
Pid
720
Project Name
Reconstruction of the West and North Docks at the OH WWTP
Description
RECONSTRUCTION OF SEA WALL AND DOCK AT OWLS HEAD WWTP
Category
Wastewater Treatment
Borough
Brooklyn
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2017-08-18T00:00:00.000
Budget Forecast
62530068.25
Latest Budget Changes
-1196345.75
Total Budget Changes
10985726.80
Forecast Completion
2023-02-22T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1389
Madison Avenue Bridge Reconstruction
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 114 • Project Name: Madison Avenue Bridge Reconstruction
Date Reported As Of
2020-05-01T00:00:00.000
Pid
114
Project Name
Madison Avenue Bridge Reconstruction
Description
Replace the electrical and mechanical systems of the Madison Avenue Bridge.
Category
Bridges
Borough
Manhattan, Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2011-02-14T00:00:00.000
Budget Forecast
59244994.00
Latest Budget Changes
150000.00
Total Budget Changes
2036997.00
Total Schedule Changes
1628
Douglaston New Facility
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 960 • Project Name: Douglaston New Facility
Date Reported As Of
2020-05-01T00:00:00.000
Pid
960
Project Name
Douglaston New Facility
Category
Libraries
Managing Agency
DDC
Client Agency
Libraries-QBPL
Total Budget Changes
5348000.00
Total Schedule Changes
244
Carl Schurz Park Promenade over FDR (East 81st to 90th Streets)
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 537 • Project Name: Carl Schurz Park Promenade over FDR (East 81st to 90th Streets)
Date Reported As Of
2020-05-01T00:00:00.000
Pid
537
Project Name
Carl Schurz Park Promenade over FDR (East 81st to 90th Streets)
Description
Replace the Promenade over FDR Drive between East 81st to 90th Streets in Manhattan.
Category
Bridges
Borough
Manhattan
Managing Agency
DOT
Client Agency
DOT, DPR
Current Phase
Design
Design Start
2017-05-30T00:00:00.000
Budget Forecast
313202421.00
Latest Budget Changes
-350000.00
Total Budget Changes
-197139579.00
Forecast Completion
2028-02-18T00:00:00.000
Latest Schedule Changes
840
Total Schedule Changes
1571
Lower Concourse: Park
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 961 • Project Name: Lower Concourse: Park
Date Reported As Of
2020-05-01T00:00:00.000
Pid
961
Project Name
Lower Concourse: Park
Description
Four-acre waterfront park in Lower Concourse, Bronx.
Category
Parks
Managing Agency
EDC
Client Agency
DPR
Current Phase
Design
Design Start
2019-09-30T00:00:00.000
Budget Forecast
35407359.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2023-12-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
456
Grand Concourse Metro North Railroad Bridge Construction
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 120 • Project Name: Grand Concourse Metro North Railroad Bridge Construction
Date Reported As Of
2020-05-01T00:00:00.000
Pid
120
Project Name
Grand Concourse Metro North Railroad Bridge Construction
Description
Repair the existing bridge and separate the NYCDOT and NYCT components. Includes new steel plate girders, concrete deck, pedestals, backwalls, sidewalks, and bridge railing.
Category
Bridges
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2000-02-14T00:00:00.000
Budget Forecast
74551379.00
Latest Budget Changes
360000.00
Total Budget Changes
22682117.00
Forecast Completion
2023-01-16T00:00:00.000
Latest Schedule Changes
232
Total Schedule Changes
836
Coney Island Area, Phase 3A
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 516 • Project Name: Coney Island Area, Phase 3A
Date Reported As Of
2020-05-01T00:00:00.000
Pid
516
Project Name
Coney Island Area, Phase 3A
Category
Industrial Development
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Environmental Protection
Total Budget Changes
25273000.00
Total Schedule Changes
1215
SOUTHEAST QUEENS PRIORITY GRIDS - GROUP 2
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 847 • Project Name: SOUTHEAST QUEENS PRIORITY GRIDS - GROUP 2
Date Reported As Of
2020-05-01T00:00:00.000
Pid
847
Project Name
SOUTHEAST QUEENS PRIORITY GRIDS - GROUP 2
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Total Budget Changes
14480000.00
Total Schedule Changes
1630
East 156th Street Bridge over Access to Housing
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 588 • Project Name: East 156th Street Bridge over Access to Housing
Date Reported As Of
2020-05-01T00:00:00.000
Pid
588
Project Name
East 156th Street Bridge over Access to Housing
Description
Replace the East 156th Street bridge over Access to Housing, Bronx.
Category
Bridges, Streets and Roadways
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-10-05T00:00:00.000
Budget Forecast
66500331.00
Latest Budget Changes
500000.00
Total Budget Changes
-363846.00
Forecast Completion
2028-08-01T00:00:00.000
Latest Schedule Changes
90
Total Schedule Changes
1720
Metropolitan Hospital Perimeter Flood Protection
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 562 • Project Name: Metropolitan Hospital Perimeter Flood Protection
The priority mitigation projects at Coler include key critical mitigation projects to improve the resiliency of the campus.
Category
Health and Hospitals
Borough
Manhattan
Managing Agency
EDC
Client Agency
H+H
Current Phase
Construction
Design Start
2014-09-01T00:00:00.000
Budget Forecast
12073687.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2020-10-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2085
Reconstruction of the Port Jervis Wastewater Treatment Plant
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 444 • Project Name: Reconstruction of the Port Jervis Wastewater Treatment Plant
Date Reported As Of
2020-05-01T00:00:00.000
Pid
444
Project Name
Reconstruction of the Port Jervis Wastewater Treatment Plant
Description
Reconstruction of the Port Jervis WWTP as required based on the effluent limits proposed by the Delaware River Basin Commission (DRBC)
Category
Wastewater Treatment
Borough
Port Jervis
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2014-06-17T00:00:00.000
Budget Forecast
45700000.00
Latest Budget Changes
2350000.00
Total Budget Changes
9428438.55
Forecast Completion
2024-08-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2445
FDR Rehabilitation, Northbound (East 42nd to 49th Streets)
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 502 • Project Name: FDR Rehabilitation, Northbound (East 42nd to 49th Streets)
Date Reported As Of
2020-05-01T00:00:00.000
Pid
502
Project Name
FDR Rehabilitation, Northbound (East 42nd to 49th Streets)
Description
Repair the northbound FDR from East 42nd to 49th Streets.
Category
Bridges
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2016-08-30T00:00:00.000
Budget Forecast
99615178.00
Latest Budget Changes
0.00
Total Budget Changes
-2802822.00
Forecast Completion
2028-01-02T00:00:00.000
Latest Schedule Changes
302
Total Schedule Changes
1816
Primary Treatment Improvement at Wards Island WWTP
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 452 • Project Name: Primary Treatment Improvement at Wards Island WWTP
Date Reported As Of
2020-05-01T00:00:00.000
Pid
452
Project Name
Primary Treatment Improvement at Wards Island WWTP
Description
Replacement of internal mechanisms, concrete repairs, effluent weirs, scum troughs, grease pit collection system, electrical upgrades, HVAC upgrades, evaluation and improvement of cross collector drainage in 10 PST.
Category
Wastewater Treatment
Borough
Manhattan
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2017-11-06T00:00:00.000
Budget Forecast
95860322.35
Latest Budget Changes
70585.00
Total Budget Changes
99651290.98
Forecast Completion
2025-11-01T00:00:00.000
Latest Schedule Changes
123
Total Schedule Changes
2142
RECONSTRUCTION OF E 177 STREET/DEVOE AVENUE
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 623 • Project Name: RECONSTRUCTION OF E 177 STREET/DEVOE AVENUE
Date Reported As Of
2020-05-01T00:00:00.000
Pid
623
Project Name
RECONSTRUCTION OF E 177 STREET/DEVOE AVENUE
Category
Industrial Development, Streets and Roadways
Borough
Bronx
Managing Agency
DDC
Client Agency
Transportation
Total Budget Changes
25050000.00
Total Schedule Changes
1839
DBCD South Site Cultural Fit-Out
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 484 • Project Name: DBCD South Site Cultural Fit-Out
Date Reported As Of
2020-05-01T00:00:00.000
Pid
484
Project Name
DBCD South Site Cultural Fit-Out
Description
Interior fit-out of the south site cultural unit.
Category
Arts and Culture
Borough
Brooklyn
Managing Agency
EDC
Client Agency
DCLA
Current Phase
Construction Procurement
Design Start
2014-12-01T00:00:00.000
Budget Forecast
51070000.00
Latest Budget Changes
0.00
Total Budget Changes
36789601.16
Forecast Completion
2023-04-02T00:00:00.000
Latest Schedule Changes
124
Total Schedule Changes
1706
Beverly Road over Brighton Subway Line
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 709 • Project Name: Beverly Road over Brighton Subway Line
Date Reported As Of
2020-05-01T00:00:00.000
Pid
709
Project Name
Beverly Road over Brighton Subway Line
Description
Repair the Beverly Road bridge over BMT Subway Brighton, Brooklyn
Category
Bridges
Borough
Brooklyn
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2020-01-06T00:00:00.000
Budget Forecast
48202000.00
Latest Budget Changes
500000.00
Total Budget Changes
1279646.00
Forecast Completion
2028-07-11T00:00:00.000
Latest Schedule Changes
1057
Total Schedule Changes
1864
Replacement of The Digester at The Hunts Point WWTP
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 580 • Project Name: Replacement of The Digester at The Hunts Point WWTP
Date Reported As Of
2020-05-01T00:00:00.000
Pid
580
Project Name
Replacement of The Digester at The Hunts Point WWTP
Description
Construction of New Anaerobic Digesters
Category
Wastewater Treatment
Borough
Bronx
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2017-10-22T00:00:00.000
Budget Forecast
422341923.00
Latest Budget Changes
-6000.00
Total Budget Changes
72852004.14
Forecast Completion
2024-12-29T00:00:00.000
Latest Schedule Changes
-49
Total Schedule Changes
1355
253 Broadway NYC. Fire Alarm Raplacement
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 850 • Project Name: 253 Broadway NYC. Fire Alarm Raplacement
Date Reported As Of
2020-05-01T00:00:00.000
Pid
850
Project Name
253 Broadway NYC. Fire Alarm Raplacement
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
DCAS
Total Budget Changes
17827000.00
Total Schedule Changes
1553
Queens Public School 46 Additionl
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 1027 • Project Name: Queens Public School 46 Additionl
Date Reported As Of
2020-05-01T00:00:00.000
Pid
1027
Project Name
Queens Public School 46 Additionl
Description
ADDITION/PLAYGROUND REDEVELOPMENT PROJECT
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2019-02-01T00:00:00.000
Budget Forecast
63735015.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2022-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
365
Brooklyn Bridge - Approach Arches Rehabilitation
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 584 • Project Name: Brooklyn Bridge - Approach Arches Rehabilitation
Date Reported As Of
2020-05-01T00:00:00.000
Pid
584
Project Name
Brooklyn Bridge - Approach Arches Rehabilitation
Description
Rehabilitate approach arches and towers of Brooklyn Bridge. Including masonry cleaning, masonry repairs, repointing, rehabilition of transverse walls, new infill walls of the approach arch blocks. Clean and repoint the tower masonry, reinforce the gothic arches of the towers, and rehabilitate the tower tops.
Category
Bridges
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2016-04-13T00:00:00.000
Budget Forecast
334587414.00
Latest Budget Changes
-1300000.00
Total Budget Changes
33135732.10
Forecast Completion
2023-02-19T00:00:00.000
Latest Schedule Changes
263
Total Schedule Changes
1908
20th Avenue Storm and Sanitary Sewer Construction
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 432 • Project Name: 20th Avenue Storm and Sanitary Sewer Construction
Date Reported As Of
2020-05-01T00:00:00.000
Pid
432
Project Name
20th Avenue Storm and Sanitary Sewer Construction
Category
Sewers
Borough
Queens
Managing Agency
DDC
Client Agency
Environmental Protection
Total Budget Changes
117177000.00
Total Schedule Changes
2180
WM REPLMT EAST NEW YORK AVE
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 991 • Project Name: WM REPLMT EAST NEW YORK AVE
Date Reported As Of
2020-05-01T00:00:00.000
Pid
991
Project Name
WM REPLMT EAST NEW YORK AVE
Category
Water Supply
Managing Agency
DDC
Client Agency
Environmental Protection
Total Budget Changes
29337000.00
Total Schedule Changes
913
Harlem River Drive Ramp Reconstruction (George Washington Bridge)
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 708 • Project Name: Harlem River Drive Ramp Reconstruction (George Washington Bridge)
Date Reported As Of
2020-05-01T00:00:00.000
Pid
708
Project Name
Harlem River Drive Ramp Reconstruction (George Washington Bridge)
Description
Repair the Harlem River Drive Ramp to George Washington Bridge over Harlem River Drive Southbound (Trans-Manhattan Expressway), Manhattan
Category
Bridges, Streets and Roadways
Borough
Manhattan
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2019-02-07T00:00:00.000
Budget Forecast
430582546.00
Latest Budget Changes
0.00
Total Budget Changes
-3711870.00
Forecast Completion
2028-04-18T00:00:00.000
Latest Schedule Changes
4
Total Schedule Changes
2697
4Th Ave. Safety Improvements Phase II-Vision Zero
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 833 • Project Name: 4Th Ave. Safety Improvements Phase II-Vision Zero
Date Reported As Of
2020-05-01T00:00:00.000
Pid
833
Project Name
4Th Ave. Safety Improvements Phase II-Vision Zero
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Total Budget Changes
-11525000.00
Total Schedule Changes
1106
Freshkills South Park Synthetic Turf Fields and Landscape Construction
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 1016 • Project Name: Freshkills South Park Synthetic Turf Fields and Landscape Construction
Date Reported As Of
2020-05-01T00:00:00.000
Pid
1016
Project Name
Freshkills South Park Synthetic Turf Fields and Landscape Construction
Description
This project will construct synthetic turf athletic fields, roadways, a parking lot with associated landscaping and stormwater management, multi-use and pedestrian paths, benches, signage, fencing, and lighting, and restore woodlands and wetlands.
Category
Parks
Managing Agency
DPR
Client Agency
DPR
Current Phase
Design
Design Start
2016-11-30T00:00:00.000
Budget Forecast
37674141.28
Latest Budget Changes
0.00
Total Budget Changes
1436858.72
Forecast Completion
2023-04-18T00:00:00.000
Latest Schedule Changes
214
Total Schedule Changes
1309
Storm Mitigation Loan Program at Hunts Point
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 672 • Project Name: Storm Mitigation Loan Program at Hunts Point
Date Reported As Of
2020-05-01T00:00:00.000
Pid
672
Project Name
Storm Mitigation Loan Program at Hunts Point
Description
SMLP portion for Hunts Point WRRF as part of the New York City Wastewater Resiliency Program.
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2018-04-16T00:00:00.000
Budget Forecast
35957095.79
Latest Budget Changes
-3978946.89
Total Budget Changes
20080597.79
Forecast Completion
2022-04-25T00:00:00.000
Latest Schedule Changes
110
Total Schedule Changes
1091
Sewer When & Where Contract In S.E. Queens
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 793 • Project Name: Sewer When & Where Contract In S.E. Queens
Date Reported As Of
2020-05-01T00:00:00.000
Pid
793
Project Name
Sewer When & Where Contract In S.E. Queens
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Total Budget Changes
7404000.00
Total Schedule Changes
1834
Bronx Animal Care Center
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 893 • Project Name: Bronx Animal Care Center
Date Reported As Of
2020-05-01T00:00:00.000
Pid
893
Project Name
Bronx Animal Care Center
Category
Health and Hospitals
Managing Agency
DDC
Client Agency
Health
Total Budget Changes
24815617.00
Total Schedule Changes
110
West Tremont Avenue over Metro North Railroad
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 503 • Project Name: West Tremont Avenue over Metro North Railroad
Date Reported As Of
2020-05-01T00:00:00.000
Pid
503
Project Name
West Tremont Avenue over Metro North Railroad
Description
Replace/Rehab the West Tremont Avenue bridge over the Metro North line, located in the Bronx.
Category
Bridges
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-05-30T00:00:00.000
Budget Forecast
57644487.00
Latest Budget Changes
-425000.00
Total Budget Changes
37794543.00
Forecast Completion
2026-11-27T00:00:00.000
Latest Schedule Changes
4
Total Schedule Changes
1253
Electronic Medical Records Upgrade
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 403 • Project Name: Electronic Medical Records Upgrade
Date Reported As Of
2020-05-01T00:00:00.000
Pid
403
Project Name
Electronic Medical Records Upgrade
Description
The EPIC - EMR Program: Electronic Medical Records (EMR) System - a single enterprise-wide EMR to meet the needs of HHC's expansive size and improve patient care will replace the legacy EMR - QuadraMed, which is over 25 years old.
Category
Health and Hospitals, IT
Borough
Citywide
Managing Agency
HHC
Client Agency
H+H
Current Phase
IT
Budget Forecast
764063231.00
Latest Budget Changes
0.00
Total Budget Changes
15184947.00
Forecast Completion
2021-05-30T00:00:00.000
Latest Schedule Changes
455
Total Schedule Changes
2032
Staten Island 1 & 3 Garage Construction & Rehab
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 769 • Project Name: Staten Island 1 & 3 Garage Construction & Rehab
Date Reported As Of
2020-05-01T00:00:00.000
Pid
769
Project Name
Staten Island 1 & 3 Garage Construction & Rehab
Category
Sanitation
Borough
Staten Island
Managing Agency
DDC
Client Agency
Sanitation
Total Budget Changes
68555000.00
Total Schedule Changes
406
Construction of Gowanus CSO retention FAC Superfund Site
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 550 • Project Name: Construction of Gowanus CSO retention FAC Superfund Site
Date Reported As Of
2020-05-01T00:00:00.000
Pid
550
Project Name
Construction of Gowanus CSO retention FAC Superfund Site
Description
CSO Facilities, bulkheads, pilots and other requirements to comply with Gowanus Canal Superfund Adminstrative Orders
Category
Industrial Development
Borough
Brooklyn
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2017-11-22T00:00:00.000
Budget Forecast
1446700000.00
Latest Budget Changes
0.00
Total Budget Changes
432995114.00
Forecast Completion
2031-07-07T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1086
Grant Park Construction
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 1015 • Project Name: Grant Park Construction
Date Reported As Of
2020-05-01T00:00:00.000
Pid
1015
Project Name
Grant Park Construction
Description
This project will construct Grant Park, including converting the roadbed to recreational space.
Category
Parks
Managing Agency
DPR
Client Agency
DPR
Current Phase
Design
Design Start
2019-05-29T00:00:00.000
Budget Forecast
31101000.00
Latest Budget Changes
0.00
Total Budget Changes
1489000.00
Total Schedule Changes
612
Rehab Of Queens District 11/13 Sanitation Garage
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 770 • Project Name: Rehab Of Queens District 11/13 Sanitation Garage
Date Reported As Of
2020-05-01T00:00:00.000
Pid
770
Project Name
Rehab Of Queens District 11/13 Sanitation Garage
Category
Sanitation
Borough
Queens
Managing Agency
DDC
Client Agency
Sanitation
Total Budget Changes
36221000.00
Total Schedule Changes
1521
CONSTRUCTION OF BMPs NC 6 AND 15 - SI
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 631 • Project Name: CONSTRUCTION OF BMPs NC 6 AND 15 - SI
Date Reported As Of
2020-05-01T00:00:00.000
Pid
631
Project Name
CONSTRUCTION OF BMPs NC 6 AND 15 - SI
Category
Industrial Development
Borough
Staten Island
Managing Agency
DDC
Client Agency
Environmental Protection
Total Budget Changes
1921000.00
Total Schedule Changes
925
Water Main Replacement In 222 Street, Queens
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 768 • Project Name: Water Main Replacement In 222 Street, Queens
Date Reported As Of
2020-05-01T00:00:00.000
Pid
768
Project Name
Water Main Replacement In 222 Street, Queens
Category
Water Supply
Managing Agency
DDC
Client Agency
Environmental Protection
Total Budget Changes
7195000.00
Total Schedule Changes
2236
SUNSET PARK GOWANUS CONNECTOR, BK
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 979 • Project Name: SUNSET PARK GOWANUS CONNECTOR, BK
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 935 • Project Name: FUEL TANK REPLACEMENT - 71
Date Reported As Of
2020-05-01T00:00:00.000
Pid
935
Project Name
FUEL TANK REPLACEMENT - 71
Category
Industrial Development
Managing Agency
DDC
Client Agency
DCAS
Total Budget Changes
3444000.00
Total Schedule Changes
548
SAN & STRM SEWER, WM IN CONEY ISLAND AREA, PH 4
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 1009 • Project Name: SAN & STRM SEWER, WM IN CONEY ISLAND AREA, PH 4
Date Reported As Of
2020-05-01T00:00:00.000
Pid
1009
Project Name
SAN & STRM SEWER, WM IN CONEY ISLAND AREA, PH 4
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Total Budget Changes
1984000.00
Total Schedule Changes
1431
Wyckoff Avenue Street Reconstruction
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 191 • Project Name: Wyckoff Avenue Street Reconstruction
Date Reported As Of
2020-05-01T00:00:00.000
Pid
191
Project Name
Wyckoff Avenue Street Reconstruction
Category
Streets and Roadways
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Trans. & Env. Protection
Total Budget Changes
43926000.00
Total Schedule Changes
226
Gilboa Dam Reconstruction, Phase IV
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 406 • Project Name: Gilboa Dam Reconstruction, Phase IV
Date Reported As Of
2020-05-01T00:00:00.000
Pid
406
Project Name
Gilboa Dam Reconstruction, Phase IV
Description
This project will rehabilitate the mechanics and the architecture of the Shandaken Tunnel Intake Chamber, which includes the replacement of gates and general site improvements.
Category
Water Supply
Borough
Upstate
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2008-12-01T00:00:00.000
Budget Forecast
71088459.90
Latest Budget Changes
3631893.36
Total Budget Changes
33535991.20
Forecast Completion
2021-06-09T00:00:00.000
Latest Schedule Changes
44
Total Schedule Changes
1684
NEW UTRECH LIBRARY MAJOR RENOVATIONS
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 841 • Project Name: NEW UTRECH LIBRARY MAJOR RENOVATIONS
Date Reported As Of
2020-05-01T00:00:00.000
Pid
841
Project Name
NEW UTRECH LIBRARY MAJOR RENOVATIONS
Category
Libraries
Managing Agency
DDC
Client Agency
Libraries-BPL
Total Budget Changes
290000.00
Total Schedule Changes
1188
Power Distribution Improvements at Tallman Island
Date Reported As Of: 2020-05-01T00:00:00.000 • Pid: 907 • Project Name: Power Distribution Improvements at Tallman Island