Capital Projects

All major infrastructure and information technology projects with a budget of $25 million or more that are currently active (in the design, procurement, or construction phase).

City Government Mayor's Office of Operations (OPS) Dataset n7gv-k5yt 16 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
Edgewood Triangle Roadway Reconstruction
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 204 • Project Name: Edgewood Triangle Roadway Reconstruction
Date Reported As Of
2019-09-01T00:00:00.000
Pid
204
Project Name
Edgewood Triangle Roadway Reconstruction
Description
Reconstruct roadway and extend storm and sanitary sewers in portions of Brookville Boulevard, Edgewood Street, 147th Avenue, and adjacent streets west of 241st Street.
Category
Streets and Roadways
Borough
Queens
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2013-02-13T00:00:00.000
Budget Forecast
98423000.00
Latest Budget Changes
0.00
Total Budget Changes
106503000.00
Forecast Completion
2024-04-21T00:00:00.000
Latest Schedule Changes
30
Total Schedule Changes
3597
Coastal Resiliency Area 1 - East 23Rd St. To Montg
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 773 • Project Name: Coastal Resiliency Area 1 - East 23Rd St. To Montg
Date Reported As Of
2019-09-01T00:00:00.000
Pid
773
Project Name
Coastal Resiliency Area 1 - East 23Rd St. To Montg
Description
East Side Coastal Resiliency - Area 1 - East 23rd St. to Montgomery St., Manhattan
Category
Industrial Development, Parks
Managing Agency
DDC
Client Agency
Parks & Recreation
Current Phase
Design
Design Start
2016-04-27T00:00:00.000
Budget Forecast
1231314000.00
Latest Budget Changes
-8390000.00
Total Budget Changes
-418193636.37
Forecast Completion
2023-03-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
836
Power Distribution at Bowery Bay WWTP
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 522 • Project Name: Power Distribution at Bowery Bay WWTP
Date Reported As Of
2019-09-01T00:00:00.000
Pid
522
Project Name
Power Distribution at Bowery Bay WWTP
Description
Power Distribution at Bowery Bay WWTP.
Category
Wastewater Treatment
Borough
Queens
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction Procurement
Design Start
2015-11-13T00:00:00.000
Budget Forecast
69367895.20
Latest Budget Changes
2061996.20
Total Budget Changes
24235381.01
Forecast Completion
2022-10-31T00:00:00.000
Latest Schedule Changes
42
Total Schedule Changes
1684
Rehab Of Queens District 11/13 Sanitation Garage
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 770 • Project Name: Rehab Of Queens District 11/13 Sanitation Garage
Date Reported As Of
2019-09-01T00:00:00.000
Pid
770
Project Name
Rehab Of Queens District 11/13 Sanitation Garage
Description
The project is to extend the useful life of the facility through rehabilitation of the building structure and systems. This shall include: structural work, replacement of building MEP systems, architectural upgrade and replacement in kind of sidewalks and driveways
Category
Sanitation
Borough
Queens
Managing Agency
DDC
Client Agency
Sanitation
Current Phase
Design
Design Start
2017-03-06T00:00:00.000
Budget Forecast
68094000.00
Latest Budget Changes
6197000.00
Total Budget Changes
36221000.00
Forecast Completion
2023-07-01T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1521
Staten Island 1 & 3 Garage Construction & Rehab
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 769 • Project Name: Staten Island 1 & 3 Garage Construction & Rehab
Date Reported As Of
2019-09-01T00:00:00.000
Pid
769
Project Name
Staten Island 1 & 3 Garage Construction & Rehab
Description
The Department of Sanitation of the City of New York (DSNY) is planning to develop a Staten Island Districts 1 and 3 campus that will include a new garage serving both districts and renovation of the existing Borough Repair Shop. The site is to be reconfigured with new grading and drainage, new covered salt storage, new outdoor fueling, new household special waste collection, outdoor DSNY truck parking and a new force main sanitary line to connect to the NYC DEP sewer.
Category
Sanitation
Borough
Staten Island
Managing Agency
DDC
Client Agency
Sanitation
Current Phase
Construction Procurement
Design Start
2017-07-14T00:00:00.000
Budget Forecast
183135000.00
Latest Budget Changes
7603000.00
Total Budget Changes
68555000.00
Forecast Completion
2024-02-26T00:00:00.000
Latest Schedule Changes
71
Total Schedule Changes
406
Gilboa Dam Reconstruction, Phase IV
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 406 • Project Name: Gilboa Dam Reconstruction, Phase IV
Date Reported As Of
2019-09-01T00:00:00.000
Pid
406
Project Name
Gilboa Dam Reconstruction, Phase IV
Description
This project will rehabilitate the mechanics and the architecture of the Shandaken Tunnel Intake Chamber, which includes the replacement of gates and general site improvements.
Category
Water Supply
Borough
Upstate
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2008-12-01T00:00:00.000
Budget Forecast
67129022.92
Latest Budget Changes
156241.01
Total Budget Changes
33535991.20
Forecast Completion
2021-01-25T00:00:00.000
Latest Schedule Changes
-255
Total Schedule Changes
1684
FUEL TANK REPLACEMENT - 71
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 935 • Project Name: FUEL TANK REPLACEMENT - 71
Date Reported As Of
2019-09-01T00:00:00.000
Pid
935
Project Name
FUEL TANK REPLACEMENT - 71
Description
By Notice To Proceed letter dated September 21, 2018, the New York City Department of Design and Construction (“DDC”) directed PMS Construction Management Corp. (“PMS”) to commence work on Capis ID PW348-71, Contract No. 20191404531 CM/Design/Build for the Replacement and Upgrade of Petroleum Storage Tanks for the Borough of Manhattan. The contract was awarded for a maximum fee of $28,026,750.00 and was partially registered by the Comptroller on September 21, 2018 in the amount of $4,885,000.00. The term of the contract is 1,095 consecutive calendar days from September 21, 2018. Contract termination date is September 19, 2021.
Category
Industrial Development
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Construction Procurement
Design Start
2018-10-02T00:00:00.000
Budget Forecast
29265000.00
Latest Budget Changes
0.00
Total Budget Changes
3444000.00
Forecast Completion
2023-01-20T00:00:00.000
Latest Schedule Changes
123
Total Schedule Changes
548
SUNSET PARK GOWANUS CONNECTOR, BK
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 979 • Project Name: SUNSET PARK GOWANUS CONNECTOR, BK
Date Reported As Of
2019-09-01T00:00:00.000
Pid
979
Project Name
SUNSET PARK GOWANUS CONNECTOR, BK
Description
Sunset Park Gowanus Connector - Brooklyn Waterfront Greenway.
Category
Parks, Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction Procurement
Design Start
2017-09-18T00:00:00.000
Budget Forecast
45271000.00
Total Budget Changes
-16441000.00
Forecast Completion
2022-06-26T00:00:00.000
Total Schedule Changes
445
Water Main Replacement In 222 Street, Queens
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 768 • Project Name: Water Main Replacement In 222 Street, Queens
Date Reported As Of
2019-09-01T00:00:00.000
Pid
768
Project Name
Water Main Replacement In 222 Street, Queens
Description
WATER MAIN REPLACEMENT IN 222 STREET
Category
Water Supply
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2018-04-02T00:00:00.000
Budget Forecast
39530000.00
Latest Budget Changes
0.00
Total Budget Changes
7195000.00
Forecast Completion
2024-01-19T00:00:00.000
Latest Schedule Changes
366
Total Schedule Changes
2236
New 116Th Pct
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 762 • Project Name: New 116Th Pct
Date Reported As Of
2019-09-01T00:00:00.000
Pid
762
Project Name
New 116Th Pct
Description
Construction of a new precinct station house facility and associated site work for the new 116th Precinct.
Category
Public Safety and Criminal Justice
Managing Agency
DDC
Client Agency
Police
Current Phase
Construction Procurement
Design Start
2017-09-14T00:00:00.000
Budget Forecast
94624000.00
Latest Budget Changes
67000.00
Total Budget Changes
33852900.86
Forecast Completion
2022-06-08T00:00:00.000
Latest Schedule Changes
64
Total Schedule Changes
727
Construction Of Sanitary Sewers, Storm Sewers (Bm
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 760 • Project Name: Construction Of Sanitary Sewers, Storm Sewers (Bm
Date Reported As Of
2019-09-01T00:00:00.000
Pid
760
Project Name
Construction Of Sanitary Sewers, Storm Sewers (Bm
Description
Construction of storm sewers, sanitary sewers, water mains and Best Management Practice (BMP) NC-16 in Mason Avenue area, Borough of Staten Island.
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction Procurement
Design Start
2016-08-29T00:00:00.000
Budget Forecast
53121000.00
Latest Budget Changes
-347000.00
Total Budget Changes
37691000.00
Forecast Completion
2022-11-10T00:00:00.000
Latest Schedule Changes
56
Total Schedule Changes
595
Reconstruction Of Trinity Pl
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 755 • Project Name: Reconstruction Of Trinity Pl
Date Reported As Of
2019-09-01T00:00:00.000
Pid
755
Project Name
Reconstruction Of Trinity Pl
Description
Reconstruction of Trinity Place from Morris Street to Cedar Street, Borough of Manhattan
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2018-10-01T00:00:00.000
Budget Forecast
41510000.00
Latest Budget Changes
0.00
Total Budget Changes
13224000.00
Forecast Completion
2024-01-17T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
730
Upgrades At Brooklyn Animal Shelter
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 750 • Project Name: Upgrades At Brooklyn Animal Shelter
Date Reported As Of
2019-09-01T00:00:00.000
Pid
750
Project Name
Upgrades At Brooklyn Animal Shelter
Description
Demolish existing on-story facility. Construct a two-story new building for animal care center with a drive-through parking lot to meet the new program. Phasing is required to meet 24/7 operation.
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
Health
Current Phase
Design
Design Start
2016-07-20T00:00:00.000
Budget Forecast
49019000.00
Latest Budget Changes
21500000.00
Total Budget Changes
21288000.00
Forecast Completion
2023-10-10T00:00:00.000
Latest Schedule Changes
61
Total Schedule Changes
1355
Porpoise Bridge In Flushing Meadows-Corona Park
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 749 • Project Name: Porpoise Bridge In Flushing Meadows-Corona Park
Date Reported As Of
2019-09-01T00:00:00.000
Pid
749
Project Name
Porpoise Bridge In Flushing Meadows-Corona Park
Description
Feasibility Study for the repair and or restoration for Porpoise (Tide Gate) Bridge in Flushing Meadows Corona Park.
Category
Bridges
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2017-09-18T00:00:00.000
Budget Forecast
64905000.00
Latest Budget Changes
0.00
Total Budget Changes
82000.00
Forecast Completion
2024-07-23T00:00:00.000
Latest Schedule Changes
365
Total Schedule Changes
1110
Dumbo and Vinegar Hill Area Roadway Reconstruction and Renovation
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 193 • Project Name: Dumbo and Vinegar Hill Area Roadway Reconstruction and Renovation
Date Reported As Of
2019-09-01T00:00:00.000
Pid
193
Project Name
Dumbo and Vinegar Hill Area Roadway Reconstruction and Renovation
Description
Reconstruction DUMBO/Vinegar Hill Area including Trunk and Distribution water main replacement; Installation of HLSS and Combined Sewer replacement; Restoration of Belgian block in Water Street; Street lighting and Traffic Signal work.
Category
Streets and Roadways
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction
Design Start
2012-06-07T00:00:00.000
Budget Forecast
122502000.00
Latest Budget Changes
7552000.00
Total Budget Changes
96724000.00
Forecast Completion
2024-06-04T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
3253
BROWNSVILLE LIBRARY MAJOR RENOVATIONS
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 977 • Project Name: BROWNSVILLE LIBRARY MAJOR RENOVATIONS
Date Reported As Of
2019-09-01T00:00:00.000
Pid
977
Project Name
BROWNSVILLE LIBRARY MAJOR RENOVATIONS
Category
Libraries
Managing Agency
DDC
Client Agency
Libraries-BPL
Current Phase
Design
Design Start
2018-06-28T00:00:00.000
Budget Forecast
25502000.00
Total Budget Changes
6752000.00
Forecast Completion
2024-12-30T00:00:00.000
Total Schedule Changes
916
DELANCEY STREET SAFETY IMPROVEMENTS
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 983 • Project Name: DELANCEY STREET SAFETY IMPROVEMENTS
Date Reported As Of
2019-09-01T00:00:00.000
Pid
983
Project Name
DELANCEY STREET SAFETY IMPROVEMENTS
Description
DELANCEY STREET SAFETY IMPROVEMENTS
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2017-07-19T00:00:00.000
Budget Forecast
35594000.00
Total Budget Changes
20937000.00
Forecast Completion
2024-06-22T00:00:00.000
Total Schedule Changes
1217
Croton Above Ground Structure And Landscaping
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 747 • Project Name: Croton Above Ground Structure And Landscaping
Date Reported As Of
2019-09-01T00:00:00.000
Pid
747
Project Name
Croton Above Ground Structure And Landscaping
Description
The new Mosholu Golf Course Club House, together with fifty-five Driving Range Tee Boxes and ten-acres of re-landscaping comprise the phase IV and final of the vast DEP Croton Water Treatment Plant project, currently under construction in Van Cortlandt Park in the Bronx. Through a multifunctional design strategy the project reinstates the pre-existing golf program and facility, creates civic space for community use and ensures security for a multi-billion dollar public works facility.
Category
Industrial Development
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2012-05-23T00:00:00.000
Budget Forecast
103896000.00
Latest Budget Changes
-60000.00
Total Budget Changes
75117000.00
Forecast Completion
2021-03-18T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
897
Shore Road Bridge over Hutchinson River
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 541 • Project Name: Shore Road Bridge over Hutchinson River
Date Reported As Of
2019-09-01T00:00:00.000
Pid
541
Project Name
Shore Road Bridge over Hutchinson River
Description
Replace the Shore Road Bridge over the Hutchinson River with a new bridge.
Category
Bridges, Streets and Roadways
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-06-30T00:00:00.000
Budget Forecast
317488743.00
Latest Budget Changes
1750000.00
Total Budget Changes
-19049921.84
Total Schedule Changes
1477
Reconstruction Of Arthur Kill Road, Phase I
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 741 • Project Name: Reconstruction Of Arthur Kill Road, Phase I
Date Reported As Of
2019-09-01T00:00:00.000
Pid
741
Project Name
Reconstruction Of Arthur Kill Road, Phase I
Description
Reconstruction of Arthur Kill Rd from Clark Avenue to Richmond Avenue including widening of roadway
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2016-12-16T00:00:00.000
Budget Forecast
40398000.00
Latest Budget Changes
300000.00
Total Budget Changes
22503000.00
Forecast Completion
2023-10-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1415
New Ferry Boat Construction
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 94 • Project Name: New Ferry Boat Construction
Date Reported As Of
2019-09-01T00:00:00.000
Pid
94
Project Name
New Ferry Boat Construction
Description
Replace one Barberi class boat and the John F. Kennedy boat which are approaching the end of their useful lives with new Staten Island ferries. Replacement is needed to continue reliable service.
Category
Ferries
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2014-09-15T00:00:00.000
Budget Forecast
349399872.00
Latest Budget Changes
-470000.00
Total Budget Changes
-238419180.00
Total Schedule Changes
549
Far Rockaway New Facility
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 730 • Project Name: Far Rockaway New Facility
Date Reported As Of
2019-09-01T00:00:00.000
Pid
730
Project Name
Far Rockaway New Facility
Description
Construction of a new 18,000 sq.ft. Branch employing the latest technology and sustainable design.
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
Libraries-QBPL
Current Phase
Construction
Design Start
2012-01-10T00:00:00.000
Budget Forecast
32709000.00
Latest Budget Changes
0.00
Total Budget Changes
-623757.91
Forecast Completion
2020-09-15T00:00:00.000
Latest Schedule Changes
-318
Total Schedule Changes
-78
Emergency Communications Transformation Program (ECTP) Upgrades and Enhancements
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 267 • Project Name: Emergency Communications Transformation Program (ECTP) Upgrades and Enhancements
Date Reported As Of
2019-09-01T00:00:00.000
Pid
267
Project Name
Emergency Communications Transformation Program (ECTP) Upgrades and Enhancements
Description
Upgrade and enhancement of emergency technology infrastructure to improve interoperability and coordination among public safety agencies and improve call processing time to decrease overall response times.
Category
IT
Borough
Citywide
Managing Agency
DOITT
Client Agency
FDNY, NYPD
Current Phase
IT
Budget Forecast
2277311983.63
Latest Budget Changes
27421112.64
Total Budget Changes
73735148.87
Forecast Completion
2020-08-31T00:00:00.000
Latest Schedule Changes
162
Total Schedule Changes
2252
FUEL TANK REPLACEMENT
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 1005 • Project Name: FUEL TANK REPLACEMENT
Date Reported As Of
2019-09-01T00:00:00.000
Pid
1005
Project Name
FUEL TANK REPLACEMENT
Description
FUEL TANK REPLACEMENT
Category
Industrial Development
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Construction
Design Start
2018-04-25T00:00:00.000
Budget Forecast
32145000.00
Total Budget Changes
-6429000.00
Forecast Completion
2022-04-04T00:00:00.000
Total Schedule Changes
914
Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 112 • Project Name: Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Date Reported As Of
2019-09-01T00:00:00.000
Pid
112
Project Name
Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Description
Repair abutments, piers, approaches, and steel superstructure located in Pelham Bay, Bronx; replace reinforced concrete deck.
Category
Bridges, Streets and Roadways
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
1995-01-17T00:00:00.000
Budget Forecast
81833276.00
Latest Budget Changes
-859946.00
Total Budget Changes
20945057.00
Total Schedule Changes
1592
Revenue Cycle Implementation
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 723 • Project Name: Revenue Cycle Implementation
Date Reported As Of
2019-09-01T00:00:00.000
Pid
723
Project Name
Revenue Cycle Implementation
Description
The Epic Revenue Cycle system will be enterprise-wide and help increase revenue (by proper billing of services provided) in addition to ensuring patient safety and improved patient care, a top priority in workflows.
Category
Health and Hospitals, IT
Borough
Citywide
Managing Agency
HHC
Client Agency
H+H
Current Phase
IT
Budget Forecast
289117990.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2019-12-07T00:00:00.000
Latest Schedule Changes
706
Total Schedule Changes
1279
Rondout-West Branch Bypass Tunnel Construction Project 2
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 409 • Project Name: Rondout-West Branch Bypass Tunnel Construction Project 2
Date Reported As Of
2019-09-01T00:00:00.000
Pid
409
Project Name
Rondout-West Branch Bypass Tunnel Construction Project 2
Description
To address existing leaks in the Delaware Aqueduct, a 3-mile bypass tunnel will be constructed near the town of Roseton and the existing tunnel will be repaired near the town of Wawarsing.
Category
Water Supply
Borough
Marlboro
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2012-03-23T00:00:00.000
Budget Forecast
877670452.38
Latest Budget Changes
-4569179.33
Total Budget Changes
202552329.25
Forecast Completion
2025-12-06T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
256
Throgs Neck Pumping Station Rehabilitation and Improvements
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 722 • Project Name: Throgs Neck Pumping Station Rehabilitation and Improvements
Date Reported As Of
2019-09-01T00:00:00.000
Pid
722
Project Name
Throgs Neck Pumping Station Rehabilitation and Improvements
Description
Throgs Neck Pumping Station Rehabilitation and Improvements
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2018-06-11T00:00:00.000
Budget Forecast
48108647.00
Latest Budget Changes
101736.00
Total Budget Changes
25708336.86
Forecast Completion
2023-04-26T00:00:00.000
Latest Schedule Changes
47
Total Schedule Changes
1306
Storm Mitigation Loan Program at Red Hook
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 721 • Project Name: Storm Mitigation Loan Program at Red Hook
Date Reported As Of
2019-09-01T00:00:00.000
Pid
721
Project Name
Storm Mitigation Loan Program at Red Hook
Description
SMLP portion for Red Hook WRRF as part of the New York City Wastewater Resiliency Program.
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2018-11-01T00:00:00.000
Budget Forecast
23924743.23
Latest Budget Changes
-14185861.54
Total Budget Changes
13549422.97
Forecast Completion
2021-12-06T00:00:00.000
Latest Schedule Changes
33
Total Schedule Changes
921
Reconstruction of the West and North Docks at the OH WWTP
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 720 • Project Name: Reconstruction of the West and North Docks at the OH WWTP
Date Reported As Of
2019-09-01T00:00:00.000
Pid
720
Project Name
Reconstruction of the West and North Docks at the OH WWTP
Description
RECONSTRUCTION OF SEA WALL AND DOCK AT OWLS HEAD WWTP
Category
Wastewater Treatment
Borough
Brooklyn
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2017-08-18T00:00:00.000
Budget Forecast
63323000.00
Latest Budget Changes
0.00
Total Budget Changes
10985726.80
Forecast Completion
2022-02-11T00:00:00.000
Latest Schedule Changes
95
Total Schedule Changes
1389
Broadway Bridge over Harlem River Replacement
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 106 • Project Name: Broadway Bridge over Harlem River Replacement
Date Reported As Of
2019-09-01T00:00:00.000
Pid
106
Project Name
Broadway Bridge over Harlem River Replacement
Description
Replace deteriorated members of lift span superstructure, concrete deck, lift electrical and mechanical systems, and fenders.
Category
Bridges
Borough
Bronx, Manhattan
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2005-04-01T00:00:00.000
Budget Forecast
184323980.00
Latest Budget Changes
-5809999.00
Total Budget Changes
39724388.00
Total Schedule Changes
2797
Harlem River Drive Ramp Reconstruction (George Washington Bridge)
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 708 • Project Name: Harlem River Drive Ramp Reconstruction (George Washington Bridge)
Date Reported As Of
2019-09-01T00:00:00.000
Pid
708
Project Name
Harlem River Drive Ramp Reconstruction (George Washington Bridge)
Description
Repair the Harlem River Drive Ramp to George Washington Bridge over Harlem River Drive Southbound (Trans-Manhattan Expressway), Manhattan
Category
Bridges, Streets and Roadways
Borough
Manhattan
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2019-02-07T00:00:00.000
Budget Forecast
430583000.00
Latest Budget Changes
0.00
Total Budget Changes
-3711870.00
Total Schedule Changes
2697
49th Avenue Bridge Replacement
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 131 • Project Name: 49th Avenue Bridge Replacement
Date Reported As Of
2019-09-01T00:00:00.000
Pid
131
Project Name
49th Avenue Bridge Replacement
Description
Replace the 49th Avenue bridge over Long Island Railroad and Amtrak in Hunters Point, Queens.
Category
Bridges, Streets and Roadways
Borough
Queens
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-08-15T00:00:00.000
Budget Forecast
117274000.00
Latest Budget Changes
500000.00
Total Budget Changes
32902419.00
Total Schedule Changes
1449
Pelham Bay Equestrian Park over Amtrak
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 703 • Project Name: Pelham Bay Equestrian Park over Amtrak
Date Reported As Of
2019-09-01T00:00:00.000
Pid
703
Project Name
Pelham Bay Equestrian Park over Amtrak
Description
Repair the Pelham Bay Equestrian Park bridge over Amtrak, the Bronx
Category
Bridges
Borough
Bronx
Managing Agency
DOT
Client Agency
DPR
Current Phase
Design
Design Start
2019-01-30T00:00:00.000
Budget Forecast
43537997.00
Latest Budget Changes
41329000.00
Total Budget Changes
137997.00
Total Schedule Changes
1029
Wyckoff Avenue Street Reconstruction
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 191 • Project Name: Wyckoff Avenue Street Reconstruction
Date Reported As Of
2019-09-01T00:00:00.000
Pid
191
Project Name
Wyckoff Avenue Street Reconstruction
Description
Reconstruction of Wyckoff Avenue from Flushing Avenue to Cooper Avenue, in the Boroughs of Brooklyn and Queens..
Category
Streets and Roadways
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Trans. & Env. Protection
Current Phase
Design
Design Start
2017-03-29T00:00:00.000
Budget Forecast
74075000.00
Latest Budget Changes
30330000.00
Total Budget Changes
43926000.00
Forecast Completion
2023-03-29T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
226
East 174th Street over Sheridan Expressway - Amtrak
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 701 • Project Name: East 174th Street over Sheridan Expressway - Amtrak
Date Reported As Of
2019-09-01T00:00:00.000
Pid
701
Project Name
East 174th Street over Sheridan Expressway - Amtrak
Description
Repair the East 174th Street bridge over Sheridan Expressway/ AMTRAK, the Bronx
Category
Bridges
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2018-08-16T00:00:00.000
Budget Forecast
141940200.00
Latest Budget Changes
1000200.00
Total Budget Changes
5146882.00
Total Schedule Changes
1431
Raise Shorelines Citywide
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 689 • Project Name: Raise Shorelines Citywide
Date Reported As Of
2019-09-01T00:00:00.000
Pid
689
Project Name
Raise Shorelines Citywide
Description
The design and construction of shoreline reconstruction projects necessary to provide Citywide protection from future flooding caused by elevated seal elvels.
Category
Industrial Development
Borough
Citywide
Managing Agency
EDC
Client Agency
ORR
Current Phase
Design
Design Start
2017-08-01T00:00:00.000
Budget Forecast
89152926.86
Latest Budget Changes
28730525.86
Total Budget Changes
0.00
Forecast Completion
2022-12-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
639
Storm Mitigation Loan Program at Hunts Point
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 672 • Project Name: Storm Mitigation Loan Program at Hunts Point
Date Reported As Of
2019-09-01T00:00:00.000
Pid
672
Project Name
Storm Mitigation Loan Program at Hunts Point
Description
SMLP portion for Hunts Point WRRF as part of the New York City Wastewater Resiliency Program.
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2018-04-16T00:00:00.000
Budget Forecast
40053442.93
Latest Budget Changes
0.00
Total Budget Changes
20080597.79
Forecast Completion
2021-08-16T00:00:00.000
Latest Schedule Changes
82
Total Schedule Changes
1091
North River Wastewater Treatment Plant Cogeneration and Electrification
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 423 • Project Name: North River Wastewater Treatment Plant Cogeneration and Electrification
Date Reported As Of
2019-09-01T00:00:00.000
Pid
423
Project Name
North River Wastewater Treatment Plant Cogeneration and Electrification
Description
NR-COGEN, ACECOGEN, SANDNR
Category
Wastewater Treatment
Borough
New York
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2013-07-01T00:00:00.000
Budget Forecast
246332584.37
Latest Budget Changes
22824007.00
Total Budget Changes
134242052.88
Forecast Completion
2022-08-08T00:00:00.000
Latest Schedule Changes
14
Total Schedule Changes
1712
Storm Mitigation Loan Program at Bowery Bay
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 671 • Project Name: Storm Mitigation Loan Program at Bowery Bay
Date Reported As Of
2019-09-01T00:00:00.000
Pid
671
Project Name
Storm Mitigation Loan Program at Bowery Bay
Description
SMLP portion for Bowery Bay WRRF as part of the New York City Wastewater Resiliency Program.
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2018-04-30T00:00:00.000
Budget Forecast
31053956.85
Latest Budget Changes
1640283.06
Total Budget Changes
-19623216.41
Forecast Completion
2021-11-16T00:00:00.000
Latest Schedule Changes
35
Total Schedule Changes
1026
The Reconstruction of The Lower Catskill Aqueduct
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 667 • Project Name: The Reconstruction of The Lower Catskill Aqueduct
Date Reported As Of
2019-09-01T00:00:00.000
Pid
667
Project Name
The Reconstruction of The Lower Catskill Aqueduct
Description
Reconstruction of Aqueduct structures; Replacement of mechanical equipment; cleaning the aqueduct interior & rehabilitation & repair of cracks & leaks. All relevent assessments, investigations, piloting, plans and reports.
Category
Water Supply
Borough
Citywide
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2019-04-15T00:00:00.000
Budget Forecast
315260845.00
Latest Budget Changes
-16000000.00
Total Budget Changes
-65760729.00
Forecast Completion
2025-06-01T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1421
Battery Park Underpass Emergency Relief Betterments
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 540 • Project Name: Battery Park Underpass Emergency Relief Betterments
Date Reported As Of
2019-09-01T00:00:00.000
Pid
540
Project Name
Battery Park Underpass Emergency Relief Betterments
Description
Resiliency betterments for Battery Park and West Street underpasses.
Category
Bridges
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2018-04-01T00:00:00.000
Budget Forecast
19810000.00
Latest Budget Changes
5000.00
Total Budget Changes
47923308.00
Total Schedule Changes
1197
TLC - NEW OFFICE FACILITY - 24-55 BQE WEST
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 665 • Project Name: TLC - NEW OFFICE FACILITY - 24-55 BQE WEST
Date Reported As Of
2019-09-01T00:00:00.000
Pid
665
Project Name
TLC - NEW OFFICE FACILITY - 24-55 BQE WEST
Description
Replace existing administration wing; provide new parking and new inspection lane within the facility.
Category
Other Government Facilities
Borough
Queens
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Construction Procurement
Design Start
2015-09-15T00:00:00.000
Budget Forecast
79981000.00
Latest Budget Changes
0.00
Total Budget Changes
75370000.00
Forecast Completion
2024-02-18T00:00:00.000
Latest Schedule Changes
21
Total Schedule Changes
1248
Pelham Parkway Roadway Reconstruction, Phase 2
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 180 • Project Name: Pelham Parkway Roadway Reconstruction, Phase 2
Date Reported As Of
2019-09-01T00:00:00.000
Pid
180
Project Name
Pelham Parkway Roadway Reconstruction, Phase 2
Description
Pelham Pkwy main road W/B from Bronx River Pkwy to Hutchinson River Pkwy Pelham Pkwy North Service Rd. (S/R) from Bronx Park East to Eastchester Rd. Stillwell Ave from westbound mainline to north service road
Category
Streets and Roadways
Borough
Bronx
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction
Design Start
2002-02-15T00:00:00.000
Budget Forecast
150046000.00
Latest Budget Changes
5487000.00
Total Budget Changes
125164000.00
Forecast Completion
2023-03-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2869
Riverside Drive/West 158th Street Bridge Rehabilitation
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 113 • Project Name: Riverside Drive/West 158th Street Bridge Rehabilitation
Date Reported As Of
2019-09-01T00:00:00.000
Pid
113
Project Name
Riverside Drive/West 158th Street Bridge Rehabilitation
Description
Replace deck of the Riverside Drive viaduct/ bridge over West 158th Street.
Category
Bridges, Streets and Roadways
Borough
Manhattan
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2014-10-22T00:00:00.000
Budget Forecast
159495510.00
Latest Budget Changes
-750000.00
Total Budget Changes
96922794.00
Total Schedule Changes
2152
STM & SAN SWR, N.B. WHITESTONE EXPWY SERV RD, PH 3
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 652 • Project Name: STM & SAN SWR, N.B. WHITESTONE EXPWY SERV RD, PH 3
Date Reported As Of
2019-09-01T00:00:00.000
Pid
652
Project Name
STM & SAN SWR, N.B. WHITESTONE EXPWY SERV RD, PH 3
Description
Installation of Storm sewers, Sanitary sewers, & Water mains in Whitestone Area-Phase 3
Category
Sewers
Borough
Queens
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2016-07-15T00:00:00.000
Budget Forecast
60763000.00
Latest Budget Changes
0.00
Total Budget Changes
15468000.00
Forecast Completion
2023-08-16T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
684
Grand Concourse Metro North Railroad Bridge Construction
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 120 • Project Name: Grand Concourse Metro North Railroad Bridge Construction
Date Reported As Of
2019-09-01T00:00:00.000
Pid
120
Project Name
Grand Concourse Metro North Railroad Bridge Construction
Description
Repair the existing bridge and separate the NYCDOT and NYCT components. Includes new steel plate girders, concrete deck, pedestals, backwalls, sidewalks, and bridge railing.
Category
Bridges
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction Procurement
Design Start
2000-02-14T00:00:00.000
Budget Forecast
116716055.00
Latest Budget Changes
44383706.00
Total Budget Changes
22682117.00
Total Schedule Changes
836
STM & SAN SWR, WILLET PT BLVD WHITESTONE AREA, PH2
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 651 • Project Name: STM & SAN SWR, WILLET PT BLVD WHITESTONE AREA, PH2
Date Reported As Of
2019-09-01T00:00:00.000
Pid
651
Project Name
STM & SAN SWR, WILLET PT BLVD WHITESTONE AREA, PH2
Description
Installation of Storm sewers, Sanitary sewers, & Water mains in Whitestone Area.
Category
Sewers
Borough
Queens
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2013-03-15T00:00:00.000
Budget Forecast
99690000.00
Latest Budget Changes
3693000.00
Total Budget Changes
41243000.00
Forecast Completion
2022-09-15T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
642
253 Broadway Landmark's Space Renovations
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 639 • Project Name: 253 Broadway Landmark's Space Renovations
Date Reported As Of
2019-09-01T00:00:00.000
Pid
639
Project Name
253 Broadway Landmark's Space Renovations
Description
Renovate 4 floors of the building to create new office space for the Landmarks Preservation Commission, including new hearing room.
Category
Other Government Facilities
Borough
Manhattan
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Construction
Design Start
2013-01-23T00:00:00.000
Budget Forecast
73932000.00
Latest Budget Changes
104000.00
Total Budget Changes
35010000.00
Forecast Completion
2021-02-26T00:00:00.000
Latest Schedule Changes
241
Total Schedule Changes
1696
Grand Street Bridge over Newtown Creek
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 534 • Project Name: Grand Street Bridge over Newtown Creek
Date Reported As Of
2019-09-01T00:00:00.000
Pid
534
Project Name
Grand Street Bridge over Newtown Creek
Description
Replace the existing structure (swing-type bridge) with a new bridge; located between Gardner Avenue in Brooklyn and 47th Street in Queens.
Category
Bridges, Streets and Roadways
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2019-06-17T00:00:00.000
Budget Forecast
140803000.00
Latest Budget Changes
-3815744.00
Total Budget Changes
160682490.00
Total Schedule Changes
1645