Capital Projects

All major infrastructure and information technology projects with a budget of $25 million or more that are currently active (in the design, procurement, or construction phase).

City Government Mayor's Office of Operations (OPS) Dataset n7gv-k5yt 16 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
West 59th Street Marine Transfer Station Construction, Phase 2
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 347 • Project Name: West 59th Street Marine Transfer Station Construction, Phase 2
Date Reported As Of
2019-09-01T00:00:00.000
Pid
347
Project Name
West 59th Street Marine Transfer Station Construction, Phase 2
Description
Project 2 Scope: Refurbishment of the existing pier building including: repair of existing pier structure including pile caps and fendering; construction of new emergency generator, electrical, mechanical, fire pump and fire valve rooms; new exit passageway construction and existing exit passageway refurbishment; re-arrangement and refurbishment of the Operations Building interiors; replacement of fire suppression system throughout the entire pier structure; mechanical, electrical and plumbing system upgrades; refurbishment and painting the existing pier interior steel framing and wall/roof surfaces; recoating the structure's exterior cladding systems including metal wall and roof panel system and translucent panel wall cladding system.
Category
Sanitation
Borough
Manhattan
Managing Agency
DDC
Client Agency
Sanitation
Current Phase
Construction
Design Start
2012-01-17T00:00:00.000
Budget Forecast
103223000.00
Latest Budget Changes
22000.00
Total Budget Changes
126753576.46
Forecast Completion
2020-08-27T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1949
New Stapleton Waterfront: Phases 2 and 3
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 962 • Project Name: New Stapleton Waterfront: Phases 2 and 3
Date Reported As Of
2019-09-01T00:00:00.000
Pid
962
Project Name
New Stapleton Waterfront: Phases 2 and 3
Description
Mixed-use residential community on Staten Island's North Shore.
Category
Industrial Development
Managing Agency
EDC
Client Agency
EDC
Current Phase
Design
Design Start
2015-09-30T00:00:00.000
Budget Forecast
98407645.00
Total Budget Changes
100733778.00
Forecast Completion
2024-11-01T00:00:00.000
Total Schedule Changes
913
Bronx Sanitation Garage Rehabilitation: Community District 6
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 971 • Project Name: Bronx Sanitation Garage Rehabilitation: Community District 6
Date Reported As Of
2019-09-01T00:00:00.000
Pid
971
Project Name
Bronx Sanitation Garage Rehabilitation: Community District 6
Description
Rehabilitation of garage, broom garage and salt shed that serves Bronx Community Disrtict 6 located at 800 East 176th Street, Bronx.
Category
Sanitation
Managing Agency
DSNY
Client Agency
DSNY
Current Phase
Design
Design Start
2017-06-20T00:00:00.000
Budget Forecast
39941681.00
Total Budget Changes
0.00
Forecast Completion
2025-06-30T00:00:00.000
Total Schedule Changes
913
Pelham Parkway Bridge Reconstruction over Hutchinson Parkway
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 506 • Project Name: Pelham Parkway Bridge Reconstruction over Hutchinson Parkway
Date Reported As Of
2019-09-01T00:00:00.000
Pid
506
Project Name
Pelham Parkway Bridge Reconstruction over Hutchinson Parkway
Description
Replace the Pelham Parkway bridge over Hutchinson River Parkway, Bronx.
Category
Bridges, Streets and Roadways
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-05-30T00:00:00.000
Budget Forecast
57220478.00
Latest Budget Changes
-350000.00
Total Budget Changes
10338071.57
Total Schedule Changes
1934
FUEL TANK & SUMP REPLACEMENTS - BROOKLYN
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 899 • Project Name: FUEL TANK & SUMP REPLACEMENTS - BROOKLYN
Date Reported As Of
2019-09-01T00:00:00.000
Pid
899
Project Name
FUEL TANK & SUMP REPLACEMENTS - BROOKLYN
Description
CITYWIDE FUEL TANK REPLACEMENT PROGRAM FOR NEW 2015 EPA PETROLEUM BULK STORAGE REGULATIONS
Category
Industrial Development
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Design
Design Start
2019-08-16T00:00:00.000
Budget Forecast
27500000.00
Latest Budget Changes
0.00
Total Budget Changes
-1940000.00
Forecast Completion
2023-06-30T00:00:00.000
Latest Schedule Changes
91
Total Schedule Changes
663
FUEL TANK & SUMP REPLACEMENTS - QUEENS
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 898 • Project Name: FUEL TANK & SUMP REPLACEMENTS - QUEENS
Date Reported As Of
2019-09-01T00:00:00.000
Pid
898
Project Name
FUEL TANK & SUMP REPLACEMENTS - QUEENS
Description
CITYWIDE FUEL TANK REPLACEMENT PROGRAM FOR NEW 2015 EPA PETROLEUM BULK STORAGE REGULATIONS
Category
Industrial Development
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Design
Design Start
2019-07-16T00:00:00.000
Budget Forecast
27500000.00
Latest Budget Changes
0.00
Total Budget Changes
-1850000.00
Forecast Completion
2023-06-30T00:00:00.000
Latest Schedule Changes
91
Total Schedule Changes
663
Studio Museum in Harlem New Building
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 896 • Project Name: Studio Museum in Harlem New Building
Date Reported As Of
2019-09-01T00:00:00.000
Pid
896
Project Name
Studio Museum in Harlem New Building
Description
The Project will combine two adjacent lots on 125th Street: the sculpture court, City-owned lot 11, and the Museum building on lot 9, owned by the Museum. Existing structures on both lots will be demolished for the new, six story 82,000sf City owned building.
Category
Arts and Culture
Managing Agency
DDC
Client Agency
Cultural Affairs
Current Phase
Construction
Design Start
2018-09-25T00:00:00.000
Budget Forecast
59431000.00
Latest Budget Changes
0.00
Total Budget Changes
-190000.00
Forecast Completion
2022-11-25T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
856
FUEL TANK & SUMP REPLACEMENTS - MANHATTAN/S.I.
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 900 • Project Name: FUEL TANK & SUMP REPLACEMENTS - MANHATTAN/S.I.
Date Reported As Of
2019-09-01T00:00:00.000
Pid
900
Project Name
FUEL TANK & SUMP REPLACEMENTS - MANHATTAN/S.I.
Description
CITYWIDE FUEL TANK REPLACEMENT PROGRAM FOR NEW 2015 EPA PETROLEUM BULK STORAGE REGULATIONS
Category
Industrial Development
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Design
Design Start
2019-07-17T00:00:00.000
Budget Forecast
27400000.00
Latest Budget Changes
0.00
Total Budget Changes
-1754000.00
Forecast Completion
2023-06-30T00:00:00.000
Latest Schedule Changes
91
Total Schedule Changes
663
Brooklyn Civil Court move to 210 Joralemon St
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 509 • Project Name: Brooklyn Civil Court move to 210 Joralemon St
Date Reported As Of
2019-09-01T00:00:00.000
Pid
509
Project Name
Brooklyn Civil Court move to 210 Joralemon St
Description
Relocation of Brooklyn Civil and Housing Court to 210 Joralemon St
Category
Public Safety and Criminal Justice
Borough
Brooklyn
Managing Agency
DCAS
Client Agency
DCAS
Current Phase
Design
Design Start
2016-07-27T00:00:00.000
Budget Forecast
251443000.00
Latest Budget Changes
0.00
Total Budget Changes
200931011.96
Forecast Completion
2023-06-17T00:00:00.000
Latest Schedule Changes
92
Total Schedule Changes
1977
SAN & STRM SEWER, WM IN CONEY ISLAND AREA, PH 4
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 1009 • Project Name: SAN & STRM SEWER, WM IN CONEY ISLAND AREA, PH 4
Date Reported As Of
2019-09-01T00:00:00.000
Pid
1009
Project Name
SAN & STRM SEWER, WM IN CONEY ISLAND AREA, PH 4
Description
Storm, Sanitary Sewers & Water Mains in Coney Island Area - Phase 04, Brooklyn
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2019-07-25T00:00:00.000
Budget Forecast
27929000.00
Total Budget Changes
1984000.00
Forecast Completion
2024-08-09T00:00:00.000
Total Schedule Changes
1431
Bronx Animal Care Center
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 893 • Project Name: Bronx Animal Care Center
Date Reported As Of
2019-09-01T00:00:00.000
Pid
893
Project Name
Bronx Animal Care Center
Description
Bronx Animal Care Center & Veterinary Clinic is a new 50,000 SF facility that will be housing admissions, adoptions, medical services, and boarding for approximately 70 dogs, 140 cats, 30 rabbits and 20 animals or other species. In addition to the animal housing, the Bronx Animal Care Center will include a wildlife area to rehabilitate wild birds, academic partnership for youth, and enhanced senior services. Site work will include yards to facilitate dog adoptions, covered exercise runs, courtyards, and parking for staff, visitors, and shelter vehicles, as well as site lighting and low maintenance planting throughout. The building and associated landscape are to achieve LEED Gold standards.
Category
Health and Hospitals
Managing Agency
DDC
Client Agency
Health
Current Phase
Design
Design Start
2019-06-20T00:00:00.000
Budget Forecast
69375000.00
Latest Budget Changes
0.00
Total Budget Changes
24815617.00
Forecast Completion
2024-03-01T00:00:00.000
Latest Schedule Changes
-122
Total Schedule Changes
110
Brooklyn Public School 730 New Construction
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 876 • Project Name: Brooklyn Public School 730 New Construction
Date Reported As Of
2019-09-01T00:00:00.000
Pid
876
Project Name
Brooklyn Public School 730 New Construction
Description
Design and construction of a new school
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2018-01-26T00:00:00.000
Budget Forecast
54362143.00
Latest Budget Changes
3837481.00
Total Budget Changes
6379885.00
Forecast Completion
2021-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
730
Network Infrastructure Refresh Program
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 863 • Project Name: Network Infrastructure Refresh Program
Date Reported As Of
2019-09-01T00:00:00.000
Pid
863
Project Name
Network Infrastructure Refresh Program
Description
This project has a two-fold basis: 1) The ongoing Network Refresh which is needed to replace aging, end-of-life, end-of-support equipment across the NYC H+H. 2) Networking capacity needed to support the Electronic Medical Records system.
Category
Health and Hospitals, IT
Managing Agency
HHC
Client Agency
H+H
Current Phase
IT
Budget Forecast
160090000.00
Latest Budget Changes
0.00
Total Budget Changes
180514000.00
Forecast Completion
2023-12-31T00:00:00.000
RECONSTRUCTION OF ROSEDALE AREA, PHASE 2
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 1011 • Project Name: RECONSTRUCTION OF ROSEDALE AREA, PHASE 2
Date Reported As Of
2019-09-01T00:00:00.000
Pid
1011
Project Name
RECONSTRUCTION OF ROSEDALE AREA, PHASE 2
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2018-06-07T00:00:00.000
Budget Forecast
39360000.00
Total Budget Changes
61291000.00
Forecast Completion
2024-08-14T00:00:00.000
Total Schedule Changes
829
2nd Avenue Watermain Trunk Construction
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 388 • Project Name: 2nd Avenue Watermain Trunk Construction
Date Reported As Of
2019-09-01T00:00:00.000
Pid
388
Project Name
2nd Avenue Watermain Trunk Construction
Description
Trunk and Distribution Main Connection to shaft 32B in 2nd Ave., etc., together with all work incidental thereto, Borough of Manhattan. 2nd Avenue from East 33rd Street to East 37th Street
Category
Water Supply
Borough
Manhattan
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2013-09-30T00:00:00.000
Budget Forecast
48794000.00
Latest Budget Changes
2994000.00
Total Budget Changes
-7266000.00
Forecast Completion
2021-06-02T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2113
Belt System - Cross Island over 115th Avenue/Dutch Broadway
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 558 • Project Name: Belt System - Cross Island over 115th Avenue/Dutch Broadway
Date Reported As Of
2019-09-01T00:00:00.000
Pid
558
Project Name
Belt System - Cross Island over 115th Avenue/Dutch Broadway
Description
Repair the Cross Island bridge over 115th Avenue/Dutch Broadway, Queens.
Category
Bridges
Borough
Queens
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-10-03T00:00:00.000
Budget Forecast
25753171.00
Latest Budget Changes
-85000.00
Total Budget Changes
17528706.00
Total Schedule Changes
1845
South Bronx East-West Crosstown SBS
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 1008 • Project Name: South Bronx East-West Crosstown SBS
Date Reported As Of
2019-09-01T00:00:00.000
Pid
1008
Project Name
South Bronx East-West Crosstown SBS
Description
The South Bronx Crosstown SBS capital project (BRT) will add bus pads and construct bus bulbs, curb and median extensions, and pedestrian islands for enhanced pedestrian safety and access improvements.
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2019-07-01T00:00:00.000
Budget Forecast
50608000.00
Total Budget Changes
3130000.00
Forecast Completion
2025-09-13T00:00:00.000
Total Schedule Changes
626
Metropolitan Avenue Bridge over CSX Transport
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 556 • Project Name: Metropolitan Avenue Bridge over CSX Transport
Date Reported As Of
2019-09-01T00:00:00.000
Pid
556
Project Name
Metropolitan Avenue Bridge over CSX Transport
Description
Replace the Metropolitan Avenue bridge over CSX Transport, Queens.
Category
Bridges, Streets and Roadways
Borough
Queens
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-09-28T00:00:00.000
Budget Forecast
72926394.00
Latest Budget Changes
4474000.00
Total Budget Changes
4699394.00
Total Schedule Changes
2027
FUEL TANK & SUMP REPLACEMENTS - BRONX
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 901 • Project Name: FUEL TANK & SUMP REPLACEMENTS - BRONX
Date Reported As Of
2019-09-01T00:00:00.000
Pid
901
Project Name
FUEL TANK & SUMP REPLACEMENTS - BRONX
Description
CITYWIDE FUEL TANK REPLACEMENT PROGRAM FOR NEW 2015 EPA PETROLEUM BULK STORAGE REGULATIONS
Category
Industrial Development
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Design
Design Start
2019-08-20T00:00:00.000
Budget Forecast
27500000.00
Latest Budget Changes
0.00
Total Budget Changes
-1834000.00
Forecast Completion
2023-06-30T00:00:00.000
Latest Schedule Changes
91
Total Schedule Changes
663
Brooklyn Supreme Court Fire Alarm System Upgrade
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 510 • Project Name: Brooklyn Supreme Court Fire Alarm System Upgrade
Date Reported As Of
2019-09-01T00:00:00.000
Pid
510
Project Name
Brooklyn Supreme Court Fire Alarm System Upgrade
Description
Brooklyn Supreme Court, Fire Alarm, Sprinkler, 360 Adams Street - New addressable fire detection and alarm system and new sprinkler system.
Category
Public Safety and Criminal Justice
Borough
Brooklyn
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Design
Design Start
2017-03-31T00:00:00.000
Budget Forecast
63107000.00
Latest Budget Changes
5045000.00
Total Budget Changes
47003000.00
Forecast Completion
2023-12-01T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1533
79th St Boat Basin
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 862 • Project Name: 79th St Boat Basin
Date Reported As Of
2019-09-01T00:00:00.000
Pid
862
Project Name
79th St Boat Basin
Description
Reconstruction of bulkhead and piers at 79th St Boat Basin on behalf of NYCDPR .
Category
Parks
Managing Agency
EDC
Client Agency
DPR
Current Phase
Design
Design Start
2019-06-13T00:00:00.000
Budget Forecast
89219175.00
Latest Budget Changes
-1131246.67
Total Budget Changes
-1131246.67
Forecast Completion
2023-08-30T00:00:00.000
Latest Schedule Changes
112
Total Schedule Changes
1036
West 33rd Street
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 861 • Project Name: West 33rd Street
Date Reported As Of
2019-09-01T00:00:00.000
Pid
861
Project Name
West 33rd Street
Description
Regrading and reconstruction of 33rd Street Viaduct between 11th and 12th Avenue..
Category
Streets and Roadways
Managing Agency
EDC
Client Agency
DOT
Current Phase
Design
Design Start
2018-09-01T00:00:00.000
Budget Forecast
100000000.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2022-11-30T00:00:00.000
Latest Schedule Changes
275
Total Schedule Changes
1736
Bellevue Medical Center Priority Mitigation Projects
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 545 • Project Name: Bellevue Medical Center Priority Mitigation Projects
Date Reported As Of
2019-09-01T00:00:00.000
Pid
545
Project Name
Bellevue Medical Center Priority Mitigation Projects
Description
Priority mitigation projects for the repair/restoration and hazard mitigation for Bellevue Hospital, damaged during Superstorm Sandy
Category
Health and Hospitals
Borough
Manhattan
Managing Agency
EDC
Client Agency
H+H
Current Phase
Construction
Design Start
2014-01-01T00:00:00.000
Budget Forecast
53184355.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2020-06-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1854
Manhattan Greenway: Harlem River
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 860 • Project Name: Manhattan Greenway: Harlem River
Date Reported As Of
2019-09-01T00:00:00.000
Pid
860
Project Name
Manhattan Greenway: Harlem River
Description
The Manhattan Greenway Harlem River project, between West 125th Street and Swindler Cove, involves the creation of a park, greenway, and the reconstruction of the bulkhead.
Category
Parks
Managing Agency
EDC
Client Agency
DPR
Current Phase
Design
Design Start
2019-06-15T00:00:00.000
Budget Forecast
227658000.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2024-04-15T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
888
Manhattan Greenway: East Midtown
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 859 • Project Name: Manhattan Greenway: East Midtown
Date Reported As Of
2019-09-01T00:00:00.000
Pid
859
Project Name
Manhattan Greenway: East Midtown
Description
The East Midtown Waterfront Greenway project involves the creation of a waterfront esplanade between East 53rd and East 59th Streets.
Category
Parks
Managing Agency
EDC
Client Agency
EDC
Current Phase
Construction
Design Start
2017-10-01T00:00:00.000
Budget Forecast
130000000.00
Latest Budget Changes
0.00
Total Budget Changes
24840000.00
Forecast Completion
2022-11-30T00:00:00.000
Latest Schedule Changes
29
Total Schedule Changes
487
Roma and Hett Avenue Storm and Sanitary Sewer Installation
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 206 • Project Name: Roma and Hett Avenue Storm and Sanitary Sewer Installation
Date Reported As Of
2019-09-01T00:00:00.000
Pid
206
Project Name
Roma and Hett Avenue Storm and Sanitary Sewer Installation
Description
Install storm and sanitary sewers at multiple locations.
Category
Sewers
Borough
Staten Island
Managing Agency
DDC
Client Agency
Trans. & Env. Protection
Current Phase
Construction
Design Start
2014-10-15T00:00:00.000
Budget Forecast
98496000.00
Latest Budget Changes
65000.00
Total Budget Changes
62973000.00
Forecast Completion
2022-06-28T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
-8
RECONSTRUCTION OF FRONT STREET, MANHATTAN
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 1012 • Project Name: RECONSTRUCTION OF FRONT STREET, MANHATTAN
Date Reported As Of
2019-09-01T00:00:00.000
Pid
1012
Project Name
RECONSTRUCTION OF FRONT STREET, MANHATTAN
Description
Reconstruction of Front Street, Manhattan
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction Procurement
Design Start
2015-07-31T00:00:00.000
Budget Forecast
27356000.00
Total Budget Changes
6153000.00
Forecast Completion
2022-06-16T00:00:00.000
Total Schedule Changes
484
Orchard Beach Pavilion
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 858 • Project Name: Orchard Beach Pavilion
Date Reported As Of
2019-09-01T00:00:00.000
Pid
858
Project Name
Orchard Beach Pavilion
Description
The restoration of the existing landmarked Orchard Beach Pavilion (located in Bronx, NY) which includes the construction of an ADA ramp at the main entrance of the Pavilion to improve accessibility to the beach passageway.
Category
Parks
Managing Agency
EDC
Client Agency
DPR
Current Phase
Design
Design Start
2018-11-30T00:00:00.000
Budget Forecast
60000000.00
Latest Budget Changes
0.00
Total Budget Changes
35628847.00
Forecast Completion
2022-08-01T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
942
TRENCH RESTORATION BROOKLYN
Date Reported As Of: 2019-09-01T00:00:00.000 • Pid: 855 • Project Name: TRENCH RESTORATION BROOKLYN
Date Reported As Of
2019-09-01T00:00:00.000
Pid
855
Project Name
TRENCH RESTORATION BROOKLYN
Description
Trench Restoration in The Borough Of Brooklyn including Full Street Reconstruction
Category
Industrial Development
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2018-06-05T00:00:00.000
Budget Forecast
25448000.00
Latest Budget Changes
-1590000.00
Total Budget Changes
6536000.00
Forecast Completion
2023-08-14T00:00:00.000
Latest Schedule Changes
366
Total Schedule Changes
1467
Orchard Beach Pavilion
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 858 • Project Name: Orchard Beach Pavilion
Date Reported As Of
2019-05-01T00:00:00.000
Pid
858
Project Name
Orchard Beach Pavilion
Description
The restoration of the existing landmarked Orchard Beach Pavilion (located in Bronx, NY) which includes the construction of an ADA ramp at the main entrance of the Pavilion to improve accessibility to the beach passageway.
Category
Parks
Managing Agency
EDC
Client Agency
DPR
Current Phase
Design
Design Start
2018-11-30T00:00:00.000
Budget Forecast
60000000.00
Latest Budget Changes
0.00
Total Budget Changes
35628847.00
Forecast Completion
2022-08-01T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
942
Oakwood Beach WWTP Sludge Thickening Improvements
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 449 • Project Name: Oakwood Beach WWTP Sludge Thickening Improvements
Date Reported As Of
2019-05-01T00:00:00.000
Pid
449
Project Name
Oakwood Beach WWTP Sludge Thickening Improvements
Description
Replacement of thickener pumps, piping, sludge pumps, mixing pumps, recirculation pumps, spray water pumps, and heat exchangers. Install Gravity Belt Thickener, GBT pumps, polymer feed system. Rehab of Thickeners, Sludge Box, and Distribution Box.
Category
Wastewater Treatment
Borough
Staten Island
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2018-08-02T00:00:00.000
Budget Forecast
73093185.00
Latest Budget Changes
29421575.00
Total Budget Changes
57138101.30
Forecast Completion
2024-09-06T00:00:00.000
Latest Schedule Changes
294
Total Schedule Changes
3241
Carl Schurz Park Promenade over FDR (East 81st to 90th Streets)
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 537 • Project Name: Carl Schurz Park Promenade over FDR (East 81st to 90th Streets)
Date Reported As Of
2019-05-01T00:00:00.000
Pid
537
Project Name
Carl Schurz Park Promenade over FDR (East 81st to 90th Streets)
Description
Replace the Promenade over FDR between East 81st to 90th Streets in Manhattan.
Category
Bridges
Borough
Manhattan
Managing Agency
DOT
Client Agency
DOT, DPR
Current Phase
Design
Design Start
2017-05-30T00:00:00.000
Budget Forecast
36112421.00
Latest Budget Changes
350000.00
Total Budget Changes
-197139579.00
Forecast Completion
2025-10-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1571
Boston Road Bridge Over Hutchinson River Rehabilitation
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 539 • Project Name: Boston Road Bridge Over Hutchinson River Rehabilitation
Date Reported As Of
2019-05-01T00:00:00.000
Pid
539
Project Name
Boston Road Bridge Over Hutchinson River Rehabilitation
Description
Rehabilitation of Boston Road Bridge over Hutchinson River, located in the Bornx.
Category
Bridges, Streets and Roadways
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2018-04-16T00:00:00.000
Budget Forecast
43372092.00
Latest Budget Changes
1444000.00
Total Budget Changes
49309814.00
Forecast Completion
2024-05-14T00:00:00.000
Latest Schedule Changes
71
Total Schedule Changes
803
Battery Park Underpass Emergency Relief Betterments
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 540 • Project Name: Battery Park Underpass Emergency Relief Betterments
Date Reported As Of
2019-05-01T00:00:00.000
Pid
540
Project Name
Battery Park Underpass Emergency Relief Betterments
Description
Resiliency betterments for Battery Park and West Street underpasses.
Category
Bridges
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2018-04-01T00:00:00.000
Budget Forecast
19805000.00
Latest Budget Changes
-5000.00
Total Budget Changes
47923308.00
Forecast Completion
2022-03-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1197
Shore Road Bridge over Hutchinson River
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 541 • Project Name: Shore Road Bridge over Hutchinson River
Date Reported As Of
2019-05-01T00:00:00.000
Pid
541
Project Name
Shore Road Bridge over Hutchinson River
Description
Replace the Shore Road Bridge over the Hutchinson River with a new bridge.
Category
Bridges, Streets and Roadways
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-06-30T00:00:00.000
Budget Forecast
315738743.00
Latest Budget Changes
-5428000.00
Total Budget Changes
-19049921.84
Forecast Completion
2025-12-17T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1477
49th Avenue Bridge Replacement
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 131 • Project Name: 49th Avenue Bridge Replacement
Date Reported As Of
2019-05-01T00:00:00.000
Pid
131
Project Name
49th Avenue Bridge Replacement
Description
Replace the 49th Avenue bridge over Long Island Railroad and Amtrak in Hunters Point, Queens.
Category
Bridges, Streets and Roadways
Borough
Queens
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-08-15T00:00:00.000
Budget Forecast
116774000.00
Latest Budget Changes
34296000.00
Total Budget Changes
32902419.00
Forecast Completion
2024-07-13T00:00:00.000
Latest Schedule Changes
173
Total Schedule Changes
1449
Coler Specialty Hospital Priority Mitigation Projects
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 544 • Project Name: Coler Specialty Hospital Priority Mitigation Projects
Date Reported As Of
2019-05-01T00:00:00.000
Pid
544
Project Name
Coler Specialty Hospital Priority Mitigation Projects
Description
The priority mitigation projects at Coler include key critical mitigation projects to improve the resiliency of the campus.
Category
Health and Hospitals
Borough
Manhattan
Managing Agency
EDC
Client Agency
H+H
Current Phase
Construction
Design Start
2014-09-01T00:00:00.000
Budget Forecast
23156983.99
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2020-10-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2085
Bellevue Medical Center Priority Mitigation Projects
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 545 • Project Name: Bellevue Medical Center Priority Mitigation Projects
Date Reported As Of
2019-05-01T00:00:00.000
Pid
545
Project Name
Bellevue Medical Center Priority Mitigation Projects
Description
Priority mitigation projects for the repair/restoration and hazard mitigation for Bellevue Hospital, damaged during Superstorm Sandy
Category
Health and Hospitals
Borough
Manhattan
Managing Agency
EDC
Client Agency
H+H
Current Phase
Construction
Design Start
2014-01-01T00:00:00.000
Budget Forecast
53184355.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2020-06-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1854
Construction of Gowanus CSO retention FAC Superfund Site
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 550 • Project Name: Construction of Gowanus CSO retention FAC Superfund Site
Date Reported As Of
2019-05-01T00:00:00.000
Pid
550
Project Name
Construction of Gowanus CSO retention FAC Superfund Site
Description
CSO Facilities, bulkheads, pilots and other requirements to comply with Gowanus Canal Superfund Adminstrative Orders
Category
Industrial Development
Borough
Brooklyn
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2017-11-22T00:00:00.000
Budget Forecast
1350400000.00
Latest Budget Changes
0.00
Total Budget Changes
432995114.00
Forecast Completion
2031-07-07T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1086
Jerome Reservoir and Aqueduct Rehabilitation
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 448 • Project Name: Jerome Reservoir and Aqueduct Rehabilitation
Date Reported As Of
2019-05-01T00:00:00.000
Pid
448
Project Name
Jerome Reservoir and Aqueduct Rehabilitation
Description
Improvements to: fencing, vegetation, roadway, drainage, ext. above-ground retaining walls. Including repair of dam inlet archway & wingwall, re-pointing of stones & reinforcement of east reservoir wall, & leakage/seepage protection within OCA.
Category
Water Supply
Borough
Bronx
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2016-02-24T00:00:00.000
Budget Forecast
52813862.20
Latest Budget Changes
23.00
Total Budget Changes
-833277.14
Forecast Completion
2022-10-05T00:00:00.000
Latest Schedule Changes
174
Total Schedule Changes
2363
Kensico Eastview Connection Tunnel Construction
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 554 • Project Name: Kensico Eastview Connection Tunnel Construction
Date Reported As Of
2019-05-01T00:00:00.000
Pid
554
Project Name
Kensico Eastview Connection Tunnel Construction
Description
A new 2+ mile, 27-ft internal diamter tunnel between Kensico and Cat-Del UV Facility (Eastview). The tunnel will include a new screen chamber and will provide ciritcal redundancy to the Delaware Aqueduct in this area.
Category
Water Supply
Borough
Valhalla
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2017-08-01T00:00:00.000
Budget Forecast
1452196604.80
Latest Budget Changes
-11131219.00
Total Budget Changes
881770648.00
Forecast Completion
2031-05-27T00:00:00.000
Latest Schedule Changes
274
Total Schedule Changes
3132
Metropolitan Avenue Bridge over CSX Transport
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 556 • Project Name: Metropolitan Avenue Bridge over CSX Transport
Date Reported As Of
2019-05-01T00:00:00.000
Pid
556
Project Name
Metropolitan Avenue Bridge over CSX Transport
Description
Replace the Metropolitan Avenue bridge over CSX Transport, Queens.
Category
Bridges, Streets and Roadways
Borough
Queens
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-09-28T00:00:00.000
Budget Forecast
68452394.00
Latest Budget Changes
72555000.00
Total Budget Changes
4699394.00
Forecast Completion
2027-02-19T00:00:00.000
Latest Schedule Changes
-24
Total Schedule Changes
2027
Belt System - Cross Island over 115th Avenue/Dutch Broadway
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 558 • Project Name: Belt System - Cross Island over 115th Avenue/Dutch Broadway
Date Reported As Of
2019-05-01T00:00:00.000
Pid
558
Project Name
Belt System - Cross Island over 115th Avenue/Dutch Broadway
Description
Repair the Cross Island bridge over 115th Avenue/Dutch Broadway, Queens.
Category
Bridges
Borough
Queens
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-10-03T00:00:00.000
Budget Forecast
25838171.00
Latest Budget Changes
170000.00
Total Budget Changes
17528706.00
Forecast Completion
2025-11-14T00:00:00.000
Latest Schedule Changes
798
Total Schedule Changes
1845
Brooklyn Sanitation Garage Construction: Community District 3
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 560 • Project Name: Brooklyn Sanitation Garage Construction: Community District 3
Date Reported As Of
2019-05-01T00:00:00.000
Pid
560
Project Name
Brooklyn Sanitation Garage Construction: Community District 3
Description
Construction of new Sanitation garage facility for services to Brooklyn Community District 3 to be located at Warsoff Place in Brooklyn
Category
Sanitation
Borough
Brooklyn
Managing Agency
DSNY
Client Agency
DSNY
Current Phase
Construction Procurement
Design Start
2005-07-25T00:00:00.000
Budget Forecast
204347986.93
Latest Budget Changes
10000.00
Total Budget Changes
25603365.00
Forecast Completion
2023-01-31T00:00:00.000
Latest Schedule Changes
31
Total Schedule Changes
790
Coney Island Hospital CSS Building and Perimeter Flood Protection
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 561 • Project Name: Coney Island Hospital CSS Building and Perimeter Flood Protection
Date Reported As Of
2019-05-01T00:00:00.000
Pid
561
Project Name
Coney Island Hospital CSS Building and Perimeter Flood Protection
Description
Renovation of CIH to advance the City’s resiliency plan, repair damages, and protect the hospital from future disasters.
Category
Health and Hospitals
Borough
Brooklyn
Managing Agency
EDC
Client Agency
H+H
Current Phase
Construction
Design Start
2016-02-01T00:00:00.000
Budget Forecast
678812311.00
Latest Budget Changes
0.00
Total Budget Changes
30635879.93
Forecast Completion
2023-03-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1243
Metropolitan Hospital Perimeter Flood Protection
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 562 • Project Name: Metropolitan Hospital Perimeter Flood Protection
Date Reported As Of
2019-05-01T00:00:00.000
Pid
562
Project Name
Metropolitan Hospital Perimeter Flood Protection
Category
Industrial Development
Borough
Manhattan
Managing Agency
EDC
Client Agency
H+H
Total Budget Changes
27046705.00
Total Schedule Changes
1452
Bronx Sanitation Garage Construction: Community District 9, 10, 11
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 573 • Project Name: Bronx Sanitation Garage Construction: Community District 9, 10, 11
Date Reported As Of
2019-05-01T00:00:00.000
Pid
573
Project Name
Bronx Sanitation Garage Construction: Community District 9, 10, 11
Description
Construction of new Sanitation garage facility to serve Bronx community districts 9, 10, and 11 to be located at Zerega Avenue in the Bronx
Category
Sanitation
Borough
Bronx
Managing Agency
DSNY
Client Agency
DSNY
Current Phase
Design
Design Start
2017-08-01T00:00:00.000
Budget Forecast
300856407.20
Latest Budget Changes
-3382236.00
Total Budget Changes
268983862.56
Forecast Completion
2026-12-31T00:00:00.000
Latest Schedule Changes
184
Total Schedule Changes
1919
Sunset Park Infrastructure
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 574 • Project Name: Sunset Park Infrastructure
Date Reported As Of
2019-05-01T00:00:00.000
Pid
574
Project Name
Sunset Park Infrastructure
Description
This project is construction of infrastructure and streetscape improvements in Sunset Park from 37th to 43rd Streets, between the Gowanus Expressway and the waterfront - to activate the waterfront and promote future development.
Category
Industrial Development
Borough
Brooklyn
Managing Agency
EDC
Client Agency
Mayor's Office
Current Phase
Design
Design Start
2016-06-08T00:00:00.000
Budget Forecast
37500000.00
Latest Budget Changes
0.00
Total Budget Changes
31633941.69
Forecast Completion
2022-06-28T00:00:00.000
Latest Schedule Changes
92
Total Schedule Changes
1290
Reconstruction of the Port Jervis Wastewater Treatment Plant
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 444 • Project Name: Reconstruction of the Port Jervis Wastewater Treatment Plant
Date Reported As Of
2019-05-01T00:00:00.000
Pid
444
Project Name
Reconstruction of the Port Jervis Wastewater Treatment Plant
Description
Reconstruction of the Port Jervis WWTP as required based on the effluent limits proposed by the Delaware River Basin Commission (DRBC)
Category
Wastewater Treatment
Borough
Port Jervis
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2014-06-17T00:00:00.000
Budget Forecast
56490022.00
Latest Budget Changes
0.00
Total Budget Changes
9428438.55
Forecast Completion
2024-08-03T00:00:00.000
Latest Schedule Changes
761
Total Schedule Changes
2445
Lower Concourse Initiative
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 575 • Project Name: Lower Concourse Initiative
Date Reported As Of
2019-05-01T00:00:00.000
Pid
575
Project Name
Lower Concourse Initiative
Description
The Project will improve the roadways and pedestrian facilities. The Project will consist of roadway reconstruction within Exterior Street between East 138th Street and East 150th Street.
Category
Industrial Development
Borough
Bronx
Managing Agency
EDC
Client Agency
EDC
Current Phase
Design
Design Start
2017-04-01T00:00:00.000
Budget Forecast
84520367.00
Latest Budget Changes
0.00
Total Budget Changes
-5100000.00
Forecast Completion
2022-05-03T00:00:00.000
Latest Schedule Changes
31
Total Schedule Changes
730