Capital Projects

All major infrastructure and information technology projects with a budget of $25 million or more that are currently active (in the design, procurement, or construction phase).

City Government Mayor's Office of Operations (OPS) Dataset n7gv-k5yt 16 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
Storm Sanitary Sewer Repl Springfield Gardens
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 790 • Project Name: Storm Sanitary Sewer Repl Springfield Gardens
Date Reported As Of
2019-05-01T00:00:00.000
Pid
790
Project Name
Storm Sanitary Sewer Repl Springfield Gardens
Description
SPRINGFIELD GARDENS RECONSTRUCTION PHASE 5; STORM AND SANITARY SEWER EXTENSIONS AND UPGRADES AND WATER MAIN REPLACEMENT IN 146TH AVENUE BETWEEN 153RD PLACE AND 159TH STREET, ETC, BOROUGH OF QUEENS (HWQ662G)
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2018-05-09T00:00:00.000
Budget Forecast
103179000.00
Latest Budget Changes
19466000.00
Total Budget Changes
35414000.00
Forecast Completion
2025-09-15T00:00:00.000
Latest Schedule Changes
252
Total Schedule Changes
1097
New Storm Sewer N Conduit Av-Baisley Blvd
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 792 • Project Name: New Storm Sewer N Conduit Av-Baisley Blvd
Date Reported As Of
2019-05-01T00:00:00.000
Pid
792
Project Name
New Storm Sewer N Conduit Av-Baisley Blvd
Description
Storm, Sanitary and Water Mains work in North Conduit between Baisley Blvd and Guy Brewer Blvd, South Queens
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2018-09-10T00:00:00.000
Budget Forecast
112064000.00
Latest Budget Changes
700000.00
Total Budget Changes
31711000.00
Forecast Completion
2024-09-13T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1619
Sewer When & Where Contract In S.E. Queens
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 793 • Project Name: Sewer When & Where Contract In S.E. Queens
Date Reported As Of
2019-05-01T00:00:00.000
Pid
793
Project Name
Sewer When & Where Contract In S.E. Queens
Description
SEWER WHEN & WHERE CONTRACT IN South East Queens. NEW STORM SEWER CONSTRUCTION, REPLACEMENT OR UPGRADES TO SANITARY SEWERS AND WATER MAIN IN PROJECT AREAS. GREEN INFRASTRUCTURE PROJECTS IN CONJUNCTION WITH WHEN & WHERE PROJECTS.
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2018-05-14T00:00:00.000
Budget Forecast
30900000.00
Latest Budget Changes
30900000.00
Total Budget Changes
7404000.00
Forecast Completion
2022-08-08T00:00:00.000
Latest Schedule Changes
848
Total Schedule Changes
1834
Gilboa Dam Reconstruction, Phase III
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 405 • Project Name: Gilboa Dam Reconstruction, Phase III
Date Reported As Of
2019-05-01T00:00:00.000
Pid
405
Project Name
Gilboa Dam Reconstruction, Phase III
Description
Gilboa Dam Reconstruction Project includes construction of a new low level outlet (LLO) consisting of 2,000 feet of tunneling, an access shaft, oulet structure and gate valve controls.
Category
Water Supply
Borough
Upstate
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2004-03-18T00:00:00.000
Budget Forecast
208649861.57
Latest Budget Changes
3027887.88
Total Budget Changes
10376533.49
Forecast Completion
2021-05-22T00:00:00.000
Latest Schedule Changes
160
Total Schedule Changes
1113
West 79th Street over Amtrak and Rotunda Complex Rehabilitation
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 801 • Project Name: West 79th Street over Amtrak and Rotunda Complex Rehabilitation
Date Reported As Of
2019-05-01T00:00:00.000
Pid
801
Project Name
West 79th Street over Amtrak and Rotunda Complex Rehabilitation
Description
Rehabilitate the W. 79th St Bridge over Amtrak and Rotunda Complex
Category
Bridges, Streets and Roadways
Borough
Manhattan
Managing Agency
DOT
Client Agency
DOT, DPR
Current Phase
Construction Procurement
Design Start
2000-07-10T00:00:00.000
Budget Forecast
40514808.00
Latest Budget Changes
6087750.00
Total Budget Changes
-51088528.00
Forecast Completion
2024-10-26T00:00:00.000
Latest Schedule Changes
193
Total Schedule Changes
604
East 180th Street over Metro North Railroad (Harrison Line)
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 811 • Project Name: East 180th Street over Metro North Railroad (Harrison Line)
Date Reported As Of
2019-05-01T00:00:00.000
Pid
811
Project Name
East 180th Street over Metro North Railroad (Harrison Line)
Description
Rehabilitation of East 180th Street Bridge over Metro North Railroad, the Bronx
Category
Bridges
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction Procurement
Design Start
2017-02-06T00:00:00.000
Budget Forecast
38879945.00
Latest Budget Changes
1570000.00
Total Budget Changes
4194366.00
Forecast Completion
2022-09-26T00:00:00.000
Latest Schedule Changes
186
Total Schedule Changes
664
4Th Ave. Safety Improvements Phase II-Vision Zero
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 833 • Project Name: 4Th Ave. Safety Improvements Phase II-Vision Zero
Date Reported As Of
2019-05-01T00:00:00.000
Pid
833
Project Name
4Th Ave. Safety Improvements Phase II-Vision Zero
Description
4TH AVENUE SAFETY IMPROVEMENTS PHASE II - VISION ZERO GREAT STREETS
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction Procurement
Design Start
2017-06-01T00:00:00.000
Budget Forecast
58469000.00
Latest Budget Changes
-4484000.00
Total Budget Changes
-11525000.00
Forecast Completion
2021-11-03T00:00:00.000
Latest Schedule Changes
127
Total Schedule Changes
1106
Madison Avenue Bridge Reconstruction
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 114 • Project Name: Madison Avenue Bridge Reconstruction
Date Reported As Of
2019-05-01T00:00:00.000
Pid
114
Project Name
Madison Avenue Bridge Reconstruction
Description
Replace the electrical and mechanical systems of the Madison Avenue Bridge.
Category
Bridges
Borough
Manhattan, Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2011-02-14T00:00:00.000
Budget Forecast
55017599.00
Latest Budget Changes
850000.00
Total Budget Changes
2036997.00
Forecast Completion
2022-04-13T00:00:00.000
Latest Schedule Changes
30
Total Schedule Changes
1628
Supreme Courthouse Fire Alarm/ Protection Upgrade
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 837 • Project Name: Supreme Courthouse Fire Alarm/ Protection Upgrade
Date Reported As Of
2019-05-01T00:00:00.000
Pid
837
Project Name
Supreme Courthouse Fire Alarm/ Protection Upgrade
Description
Bronx Supreme Court, Fire Alarm, Sprinkler, 851 Grand Concourse - Replace the existing fire alarm system and install a new sprinkler system.
Category
Public Safety and Criminal Justice
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Design
Design Start
2018-07-11T00:00:00.000
Budget Forecast
55200000.00
Latest Budget Changes
12019610.00
Total Budget Changes
37248610.00
Forecast Completion
2024-01-09T00:00:00.000
Latest Schedule Changes
95
Total Schedule Changes
1319
Asphalt Plant, 30-01 Harper St, Queens Demo/Cons
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 840 • Project Name: Asphalt Plant, 30-01 Harper St, Queens Demo/Cons
Date Reported As Of
2019-05-01T00:00:00.000
Pid
840
Project Name
Asphalt Plant, 30-01 Harper St, Queens Demo/Cons
Description
Demolition and rebuild of the existing structures housing the equipment and related facilities necessary for the production, storage and distribution of asphalt at the NYC Harper Street Asphalt Plant facility. All of the existing equipment, storage facilities, and related buildings will be replaced with a new state of the art plant. In addition, the work will involve installing sanitary and storm drainage systems to comply with current government regulatory standard
Category
Industrial Development
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2019-04-03T00:00:00.000
Budget Forecast
41777000.00
Latest Budget Changes
1063745.00
Total Budget Changes
55883745.00
Forecast Completion
2023-12-04T00:00:00.000
Latest Schedule Changes
175
Total Schedule Changes
1211
NEW UTRECH LIBRARY MAJOR RENOVATIONS
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 841 • Project Name: NEW UTRECH LIBRARY MAJOR RENOVATIONS
Date Reported As Of
2019-05-01T00:00:00.000
Pid
841
Project Name
NEW UTRECH LIBRARY MAJOR RENOVATIONS
Description
New Utrech branch library is a comprehensive interior and exterior renovation which includes new fire alarm/ BMS, new interior layout, new HVAC, new roof, exterior rehabilitation and landscape.
Category
Libraries
Managing Agency
DDC
Client Agency
Libraries-BPL
Current Phase
Design
Design Start
2018-06-27T00:00:00.000
Budget Forecast
26368000.00
Latest Budget Changes
0.00
Total Budget Changes
290000.00
Forecast Completion
2024-06-18T00:00:00.000
Latest Schedule Changes
-74
Total Schedule Changes
1188
SOUTH BROOKLYN CROSSTOWN SBS
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 843 • Project Name: SOUTH BROOKLYN CROSSTOWN SBS
Date Reported As Of
2019-05-01T00:00:00.000
Pid
843
Project Name
SOUTH BROOKLYN CROSSTOWN SBS
Description
The construction of Southern Brooklyn Crosstown Select Bus Service (SBS)
Category
Industrial Development
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2018-07-17T00:00:00.000
Budget Forecast
82909000.00
Latest Budget Changes
100000.00
Total Budget Changes
29789000.00
Forecast Completion
2024-11-13T00:00:00.000
Latest Schedule Changes
-311
Total Schedule Changes
819
RECONST. OF COLUMBIA ST., PH II/BED-768B/SEK002321
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 845 • Project Name: RECONST. OF COLUMBIA ST., PH II/BED-768B/SEK002321
Date Reported As Of
2019-05-01T00:00:00.000
Pid
845
Project Name
RECONST. OF COLUMBIA ST., PH II/BED-768B/SEK002321
Description
Roadway reconstruction including new sewers, water main, street lighting and traffic signals: Columbia Street south of Hamilton Avenue.
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2019-07-01T00:00:00.000
Budget Forecast
113874000.00
Latest Budget Changes
0.00
Total Budget Changes
6730000.00
Forecast Completion
2024-07-14T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
972
Electronic Medical Records Upgrade
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 403 • Project Name: Electronic Medical Records Upgrade
Date Reported As Of
2019-05-01T00:00:00.000
Pid
403
Project Name
Electronic Medical Records Upgrade
Description
The EPIC - EMR Program: Electronic Medical Records (EMR) System - a single enterprise-wide EMR to meet the needs of HHC's expansive size and improve patient care will replace the legacy EMR - QuadraMed, which is over 25 years old.
Category
Health and Hospitals, IT
Borough
Citywide
Managing Agency
HHC
Client Agency
H+H
Current Phase
IT
Budget Forecast
764063231.00
Latest Budget Changes
0.00
Total Budget Changes
15184947.00
Forecast Completion
2016-04-02T00:00:00.000
Latest Schedule Changes
-1330
Total Schedule Changes
2032
SOUTHEAST QUEENS PRIORITY GRIDS - GROUP 2
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 847 • Project Name: SOUTHEAST QUEENS PRIORITY GRIDS - GROUP 2
Date Reported As Of
2019-05-01T00:00:00.000
Pid
847
Project Name
SOUTHEAST QUEENS PRIORITY GRIDS - GROUP 2
Description
SOUTHEAST QUEENS PRIORITY GRIDS - GROUP 2
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2018-10-09T00:00:00.000
Budget Forecast
44050000.00
Latest Budget Changes
25549000.00
Total Budget Changes
14480000.00
Forecast Completion
2024-07-10T00:00:00.000
Latest Schedule Changes
-65
Total Schedule Changes
1630
HIGH LEVEL STM SEWERS IN GOWANUS CANAL AREA-PH II
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 849 • Project Name: HIGH LEVEL STM SEWERS IN GOWANUS CANAL AREA-PH II
Date Reported As Of
2019-05-01T00:00:00.000
Pid
849
Project Name
HIGH LEVEL STM SEWERS IN GOWANUS CANAL AREA-PH II
Description
High Level Storm and Combine Sewer installation and Water Main replacement in Gowanus Canal Area Phase-2, Brooklyn.
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2016-09-30T00:00:00.000
Budget Forecast
34583000.00
Latest Budget Changes
392000.00
Total Budget Changes
8657000.00
Forecast Completion
2021-09-29T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
813
253 Broadway NYC. Fire Alarm Raplacement
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 850 • Project Name: 253 Broadway NYC. Fire Alarm Raplacement
Date Reported As Of
2019-05-01T00:00:00.000
Pid
850
Project Name
253 Broadway NYC. Fire Alarm Raplacement
Description
Installation of new building wide fire alarm and sprinkler distribution for 253 Broadway
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Design
Design Start
2018-01-22T00:00:00.000
Budget Forecast
29634000.00
Latest Budget Changes
-11882985.40
Total Budget Changes
17827000.00
Forecast Completion
2022-03-04T00:00:00.000
Latest Schedule Changes
-210
Total Schedule Changes
1553
FUEL TANK REPLACEMENT
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 851 • Project Name: FUEL TANK REPLACEMENT
Date Reported As Of
2019-05-01T00:00:00.000
Pid
851
Project Name
FUEL TANK REPLACEMENT
Description
The scope of work consists of providing all necessary construction management, design, and r.onstruction services required to perform ail phases of the project: Surveying, tank testing, investigation, design, construction, and construction management for the closure, removal, upgrade, or replacement of petroieum product storage tanks at various City owned sites. This work must comply with all local, state, nnd federal laws nnd regulations governing tanks and associated work. The general scope of work for tank replacement includes: File NYSDEC PBS application; mobilization; securing all required NYC agency approvals & permits; site survey; geophysical survey; drilling for laboratory soil and groundwater samples; crane & rigging; saw cutting; demo & disposal of old tanks, piping, and concrete vaults; dewatering� of excavation; tank bottom sludge removal & disposal; remove/transfer/dispose product; laboratory analysis of soil and groundwater; excavate, remove, dispose incidental contaminated soil; install shoring, new tanks and tan�k sumps, piping, monitoring and leak detection system, overfill protection and alarms, electrical wiring; construction of concrete slabs and block piers; backfill excavation; resurfacing; demobilization; performance of a closeout investigation and the preparation and filing of appropriate reports; obtaining FDNY and DOB closeout documents; preparing ""As-built"" drawings.
Category
Industrial Development
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Construction
Design Start
2017-10-30T00:00:00.000
Budget Forecast
31493000.00
Latest Budget Changes
0.00
Total Budget Changes
207000.00
Forecast Completion
2021-10-14T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1278
TRENCH RESTORATION BROOKLYN
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 855 • Project Name: TRENCH RESTORATION BROOKLYN
Date Reported As Of
2019-05-01T00:00:00.000
Pid
855
Project Name
TRENCH RESTORATION BROOKLYN
Description
Trench Restoration in The Borough Of Brooklyn including Full Street Reconstruction
Category
Industrial Development
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2018-06-05T00:00:00.000
Budget Forecast
27038000.00
Latest Budget Changes
0.00
Total Budget Changes
6536000.00
Forecast Completion
2022-08-13T00:00:00.000
Latest Schedule Changes
-27
Total Schedule Changes
1467
Manhattan Greenway: East Midtown
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 859 • Project Name: Manhattan Greenway: East Midtown
Date Reported As Of
2019-05-01T00:00:00.000
Pid
859
Project Name
Manhattan Greenway: East Midtown
Description
The East Midtown Waterfront Greenway project involves the creation of a waterfront esplanade between East 53rd and East 59th Streets.
Category
Parks
Managing Agency
EDC
Client Agency
EDC
Current Phase
Construction Procurement
Design Start
2017-10-01T00:00:00.000
Budget Forecast
130000000.00
Latest Budget Changes
0.00
Total Budget Changes
24840000.00
Forecast Completion
2022-11-01T00:00:00.000
Latest Schedule Changes
1
Total Schedule Changes
487
Manhattan Greenway: Harlem River
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 860 • Project Name: Manhattan Greenway: Harlem River
Date Reported As Of
2019-05-01T00:00:00.000
Pid
860
Project Name
Manhattan Greenway: Harlem River
Description
The Manhattan Greenway Harlem River project, between West 125th Street and Swindler Cove, involves the creation of a park, greenway, and the reconstruction of the bulkhead.
Category
Parks
Managing Agency
EDC
Client Agency
DPR
Current Phase
Design
Design Start
2019-06-15T00:00:00.000
Budget Forecast
227658000.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2024-04-15T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
888
West 33rd Street
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 861 • Project Name: West 33rd Street
Date Reported As Of
2019-05-01T00:00:00.000
Pid
861
Project Name
West 33rd Street
Description
Regrading and reconstruction of 33rd Street Viaduct between 11th and 12th Avenue..
Category
Streets and Roadways
Managing Agency
EDC
Client Agency
DOT
Current Phase
Design
Design Start
2018-09-01T00:00:00.000
Budget Forecast
100000000.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2022-02-28T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1736
Network Infrastructure Refresh Program
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 863 • Project Name: Network Infrastructure Refresh Program
Date Reported As Of
2019-05-01T00:00:00.000
Pid
863
Project Name
Network Infrastructure Refresh Program
Description
This project has a two-fold basis: 1) The ongoing Network Refresh which is needed to replace aging, end-of-life, end-of-support equipment across the NYC H+H. 2) Networking capacity needed to support the Electronic Medical Records system.
Category
Health and Hospitals, IT
Managing Agency
HHC
Client Agency
H+H
Current Phase
IT
Budget Forecast
160090000.00
Latest Budget Changes
160090000.00
Total Budget Changes
180514000.00
2nd Avenue Watermain Trunk Construction
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 388 • Project Name: 2nd Avenue Watermain Trunk Construction
Date Reported As Of
2019-05-01T00:00:00.000
Pid
388
Project Name
2nd Avenue Watermain Trunk Construction
Description
Trunk and Distribution Main Connection to shaft 32B in 2nd Ave., etc., together with all work incidental thereto, Borough of Manhattan. 2nd Avenue from East 33rd Street to East 37th Street
Category
Water Supply
Borough
Manhattan
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2013-09-30T00:00:00.000
Budget Forecast
45800000.00
Latest Budget Changes
0.00
Total Budget Changes
-7266000.00
Forecast Completion
2021-06-02T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2113
Brooklyn Public School 730 New Construction
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 876 • Project Name: Brooklyn Public School 730 New Construction
Date Reported As Of
2019-05-01T00:00:00.000
Pid
876
Project Name
Brooklyn Public School 730 New Construction
Description
Design and construction of a new school
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction
Design Start
2018-01-26T00:00:00.000
Budget Forecast
50524662.00
Latest Budget Changes
-9344914.00
Total Budget Changes
6379885.00
Forecast Completion
2021-09-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
730
Bronx Animal Care Center
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 893 • Project Name: Bronx Animal Care Center
Date Reported As Of
2019-05-01T00:00:00.000
Pid
893
Project Name
Bronx Animal Care Center
Description
Bronx Animal Care Center & Veterinary Clinic is a new 50,000 SF facility that will be housing admissions, adoptions, medical services, and boarding for approximately 70 dogs, 140 cats, 30 rabbits and 20 animals or other species. In addition to the animal housing, the Bronx Animal Care Center will include a wildlife area to rehabilitate wild birds, academic partnership for youth, and enhanced senior services. Site work will include yards to facilitate dog adoptions, covered exercise runs, courtyards, and parking for staff, visitors, and shelter vehicles, as well as site lighting and low maintenance planting throughout. The building and associated landscape are to achieve LEED Gold standards.
Category
Health and Hospitals
Managing Agency
DDC
Client Agency
Health
Current Phase
Design
Design Start
2019-06-20T00:00:00.000
Budget Forecast
69375000.00
Latest Budget Changes
-2288383.00
Total Budget Changes
24815617.00
Forecast Completion
2024-07-01T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
110
Studio Museum in Harlem New Building
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 896 • Project Name: Studio Museum in Harlem New Building
Date Reported As Of
2019-05-01T00:00:00.000
Pid
896
Project Name
Studio Museum in Harlem New Building
Description
The Project will combine two adjacent lots on 125th Street: the sculpture court, City-owned lot 11, and the Museum building on lot 9, owned by the Museum. Existing structures on both lots will be demolished for the new, six story 82,000sf City owned building.
Category
Arts and Culture
Managing Agency
DDC
Client Agency
Cultural Affairs
Current Phase
Construction
Design Start
2018-09-25T00:00:00.000
Budget Forecast
59431000.00
Latest Budget Changes
100000.00
Total Budget Changes
-190000.00
Forecast Completion
2022-11-25T00:00:00.000
Latest Schedule Changes
273
Total Schedule Changes
856
FUEL TANK & SUMP REPLACEMENTS - QUEENS
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 898 • Project Name: FUEL TANK & SUMP REPLACEMENTS - QUEENS
Date Reported As Of
2019-05-01T00:00:00.000
Pid
898
Project Name
FUEL TANK & SUMP REPLACEMENTS - QUEENS
Category
Industrial Development
Managing Agency
DDC
Client Agency
DCAS
Total Budget Changes
-1850000.00
Total Schedule Changes
663
FUEL TANK & SUMP REPLACEMENTS - BROOKLYN
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 899 • Project Name: FUEL TANK & SUMP REPLACEMENTS - BROOKLYN
Date Reported As Of
2019-05-01T00:00:00.000
Pid
899
Project Name
FUEL TANK & SUMP REPLACEMENTS - BROOKLYN
Category
Industrial Development
Managing Agency
DDC
Client Agency
DCAS
Total Budget Changes
-1940000.00
Total Schedule Changes
663
FUEL TANK & SUMP REPLACEMENTS - MANHATTAN/S.I.
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 900 • Project Name: FUEL TANK & SUMP REPLACEMENTS - MANHATTAN/S.I.
Date Reported As Of
2019-05-01T00:00:00.000
Pid
900
Project Name
FUEL TANK & SUMP REPLACEMENTS - MANHATTAN/S.I.
Category
Industrial Development
Managing Agency
DDC
Client Agency
DCAS
Total Budget Changes
-1754000.00
Total Schedule Changes
663
FUEL TANK & SUMP REPLACEMENTS - BRONX
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 901 • Project Name: FUEL TANK & SUMP REPLACEMENTS - BRONX
Date Reported As Of
2019-05-01T00:00:00.000
Pid
901
Project Name
FUEL TANK & SUMP REPLACEMENTS - BRONX
Category
Industrial Development
Managing Agency
DDC
Client Agency
DCAS
Total Budget Changes
-1834000.00
Total Schedule Changes
663
Headworks Improvements at Tallman Island
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 906 • Project Name: Headworks Improvements at Tallman Island
Date Reported As Of
2019-05-01T00:00:00.000
Pid
906
Project Name
Headworks Improvements at Tallman Island
Description
Headworks Improvements at Tallman Island intended to bring the headworks into a state of good repair. The headworks was last upgraded in 1979, and the service lives of critical systems are nearing their endpoints.
Category
Industrial Development
Managing Agency
DEP
Client Agency
WWC
Current Phase
Design
Design Start
2019-07-01T00:00:00.000
Budget Forecast
47204478.00
Latest Budget Changes
17380000.00
Total Budget Changes
19975649.96
Forecast Completion
2025-03-07T00:00:00.000
Latest Schedule Changes
61
Total Schedule Changes
586
Power Distribution Improvements at Tallman Island
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 907 • Project Name: Power Distribution Improvements at Tallman Island
Date Reported As Of
2019-05-01T00:00:00.000
Pid
907
Project Name
Power Distribution Improvements at Tallman Island
Description
Power Distribution Improvements
Category
Industrial Development
Managing Agency
DEP
Client Agency
WWC
Current Phase
Design
Design Start
2018-05-29T00:00:00.000
Budget Forecast
61053693.00
Latest Budget Changes
5671028.00
Total Budget Changes
10926063.83
Forecast Completion
2025-04-28T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
651
DOH Public Health Lab
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 909 • Project Name: DOH Public Health Lab
Date Reported As Of
2019-05-01T00:00:00.000
Pid
909
Project Name
DOH Public Health Lab
Description
The construction of an approximately 230,000 sq ft municipal Public Health Lab building for DOHMH.
Category
Health and Hospitals
Managing Agency
EDC
Client Agency
DOHMH
Current Phase
Design
Design Start
2019-01-01T00:00:00.000
Budget Forecast
613797320.29
Latest Budget Changes
0.00
Total Budget Changes
19334959.71
Forecast Completion
2025-01-01T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1
Flatbush Avenue Trunk Watermain Replacement
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 370 • Project Name: Flatbush Avenue Trunk Watermain Replacement
Date Reported As Of
2019-05-01T00:00:00.000
Pid
370
Project Name
Flatbush Avenue Trunk Watermain Replacement
Description
72"" Trunk Water Main and Combined Sewer Replacement in Flatbush Ave. between Sterling Pl. and 8th Ave., etc., Borough of Brooklyn. WM-6 in:
Category
Wastewater Treatment
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2014-11-24T00:00:00.000
Budget Forecast
49736000.00
Latest Budget Changes
250000.00
Total Budget Changes
39272000.00
Forecast Completion
2021-07-12T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2266
FUEL TANK REPLACEMENT - 71
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 935 • Project Name: FUEL TANK REPLACEMENT - 71
Date Reported As Of
2019-05-01T00:00:00.000
Pid
935
Project Name
FUEL TANK REPLACEMENT - 71
Description
By Notice To Proceed letter dated September 21, 2018, the New York City Department of Design and Construction (�DDC�) directed PMS Construction Management Corp. (�PMS�) to commence work on Capis ID PW348-71, Contract No. 20191404531 CM/Design/Build for the Replacement and Upgrade of Petroleum Storage Tanks for the Borough of Manhattan. The contract was awarded for a maximum fee of $28,026,750.00 and was partially registered by the Comptroller on September 21, 2018 in the amount of $4,885,000.00. The term of the contract is 1,095 consecutive calendar days from September 21, 2018. Contract termination date is September 19, 2021.
Category
Industrial Development
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Design
Design Start
2018-10-02T00:00:00.000
Budget Forecast
29265000.00
Latest Budget Changes
0.00
Total Budget Changes
3444000.00
Forecast Completion
2022-09-19T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
548
Riverside Drive/West 158th Street Bridge Rehabilitation
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 113 • Project Name: Riverside Drive/West 158th Street Bridge Rehabilitation
Date Reported As Of
2019-05-01T00:00:00.000
Pid
113
Project Name
Riverside Drive/West 158th Street Bridge Rehabilitation
Description
Replace deck of the Riverside Drive viaduct/ bridge over West 158th Street.
Category
Bridges, Streets and Roadways
Borough
Manhattan
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2014-10-22T00:00:00.000
Budget Forecast
160245510.00
Latest Budget Changes
32676659.78
Total Budget Changes
96922794.00
Forecast Completion
2022-06-27T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2152
Hannah Street Pumping Station Construction
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 364 • Project Name: Hannah Street Pumping Station Construction
Date Reported As Of
2019-05-01T00:00:00.000
Pid
364
Project Name
Hannah Street Pumping Station Construction
Description
This project will reconstruct the Hannah St. Pumping Station, the largest City-owned wastewater collection and pumping station on Staten Island. Built in 1977, the facility has numerous deficiencies, needing a comprehensive upgrade.
Category
Wastewater Treatment
Borough
Staten Island
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2012-10-01T00:00:00.000
Budget Forecast
69767304.23
Latest Budget Changes
0.00
Total Budget Changes
67909196.80
Forecast Completion
2022-03-16T00:00:00.000
Latest Schedule Changes
98
Total Schedule Changes
3238
Brooklyn P.S. at 4302 4TH AVE
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 949 • Project Name: Brooklyn P.S. at 4302 4TH AVE
Date Reported As Of
2019-05-01T00:00:00.000
Pid
949
Project Name
Brooklyn P.S. at 4302 4TH AVE
Description
Design and construction of a new school
Category
Schools
Managing Agency
SCA
Client Agency
DOE
Current Phase
Construction Procurement
Design Start
2017-11-17T00:00:00.000
Budget Forecast
66279759.00
Total Budget Changes
-221356.00
Forecast Completion
2022-09-03T00:00:00.000
Total Schedule Changes
365
Bronx Sanitation Garage Rehabilitation: Community District 12
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 956 • Project Name: Bronx Sanitation Garage Rehabilitation: Community District 12
Date Reported As Of
2019-05-01T00:00:00.000
Pid
956
Project Name
Bronx Sanitation Garage Rehabilitation: Community District 12
Description
Rehabilitation of garage that serves Bronx Community District 12 located at 1635 East 233rd Street, Bronx.
Category
Sanitation
Managing Agency
DSNY
Client Agency
DSNY
Current Phase
Design
Design Start
2017-11-01T00:00:00.000
Budget Forecast
57376185.00
Total Budget Changes
0.00
Forecast Completion
2024-07-31T00:00:00.000
Total Schedule Changes
1064
West 59th Street Marine Transfer Station Construction, Phase 2
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 347 • Project Name: West 59th Street Marine Transfer Station Construction, Phase 2
Date Reported As Of
2019-05-01T00:00:00.000
Pid
347
Project Name
West 59th Street Marine Transfer Station Construction, Phase 2
Description
Project 2 Scope: Refurbishment of the existing pier building including: repair of existing pier structure including pile caps and fendering; construction of new emergency generator, electrical, mechanical, fire pump and fire valve rooms; new exit passageway construction and existing exit passageway refurbishment; re-arrangement and refurbishment of the Operations Building interiors; replacement of fire suppression system throughout the entire pier structure; mechanical, electrical and plumbing system upgrades; refurbishment and painting the existing pier interior steel framing and wall/roof surfaces; recoating the structure's exterior cladding systems including metal wall and roof panel system and translucent panel wall cladding system.
Category
Sanitation
Borough
Manhattan
Managing Agency
DDC
Client Agency
Sanitation
Current Phase
Construction
Design Start
2012-01-17T00:00:00.000
Budget Forecast
103201000.00
Latest Budget Changes
10567000.00
Total Budget Changes
126753576.46
Forecast Completion
2020-08-27T00:00:00.000
Latest Schedule Changes
296
Total Schedule Changes
1949
Dutch Kills and Lower Newtown Creek Enhanced Aeration Work
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 313 • Project Name: Dutch Kills and Lower Newtown Creek Enhanced Aeration Work
Date Reported As Of
2019-05-01T00:00:00.000
Pid
313
Project Name
Dutch Kills and Lower Newtown Creek Enhanced Aeration Work
Description
This project will upgrade the Borden Ave Pump Station by expanding its footprint; providing replacement equipment; converting dry well to wet well; and providing provisions for future project to expand capacity of pump station to 26 MGD.
Category
Wastewater Treatment
Borough
Queens
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2014-01-01T00:00:00.000
Budget Forecast
31571569.00
Latest Budget Changes
-3875767.00
Total Budget Changes
-4338327.57
Forecast Completion
2024-01-14T00:00:00.000
Latest Schedule Changes
213
Total Schedule Changes
1891
Emergency Communications Transformation Program (ECTP) Upgrades and Enhancements
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 267 • Project Name: Emergency Communications Transformation Program (ECTP) Upgrades and Enhancements
Date Reported As Of
2019-05-01T00:00:00.000
Pid
267
Project Name
Emergency Communications Transformation Program (ECTP) Upgrades and Enhancements
Description
Upgrade and enhancement of emergency technology infrastructure to improve interoperability and coordination among public safety agencies and improve call processing time to decrease overall response times.
Category
IT
Borough
Citywide
Managing Agency
DOITT
Client Agency
FDNY, NYPD
Current Phase
IT
Budget Forecast
2249890870.99
Latest Budget Changes
3564413.76
Total Budget Changes
73735148.87
Forecast Completion
2020-03-22T00:00:00.000
Latest Schedule Changes
143
Total Schedule Changes
2252
Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 112 • Project Name: Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Date Reported As Of
2019-05-01T00:00:00.000
Pid
112
Project Name
Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Description
Repair abutments, piers, approaches, and steel superstructure located in Pelham Bay, Bronx; replace reinforced concrete deck.
Category
Bridges, Streets and Roadways
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
1995-01-17T00:00:00.000
Budget Forecast
82693222.00
Latest Budget Changes
1750000.00
Total Budget Changes
20945057.00
Forecast Completion
2021-09-13T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1592
Roma and Hett Avenue Storm and Sanitary Sewer Installation
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 206 • Project Name: Roma and Hett Avenue Storm and Sanitary Sewer Installation
Date Reported As Of
2019-05-01T00:00:00.000
Pid
206
Project Name
Roma and Hett Avenue Storm and Sanitary Sewer Installation
Description
Install storm and sanitary sewers at multiple locations.
Category
Sewers
Borough
Staten Island
Managing Agency
DDC
Client Agency
Trans. & Env. Protection
Current Phase
Construction
Design Start
2014-10-15T00:00:00.000
Budget Forecast
98431000.00
Latest Budget Changes
13101000.00
Total Budget Changes
62973000.00
Forecast Completion
2022-06-28T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
-8
Edgewood Triangle Roadway Reconstruction
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 204 • Project Name: Edgewood Triangle Roadway Reconstruction
Date Reported As Of
2019-05-01T00:00:00.000
Pid
204
Project Name
Edgewood Triangle Roadway Reconstruction
Description
Reconstruct roadway and extend storm and sanitary sewers in portions of Brookville Boulevard, Edgewood Street, 147th Avenue, and adjacent streets west of 241st Street.
Category
Streets and Roadways
Borough
Queens
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2013-02-13T00:00:00.000
Budget Forecast
98423000.00
Latest Budget Changes
78077000.00
Total Budget Changes
106503000.00
Forecast Completion
2024-03-22T00:00:00.000
Latest Schedule Changes
574
Total Schedule Changes
3597
Dumbo and Vinegar Hill Area Roadway Reconstruction and Renovation
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 193 • Project Name: Dumbo and Vinegar Hill Area Roadway Reconstruction and Renovation
Date Reported As Of
2019-05-01T00:00:00.000
Pid
193
Project Name
Dumbo and Vinegar Hill Area Roadway Reconstruction and Renovation
Description
Reconstruction DUMBO/Vinegar Hill Area including Trunk and Distribution water main replacement; Installation of HLSS and Combined Sewer replacement; Restoration of Belgian block in Water Street; Street lighting and Traffic Signal work.
Category
Streets and Roadways
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction
Design Start
2012-06-07T00:00:00.000
Budget Forecast
114950000.00
Latest Budget Changes
-4967000.00
Total Budget Changes
96724000.00
Forecast Completion
2024-06-04T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
3253
New Ferry Boat Construction
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 94 • Project Name: New Ferry Boat Construction
Date Reported As Of
2019-05-01T00:00:00.000
Pid
94
Project Name
New Ferry Boat Construction
Description
Replace one Barberi class boat and the John F. Kennedy boat which are approaching the end of their useful lives with new Staten Island ferries. Replacement is needed to continue reliable service.
Category
Ferries
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2014-09-15T00:00:00.000
Budget Forecast
349869872.00
Latest Budget Changes
21980482.00
Total Budget Changes
-238419180.00
Forecast Completion
2021-08-06T00:00:00.000
Latest Schedule Changes
159
Total Schedule Changes
549
Broadway Bridge over Harlem River Replacement
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 106 • Project Name: Broadway Bridge over Harlem River Replacement
Date Reported As Of
2019-05-01T00:00:00.000
Pid
106
Project Name
Broadway Bridge over Harlem River Replacement
Description
Replace deteriorated members of lift span superstructure, concrete deck, lift electrical and mechanical systems, and fenders.
Category
Bridges
Borough
Bronx, Manhattan
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2005-04-01T00:00:00.000
Budget Forecast
190133979.00
Latest Budget Changes
999999.00
Total Budget Changes
39724388.00
Forecast Completion
2022-03-25T00:00:00.000
Latest Schedule Changes
249
Total Schedule Changes
2797
Wyckoff Avenue Street Reconstruction
Date Reported As Of: 2019-05-01T00:00:00.000 • Pid: 191 • Project Name: Wyckoff Avenue Street Reconstruction
Date Reported As Of
2019-05-01T00:00:00.000
Pid
191
Project Name
Wyckoff Avenue Street Reconstruction
Description
Reconstruction of Wyckoff Avenue from Flushing Avenue to Cooper Avenue, in the Boroughs of Brooklyn and Queens..
Category
Streets and Roadways
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Trans. & Env. Protection
Current Phase
Design
Design Start
2017-03-29T00:00:00.000
Budget Forecast
43745000.00
Latest Budget Changes
-30403000.00
Total Budget Changes
43926000.00
Forecast Completion
2023-03-29T00:00:00.000
Latest Schedule Changes
-2832
Total Schedule Changes
226