Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 776 • Project Name: Storm & Combined Sewers In 229 Street
Date Reported As Of
2018-08-01T00:00:00.000
Pid
776
Project Name
Storm & Combined Sewers In 229 Street
Description
High Level Storm and Combined Sewer in 229th Street and 230th Place Between 145th Avenue and 147th Ave. (Spine Springfield/Laurelton Blvd)
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2015-04-30T00:00:00.000
Budget Forecast
132415000.00
Latest Budget Changes
2808000.00
Total Budget Changes
-9148000.00
Forecast Completion
2021-07-28T00:00:00.000
Latest Schedule Changes
-50
Total Schedule Changes
652
Coastal Resiliency Area 1 - East 23Rd St. To Montg
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 773 • Project Name: Coastal Resiliency Area 1 - East 23Rd St. To Montg
Date Reported As Of
2018-08-01T00:00:00.000
Pid
773
Project Name
Coastal Resiliency Area 1 - East 23Rd St. To Montg
Description
East Side Coastal Resiliency - East 23rd St. to Montgomery St.
Category
Industrial Development, Parks
Managing Agency
DDC
Client Agency
Parks & Recreation
Current Phase
Design
Design Start
2017-04-01T00:00:00.000
Budget Forecast
510854000.00
Latest Budget Changes
0.00
Total Budget Changes
-418193636.37
Forecast Completion
2025-04-30T00:00:00.000
Latest Schedule Changes
364
Total Schedule Changes
836
Gilboa Dam Reconstruction, Phase IV
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 406 • Project Name: Gilboa Dam Reconstruction, Phase IV
Date Reported As Of
2018-08-01T00:00:00.000
Pid
406
Project Name
Gilboa Dam Reconstruction, Phase IV
Description
This project will rehabilitate the mechanics and the architecture of the Shandaken Tunnel Intake Chamber, which includes the replacement of gates and general site improvements.
Category
Water Supply
Borough
Upstate
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2008-12-01T00:00:00.000
Budget Forecast
66290311.40
Latest Budget Changes
1767086.70
Total Budget Changes
33535991.20
Forecast Completion
2021-10-07T00:00:00.000
Latest Schedule Changes
1
Total Schedule Changes
1684
Rehab Of Queens District 11/13 Sanitation Garage
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 770 • Project Name: Rehab Of Queens District 11/13 Sanitation Garage
Date Reported As Of
2018-08-01T00:00:00.000
Pid
770
Project Name
Rehab Of Queens District 11/13 Sanitation Garage
Description
Rehab Of Queens District 11/13 Sanitation Garage
Category
Sanitation
Borough
Queens
Managing Agency
DDC
Client Agency
Sanitation
Current Phase
Design
Design Start
2017-03-06T00:00:00.000
Budget Forecast
38097000.00
Latest Budget Changes
272000.00
Total Budget Changes
36221000.00
Forecast Completion
2022-10-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1521
Coney Island Hospital CSS Building and Perimeter Flood Protection
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 561 • Project Name: Coney Island Hospital CSS Building and Perimeter Flood Protection
Date Reported As Of
2018-08-01T00:00:00.000
Pid
561
Project Name
Coney Island Hospital CSS Building and Perimeter Flood Protection
Description
Renovation of CIH to advance the City’s resiliency plan, repair damages, and protect the hospital from future disasters.
Category
Health and Hospitals
Borough
Brooklyn
Managing Agency
EDC
Client Agency
H+H
Current Phase
Construction
Design Start
2016-02-01T00:00:00.000
Budget Forecast
678812311.00
Latest Budget Changes
13057911.00
Total Budget Changes
30635879.93
Forecast Completion
2023-03-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1243
Edgewood Triangle Roadway Reconstruction
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 204 • Project Name: Edgewood Triangle Roadway Reconstruction
Date Reported As Of
2018-08-01T00:00:00.000
Pid
204
Project Name
Edgewood Triangle Roadway Reconstruction
Description
Reconstruct roadway and extend storm and sanitary sewers in portions of Brookville Boulevard, Edgewood Street, 147th Avenue, and adjacent streets west of 241st Street.
Category
Streets and Roadways
Borough
Queens
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2013-02-13T00:00:00.000
Budget Forecast
81463000.00
Latest Budget Changes
65645000.00
Total Budget Changes
106503000.00
Forecast Completion
2022-09-06T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
3597
Dutch Kills and Lower Newtown Creek Enhanced Aeration Work
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 313 • Project Name: Dutch Kills and Lower Newtown Creek Enhanced Aeration Work
Date Reported As Of
2018-08-01T00:00:00.000
Pid
313
Project Name
Dutch Kills and Lower Newtown Creek Enhanced Aeration Work
Description
This project will construct a blower facility and install a diffused aeration system in Dutch Kills and Newtown Creek to increase dissolved oxygen content in the project area to meet DEC standards for the water body.
Category
Wastewater Treatment
Borough
Queens
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction Procurement
Design Start
2014-01-01T00:00:00.000
Budget Forecast
33807921.00
Latest Budget Changes
-10803497.00
Total Budget Changes
-4338327.57
Forecast Completion
2022-12-12T00:00:00.000
Latest Schedule Changes
139
Total Schedule Changes
1891
Carl Schurz Park Promenade over FDR (East 81st to 90th Streets)
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 537 • Project Name: Carl Schurz Park Promenade over FDR (East 81st to 90th Streets)
Date Reported As Of
2018-08-01T00:00:00.000
Pid
537
Project Name
Carl Schurz Park Promenade over FDR (East 81st to 90th Streets)
Description
Replace the Promenade over FDR between East 81st to 90th Streets in Manhattan.
Category
Bridges
Borough
Manhattan
Managing Agency
DOT
Client Agency
DOT, DPR
Current Phase
Design
Design Start
2017-05-30T00:00:00.000
Budget Forecast
348754421.00
Latest Budget Changes
350000.00
Total Budget Changes
-197139579.00
Forecast Completion
2025-10-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1571
Staten Island 1 & 3 Garage Construction & Rehab
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 769 • Project Name: Staten Island 1 & 3 Garage Construction & Rehab
Date Reported As Of
2018-08-01T00:00:00.000
Pid
769
Project Name
Staten Island 1 & 3 Garage Construction & Rehab
Description
The Department of Sanitation of the City of New York (DSNY) is planning to develop a Staten Island Districts 1 and 3 campus that will include a new garage serving both districts and renovation of the existing Borough Repair Shop.
Category
Sanitation
Borough
Staten Island
Managing Agency
DDC
Client Agency
Sanitation
Current Phase
Design
Design Start
2017-07-14T00:00:00.000
Budget Forecast
159560000.00
Latest Budget Changes
21416000.00
Total Budget Changes
68555000.00
Forecast Completion
2023-02-13T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
406
5th Avenue Bridge Reconstruction over LIRR and Sea Beach, Brooklyn
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 504 • Project Name: 5th Avenue Bridge Reconstruction over LIRR and Sea Beach, Brooklyn
Date Reported As Of
2018-08-01T00:00:00.000
Pid
504
Project Name
5th Avenue Bridge Reconstruction over LIRR and Sea Beach, Brooklyn
Description
Replace the 5th Avenue Bridge over LIRR & Sea Beach, Brooklyn.
Category
Bridges
Borough
Brooklyn
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-11-30T00:00:00.000
Budget Forecast
49319823.00
Latest Budget Changes
2039849.00
Total Budget Changes
36577693.00
Forecast Completion
2024-11-04T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
969
Water Main Replacement In 222 Street, Queens
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 768 • Project Name: Water Main Replacement In 222 Street, Queens
Date Reported As Of
2018-08-01T00:00:00.000
Pid
768
Project Name
Water Main Replacement In 222 Street, Queens
Description
Water Main replacement in 222th Street
Category
Water Supply
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2018-04-02T00:00:00.000
Budget Forecast
39691000.00
Latest Budget Changes
5215000.00
Total Budget Changes
7195000.00
Forecast Completion
2022-01-18T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2236
New 116Th Pct
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 762 • Project Name: New 116Th Pct
Date Reported As Of
2018-08-01T00:00:00.000
Pid
762
Project Name
New 116Th Pct
Description
New 116Th Precinct at 244-04 North Conduit Avenue, Queens, NY 11442. Design and build of a 45,700 SF building on existing City owned property.
Category
Public Safety and Criminal Justice
Managing Agency
DDC
Client Agency
Police
Current Phase
Design
Design Start
2017-09-14T00:00:00.000
Budget Forecast
76950000.00
Latest Budget Changes
38900.86
Total Budget Changes
33852900.86
Forecast Completion
2022-04-05T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
727
Metropolitan Hospital Perimeter Flood Protection
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 562 • Project Name: Metropolitan Hospital Perimeter Flood Protection
Date Reported As Of
2018-08-01T00:00:00.000
Pid
562
Project Name
Metropolitan Hospital Perimeter Flood Protection
Category
Industrial Development
Borough
Manhattan
Managing Agency
EDC
Client Agency
H+H
Total Budget Changes
27046705.00
Total Schedule Changes
1452
Bronx Sanitation Garage Construction: Community District 9, 10, 11
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 573 • Project Name: Bronx Sanitation Garage Construction: Community District 9, 10, 11
Date Reported As Of
2018-08-01T00:00:00.000
Pid
573
Project Name
Bronx Sanitation Garage Construction: Community District 9, 10, 11
Description
Construction of new Sanitation garage facility to serve Bronx community districts 9, 10, and 11 to be located at Zerega Avenue in the Bronx
Category
Sanitation
Borough
Bronx
Managing Agency
DSNY
Client Agency
DSNY
Current Phase
Design
Design Start
2017-08-01T00:00:00.000
Budget Forecast
291383225.00
Latest Budget Changes
0.00
Total Budget Changes
268983862.56
Forecast Completion
2026-06-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1919
Construction Of Sanitary Sewers, Storm Sewers (Bm
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 760 • Project Name: Construction Of Sanitary Sewers, Storm Sewers (Bm
Date Reported As Of
2018-08-01T00:00:00.000
Pid
760
Project Name
Construction Of Sanitary Sewers, Storm Sewers (Bm
Description
Construction of storm sewers, sanitary sewers, water mains and Best Management Practice (BMP) NC-16 in Mason Avenue area
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction Procurement
Design Start
2016-08-29T00:00:00.000
Budget Forecast
34271000.00
Latest Budget Changes
1562000.00
Total Budget Changes
37691000.00
Forecast Completion
2022-04-15T00:00:00.000
Latest Schedule Changes
1
Total Schedule Changes
595
Upgrades At Brooklyn Animal Shelter
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 750 • Project Name: Upgrades At Brooklyn Animal Shelter
Date Reported As Of
2018-08-01T00:00:00.000
Pid
750
Project Name
Upgrades At Brooklyn Animal Shelter
Description
Brooklyn Animal Care Center
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
Health
Current Phase
Design
Design Start
2016-07-20T00:00:00.000
Budget Forecast
27284000.00
Latest Budget Changes
1440000.00
Total Budget Changes
21288000.00
Forecast Completion
2022-04-15T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1355
West Tremont Avenue over Metro North Railroad
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 503 • Project Name: West Tremont Avenue over Metro North Railroad
Date Reported As Of
2018-08-01T00:00:00.000
Pid
503
Project Name
West Tremont Avenue over Metro North Railroad
Description
Repair the West Tremont Avenue bridge over the Metro North line, located in the Bronx.
Category
Bridges
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-05-30T00:00:00.000
Budget Forecast
60836172.00
Latest Budget Changes
6698172.00
Total Budget Changes
37794543.00
Forecast Completion
2025-09-17T00:00:00.000
Latest Schedule Changes
253
Total Schedule Changes
1253
Porpoise Bridge In Flushing Meadows-Corona Park
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 749 • Project Name: Porpoise Bridge In Flushing Meadows-Corona Park
Date Reported As Of
2018-08-01T00:00:00.000
Pid
749
Project Name
Porpoise Bridge In Flushing Meadows-Corona Park
Description
PORPOISE BRIDGE IN FLUSHING MEADOWS-CORONA PARK
Category
Bridges
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2017-09-18T00:00:00.000
Budget Forecast
64905000.00
Latest Budget Changes
0.00
Total Budget Changes
82000.00
Forecast Completion
2023-07-29T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1110
Sunset Park Infrastructure
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 574 • Project Name: Sunset Park Infrastructure
Date Reported As Of
2018-08-01T00:00:00.000
Pid
574
Project Name
Sunset Park Infrastructure
Description
This project is construction of infrastructure and streetscape improvements in Sunset Park from 37th to 43rd Streets, between the Gowanus Expressway and the waterfront - to activate the waterfront and promote future development.
Category
Industrial Development
Borough
Brooklyn
Managing Agency
EDC
Client Agency
Mayor's Office
Current Phase
Design
Design Start
2016-06-08T00:00:00.000
Budget Forecast
37500000.00
Latest Budget Changes
0.00
Total Budget Changes
31633941.69
Forecast Completion
2021-11-28T00:00:00.000
Latest Schedule Changes
182
Total Schedule Changes
1290
Croton Above Ground Structure And Landscaping
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 747 • Project Name: Croton Above Ground Structure And Landscaping
Date Reported As Of
2018-08-01T00:00:00.000
Pid
747
Project Name
Croton Above Ground Structure And Landscaping
Category
Industrial Development
Managing Agency
DDC
Client Agency
Environmental Protection
Total Budget Changes
75117000.00
Total Schedule Changes
897
Dumbo and Vinegar Hill Area Roadway Reconstruction and Renovation
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 193 • Project Name: Dumbo and Vinegar Hill Area Roadway Reconstruction and Renovation
Date Reported As Of
2018-08-01T00:00:00.000
Pid
193
Project Name
Dumbo and Vinegar Hill Area Roadway Reconstruction and Renovation
Description
Reconstruction and restoration of Belgian block roadways in the DUMBO and Vinegar Hill communities concurrent with installation of new water main, combined sewers and storm sewers, plus construction of the Pearl Street Triangle Plaza.
Category
Streets and Roadways
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction Procurement
Design Start
2012-06-07T00:00:00.000
Budget Forecast
113352000.00
Latest Budget Changes
52572000.00
Total Budget Changes
96724000.00
Forecast Completion
2020-03-21T00:00:00.000
Latest Schedule Changes
190
Total Schedule Changes
3253
Reconstruction Of Arthur Kill Road, Phase I
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 741 • Project Name: Reconstruction Of Arthur Kill Road, Phase I
Date Reported As Of
2018-08-01T00:00:00.000
Pid
741
Project Name
Reconstruction Of Arthur Kill Road, Phase I
Description
Reconstruction of Arthur Kill Road From Clark Avenue to Richmond Avenue including widening of roadway
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2016-12-16T00:00:00.000
Budget Forecast
39897000.00
Latest Budget Changes
2101000.00
Total Budget Changes
22503000.00
Forecast Completion
2023-03-13T00:00:00.000
Latest Schedule Changes
256
Total Schedule Changes
1415
Reconstruction of the Port Jervis Wastewater Treatment Plant
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 444 • Project Name: Reconstruction of the Port Jervis Wastewater Treatment Plant
Date Reported As Of
2018-08-01T00:00:00.000
Pid
444
Project Name
Reconstruction of the Port Jervis Wastewater Treatment Plant
Description
Reconstruction of the Port Jervis WWTP as required based on the effluent limits proposed by the Delaware River Basin Commission (DRBC)
Category
Wastewater Treatment
Borough
Port Jervis
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction Procurement
Design Start
2014-06-17T00:00:00.000
Budget Forecast
56765729.45
Latest Budget Changes
6263016.05
Total Budget Changes
9428438.55
Forecast Completion
2021-11-19T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2445
Rondout-West Branch Bypass Tunnel Construction Project 2
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 409 • Project Name: Rondout-West Branch Bypass Tunnel Construction Project 2
Date Reported As Of
2018-08-01T00:00:00.000
Pid
409
Project Name
Rondout-West Branch Bypass Tunnel Construction Project 2
Description
To address existing leaks in the Delaware Aqueduct, a 3-mile bypass tunnel will be constructed near the town of Roseton and the existing tunnel will be repaired near the town of Wawarsing.
Category
Water Supply
Borough
Marlboro
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2012-03-23T00:00:00.000
Budget Forecast
891537907.44
Latest Budget Changes
1872532.89
Total Budget Changes
202552329.25
Forecast Completion
2023-09-26T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
256
FDR Rehabilitation, Northbound (East 42nd to 49th Streets)
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 502 • Project Name: FDR Rehabilitation, Northbound (East 42nd to 49th Streets)
Date Reported As Of
2018-08-01T00:00:00.000
Pid
502
Project Name
FDR Rehabilitation, Northbound (East 42nd to 49th Streets)
Description
Repair the northbound FDR from East 42nd to 49th Streets.
Category
Bridges
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2016-08-30T00:00:00.000
Budget Forecast
98115670.00
Latest Budget Changes
0.00
Total Budget Changes
-2802822.00
Forecast Completion
2027-07-12T00:00:00.000
Latest Schedule Changes
833
Total Schedule Changes
1816
Revenue Cycle Implementation
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 723 • Project Name: Revenue Cycle Implementation
Date Reported As Of
2018-08-01T00:00:00.000
Pid
723
Project Name
Revenue Cycle Implementation
Description
The Epic Revenue Cycle system will be enterprise-wide and help increase revenue (by proper billing of services provided) in addition to ensuring patient safety and improved patient care, a top priority in workflows.
Category
Health and Hospitals, IT
Borough
Citywide
Managing Agency
HHC
Client Agency
H+H
Current Phase
IT
Budget Forecast
289117990.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2018-10-20T00:00:00.000
Latest Schedule Changes
-619
Total Schedule Changes
1279
Lower Concourse Initiative
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 575 • Project Name: Lower Concourse Initiative
Date Reported As Of
2018-08-01T00:00:00.000
Pid
575
Project Name
Lower Concourse Initiative
Description
The Project will improve the roadways and pedestrian facilities. The Project will consist of roadway reconstruction within Exterior Street between East 138th Street and East 150th Street.
Category
Industrial Development
Borough
Bronx
Managing Agency
EDC
Client Agency
EDC
Current Phase
Design
Design Start
2017-04-01T00:00:00.000
Budget Forecast
84520367.00
Latest Budget Changes
0.00
Total Budget Changes
-5100000.00
Forecast Completion
2022-04-01T00:00:00.000
Latest Schedule Changes
212
Total Schedule Changes
730
Throgs Neck Pumping Station Rehabilitation and Improvements
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 722 • Project Name: Throgs Neck Pumping Station Rehabilitation and Improvements
Date Reported As Of
2018-08-01T00:00:00.000
Pid
722
Project Name
Throgs Neck Pumping Station Rehabilitation and Improvements
Description
Throgs Neck Pumping Station Rehabilitation and Improvements
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2018-06-11T00:00:00.000
Budget Forecast
46015605.00
Latest Budget Changes
4326119.00
Total Budget Changes
25708336.86
Forecast Completion
2022-11-22T00:00:00.000
Latest Schedule Changes
-102
Total Schedule Changes
1306
Storm Mitigation Loan Program at Red Hook
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 721 • Project Name: Storm Mitigation Loan Program at Red Hook
Date Reported As Of
2018-08-01T00:00:00.000
Pid
721
Project Name
Storm Mitigation Loan Program at Red Hook
Description
SMLP portion for Red Hook WWTP as part of the New York City Wastewater Resiliency Program.
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2018-05-30T00:00:00.000
Budget Forecast
34444531.97
Latest Budget Changes
4205214.08
Total Budget Changes
13549422.97
Forecast Completion
2021-01-20T00:00:00.000
Latest Schedule Changes
-1
Total Schedule Changes
921
Reconstruction of the West and North Docks at the OH WWTP
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 720 • Project Name: Reconstruction of the West and North Docks at the OH WWTP
Date Reported As Of
2018-08-01T00:00:00.000
Pid
720
Project Name
Reconstruction of the West and North Docks at the OH WWTP
Description
RECONSTRUCTION OF SEA WALL AND DOCK AT OWLS HEAD WWTP
Category
Wastewater Treatment
Borough
Brooklyn
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2017-08-18T00:00:00.000
Budget Forecast
56198668.00
Latest Budget Changes
-5414110.00
Total Budget Changes
10985726.80
Forecast Completion
2021-04-17T00:00:00.000
Latest Schedule Changes
340
Total Schedule Changes
1389
Battery Park Underpass Emergency Relief Betterments
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 540 • Project Name: Battery Park Underpass Emergency Relief Betterments
Date Reported As Of
2018-08-01T00:00:00.000
Pid
540
Project Name
Battery Park Underpass Emergency Relief Betterments
Description
Resiliency betterments for Battery Park and West Street underpasses.
Category
Bridges
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2018-04-01T00:00:00.000
Budget Forecast
18850000.00
Latest Budget Changes
0.00
Total Budget Changes
47923308.00
Forecast Completion
2022-03-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1197
Replacement of The Digester at The Hunts Point WWTP
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 580 • Project Name: Replacement of The Digester at The Hunts Point WWTP
Date Reported As Of
2018-08-01T00:00:00.000
Pid
580
Project Name
Replacement of The Digester at The Hunts Point WWTP
Description
Construction of New Anaerobic Digesters
Category
Wastewater Treatment
Borough
Bronx
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2017-09-21T00:00:00.000
Budget Forecast
321651100.00
Latest Budget Changes
-113880300.00
Total Budget Changes
72852004.14
Forecast Completion
2023-07-31T00:00:00.000
Latest Schedule Changes
-78
Total Schedule Changes
1355
Oakwood Beach WWTP Sludge Thickening Improvements
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 449 • Project Name: Oakwood Beach WWTP Sludge Thickening Improvements
Date Reported As Of
2018-08-01T00:00:00.000
Pid
449
Project Name
Oakwood Beach WWTP Sludge Thickening Improvements
Description
Replacement of thickener pumps, piping, sludge pumps, mixing pumps, recirculation pumps, spray water pumps, and heat exchangers. Install Gravity Belt Thickener, GBT pumps, polymer feed system. Rehab of Thickeners, Sludge Box, and Distribution Box.
Category
Wastewater Treatment
Borough
Staten Island
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2016-02-02T00:00:00.000
Budget Forecast
46441722.00
Latest Budget Changes
3843386.40
Total Budget Changes
57138101.30
Forecast Completion
2023-11-17T00:00:00.000
Latest Schedule Changes
870
Total Schedule Changes
3241
DBCD South Site Cultural Fit-Out
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 484 • Project Name: DBCD South Site Cultural Fit-Out
Date Reported As Of
2018-08-01T00:00:00.000
Pid
484
Project Name
DBCD South Site Cultural Fit-Out
Description
Interior fit-out of the south site cultural unit.
Category
Arts and Culture
Borough
Brooklyn
Managing Agency
EDC
Client Agency
DCLA
Current Phase
Design
Design Start
2014-12-01T00:00:00.000
Budget Forecast
32888855.92
Latest Budget Changes
55643.69
Total Budget Changes
36789601.16
Forecast Completion
2021-03-02T00:00:00.000
Latest Schedule Changes
154
Total Schedule Changes
1706
Broadway Bridge over Harlem River Replacement
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 106 • Project Name: Broadway Bridge over Harlem River Replacement
Date Reported As Of
2018-08-01T00:00:00.000
Pid
106
Project Name
Broadway Bridge over Harlem River Replacement
Description
Replace deteriorated members of lift span superstructure, concrete deck, lift electrical and mechanical systems, and fenders.
Category
Bridges
Borough
Bronx, Manhattan
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2005-04-01T00:00:00.000
Budget Forecast
198192458.00
Latest Budget Changes
-2077999.00
Total Budget Changes
39724388.00
Forecast Completion
2021-07-19T00:00:00.000
Latest Schedule Changes
-3
Total Schedule Changes
2797
Wyckoff Avenue Street Reconstruction
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 191 • Project Name: Wyckoff Avenue Street Reconstruction
Date Reported As Of
2018-08-01T00:00:00.000
Pid
191
Project Name
Wyckoff Avenue Street Reconstruction
Description
Reconstruction of Wyckoff Avenue from Flushing Avenue to Cooper Avenue, in the Boroughs of Brooklyn and Queens.
Category
Streets and Roadways
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Trans. & Env. Protection
Current Phase
Design
Design Start
2008-06-10T00:00:00.000
Budget Forecast
35397000.00
Latest Budget Changes
-11702000.00
Total Budget Changes
43926000.00
Forecast Completion
2030-06-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
226
East 174th Street over Sheridan Expressway - Amtrak
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 701 • Project Name: East 174th Street over Sheridan Expressway - Amtrak
Date Reported As Of
2018-08-01T00:00:00.000
Pid
701
Project Name
East 174th Street over Sheridan Expressway - Amtrak
Description
Repair the East 174th Street bridge over Sheridan Expressway/ AMTRAK, the Bronx
Category
Bridges
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2018-08-16T00:00:00.000
Budget Forecast
140940000.00
Latest Budget Changes
0.00
Total Budget Changes
5146882.00
Forecast Completion
2026-01-16T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1431
New Ferry Boat Construction
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 94 • Project Name: New Ferry Boat Construction
Date Reported As Of
2018-08-01T00:00:00.000
Pid
94
Project Name
New Ferry Boat Construction
Description
Replace one Barberi class boat and the John F. Kennedy boat which are approaching the end of their useful lives with new Staten Island ferries. Replacement is needed to continue reliable service.
Category
Ferries
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2014-09-15T00:00:00.000
Budget Forecast
285010000.00
Latest Budget Changes
-59068847.00
Total Budget Changes
-238419180.00
Forecast Completion
2021-02-08T00:00:00.000
Latest Schedule Changes
-20
Total Schedule Changes
549
Shore Road Bridge over Hutchinson River
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 541 • Project Name: Shore Road Bridge over Hutchinson River
Date Reported As Of
2018-08-01T00:00:00.000
Pid
541
Project Name
Shore Road Bridge over Hutchinson River
Description
Replace the Shore Road Bridge over the Hutchinson River with a new bridge.
Category
Bridges, Streets and Roadways
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-06-30T00:00:00.000
Budget Forecast
357738743.00
Latest Budget Changes
0.00
Total Budget Changes
-19049921.84
Forecast Completion
2025-12-17T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1477
Brooklyn Bridge - Approach Arches Rehabilitation
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 584 • Project Name: Brooklyn Bridge - Approach Arches Rehabilitation
Date Reported As Of
2018-08-01T00:00:00.000
Pid
584
Project Name
Brooklyn Bridge - Approach Arches Rehabilitation
Description
Repair approach arches, towers, and ramp substructures of Brooklyn Bridge.
Category
Bridges
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2016-04-13T00:00:00.000
Budget Forecast
325240000.00
Latest Budget Changes
-9075942.00
Total Budget Changes
33135732.10
Forecast Completion
2020-08-30T00:00:00.000
Latest Schedule Changes
-637
Total Schedule Changes
1908
Raise Shorelines Citywide
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 689 • Project Name: Raise Shorelines Citywide
Date Reported As Of
2018-08-01T00:00:00.000
Pid
689
Project Name
Raise Shorelines Citywide
Description
The design and construction of shoreline reconstruction projects necessary to provide Citywide protection from future flooding caused by elevated seal elvels.
Category
Industrial Development
Borough
Citywide
Managing Agency
EDC
Client Agency
ORR
Current Phase
Design
Design Start
2017-08-01T00:00:00.000
Budget Forecast
60422401.00
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2022-12-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
639
Catskill Aqueduct Repair and Rehabilitation
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 478 • Project Name: Catskill Aqueduct Repair and Rehabilitation
Date Reported As Of
2018-08-01T00:00:00.000
Pid
478
Project Name
Catskill Aqueduct Repair and Rehabilitation
Description
Project to ensure the reliability of the 74 mile upper Catskill Aqueduct, including replacement of mechanical components, leak mitigation, and biofilm removal/condition assessment.
Category
Water Supply
Borough
Citywide
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2015-06-19T00:00:00.000
Budget Forecast
202601657.00
Latest Budget Changes
-41920214.00
Total Budget Changes
9642889.68
Forecast Completion
2021-07-17T00:00:00.000
Latest Schedule Changes
504
Total Schedule Changes
1517
North River Wastewater Treatment Plant Cogeneration and Electrification
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 423 • Project Name: North River Wastewater Treatment Plant Cogeneration and Electrification
Date Reported As Of
2018-08-01T00:00:00.000
Pid
423
Project Name
North River Wastewater Treatment Plant Cogeneration and Electrification
Description
This project will remove the 10 existing pump and blower engines and add electric motors for the main sewage pumps, a new cogeneration facility consisting of 5 new dual fuel engines, electrical service upgrades and flood protection.
Category
Wastewater Treatment
Borough
New York
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2013-07-01T00:00:00.000
Budget Forecast
218296715.00
Latest Budget Changes
-15131991.00
Total Budget Changes
134242052.88
Forecast Completion
2022-05-22T00:00:00.000
Latest Schedule Changes
442
Total Schedule Changes
1712
Storm Mitigation Loan Program at Hunts Point
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 672 • Project Name: Storm Mitigation Loan Program at Hunts Point
Date Reported As Of
2018-08-01T00:00:00.000
Pid
672
Project Name
Storm Mitigation Loan Program at Hunts Point
Description
SMLP portion for Hunts Point WWTP as part of the New York City Wastewater Resiliency Program.
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2018-04-16T00:00:00.000
Budget Forecast
36635629.33
Latest Budget Changes
-5037051.90
Total Budget Changes
20080597.79
Forecast Completion
2020-09-09T00:00:00.000
Latest Schedule Changes
-73
Total Schedule Changes
1091
Grand Concourse Metro North Railroad Bridge Construction
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 120 • Project Name: Grand Concourse Metro North Railroad Bridge Construction
Date Reported As Of
2018-08-01T00:00:00.000
Pid
120
Project Name
Grand Concourse Metro North Railroad Bridge Construction
Description
Repair the existing bridge and separate the NYCDOT and NYCT components. Includes new steel plate girders, concrete deck, pedestals, backwalls, sidewalks, and bridge railing.
Category
Bridges
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2000-02-14T00:00:00.000
Budget Forecast
72673351.00
Latest Budget Changes
5960110.00
Total Budget Changes
22682117.00
Forecast Completion
2021-10-16T00:00:00.000
Latest Schedule Changes
123
Total Schedule Changes
836
Storm Mitigation Loan Program at Bowery Bay
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 671 • Project Name: Storm Mitigation Loan Program at Bowery Bay
Date Reported As Of
2018-08-01T00:00:00.000
Pid
671
Project Name
Storm Mitigation Loan Program at Bowery Bay
Description
SMLP portion for Bowery Bay WWTP as part of the New York City Wastewater Resiliency Program.
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2018-03-29T00:00:00.000
Budget Forecast
37570670.04
Latest Budget Changes
-20364788.78
Total Budget Changes
-19623216.41
Forecast Completion
2021-03-08T00:00:00.000
Latest Schedule Changes
109
Total Schedule Changes
1026
Primary Treatment Improvement at Wards Island WWTP
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 452 • Project Name: Primary Treatment Improvement at Wards Island WWTP
Date Reported As Of
2018-08-01T00:00:00.000
Pid
452
Project Name
Primary Treatment Improvement at Wards Island WWTP
Description
Replacement of internal mechanisms, concrete repairs, effluent weirs, scum troughs, grease pit collection system, electrical upgrades, HVAC upgrades, evaluation and improvement of cross collector drainage in 10 PST.
Category
Wastewater Treatment
Borough
Manhattan
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2017-06-30T00:00:00.000
Budget Forecast
46500000.00
Latest Budget Changes
-33000000.00
Total Budget Changes
99651290.98
Forecast Completion
2021-02-26T00:00:00.000
Latest Schedule Changes
148
Total Schedule Changes
2142
Central Park Light Infrastructure
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 586 • Project Name: Central Park Light Infrastructure
Date Reported As Of
2018-08-01T00:00:00.000
Pid
586
Project Name
Central Park Light Infrastructure
Description
Install, remove, and furnish equipment for electrical work associated with traffic signals, lighting, and distribution systems in Central Park, Manhattan.
Category
Parks, Streets and Roadways
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2016-04-29T00:00:00.000
Budget Forecast
42453656.00
Latest Budget Changes
0.00
Total Budget Changes
-3323649.60
Forecast Completion
2019-06-18T00:00:00.000
Latest Schedule Changes
-66
Total Schedule Changes
1535
TLC - NEW OFFICE FACILITY - 24-55 BQE WEST
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 665 • Project Name: TLC - NEW OFFICE FACILITY - 24-55 BQE WEST
Date Reported As Of
2018-08-01T00:00:00.000
Pid
665
Project Name
TLC - NEW OFFICE FACILITY - 24-55 BQE WEST
Description
Design and construction of new adminstration wing to replace existing administration wing, new parking, provide new inspection lane within the inspection facility.
Category
Other Government Facilities
Borough
Queens
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Design
Design Start
2015-09-15T00:00:00.000
Budget Forecast
91942584.00
Latest Budget Changes
832584.00
Total Budget Changes
75370000.00
Forecast Completion
2023-07-02T00:00:00.000
Latest Schedule Changes
214
Total Schedule Changes
1248
Boston Road Bridge Over Hutchinson River Rehabilitation
Date Reported As Of: 2018-08-01T00:00:00.000 • Pid: 539 • Project Name: Boston Road Bridge Over Hutchinson River Rehabilitation
Date Reported As Of
2018-08-01T00:00:00.000
Pid
539
Project Name
Boston Road Bridge Over Hutchinson River Rehabilitation
Description
Rehabilitation of Boston Road Bridge over Hutchinson River, located in the Bornx.