All major infrastructure and information technology projects with a budget of $25 million or more that are currently active (in the design, procurement, or construction phase).
City GovernmentMayor's Office of Operations (OPS)
Dataset n7gv-k5yt
16 fields
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 639 • Project Name: 253 Broadway Landmark's Space Renovations
Date Reported As Of
2018-03-01T00:00:00.000
Pid
639
Project Name
253 Broadway Landmark's Space Renovations
Description
Renovation of 3 floors for new office space for the Landmarks Commission, as well as new public hearing room.
Category
Other Government Facilities
Borough
Manhattan
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Construction
Design Start
2013-01-23T00:00:00.000
Budget Forecast
31529000.00
Latest Budget Changes
0.00
Total Budget Changes
35010000.00
Forecast Completion
2019-04-19T00:00:00.000
Latest Schedule Changes
193
Total Schedule Changes
1696
Bellevue Medical Center Priority Mitigation Projects
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 545 • Project Name: Bellevue Medical Center Priority Mitigation Projects
Date Reported As Of
2018-03-01T00:00:00.000
Pid
545
Project Name
Bellevue Medical Center Priority Mitigation Projects
Description
Priority mitigation projects for the repair/restoration and hazard mitigation for Bellevue Hospital, damaged during Superstorm Sandy
Category
Health and Hospitals
Borough
Manhattan
Managing Agency
EDC
Client Agency
H+H
Current Phase
Construction
Design Start
2014-01-01T00:00:00.000
Budget Forecast
51680421.00
Latest Budget Changes
739046.00
Total Budget Changes
0.00
Forecast Completion
2020-06-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1854
Replacement of the Esopus & Route 28A Railroad Bridges
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 443 • Project Name: Replacement of the Esopus & Route 28A Railroad Bridges
Date Reported As Of
2018-03-01T00:00:00.000
Pid
443
Project Name
Replacement of the Esopus & Route 28A Railroad Bridges
Description
Replacement of the Esopus Creek Bridge & Route 28A Railroad Bridge
Category
Bridges
Borough
Olive
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2016-10-11T00:00:00.000
Budget Forecast
91385531.00
Latest Budget Changes
1113910.66
Total Budget Changes
-50461071.35
Forecast Completion
2024-05-20T00:00:00.000
Latest Schedule Changes
-200
Total Schedule Changes
714
Central Park Light Infrastructure
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 586 • Project Name: Central Park Light Infrastructure
Date Reported As Of
2018-03-01T00:00:00.000
Pid
586
Project Name
Central Park Light Infrastructure
Description
Install, remove, and furnish equipment for electrical work associated with traffic signals, lighting, and distribution systems in Central Park, Manhattan.
Category
Parks, Streets and Roadways
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2016-04-29T00:00:00.000
Budget Forecast
42453656.00
Latest Budget Changes
124530.00
Total Budget Changes
-3323649.60
Forecast Completion
2019-08-23T00:00:00.000
Latest Schedule Changes
66
Total Schedule Changes
1535
Pelham Parkway Bridge Reconstruction over Hutchinson Parkway
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 506 • Project Name: Pelham Parkway Bridge Reconstruction over Hutchinson Parkway
Date Reported As Of
2018-03-01T00:00:00.000
Pid
506
Project Name
Pelham Parkway Bridge Reconstruction over Hutchinson Parkway
Description
Replace the Pelham Parkway bridge over Hutchinson Parkway, Bronx.
Category
Bridges, Streets and Roadways
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-05-30T00:00:00.000
Budget Forecast
56520020.00
Latest Budget Changes
-1000.00
Total Budget Changes
10338071.57
Forecast Completion
2025-08-26T00:00:00.000
Latest Schedule Changes
484
Total Schedule Changes
1934
Storm Sewer Outlet In 224Th St
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 784 • Project Name: Storm Sewer Outlet In 224Th St
Date Reported As Of
2018-03-01T00:00:00.000
Pid
784
Project Name
Storm Sewer Outlet In 224Th St
Description
Storm sewer at 224th St and 149th Ave and along the access road through Idlewild Parks known as Springfield Lane (Spine Farmers Blvd)
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2017-01-04T00:00:00.000
Budget Forecast
1699000.00
Total Budget Changes
155854000.00
Forecast Completion
2022-11-29T00:00:00.000
Total Schedule Changes
1238
Storm & Combined Sewers In 229 Street
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 776 • Project Name: Storm & Combined Sewers In 229 Street
Date Reported As Of
2018-03-01T00:00:00.000
Pid
776
Project Name
Storm & Combined Sewers In 229 Street
Description
High Level Storm and Combined Sewer in 229th Street and 230th Place Between 145th Avenue and 147th Ave. (Spine Springfield/Laurelton Blvd)
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction Procurement
Design Start
2015-04-30T00:00:00.000
Budget Forecast
129607000.00
Total Budget Changes
-9148000.00
Forecast Completion
2021-09-16T00:00:00.000
Total Schedule Changes
652
Carl Schurz Park Promenade over FDR (East 81st to 90th Streets)
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 537 • Project Name: Carl Schurz Park Promenade over FDR (East 81st to 90th Streets)
Date Reported As Of
2018-03-01T00:00:00.000
Pid
537
Project Name
Carl Schurz Park Promenade over FDR (East 81st to 90th Streets)
Description
Replace the Promenade over FDR between East 81st to 90th Streets in Manhattan.
Category
Bridges
Borough
Manhattan
Managing Agency
DOT
Client Agency
DOT, DPR
Current Phase
Design
Design Start
2017-05-30T00:00:00.000
Budget Forecast
348404421.00
Latest Budget Changes
35412421.00
Total Budget Changes
-197139579.00
Forecast Completion
2025-10-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1571
Combined Sewer In 70Th Street, Queens
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 788 • Project Name: Combined Sewer In 70Th Street, Queens
Date Reported As Of
2018-03-01T00:00:00.000
Pid
788
Project Name
Combined Sewer In 70Th Street, Queens
Description
COMBINED SEWER IN 70TH STREET, QUEENS
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2016-08-31T00:00:00.000
Budget Forecast
37957000.00
Total Budget Changes
94201000.00
Forecast Completion
2020-06-11T00:00:00.000
Total Schedule Changes
1155
RECONSTRUCTION OF E 177 STREET/DEVOE AVENUE
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 623 • Project Name: RECONSTRUCTION OF E 177 STREET/DEVOE AVENUE
Date Reported As Of
2018-03-01T00:00:00.000
Pid
623
Project Name
RECONSTRUCTION OF E 177 STREET/DEVOE AVENUE
Description
Reconstruction of E 177th Street /Devoe Ave etc., Bronx
Category
Industrial Development, Streets and Roadways
Borough
Bronx
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2009-09-03T00:00:00.000
Budget Forecast
25482000.00
Latest Budget Changes
0.00
Total Budget Changes
25050000.00
Forecast Completion
2021-08-14T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1839
Coastal Resiliency Area 1 - East 23Rd St. To Montg
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 773 • Project Name: Coastal Resiliency Area 1 - East 23Rd St. To Montg
Date Reported As Of
2018-03-01T00:00:00.000
Pid
773
Project Name
Coastal Resiliency Area 1 - East 23Rd St. To Montg
Description
East Side Coastal Resiliency - East 23rd St. to Montgomery St.
Category
Industrial Development, Parks
Managing Agency
DDC
Client Agency
Parks & Recreation
Current Phase
Design
Design Start
2017-04-01T00:00:00.000
Budget Forecast
510854000.00
Total Budget Changes
-418193636.37
Forecast Completion
2024-05-01T00:00:00.000
Total Schedule Changes
836
Coney Island Hospital CSS Building and Perimeter Flood Protection
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 561 • Project Name: Coney Island Hospital CSS Building and Perimeter Flood Protection
Date Reported As Of
2018-03-01T00:00:00.000
Pid
561
Project Name
Coney Island Hospital CSS Building and Perimeter Flood Protection
Description
Renovation of CIH to advance the City’s resiliency plan, repair damages, and protect the hospital from future disasters.
Category
Health and Hospitals
Borough
Brooklyn
Managing Agency
EDC
Client Agency
H+H
Current Phase
Construction
Design Start
2016-02-01T00:00:00.000
Budget Forecast
665754400.00
Latest Budget Changes
586229.00
Total Budget Changes
30635879.93
Forecast Completion
2023-03-31T00:00:00.000
Latest Schedule Changes
235
Total Schedule Changes
1243
Gilboa Dam Reconstruction, Phase IV
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 406 • Project Name: Gilboa Dam Reconstruction, Phase IV
Date Reported As Of
2018-03-01T00:00:00.000
Pid
406
Project Name
Gilboa Dam Reconstruction, Phase IV
Description
This project will rehabilitate the mechanics and the architecture of the Shandaken Tunnel Intake Chamber, which includes the replacement of gates and general site improvements.
Category
Water Supply
Borough
Upstate
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2008-12-01T00:00:00.000
Budget Forecast
64523224.70
Latest Budget Changes
-1267200.00
Total Budget Changes
33535991.20
Forecast Completion
2021-10-06T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1684
TLC - NEW OFFICE FACILITY - 24-55 BQE WEST
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 665 • Project Name: TLC - NEW OFFICE FACILITY - 24-55 BQE WEST
Date Reported As Of
2018-03-01T00:00:00.000
Pid
665
Project Name
TLC - NEW OFFICE FACILITY - 24-55 BQE WEST
Description
Design and construction of new adminstration wing to replace existing administration wing, new parking, provide new inspection lane within the inspection facility.
Category
Other Government Facilities
Borough
Queens
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Design
Design Start
2015-09-15T00:00:00.000
Budget Forecast
91110000.00
Latest Budget Changes
13934000.00
Total Budget Changes
75370000.00
Forecast Completion
2022-11-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1248
Brooklyn Sanitation Garage Construction: Community District 3
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 560 • Project Name: Brooklyn Sanitation Garage Construction: Community District 3
Date Reported As Of
2018-03-01T00:00:00.000
Pid
560
Project Name
Brooklyn Sanitation Garage Construction: Community District 3
Description
Construction of new Sanitation garage facility for services to Brooklyn Community District 3 to be located at Warsoff Place in Brooklyn
Category
Sanitation
Borough
Brooklyn
Managing Agency
DSNY
Client Agency
DSNY
Current Phase
Design
Design Start
2005-07-25T00:00:00.000
Budget Forecast
220172543.00
Latest Budget Changes
41411915.00
Total Budget Changes
25603365.00
Forecast Completion
2022-12-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
790
Ped Safety Upgrades on Atlantic Avenue, Phase 2
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 519 • Project Name: Ped Safety Upgrades on Atlantic Avenue, Phase 2
Date Reported As Of
2018-03-01T00:00:00.000
Pid
519
Project Name
Ped Safety Upgrades on Atlantic Avenue, Phase 2
Description
Safety Improvements on Atlantic Ave from Conduit Avenue to Rockaway Blvd, Phase 2, Brooklyn
The priority mitigation projects at Coler include key critical mitigation projects to improve the resiliency of the campus.
Category
Health and Hospitals
Borough
Manhattan
Managing Agency
EDC
Client Agency
H+H
Current Phase
Construction
Design Start
2014-09-01T00:00:00.000
Budget Forecast
21980342.26
Latest Budget Changes
956781.00
Total Budget Changes
0.00
Forecast Completion
2018-12-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2085
Edgewood Triangle Roadway Reconstruction
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 204 • Project Name: Edgewood Triangle Roadway Reconstruction
Date Reported As Of
2018-03-01T00:00:00.000
Pid
204
Project Name
Edgewood Triangle Roadway Reconstruction
Description
Reconstruct roadway and extend storm and sanitary sewers in portions of Brookville Boulevard, Edgewood Street, 147th Avenue, and adjacent streets west of 241st Street.
Category
Streets and Roadways
Borough
Queens
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2013-02-13T00:00:00.000
Budget Forecast
15818000.00
Latest Budget Changes
-17378000.00
Total Budget Changes
106503000.00
Forecast Completion
2022-09-06T00:00:00.000
Latest Schedule Changes
365
Total Schedule Changes
3597
Sewer When & Where Contract In S.E. Queens
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 793 • Project Name: Sewer When & Where Contract In S.E. Queens
Date Reported As Of
2018-03-01T00:00:00.000
Pid
793
Project Name
Sewer When & Where Contract In S.E. Queens
Description
Construction of Storm and Sanitary sewers at various locations in Queens Priority Grid 13 & 18
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2018-02-15T00:00:00.000
Budget Forecast
29400000.00
Total Budget Changes
7404000.00
Forecast Completion
2021-02-12T00:00:00.000
Total Schedule Changes
1834
Gilboa Dam Reconstruction, Phase III
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 405 • Project Name: Gilboa Dam Reconstruction, Phase III
Date Reported As Of
2018-03-01T00:00:00.000
Pid
405
Project Name
Gilboa Dam Reconstruction, Phase III
Description
Gilboa Dam Reconstruction Project includes construction of a new low level outlet (LLO) consisting of 2,000 feet of tunneling, an access shaft, oulet structure and gate valve controls.
Category
Water Supply
Borough
Upstate
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2004-03-18T00:00:00.000
Budget Forecast
205460484.72
Latest Budget Changes
59108.62
Total Budget Changes
10376533.49
Forecast Completion
2020-10-12T00:00:00.000
Latest Schedule Changes
77
Total Schedule Changes
1113
New 40th Precinct
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 634 • Project Name: New 40th Precinct
Date Reported As Of
2018-03-01T00:00:00.000
Pid
634
Project Name
New 40th Precinct
Description
New 40th Precinct at 567 E 149 Street, Bronx, NY 10455. Design and build of a 43,000 SF on an existing City-owned property.
Category
Public Safety and Criminal Justice
Borough
Bronx
Managing Agency
DDC
Client Agency
Police
Current Phase
Construction Procurement
Design Start
2014-09-30T00:00:00.000
Budget Forecast
75845699.75
Latest Budget Changes
4845699.75
Total Budget Changes
26020000.00
Forecast Completion
2021-06-12T00:00:00.000
Latest Schedule Changes
-13
Total Schedule Changes
711
Staten Island 1 & 3 Garage Construction & Rehab
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 769 • Project Name: Staten Island 1 & 3 Garage Construction & Rehab
Date Reported As Of
2018-03-01T00:00:00.000
Pid
769
Project Name
Staten Island 1 & 3 Garage Construction & Rehab
Description
The Department of Sanitation of the City of New York (DSNY) is planning to develop a Staten Island Districts 1 and 3 campus that will include a new garage serving both districts and renovation of the existing Borough Repair Shop.
Category
Sanitation
Borough
Staten Island
Managing Agency
DDC
Client Agency
Sanitation
Current Phase
Design
Design Start
2017-07-14T00:00:00.000
Budget Forecast
138144000.00
Total Budget Changes
68555000.00
Forecast Completion
2023-02-13T00:00:00.000
Total Schedule Changes
406
West 79th Street over Amtrak and Rotunda Complex Rehabilitation
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 801 • Project Name: West 79th Street over Amtrak and Rotunda Complex Rehabilitation
Date Reported As Of
2018-03-01T00:00:00.000
Pid
801
Project Name
West 79th Street over Amtrak and Rotunda Complex Rehabilitation
Description
Rehabilitation of the W. 79th St Bridge over Amtrak and Rotunda Complex
Category
Bridges, Streets and Roadways
Borough
Manhattan
Managing Agency
DOT
Client Agency
DOT, DPR
Current Phase
Design
Design Start
2000-07-10T00:00:00.000
Budget Forecast
250905250.00
Total Budget Changes
-51088528.00
Forecast Completion
2023-09-20T00:00:00.000
Total Schedule Changes
604
Bainbridge Avenue Trunk Water Main
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 454 • Project Name: Bainbridge Avenue Trunk Water Main
Date Reported As Of
2018-03-01T00:00:00.000
Pid
454
Project Name
Bainbridge Avenue Trunk Water Main
Description
Replacement Trunk Water Main in Bainbridge Ave, Bronx
Category
Water Supply
Borough
Bronx
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2014-03-17T00:00:00.000
Budget Forecast
47346000.00
Latest Budget Changes
0.00
Total Budget Changes
25547000.00
Forecast Completion
2019-06-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1687
5th Avenue Bridge Reconstruction over LIRR and Sea Beach, Brooklyn
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 504 • Project Name: 5th Avenue Bridge Reconstruction over LIRR and Sea Beach, Brooklyn
Date Reported As Of
2018-03-01T00:00:00.000
Pid
504
Project Name
5th Avenue Bridge Reconstruction over LIRR and Sea Beach, Brooklyn
Description
Replace the 5th Avenue Bridge over LIRR & Sea Beach, Brooklyn.
Category
Bridges
Borough
Brooklyn
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-11-30T00:00:00.000
Budget Forecast
47279974.00
Latest Budget Changes
79087.00
Total Budget Changes
36577693.00
Forecast Completion
2024-11-04T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
969
Pelham Parkway Roadway Reconstruction, Phase 2
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 180 • Project Name: Pelham Parkway Roadway Reconstruction, Phase 2
Date Reported As Of
2018-03-01T00:00:00.000
Pid
180
Project Name
Pelham Parkway Roadway Reconstruction, Phase 2
Description
Reconstruction of Pelham Parkway from the Bronx River Parkway to the Hutchinson River Parkway, including the north service road from Bronx Park East to Eastchester Road.
Category
Streets and Roadways
Borough
Bronx
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction
Design Start
2002-02-20T00:00:00.000
Budget Forecast
139615000.00
Latest Budget Changes
0.00
Total Budget Changes
125164000.00
Forecast Completion
2021-07-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2869
Water Main Replacement In 222 Street, Queens
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 768 • Project Name: Water Main Replacement In 222 Street, Queens
Date Reported As Of
2018-03-01T00:00:00.000
Pid
768
Project Name
Water Main Replacement In 222 Street, Queens
Description
Water Main replacement in 222th Street
Category
Water Supply
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2018-04-02T00:00:00.000
Budget Forecast
34476000.00
Total Budget Changes
7195000.00
Forecast Completion
2022-01-18T00:00:00.000
Total Schedule Changes
2236
Brooklyn Civil Court move to 210 Joralemon St
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 509 • Project Name: Brooklyn Civil Court move to 210 Joralemon St
Date Reported As Of
2018-03-01T00:00:00.000
Pid
509
Project Name
Brooklyn Civil Court move to 210 Joralemon St
Description
Relocation of Brooklyn Civil and Housing Court to 210 Joralemon St
Category
Public Safety and Criminal Justice
Borough
Brooklyn
Managing Agency
DCAS
Client Agency
DCAS
Current Phase
Design
Design Start
2016-07-27T00:00:00.000
Budget Forecast
247831621.00
Latest Budget Changes
14247076.69
Total Budget Changes
200931011.96
Forecast Completion
2022-01-30T00:00:00.000
Latest Schedule Changes
122
Total Schedule Changes
1977
Hannah Street Pumping Station Construction
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 364 • Project Name: Hannah Street Pumping Station Construction
Date Reported As Of
2018-03-01T00:00:00.000
Pid
364
Project Name
Hannah Street Pumping Station Construction
Description
This project will reconstruct the Hannah St. Pumping Station, the largest City-owned wastewater collection and pumping station on Staten Island. Built in 1977, the facility has numerous deficiencies, needing a comprehensive upgrade.
Category
Wastewater Treatment
Borough
Staten Island
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2012-10-01T00:00:00.000
Budget Forecast
67253660.00
Latest Budget Changes
1333660.00
Total Budget Changes
67909196.80
Forecast Completion
2020-11-01T00:00:00.000
Latest Schedule Changes
116
Total Schedule Changes
3238
Metropolitan Hospital Perimeter Flood Protection
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 562 • Project Name: Metropolitan Hospital Perimeter Flood Protection
Date Reported As Of
2018-03-01T00:00:00.000
Pid
562
Project Name
Metropolitan Hospital Perimeter Flood Protection
Description
Flood mitigation system to protect Metropolitan's campus from future flooding due and sea level rise
Category
Industrial Development
Borough
Manhattan
Managing Agency
EDC
Client Agency
H+H
Current Phase
Design
Design Start
2016-12-01T00:00:00.000
Budget Forecast
82232241.00
Latest Budget Changes
1072860.00
Total Budget Changes
27046705.00
Forecast Completion
2021-10-30T00:00:00.000
Latest Schedule Changes
334
Total Schedule Changes
1452
New 116Th Pct
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 762 • Project Name: New 116Th Pct
Date Reported As Of
2018-03-01T00:00:00.000
Pid
762
Project Name
New 116Th Pct
Description
New 116Th Precinct at 244-04 North Conduit Avenue, Queens, NY 11442. Design and build of a 45,500 SF building on existing City owned property.
Category
Public Safety and Criminal Justice
Managing Agency
DDC
Client Agency
Police
Current Phase
Design
Design Start
2017-09-14T00:00:00.000
Budget Forecast
76911099.14
Total Budget Changes
33852900.86
Forecast Completion
2022-04-05T00:00:00.000
Total Schedule Changes
727
49th Avenue Bridge Replacement
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 131 • Project Name: 49th Avenue Bridge Replacement
Date Reported As Of
2018-03-01T00:00:00.000
Pid
131
Project Name
49th Avenue Bridge Replacement
Description
Replace the 49th Avenue bridge over Long Island Railroad and Amtrak in Hunters Point, Queens.
Category
Bridges, Streets and Roadways
Borough
Queens
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-08-15T00:00:00.000
Budget Forecast
82095000.00
Latest Budget Changes
843000.00
Total Budget Changes
32902419.00
Forecast Completion
2023-05-08T00:00:00.000
Latest Schedule Changes
95
Total Schedule Changes
1449
Bronx Sanitation Garage Construction: Community District 9, 10, 11
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 573 • Project Name: Bronx Sanitation Garage Construction: Community District 9, 10, 11
Date Reported As Of
2018-03-01T00:00:00.000
Pid
573
Project Name
Bronx Sanitation Garage Construction: Community District 9, 10, 11
Description
Construction of new Sanitation garage facility to serve Bronx community districts 9, 10, and 11 to be located at Zerega Avenue in the Bronx
Category
Sanitation
Borough
Bronx
Managing Agency
DSNY
Client Agency
DSNY
Current Phase
Design
Design Start
2017-08-01T00:00:00.000
Budget Forecast
291383225.00
Latest Budget Changes
0.00
Total Budget Changes
268983862.56
Forecast Completion
2026-06-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1919
East 180th Street over Metro North Railroad (Harrison Line)
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 811 • Project Name: East 180th Street over Metro North Railroad (Harrison Line)
Date Reported As Of
2018-03-01T00:00:00.000
Pid
811
Project Name
East 180th Street over Metro North Railroad (Harrison Line)
Description
Rehabilitation of East 180th Street Bridge over Metro North Railroad, the Bronx
Category
Bridges
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-02-06T00:00:00.000
Budget Forecast
30038945.00
Total Budget Changes
4194366.00
Forecast Completion
2021-12-04T00:00:00.000
Total Schedule Changes
664
Construction Of Sanitary Sewers, Storm Sewers (Bm
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 760 • Project Name: Construction Of Sanitary Sewers, Storm Sewers (Bm
Date Reported As Of
2018-03-01T00:00:00.000
Pid
760
Project Name
Construction Of Sanitary Sewers, Storm Sewers (Bm
Description
Construction of storm sewers, sanitary sewers, water mains and Best Management Practice (BMP) NC-16 in Mason Avenue area
Category
Sewers
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2016-08-29T00:00:00.000
Budget Forecast
32709000.00
Total Budget Changes
37691000.00
Forecast Completion
2022-04-14T00:00:00.000
Total Schedule Changes
595
Belt System - Cross Island over 115th Avenue/Dutch Broadway
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 558 • Project Name: Belt System - Cross Island over 115th Avenue/Dutch Broadway
Date Reported As Of
2018-03-01T00:00:00.000
Pid
558
Project Name
Belt System - Cross Island over 115th Avenue/Dutch Broadway
Description
Repair the Cross Island bridge over 115th Avenue/Dutch Broadway, Queens.
Category
Bridges
Borough
Queens
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-10-03T00:00:00.000
Budget Forecast
24984000.00
Latest Budget Changes
0.00
Total Budget Changes
17528706.00
Forecast Completion
2023-09-08T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1845
4Th Ave. Safety Improvements Phase II-Vision Zero
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 833 • Project Name: 4Th Ave. Safety Improvements Phase II-Vision Zero
Date Reported As Of
2018-03-01T00:00:00.000
Pid
833
Project Name
4Th Ave. Safety Improvements Phase II-Vision Zero
Description
The scope includes expanding and raising the existing medians (currently in temporary materials) and includes sidewalk extensions, street trees (where feasible), benches, and wayfinding.
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2016-07-14T00:00:00.000
Budget Forecast
74377000.00
Total Budget Changes
-11525000.00
Forecast Completion
2021-06-07T00:00:00.000
Total Schedule Changes
1106
Upgrades At Brooklyn Animal Shelter
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 750 • Project Name: Upgrades At Brooklyn Animal Shelter
Date Reported As Of
2018-03-01T00:00:00.000
Pid
750
Project Name
Upgrades At Brooklyn Animal Shelter
Description
Brooklyn Animal Care Center
Category
Other Government Facilities
Managing Agency
DDC
Client Agency
Health
Current Phase
Design
Design Start
2016-07-20T00:00:00.000
Budget Forecast
25844000.00
Total Budget Changes
21288000.00
Forecast Completion
2022-04-15T00:00:00.000
Total Schedule Changes
1355
Jerome Reservoir and Aqueduct Rehabilitation
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 448 • Project Name: Jerome Reservoir and Aqueduct Rehabilitation
Date Reported As Of
2018-03-01T00:00:00.000
Pid
448
Project Name
Jerome Reservoir and Aqueduct Rehabilitation
Description
Improvements to: fencing, vegetation, roadway, drainage, ext. above-ground retaining walls. Including repair of dam inlet archway & wingwall, re-pointing of stones & reinforcement of east reservoir wall, & leakage/seepage protection within OCA.
Category
Water Supply
Borough
Bronx
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2016-02-24T00:00:00.000
Budget Forecast
49537920.20
Latest Budget Changes
8639413.24
Total Budget Changes
-833277.14
Forecast Completion
2021-05-14T00:00:00.000
Latest Schedule Changes
-79
Total Schedule Changes
2363
Oakwood Beach WWTP Headworks Improvements
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 450 • Project Name: Oakwood Beach WWTP Headworks Improvements
Date Reported As Of
2018-03-01T00:00:00.000
Pid
450
Project Name
Oakwood Beach WWTP Headworks Improvements
Description
Replacement of six bar screens, grit bin vibrator, six ring flushing pumps, six main sewage pumps and assoc. piping/valves and motor control center, replacement of four exhaust fans, gas and oxygen detectors and a 15 KVA transformer
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 749 • Project Name: Porpoise Bridge In Flushing Meadows-Corona Park
Date Reported As Of
2018-03-01T00:00:00.000
Pid
749
Project Name
Porpoise Bridge In Flushing Meadows-Corona Park
Description
PORPOISE BRIDGE IN FLUSHING MEADOWS-CORONA PARK
Category
Bridges
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2017-09-18T00:00:00.000
Budget Forecast
64905000.00
Total Budget Changes
82000.00
Forecast Completion
2023-07-29T00:00:00.000
Total Schedule Changes
1110
West Tremont Avenue over Metro North Railroad
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 503 • Project Name: West Tremont Avenue over Metro North Railroad
Date Reported As Of
2018-03-01T00:00:00.000
Pid
503
Project Name
West Tremont Avenue over Metro North Railroad
Description
Repair the West Tremont Avenue bridge over the Metro North line, located in the Bronx.
Category
Bridges
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-05-30T00:00:00.000
Budget Forecast
54138000.00
Latest Budget Changes
0.00
Total Budget Changes
37794543.00
Forecast Completion
2025-01-07T00:00:00.000
Latest Schedule Changes
253
Total Schedule Changes
1253
Croton Above Ground Structure And Landscaping
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 747 • Project Name: Croton Above Ground Structure And Landscaping
Date Reported As Of
2018-03-01T00:00:00.000
Pid
747
Project Name
Croton Above Ground Structure And Landscaping
Description
Croton Above Ground Structure And Water Management Systems
Category
Industrial Development
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction Procurement
Design Start
2012-05-23T00:00:00.000
Budget Forecast
58786000.00
Total Budget Changes
75117000.00
Forecast Completion
2021-07-01T00:00:00.000
Total Schedule Changes
897
Brooklyn Supreme Court Fire Alarm System Upgrade
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 510 • Project Name: Brooklyn Supreme Court Fire Alarm System Upgrade
Date Reported As Of
2018-03-01T00:00:00.000
Pid
510
Project Name
Brooklyn Supreme Court Fire Alarm System Upgrade
Description
New Fire Alarm and Sprinkler System at 360 Adams Street Kings County Supreme Courhouse
Category
Public Safety and Criminal Justice
Borough
Brooklyn
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Design
Design Start
2017-03-31T00:00:00.000
Budget Forecast
57503747.00
Latest Budget Changes
17880515.00
Total Budget Changes
47003000.00
Forecast Completion
2022-04-12T00:00:00.000
Latest Schedule Changes
-262
Total Schedule Changes
1533
Riverside Drive/West 158th Street Bridge Rehabilitation
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 113 • Project Name: Riverside Drive/West 158th Street Bridge Rehabilitation
Date Reported As Of
2018-03-01T00:00:00.000
Pid
113
Project Name
Riverside Drive/West 158th Street Bridge Rehabilitation
Description
Replace deck of the Riverside Drive viaduct/ bridge over West 158th Street.
Category
Bridges, Streets and Roadways
Borough
Manhattan
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2014-10-22T00:00:00.000
Budget Forecast
159357469.00
Latest Budget Changes
-3476938.00
Total Budget Changes
96922794.00
Forecast Completion
2021-12-16T00:00:00.000
Latest Schedule Changes
14
Total Schedule Changes
2152
Bruckner Expressway Westchester Creek Bridge Reconstruction
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 97 • Project Name: Bruckner Expressway Westchester Creek Bridge Reconstruction
Date Reported As Of
2018-03-01T00:00:00.000
Pid
97
Project Name
Bruckner Expressway Westchester Creek Bridge Reconstruction
Description
Replace the existing bridge with a new, wider double-leaf bascule bridge in the Bronx.
Category
Bridges, Streets and Roadways
Borough
Bronx
Managing Agency
DOT
Client Agency
DEP, DOT
Current Phase
Construction
Design Start
2012-07-23T00:00:00.000
Budget Forecast
296672102.00
Latest Budget Changes
-27073400.00
Total Budget Changes
142277136.00
Forecast Completion
2021-06-30T00:00:00.000
Latest Schedule Changes
-14
Total Schedule Changes
2086
Dumbo and Vinegar Hill Area Roadway Reconstruction and Renovation
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 193 • Project Name: Dumbo and Vinegar Hill Area Roadway Reconstruction and Renovation
Date Reported As Of
2018-03-01T00:00:00.000
Pid
193
Project Name
Dumbo and Vinegar Hill Area Roadway Reconstruction and Renovation
Description
Reconstruction and restoration of Belgian block roadways in the DUMBO and Vinegar Hill communities concurrent with installation of new water main, combined sewers and storm sewers, plus construction of the Pearl Street Triangle Plaza.
Category
Streets and Roadways
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction Procurement
Design Start
2012-06-07T00:00:00.000
Budget Forecast
60780000.00
Latest Budget Changes
0.00
Total Budget Changes
96724000.00
Forecast Completion
2019-09-13T00:00:00.000
Latest Schedule Changes
141
Total Schedule Changes
3253
Reconstruction Of Arthur Kill Road, Phase I
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 741 • Project Name: Reconstruction Of Arthur Kill Road, Phase I
Date Reported As Of
2018-03-01T00:00:00.000
Pid
741
Project Name
Reconstruction Of Arthur Kill Road, Phase I
Description
Reconstruction of Arthur Kill Road From Clark Avenue to Richmond Avenue including widening of roadway
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2016-12-16T00:00:00.000
Budget Forecast
37796000.00
Total Budget Changes
22503000.00
Forecast Completion
2022-06-30T00:00:00.000
Total Schedule Changes
1415
Rondout-West Branch Bypass Tunnel Construction Project 2
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 409 • Project Name: Rondout-West Branch Bypass Tunnel Construction Project 2
Date Reported As Of
2018-03-01T00:00:00.000
Pid
409
Project Name
Rondout-West Branch Bypass Tunnel Construction Project 2
Description
To address existing leaks in the Delaware Aqueduct, a 3-mile bypass tunnel will be constructed near the town of Roseton and the existing tunnel will be repaired near the town of Wawarsing.