Capital Projects

All major infrastructure and information technology projects with a budget of $25 million or more that are currently active (in the design, procurement, or construction phase).

City Government Mayor's Office of Operations (OPS) Dataset n7gv-k5yt 16 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
Lower Concourse Initiative
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 575 • Project Name: Lower Concourse Initiative
Date Reported As Of
2018-03-01T00:00:00.000
Pid
575
Project Name
Lower Concourse Initiative
Description
The Project will improve the roadways and pedestrian facilities. The Project will consist of roadway reconstruction within Exterior Street between East 138th Street and East 150th Street.
Category
Industrial Development
Borough
Bronx
Managing Agency
EDC
Client Agency
EDC
Current Phase
Design
Design Start
2017-04-01T00:00:00.000
Budget Forecast
84520367.00
Latest Budget Changes
0.00
Total Budget Changes
-5100000.00
Forecast Completion
2021-09-01T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
730
Electronic Medical Records Upgrade
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 403 • Project Name: Electronic Medical Records Upgrade
Date Reported As Of
2018-03-01T00:00:00.000
Pid
403
Project Name
Electronic Medical Records Upgrade
Description
The EPIC - EMR Program: Electronic Medical Records (EMR) System - a single enterprise-wide EMR to meet the needs of HHC's expansive size and improve patient care will replace the legacy EMR - QuadraMed, which is over 25 years old.
Category
Health and Hospitals, IT
Borough
Citywide
Managing Agency
HHC
Client Agency
H+H
Current Phase
IT
Budget Forecast
764063231.00
Latest Budget Changes
0.00
Total Budget Changes
15184947.00
Forecast Completion
2020-06-30T00:00:00.000
Latest Schedule Changes
-184
Total Schedule Changes
2032
Concourse Village Avenue over Metro North
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 587 • Project Name: Concourse Village Avenue over Metro North
Date Reported As Of
2018-03-01T00:00:00.000
Pid
587
Project Name
Concourse Village Avenue over Metro North
Description
Replace the Concourse Village Avenue bridge over Metro North, Bronx
Category
Bridges
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-09-19T00:00:00.000
Budget Forecast
50068796.00
Latest Budget Changes
-15487.00
Total Budget Changes
-186092.37
Forecast Completion
2024-08-20T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1865
Madison Avenue Bridge Reconstruction
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 114 • Project Name: Madison Avenue Bridge Reconstruction
Date Reported As Of
2018-03-01T00:00:00.000
Pid
114
Project Name
Madison Avenue Bridge Reconstruction
Description
Replace the electrical and mechanical systems of the Madison Avenue Bridge.
Category
Bridges
Borough
Manhattan, Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction Procurement
Design Start
2011-02-14T00:00:00.000
Budget Forecast
44742221.00
Latest Budget Changes
48131.00
Total Budget Changes
2036997.00
Forecast Completion
2020-07-11T00:00:00.000
Latest Schedule Changes
-38
Total Schedule Changes
1628
Bergen Avenue Street Reconstruction
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 170 • Project Name: Bergen Avenue Street Reconstruction
Date Reported As Of
2018-03-01T00:00:00.000
Pid
170
Project Name
Bergen Avenue Street Reconstruction
Description
Roadway reconstruction Bergen Avenue and vicinity, includes sections of: Avenues N, T, U, V, W, X and Y; 66th Street and 69th through 75th Streets; Veterans Avenue and Royce Street.
Category
Streets and Roadways
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction Procurement
Design Start
2012-12-03T00:00:00.000
Budget Forecast
88883000.00
Latest Budget Changes
0.00
Total Budget Changes
45837000.00
Forecast Completion
2020-07-30T00:00:00.000
Latest Schedule Changes
-2541
Total Schedule Changes
-388
Revenue Cycle Implementation
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 723 • Project Name: Revenue Cycle Implementation
Date Reported As Of
2018-03-01T00:00:00.000
Pid
723
Project Name
Revenue Cycle Implementation
Description
The Epic Revenue Cycle system will be enterprise-wide and help increase revenue (by proper billing of services provided) in addition to ensuring patient safety and improved patient care, a top priority in workflows.
Category
Health and Hospitals, IT
Borough
Citywide
Managing Agency
HHC
Client Agency
H+H
Current Phase
IT
Budget Forecast
289117990.00
Total Budget Changes
0.00
Forecast Completion
2020-06-30T00:00:00.000
Total Schedule Changes
1279
FDR Rehabilitation, Northbound (East 42nd to 49th Streets)
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 502 • Project Name: FDR Rehabilitation, Northbound (East 42nd to 49th Streets)
Date Reported As Of
2018-03-01T00:00:00.000
Pid
502
Project Name
FDR Rehabilitation, Northbound (East 42nd to 49th Streets)
Description
Repair the northbound FDR from East 42nd to 49th Streets.
Category
Bridges
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2016-08-30T00:00:00.000
Budget Forecast
98115670.00
Latest Budget Changes
0.00
Total Budget Changes
-2802822.00
Forecast Completion
2025-03-31T00:00:00.000
Latest Schedule Changes
-1
Total Schedule Changes
1816
Roma and Hett Avenue Storm and Sanitary Sewer Installation
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 206 • Project Name: Roma and Hett Avenue Storm and Sanitary Sewer Installation
Date Reported As Of
2018-03-01T00:00:00.000
Pid
206
Project Name
Roma and Hett Avenue Storm and Sanitary Sewer Installation
Description
Roadway reconstruction and installation of new storm sewers and the replacement of sanitary sewers and water mains in the Midland Beach section, Staten Island.
Category
Sewers
Borough
Staten Island
Managing Agency
DDC
Client Agency
Trans. & Env. Protection
Current Phase
Construction Procurement
Design Start
2008-06-19T00:00:00.000
Budget Forecast
62094000.00
Latest Budget Changes
6212000.00
Total Budget Changes
62973000.00
Forecast Completion
2019-12-20T00:00:00.000
Latest Schedule Changes
-7
Total Schedule Changes
-8
Power Distribution at Bowery Bay WWTP
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 522 • Project Name: Power Distribution at Bowery Bay WWTP
Date Reported As Of
2018-03-01T00:00:00.000
Pid
522
Project Name
Power Distribution at Bowery Bay WWTP
Description
Power Distribution at Bowery Bay WWTP.
Category
Wastewater Treatment
Borough
Queens
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction Procurement
Design Start
2015-11-13T00:00:00.000
Budget Forecast
41108688.20
Latest Budget Changes
-5999706.26
Total Budget Changes
24235381.01
Forecast Completion
2021-08-07T00:00:00.000
Latest Schedule Changes
47
Total Schedule Changes
1684
Throgs Neck Pumping Station Rehabilitation and Improvements
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 722 • Project Name: Throgs Neck Pumping Station Rehabilitation and Improvements
Date Reported As Of
2018-03-01T00:00:00.000
Pid
722
Project Name
Throgs Neck Pumping Station Rehabilitation and Improvements
Description
Throgs Neck Pumping Station Rehabilitation and Improvements
Category
Wastewater Treatment
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2018-06-11T00:00:00.000
Budget Forecast
41689486.00
Total Budget Changes
25708336.86
Forecast Completion
2023-03-04T00:00:00.000
Total Schedule Changes
1306
Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Date Reported As Of: 2018-03-01T00:00:00.000 • Pid: 112 • Project Name: Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Date Reported As Of
2018-03-01T00:00:00.000
Pid
112
Project Name
Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Description
Repair abutments, piers, approaches, and steel superstructure located in Pelham Bay, Bronx; replace reinforced concrete deck.
Category
Bridges, Streets and Roadways
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
1995-01-17T00:00:00.000
Budget Forecast
80310944.00
Latest Budget Changes
1690775.00
Total Budget Changes
20945057.00
Forecast Completion
2021-09-13T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1592
Brooklyn Supreme Court Fire Alarm System Upgrade
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 510 • Project Name: Brooklyn Supreme Court Fire Alarm System Upgrade
Date Reported As Of
2017-09-01T00:00:00.000
Pid
510
Project Name
Brooklyn Supreme Court Fire Alarm System Upgrade
Description
New Fire Alarm and Sprinkler System at 360 Adams Street Kings County Supreme Courhouse
Category
Public Safety and Criminal Justice
Borough
Brooklyn
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Design
Design Start
2017-03-31T00:00:00.000
Budget Forecast
39623232.00
Latest Budget Changes
-7417000.00
Total Budget Changes
47003000.00
Forecast Completion
2022-12-30T00:00:00.000
Latest Schedule Changes
59
Total Schedule Changes
1533
Grand Concourse Reconstruction, Phase 4 (Great Streets)
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 476 • Project Name: Grand Concourse Reconstruction, Phase 4 (Great Streets)
Date Reported As Of
2017-09-01T00:00:00.000
Pid
476
Project Name
Grand Concourse Reconstruction, Phase 4 (Great Streets)
Description
Reconstruction of Service Roads and milling and resurfacing of the main roadways on Grand Concourse from E175 Street to E Fordham Road, including median works and ped refuges.
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2016-06-22T00:00:00.000
Budget Forecast
64074000.00
Latest Budget Changes
520000.00
Total Budget Changes
57634000.00
Forecast Completion
2019-11-22T00:00:00.000
Latest Schedule Changes
167
Total Schedule Changes
1448
Brooklyn Bridge - Approach Arches Rehabilitation
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 584 • Project Name: Brooklyn Bridge - Approach Arches Rehabilitation
Date Reported As Of
2017-09-01T00:00:00.000
Pid
584
Project Name
Brooklyn Bridge - Approach Arches Rehabilitation
Description
Repair approach arches, towers, and ramp substructures of Brooklyn Bridge.
Category
Bridges
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2016-04-13T00:00:00.000
Budget Forecast
300871942.00
Latest Budget Changes
625000.10
Total Budget Changes
33135732.10
Forecast Completion
2020-09-24T00:00:00.000
Latest Schedule Changes
664
Total Schedule Changes
1908
Gilboa Dam Reconstruction, Phase III
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 405 • Project Name: Gilboa Dam Reconstruction, Phase III
Date Reported As Of
2017-09-01T00:00:00.000
Pid
405
Project Name
Gilboa Dam Reconstruction, Phase III
Description
Gilboa Dam Reconstruction Project includes construction of a new low level outlet (LLO) consisting of 2,000 feet of tunneling, an access shaft, oulet structure and gate valve controls.
Category
Water Supply
Borough
Upstate
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2004-03-18T00:00:00.000
Budget Forecast
205401376.10
Latest Budget Changes
710839.80
Total Budget Changes
10376533.49
Forecast Completion
2020-07-27T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1113
Riverside Drive/West 158th Street Bridge Rehabilitation
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 113 • Project Name: Riverside Drive/West 158th Street Bridge Rehabilitation
Date Reported As Of
2017-09-01T00:00:00.000
Pid
113
Project Name
Riverside Drive/West 158th Street Bridge Rehabilitation
Description
Replace deck of the Riverside Drive viaduct/ bridge over West 158th Street.
Category
Bridges, Streets and Roadways
Borough
Manhattan
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2014-10-22T00:00:00.000
Budget Forecast
162834407.00
Latest Budget Changes
17170804.32
Total Budget Changes
96922794.00
Forecast Completion
2021-12-02T00:00:00.000
Latest Schedule Changes
-15
Total Schedule Changes
2152
West 59th Street Marine Transfer Station Construction, Phase 2
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 347 • Project Name: West 59th Street Marine Transfer Station Construction, Phase 2
Date Reported As Of
2017-09-01T00:00:00.000
Pid
347
Project Name
West 59th Street Marine Transfer Station Construction, Phase 2
Description
Phase I repairs the inshore platform, replaces scales and control equipment, dredging around the pier, & site work. Phase 2 refurbishes existing pier building incl. pier structure, pile caps, fendering, construction of new emergency generator, etc.
Category
Sanitation
Borough
Manhattan
Managing Agency
DDC
Client Agency
Sanitation
Current Phase
Construction
Design Start
2012-01-17T00:00:00.000
Budget Forecast
88884000.00
Latest Budget Changes
3938000.00
Total Budget Changes
126753576.46
Forecast Completion
2018-11-26T00:00:00.000
Latest Schedule Changes
202
Total Schedule Changes
1949
Coney Island Hospital CSS Building and Perimeter Flood Protection
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 561 • Project Name: Coney Island Hospital CSS Building and Perimeter Flood Protection
Date Reported As Of
2017-09-01T00:00:00.000
Pid
561
Project Name
Coney Island Hospital CSS Building and Perimeter Flood Protection
Description
Renovation of CIH to advance the City’s resiliency plan, repair damages, and protect the hospital from future disasters.
Category
Health and Hospitals
Borough
Brooklyn
Managing Agency
EDC
Client Agency
H+H
Current Phase
Design
Design Start
2016-02-01T00:00:00.000
Budget Forecast
665168171.00
Latest Budget Changes
0.00
Total Budget Changes
30635879.93
Forecast Completion
2022-08-08T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1243
Bronx Sanitation Garage Construction: Community District 9, 10, 11
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 573 • Project Name: Bronx Sanitation Garage Construction: Community District 9, 10, 11
Date Reported As Of
2017-09-01T00:00:00.000
Pid
573
Project Name
Bronx Sanitation Garage Construction: Community District 9, 10, 11
Description
Construction of new Sanitation garage facility to serve Bronx community districts 9, 10, and 11 to be located at Zerega Avenue in the Bronx
Category
Sanitation
Borough
Bronx
Managing Agency
DSNY
Client Agency
DSNY
Current Phase
Design
Design Start
2017-08-01T00:00:00.000
Budget Forecast
291383225.00
Latest Budget Changes
-1066575.00
Total Budget Changes
268983862.56
Forecast Completion
2026-06-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1919
Roma and Hett Avenue Storm and Sanitary Sewer Installation
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 206 • Project Name: Roma and Hett Avenue Storm and Sanitary Sewer Installation
Date Reported As Of
2017-09-01T00:00:00.000
Pid
206
Project Name
Roma and Hett Avenue Storm and Sanitary Sewer Installation
Description
Roadway reconstruction and installation of new storm sewers and the replacement of sanitary sewers and water mains in the Midland Beach section, Staten Island.
Category
Sewers
Borough
Staten Island
Managing Agency
DDC
Client Agency
Trans. & Env. Protection
Current Phase
Design
Design Start
2008-06-19T00:00:00.000
Budget Forecast
55882000.00
Latest Budget Changes
-6192000.00
Total Budget Changes
62973000.00
Forecast Completion
2019-12-27T00:00:00.000
Latest Schedule Changes
61
Total Schedule Changes
-8
STM & SAN SWR, N.B. WHITESTONE EXPWY SERV RD, PH 3
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 652 • Project Name: STM & SAN SWR, N.B. WHITESTONE EXPWY SERV RD, PH 3
Date Reported As Of
2017-09-01T00:00:00.000
Pid
652
Project Name
STM & SAN SWR, N.B. WHITESTONE EXPWY SERV RD, PH 3
Description
Whitestone Area Storm and Sanitary Sewers Phase 3
Category
Sewers
Borough
Queens
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2016-07-15T00:00:00.000
Budget Forecast
59922000.00
Total Budget Changes
15468000.00
Forecast Completion
2022-10-07T00:00:00.000
Total Schedule Changes
684
Gilboa Dam Reconstruction, Phase IV
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 406 • Project Name: Gilboa Dam Reconstruction, Phase IV
Date Reported As Of
2017-09-01T00:00:00.000
Pid
406
Project Name
Gilboa Dam Reconstruction, Phase IV
Description
This project will rehabilitate the mechanics and the architecture of the Shandaken Tunnel Intake Chamber, which includes the replacement of gates and general site improvements.
Category
Water Supply
Borough
Upstate
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2008-12-01T00:00:00.000
Budget Forecast
65790424.70
Latest Budget Changes
583183.70
Total Budget Changes
33535991.20
Forecast Completion
2021-10-06T00:00:00.000
Latest Schedule Changes
278
Total Schedule Changes
1684
Dumbo and Vinegar Hill Area Roadway Reconstruction and Renovation
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 193 • Project Name: Dumbo and Vinegar Hill Area Roadway Reconstruction and Renovation
Date Reported As Of
2017-09-01T00:00:00.000
Pid
193
Project Name
Dumbo and Vinegar Hill Area Roadway Reconstruction and Renovation
Description
Reconstruction and restoration of Belgian block roadways in the DUMBO and Vinegar Hill communities concurrent with installation of new water main, combined sewers and storm sewers, plus construction of the Pearl Street Triangle Plaza.
Category
Streets and Roadways
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2012-06-07T00:00:00.000
Budget Forecast
60780000.00
Latest Budget Changes
41227000.00
Total Budget Changes
96724000.00
Forecast Completion
2019-04-25T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
3253
Belt System - Cross Island over 115th Avenue/Dutch Broadway
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 558 • Project Name: Belt System - Cross Island over 115th Avenue/Dutch Broadway
Date Reported As Of
2017-09-01T00:00:00.000
Pid
558
Project Name
Belt System - Cross Island over 115th Avenue/Dutch Broadway
Description
Repair the Cross Island bridge over 115th Avenue/Dutch Broadway, Queens.
Category
Bridges
Borough
Queens
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-10-03T00:00:00.000
Budget Forecast
24984000.00
Latest Budget Changes
0.00
Total Budget Changes
17528706.00
Forecast Completion
2023-09-08T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1845
Rondout-West Branch Bypass Tunnel Construction Project 2
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 409 • Project Name: Rondout-West Branch Bypass Tunnel Construction Project 2
Date Reported As Of
2017-09-01T00:00:00.000
Pid
409
Project Name
Rondout-West Branch Bypass Tunnel Construction Project 2
Description
To address existing leaks in the Delaware Aqueduct, a 3-mile bypass tunnel will be constructed near the town of Roseton and the existing tunnel will be repaired near the town of Wawarsing.
Category
Water Supply
Borough
Marlboro
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2012-03-23T00:00:00.000
Budget Forecast
887887354.44
Latest Budget Changes
-14322409.13
Total Budget Changes
202552329.25
Forecast Completion
2023-09-26T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
256
New 40th Precinct
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 634 • Project Name: New 40th Precinct
Date Reported As Of
2017-09-01T00:00:00.000
Pid
634
Project Name
New 40th Precinct
Description
New 40th Precinct at 567 E 149 Street, Bronx, NY 10455. Design and build of a 43,000 SF on an existing City-owned property.
Category
Public Safety and Criminal Justice
Borough
Bronx
Managing Agency
DDC
Client Agency
Police
Current Phase
Construction Procurement
Design Start
2014-09-30T00:00:00.000
Budget Forecast
71000000.00
Total Budget Changes
26020000.00
Forecast Completion
2021-06-25T00:00:00.000
Total Schedule Changes
711
Concourse Village Avenue over Metro North
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 587 • Project Name: Concourse Village Avenue over Metro North
Date Reported As Of
2017-09-01T00:00:00.000
Pid
587
Project Name
Concourse Village Avenue over Metro North
Description
Replace the Concourse Village Avenue bridge over Metro North, Bronx
Category
Bridges
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-09-19T00:00:00.000
Budget Forecast
50084283.00
Latest Budget Changes
0.63
Total Budget Changes
-186092.37
Forecast Completion
2024-08-20T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1865
Lower Concourse Initiative
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 575 • Project Name: Lower Concourse Initiative
Date Reported As Of
2017-09-01T00:00:00.000
Pid
575
Project Name
Lower Concourse Initiative
Description
The Project will improve the roadways and pedestrian facilities. The Project will consist of roadway reconstruction within Exterior Street between East 138th Street and East 150th Street.
Category
Industrial Development
Borough
Bronx
Managing Agency
EDC
Client Agency
EDC
Current Phase
Design
Design Start
2017-04-01T00:00:00.000
Budget Forecast
84520367.00
Latest Budget Changes
0.00
Total Budget Changes
-5100000.00
Forecast Completion
2021-09-01T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
730
Bergen Avenue Street Reconstruction
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 170 • Project Name: Bergen Avenue Street Reconstruction
Date Reported As Of
2017-09-01T00:00:00.000
Pid
170
Project Name
Bergen Avenue Street Reconstruction
Description
Roadway reconstruction Bergen Avenue and vicinity, includes sections of: Avenues N, T, U, V, W, X and Y; 66th Street and 69th through 75th Streets; Veterans Avenue and Royce Street.
Category
Streets and Roadways
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2012-12-03T00:00:00.000
Budget Forecast
88883000.00
Latest Budget Changes
415000.00
Total Budget Changes
45837000.00
Forecast Completion
2027-07-15T00:00:00.000
Latest Schedule Changes
153
Total Schedule Changes
-388
Kensico Eastview Connection Tunnel Construction
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 554 • Project Name: Kensico Eastview Connection Tunnel Construction
Date Reported As Of
2017-09-01T00:00:00.000
Pid
554
Project Name
Kensico Eastview Connection Tunnel Construction
Description
The redundant connection between Kensico and Hillview Reservoirs provides resiliency against planned or unplanned tunnel outages to deliver water.
Category
Water Supply
Borough
Valhalla
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2017-06-02T00:00:00.000
Budget Forecast
1245612532.00
Latest Budget Changes
68947854.00
Total Budget Changes
881770648.00
Forecast Completion
2024-10-11T00:00:00.000
Latest Schedule Changes
-210
Total Schedule Changes
3132
Jerome Reservoir and Aqueduct Rehabilitation
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 448 • Project Name: Jerome Reservoir and Aqueduct Rehabilitation
Date Reported As Of
2017-09-01T00:00:00.000
Pid
448
Project Name
Jerome Reservoir and Aqueduct Rehabilitation
Description
Improvements to: fencing, vegetation, roadway, drainage, ext. above-ground retaining walls. Including repair of dam inlet archway & wingwall, re-pointing of stones & reinforcement of east reservoir wall, & leakage/seepage protection within OCA.
Category
Water Supply
Borough
Bronx
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction Procurement
Design Start
2016-02-24T00:00:00.000
Budget Forecast
40898506.96
Latest Budget Changes
6592239.96
Total Budget Changes
-833277.14
Forecast Completion
2021-08-01T00:00:00.000
Latest Schedule Changes
408
Total Schedule Changes
2363
Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 112 • Project Name: Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Date Reported As Of
2017-09-01T00:00:00.000
Pid
112
Project Name
Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Description
Repair abutments, piers, approaches, and steel superstructure located in Pelham Bay, Bronx; replace reinforced concrete deck.
Category
Bridges, Streets and Roadways
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
1995-01-17T00:00:00.000
Budget Forecast
78620169.00
Latest Budget Changes
-1513183.29
Total Budget Changes
20945057.00
Forecast Completion
2021-09-13T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1592
Metropolitan Hospital Perimeter Flood Protection
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 562 • Project Name: Metropolitan Hospital Perimeter Flood Protection
Date Reported As Of
2017-09-01T00:00:00.000
Pid
562
Project Name
Metropolitan Hospital Perimeter Flood Protection
Description
Flood mitigation system to protect Metropolitan's campus from future flooding due and sea level rise
Category
Industrial Development
Borough
Manhattan
Managing Agency
EDC
Client Agency
H+H
Current Phase
Design
Design Start
2016-12-01T00:00:00.000
Budget Forecast
81159381.00
Latest Budget Changes
0.00
Total Budget Changes
27046705.00
Forecast Completion
2020-11-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1452
Electronic Medical Records Upgrade
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 403 • Project Name: Electronic Medical Records Upgrade
Date Reported As Of
2017-09-01T00:00:00.000
Pid
403
Project Name
Electronic Medical Records Upgrade
Description
The EPIC - EMR Program: Electronic Medical Records (EMR) System - a single enterprise-wide EMR to meet the needs of HHC's expansive size and improve patient care will replace the legacy EMR - QuadraMed, which is over 25 years old.
Category
Health and Hospitals, IT
Borough
Citywide
Managing Agency
HHC
Client Agency
H+H
Current Phase
IT
Budget Forecast
764063231.00
Latest Budget Changes
0.00
Total Budget Changes
15184947.00
Forecast Completion
2020-12-31T00:00:00.000
Latest Schedule Changes
755
Total Schedule Changes
2032
Carl Schurz Park Promenade over FDR (East 81st to 90th Streets)
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 537 • Project Name: Carl Schurz Park Promenade over FDR (East 81st to 90th Streets)
Date Reported As Of
2017-09-01T00:00:00.000
Pid
537
Project Name
Carl Schurz Park Promenade over FDR (East 81st to 90th Streets)
Description
Replace the Promenade over FDR between East 81st to 90th Streets in Manhattan.
Category
Bridges
Borough
Manhattan
Managing Agency
DOT
Client Agency
DOT, DPR
Current Phase
Design
Design Start
2017-05-30T00:00:00.000
Budget Forecast
312992000.00
Latest Budget Changes
0.00
Total Budget Changes
-197139579.00
Forecast Completion
2025-10-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1571
RECONSTRUCTION OF E 177 STREET/DEVOE AVENUE
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 623 • Project Name: RECONSTRUCTION OF E 177 STREET/DEVOE AVENUE
Date Reported As Of
2017-09-01T00:00:00.000
Pid
623
Project Name
RECONSTRUCTION OF E 177 STREET/DEVOE AVENUE
Description
Reconstruction of E 177th Street /Devoe Ave etc., Bronx
Category
Industrial Development, Streets and Roadways
Borough
Bronx
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2009-09-03T00:00:00.000
Budget Forecast
25482000.00
Total Budget Changes
25050000.00
Forecast Completion
2021-08-14T00:00:00.000
Total Schedule Changes
1839
BROAD CHANNEL BULKHEADS - PH II
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 617 • Project Name: BROAD CHANNEL BULKHEADS - PH II
Date Reported As Of
2017-09-01T00:00:00.000
Pid
617
Project Name
BROAD CHANNEL BULKHEADS - PH II
Description
Reconstruction of West 14, 15, 16, 17, 18 and 19th Streets from Crossbay Blvd to to Dead End
Category
Industrial Development
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2015-06-01T00:00:00.000
Budget Forecast
30933000.00
Total Budget Changes
61781000.00
Forecast Completion
2024-08-27T00:00:00.000
Total Schedule Changes
-74
Raise Shorelines Citywide
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 689 • Project Name: Raise Shorelines Citywide
Date Reported As Of
2017-09-01T00:00:00.000
Pid
689
Project Name
Raise Shorelines Citywide
Description
The design and construction of shoreline reconstruction projects necessary to provide Citywide protection from future flooding caused by elevated seal elvels.
Category
Industrial Development
Borough
Citywide
Managing Agency
EDC
Client Agency
ORR
Current Phase
Design
Design Start
2017-08-01T00:00:00.000
Budget Forecast
60422401.00
Total Budget Changes
0.00
Forecast Completion
2022-12-31T00:00:00.000
Total Schedule Changes
639
Brooklyn Sanitation Garage Construction: Community District 3
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 560 • Project Name: Brooklyn Sanitation Garage Construction: Community District 3
Date Reported As Of
2017-09-01T00:00:00.000
Pid
560
Project Name
Brooklyn Sanitation Garage Construction: Community District 3
Description
Construction of new Sanitation garage facility for services to Brooklyn Community District 3 to be located at Warsoff Place in Brooklyn
Category
Sanitation
Borough
Brooklyn
Managing Agency
DSNY
Client Agency
DSNY
Current Phase
Design
Design Start
2005-07-25T00:00:00.000
Budget Forecast
178760628.00
Latest Budget Changes
0.00
Total Budget Changes
25603365.00
Forecast Completion
2022-12-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
790
FDR Rehabilitation, Northbound (East 42nd to 49th Streets)
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 502 • Project Name: FDR Rehabilitation, Northbound (East 42nd to 49th Streets)
Date Reported As Of
2017-09-01T00:00:00.000
Pid
502
Project Name
FDR Rehabilitation, Northbound (East 42nd to 49th Streets)
Description
Repair the northbound FDR from East 42nd to 49th Streets.
Category
Bridges
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2016-08-30T00:00:00.000
Budget Forecast
98115670.00
Latest Budget Changes
-625000.39
Total Budget Changes
-2802822.00
Forecast Completion
2025-04-01T00:00:00.000
Latest Schedule Changes
-510
Total Schedule Changes
1816
East 156th Street Bridge over Access to Housing
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 588 • Project Name: East 156th Street Bridge over Access to Housing
Date Reported As Of
2017-09-01T00:00:00.000
Pid
588
Project Name
East 156th Street Bridge over Access to Housing
Description
Replace the East 156th Street bridge over Access to Housing, Bronx.
Category
Bridges, Streets and Roadways
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-10-05T00:00:00.000
Budget Forecast
65500000.00
Latest Budget Changes
0.00
Total Budget Changes
-363846.00
Forecast Completion
2024-09-05T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1720
Pelham Parkway Roadway Reconstruction, Phase 2
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 180 • Project Name: Pelham Parkway Roadway Reconstruction, Phase 2
Date Reported As Of
2017-09-01T00:00:00.000
Pid
180
Project Name
Pelham Parkway Roadway Reconstruction, Phase 2
Description
Reconstruction of Pelham Parkway from the Bronx River Parkway to the Hutchinson River Parkway, including the north service road from Bronx Park East to Eastchester Road.
Category
Streets and Roadways
Borough
Bronx
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction
Design Start
2002-02-20T00:00:00.000
Budget Forecast
139615000.00
Latest Budget Changes
5176000.00
Total Budget Changes
125164000.00
Forecast Completion
2021-07-31T00:00:00.000
Latest Schedule Changes
1141
Total Schedule Changes
2869
CONSTRUCTION OF BMPs NC 6 AND 15 - SI
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 631 • Project Name: CONSTRUCTION OF BMPs NC 6 AND 15 - SI
Date Reported As Of
2017-09-01T00:00:00.000
Pid
631
Project Name
CONSTRUCTION OF BMPs NC 6 AND 15 - SI
Description
Storm and Santary Sewers Installation and Water Main replacement in Bedford Avenue between Mason Avenue and Nugent Street. Project includes Bluebelt Best Management Practice storm sewer outlet.
Category
Industrial Development
Borough
Staten Island
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2017-08-14T00:00:00.000
Budget Forecast
31529000.00
Total Budget Changes
1921000.00
Forecast Completion
2021-11-27T00:00:00.000
Total Schedule Changes
925
Oakwood Beach WWTP Sludge Thickening Improvements
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 449 • Project Name: Oakwood Beach WWTP Sludge Thickening Improvements
Date Reported As Of
2017-09-01T00:00:00.000
Pid
449
Project Name
Oakwood Beach WWTP Sludge Thickening Improvements
Description
Replacement of thickener pumps, piping, sludge pumps, mixing pumps, recirculation pumps, spray water pumps, and heat exchangers. Install Gravity Belt Thickener, GBT pumps, polymer feed system. Rehab of Thickeners, Sludge Box, and Distribution Box.
Category
Wastewater Treatment
Borough
Staten Island
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2016-02-02T00:00:00.000
Budget Forecast
44247976.60
Latest Budget Changes
0.00
Total Budget Changes
57138101.30
Forecast Completion
2023-05-17T00:00:00.000
Latest Schedule Changes
39
Total Schedule Changes
3241
Edgewood Triangle Roadway Reconstruction
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 204 • Project Name: Edgewood Triangle Roadway Reconstruction
Date Reported As Of
2017-09-01T00:00:00.000
Pid
204
Project Name
Edgewood Triangle Roadway Reconstruction
Description
Reconstruct roadway and extend storm and sanitary sewers in portions of Brookville Boulevard, Edgewood Street, 147th Avenue, and adjacent streets west of 241st Street.
Category
Streets and Roadways
Borough
Queens
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2013-02-13T00:00:00.000
Budget Forecast
33196000.00
Latest Budget Changes
195000.00
Total Budget Changes
106503000.00
Forecast Completion
2021-09-06T00:00:00.000
Latest Schedule Changes
365
Total Schedule Changes
3597
Madison Avenue Bridge Reconstruction
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 114 • Project Name: Madison Avenue Bridge Reconstruction
Date Reported As Of
2017-09-01T00:00:00.000
Pid
114
Project Name
Madison Avenue Bridge Reconstruction
Description
Replace the electrical and mechanical systems of the Madison Avenue Bridge.
Category
Bridges
Borough
Manhattan, Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2011-02-14T00:00:00.000
Budget Forecast
44694090.00
Latest Budget Changes
-10468999.93
Total Budget Changes
2036997.00
Forecast Completion
2020-08-18T00:00:00.000
Latest Schedule Changes
412
Total Schedule Changes
1628
New Ferry Boat Construction
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 94 • Project Name: New Ferry Boat Construction
Date Reported As Of
2017-09-01T00:00:00.000
Pid
94
Project Name
New Ferry Boat Construction
Description
Replace one Barberi class boat and the John F. Kennedy boat which are approaching the end of their useful lives with new Staten Island ferries. Replacement is needed to continue reliable service.
Category
Ferries
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2014-09-15T00:00:00.000
Budget Forecast
348374272.00
Latest Budget Changes
-114710.47
Total Budget Changes
-238419180.00
Forecast Completion
2021-02-28T00:00:00.000
Latest Schedule Changes
349
Total Schedule Changes
549
Park Avenue Tunnel (Murray Hill)
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 536 • Project Name: Park Avenue Tunnel (Murray Hill)
Date Reported As Of
2017-09-01T00:00:00.000
Pid
536
Project Name
Park Avenue Tunnel (Murray Hill)
Description
Repair Park Avenue tunnel, located in Midtown, Manhattan.
Category
Bridges
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2006-08-01T00:00:00.000
Budget Forecast
40672495.00
Latest Budget Changes
300030.52
Total Budget Changes
-17773389.61
Forecast Completion
2019-01-25T00:00:00.000
Latest Schedule Changes
10
Total Schedule Changes
1568
Power Distribution at Bowery Bay WWTP
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 522 • Project Name: Power Distribution at Bowery Bay WWTP
Date Reported As Of
2017-09-01T00:00:00.000
Pid
522
Project Name
Power Distribution at Bowery Bay WWTP
Description
Power Distribution at Bowery Bay WWTP.
Category
Wastewater Treatment
Borough
Queens
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction Procurement
Design Start
2015-11-13T00:00:00.000
Budget Forecast
47108394.46
Latest Budget Changes
5550666.26
Total Budget Changes
24235381.01
Forecast Completion
2021-06-21T00:00:00.000
Latest Schedule Changes
59
Total Schedule Changes
1684
Shore Road Bridge over Hutchinson River
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 541 • Project Name: Shore Road Bridge over Hutchinson River
Date Reported As Of
2017-09-01T00:00:00.000
Pid
541
Project Name
Shore Road Bridge over Hutchinson River
Description
Replace the Shore Road Bridge over the Hutchinson River with a new bridge.
Category
Bridges, Streets and Roadways
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-06-30T00:00:00.000
Budget Forecast
358691000.00
Latest Budget Changes
0.16
Total Budget Changes
-19049921.84
Forecast Completion
2025-12-17T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1477