Capital Projects

All major infrastructure and information technology projects with a budget of $25 million or more that are currently active (in the design, procurement, or construction phase).

City Government Mayor's Office of Operations (OPS) Dataset n7gv-k5yt 16 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
Reconstruction of the Port Jervis Wastewater Treatment Plant
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 444 • Project Name: Reconstruction of the Port Jervis Wastewater Treatment Plant
Date Reported As Of
2017-09-01T00:00:00.000
Pid
444
Project Name
Reconstruction of the Port Jervis Wastewater Treatment Plant
Description
Reconstruction of the Port Jervis WWTP as required based on the effluent limits proposed by the Delaware River Basin Commission (DRBC)
Category
Wastewater Treatment
Borough
Port Jervis
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction Procurement
Design Start
2014-06-17T00:00:00.000
Budget Forecast
56470712.00
Latest Budget Changes
0.00
Total Budget Changes
9428438.55
Forecast Completion
2021-11-19T00:00:00.000
Latest Schedule Changes
238
Total Schedule Changes
2445
Sunset Park Infrastructure
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 574 • Project Name: Sunset Park Infrastructure
Date Reported As Of
2017-09-01T00:00:00.000
Pid
574
Project Name
Sunset Park Infrastructure
Description
This project is construction of infrastructure and streetscape improvements in Sunset Park from 37th to 43rd Streets, between the Gowanus Expressway and the waterfront - to activate the waterfront and promote future development.
Category
Industrial Development
Borough
Brooklyn
Managing Agency
EDC
Client Agency
Mayor's Office
Current Phase
Design
Design Start
2016-06-08T00:00:00.000
Budget Forecast
37500000.00
Latest Budget Changes
31633941.69
Total Budget Changes
31633941.69
Forecast Completion
2020-12-25T00:00:00.000
Latest Schedule Changes
68
Total Schedule Changes
1290
Flatbush Avenue Trunk Watermain Replacement
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 370 • Project Name: Flatbush Avenue Trunk Watermain Replacement
Date Reported As Of
2017-09-01T00:00:00.000
Pid
370
Project Name
Flatbush Avenue Trunk Watermain Replacement
Description
Replacement of trunk water main on Flatbush Avenue between Sterling place and 8th Avenue in addition to the distribution water main in 6th Avenue between Union Street and Park Place, and sections of adjoining streets.
Category
Wastewater Treatment
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2014-12-02T00:00:00.000
Budget Forecast
49463000.00
Latest Budget Changes
-1917000.00
Total Budget Changes
39272000.00
Forecast Completion
2021-04-20T00:00:00.000
Latest Schedule Changes
659
Total Schedule Changes
2266
Replacement of The Digester at The Hunts Point WWTP
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 580 • Project Name: Replacement of The Digester at The Hunts Point WWTP
Date Reported As Of
2017-09-01T00:00:00.000
Pid
580
Project Name
Replacement of The Digester at The Hunts Point WWTP
Description
Construction of New Anaerobic Digesters
Category
Wastewater Treatment
Borough
Bronx
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2017-09-21T00:00:00.000
Budget Forecast
320921000.00
Latest Budget Changes
0.00
Total Budget Changes
72852004.14
Forecast Completion
2023-10-27T00:00:00.000
Latest Schedule Changes
465
Total Schedule Changes
1355
253 Broadway Landmark's Space Renovations
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 639 • Project Name: 253 Broadway Landmark's Space Renovations
Date Reported As Of
2017-09-01T00:00:00.000
Pid
639
Project Name
253 Broadway Landmark's Space Renovations
Description
Renovation of 3 floors for new office space for the Landmarks Commission, as well as new public hearing room.
Category
Other Government Facilities
Borough
Manhattan
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Construction
Design Start
2013-01-23T00:00:00.000
Budget Forecast
31529000.00
Total Budget Changes
35010000.00
Forecast Completion
2018-10-08T00:00:00.000
Total Schedule Changes
1696
Catskill Aqueduct Repair and Rehabilitation
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 478 • Project Name: Catskill Aqueduct Repair and Rehabilitation
Date Reported As Of
2017-09-01T00:00:00.000
Pid
478
Project Name
Catskill Aqueduct Repair and Rehabilitation
Description
Project to ensure the reliability of the 74 mile upper Catskill Aqueduct, including replacement of mechanical components, leak mitigation, and biofilm removal/condition assessment.
Category
Water Supply
Borough
Citywide
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction Procurement
Design Start
2015-06-19T00:00:00.000
Budget Forecast
245306804.00
Latest Budget Changes
1667747.00
Total Budget Changes
9642889.68
Forecast Completion
2020-02-21T00:00:00.000
Latest Schedule Changes
64
Total Schedule Changes
1517
RECONSTRUCTION OF QUEENS BLVD - PHASE 2
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 619 • Project Name: RECONSTRUCTION OF QUEENS BLVD - PHASE 2
Date Reported As Of
2017-09-01T00:00:00.000
Pid
619
Project Name
RECONSTRUCTION OF QUEENS BLVD - PHASE 2
Description
Reconstruction of Queens Blvd between 73rd St and Eliot Avenue (Segment 2). Great Streets Vision Zero
Category
Industrial Development
Borough
Queens
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2016-10-20T00:00:00.000
Budget Forecast
71842000.00
Total Budget Changes
14201000.00
Forecast Completion
2023-04-12T00:00:00.000
Total Schedule Changes
2315
Replacement of the Esopus & Route 28A Railroad Bridges
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 443 • Project Name: Replacement of the Esopus & Route 28A Railroad Bridges
Date Reported As Of
2017-09-01T00:00:00.000
Pid
443
Project Name
Replacement of the Esopus & Route 28A Railroad Bridges
Description
Replacement of the Esopus & Route 28A Railroad Bridges
Category
Bridges
Borough
Olive
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2016-10-11T00:00:00.000
Budget Forecast
90271620.34
Latest Budget Changes
-16319073.66
Total Budget Changes
-50461071.35
Forecast Completion
2024-12-06T00:00:00.000
Latest Schedule Changes
-65
Total Schedule Changes
714
Brooklyn Civil Court move to 210 Joralemon St
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 509 • Project Name: Brooklyn Civil Court move to 210 Joralemon St
Date Reported As Of
2017-09-01T00:00:00.000
Pid
509
Project Name
Brooklyn Civil Court move to 210 Joralemon St
Description
Relocation of Brooklyn Civil and Housing Court to 210 Joralemon St
Category
Public Safety and Criminal Justice
Borough
Brooklyn
Managing Agency
DCAS
Client Agency
DCAS
Current Phase
Design
Design Start
2016-07-27T00:00:00.000
Budget Forecast
233584544.31
Latest Budget Changes
107173544.31
Total Budget Changes
200931011.96
Forecast Completion
2021-09-30T00:00:00.000
Latest Schedule Changes
1
Total Schedule Changes
1977
Metropolitan Avenue Bridge over CSX Transport
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 556 • Project Name: Metropolitan Avenue Bridge over CSX Transport
Date Reported As Of
2017-09-01T00:00:00.000
Pid
556
Project Name
Metropolitan Avenue Bridge over CSX Transport
Description
Replace the Metropolitan Avenue bridge over CSX Transport, Queens.
Category
Bridges, Streets and Roadways
Borough
Queens
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-09-28T00:00:00.000
Budget Forecast
67602000.00
Latest Budget Changes
0.00
Total Budget Changes
4699394.00
Forecast Completion
2024-09-02T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2027
Bruckner Expressway Westchester Creek Bridge Reconstruction
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 97 • Project Name: Bruckner Expressway Westchester Creek Bridge Reconstruction
Date Reported As Of
2017-09-01T00:00:00.000
Pid
97
Project Name
Bruckner Expressway Westchester Creek Bridge Reconstruction
Description
Replace the existing bridge with a new, wider double-leaf bascule bridge in the Bronx.
Category
Bridges, Streets and Roadways
Borough
Bronx
Managing Agency
DOT
Client Agency
DEP, DOT
Current Phase
Construction
Design Start
2012-07-23T00:00:00.000
Budget Forecast
323745502.00
Latest Budget Changes
-296512.70
Total Budget Changes
142277136.00
Forecast Completion
2021-07-14T00:00:00.000
Latest Schedule Changes
-8
Total Schedule Changes
2086
Bellevue Medical Center Priority Mitigation Projects
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 545 • Project Name: Bellevue Medical Center Priority Mitigation Projects
Date Reported As Of
2017-09-01T00:00:00.000
Pid
545
Project Name
Bellevue Medical Center Priority Mitigation Projects
Description
Priority mitigation projects for the repair/restoration and hazard mitigation for Bellevue Hospital, damaged during Superstorm Sandy
Category
Health and Hospitals
Borough
Manhattan
Managing Agency
EDC
Client Agency
H+H
Current Phase
Construction
Design Start
2014-01-01T00:00:00.000
Budget Forecast
50941375.00
Latest Budget Changes
-97506.00
Total Budget Changes
0.00
Forecast Completion
2020-06-30T00:00:00.000
Latest Schedule Changes
731
Total Schedule Changes
1854
Central Park Light Infrastructure
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 586 • Project Name: Central Park Light Infrastructure
Date Reported As Of
2017-09-01T00:00:00.000
Pid
586
Project Name
Central Park Light Infrastructure
Description
Install, remove, and furnish equipment for electrical work associated with traffic signals, lighting, and distribution systems in Central Park, Manhattan.
Category
Parks, Streets and Roadways
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2016-04-29T00:00:00.000
Budget Forecast
42329126.00
Latest Budget Changes
-49999.60
Total Budget Changes
-3323649.60
Forecast Completion
2019-06-18T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1535
Roosevelt Avenue Bridge Superstructure and Substructure Repairs
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 101 • Project Name: Roosevelt Avenue Bridge Superstructure and Substructure Repairs
Date Reported As Of
2017-09-01T00:00:00.000
Pid
101
Project Name
Roosevelt Avenue Bridge Superstructure and Substructure Repairs
Description
Repair the bridge superstructure and substructure and install a new concrete-filled steel grid deck.
Category
Bridges
Borough
Queens
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2003-03-10T00:00:00.000
Budget Forecast
105436907.00
Latest Budget Changes
-1303107.24
Total Budget Changes
23798213.00
Forecast Completion
2019-05-27T00:00:00.000
Latest Schedule Changes
20
Total Schedule Changes
2003
Oakwood Beach WWTP Headworks Improvements
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 450 • Project Name: Oakwood Beach WWTP Headworks Improvements
Date Reported As Of
2017-09-01T00:00:00.000
Pid
450
Project Name
Oakwood Beach WWTP Headworks Improvements
Description
Replacement of six bar screens, grit bin vibrator, six ring flushing pumps, six main sewage pumps and assoc. piping/valves and motor control center, replacement of four exhaust fans, gas and oxygen detectors and a 15 KVA transformer
Category
Wastewater Treatment
Borough
Staten Island
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2015-10-20T00:00:00.000
Budget Forecast
54063510.00
Latest Budget Changes
10899433.20
Total Budget Changes
31867440.00
Forecast Completion
2022-04-09T00:00:00.000
Latest Schedule Changes
-26
Total Schedule Changes
2857
Coney Island Area, Phase 3A
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 516 • Project Name: Coney Island Area, Phase 3A
Date Reported As Of
2017-09-01T00:00:00.000
Pid
516
Project Name
Coney Island Area, Phase 3A
Description
Reconstruction of Storm and Sanitary sewers, Trunk and Distribution Water Main in Coney Island Area -Phase 3A, Borough of Brooklyn.
Category
Industrial Development
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2014-03-17T00:00:00.000
Budget Forecast
39427000.00
Latest Budget Changes
0.00
Total Budget Changes
25273000.00
Forecast Completion
2021-09-06T00:00:00.000
Latest Schedule Changes
60
Total Schedule Changes
1215
Bainbridge Avenue Trunk Water Main
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 454 • Project Name: Bainbridge Avenue Trunk Water Main
Date Reported As Of
2017-09-01T00:00:00.000
Pid
454
Project Name
Bainbridge Avenue Trunk Water Main
Description
Replacement Trunk Water Main in Bainbridge Ave, Bronx
Category
Water Supply
Borough
Bronx
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2014-03-17T00:00:00.000
Budget Forecast
47346000.00
Latest Budget Changes
202000.00
Total Budget Changes
25547000.00
Forecast Completion
2019-06-30T00:00:00.000
Latest Schedule Changes
30
Total Schedule Changes
1687
Dutch Kills and Lower Newtown Creek Enhanced Aeration Work
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 313 • Project Name: Dutch Kills and Lower Newtown Creek Enhanced Aeration Work
Date Reported As Of
2017-09-01T00:00:00.000
Pid
313
Project Name
Dutch Kills and Lower Newtown Creek Enhanced Aeration Work
Description
This project will construct a blower facility and install a diffused aeration system in Dutch Kills and Newtown Creek to increase dissolved oxygen content in the project area to meet DEC standards for the water body.
Category
Wastewater Treatment
Borough
Queens
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction Procurement
Design Start
2014-01-01T00:00:00.000
Budget Forecast
40835112.00
Latest Budget Changes
917000.00
Total Budget Changes
-4338327.57
Forecast Completion
2022-12-12T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1891
TLC - NEW OFFICE FACILITY - 24-55 BQE WEST
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 665 • Project Name: TLC - NEW OFFICE FACILITY - 24-55 BQE WEST
Date Reported As Of
2017-09-01T00:00:00.000
Pid
665
Project Name
TLC - NEW OFFICE FACILITY - 24-55 BQE WEST
Description
Design and construction of new adminstration wing to replace existing administration wing, new parking, provide new inspection lane within the inspection facility.
Category
Other Government Facilities
Borough
Queens
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Design
Design Start
2015-09-15T00:00:00.000
Budget Forecast
77176000.00
Total Budget Changes
75370000.00
Forecast Completion
2022-11-30T00:00:00.000
Total Schedule Changes
1248
Grand Concourse Metro North Railroad Bridge Construction
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 120 • Project Name: Grand Concourse Metro North Railroad Bridge Construction
Date Reported As Of
2017-09-01T00:00:00.000
Pid
120
Project Name
Grand Concourse Metro North Railroad Bridge Construction
Description
Repair the existing bridge and separate the NYCDOT and NYCT components. Includes new steel plate girders, concrete deck, pedestals, backwalls, sidewalks, and bridge railing.
Category
Bridges
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2000-02-14T00:00:00.000
Budget Forecast
66085487.00
Latest Budget Changes
-5447753.57
Total Budget Changes
22682117.00
Forecast Completion
2021-03-23T00:00:00.000
Latest Schedule Changes
18
Total Schedule Changes
836
RECONSTRUCTION OF QUEENS BLVD - PHASE 1
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 618 • Project Name: RECONSTRUCTION OF QUEENS BLVD - PHASE 1
Date Reported As Of
2017-09-01T00:00:00.000
Pid
618
Project Name
RECONSTRUCTION OF QUEENS BLVD - PHASE 1
Description
Reconstruction of Queens Blvd between Roosevelt Ave and 73rd St. (Segment 1) Great Streets Vision Zero.
Category
Industrial Development
Borough
Queens
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2016-08-11T00:00:00.000
Budget Forecast
75466000.00
Total Budget Changes
176245000.00
Forecast Completion
2023-11-14T00:00:00.000
Total Schedule Changes
1906
2nd Avenue Watermain Trunk Construction
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 388 • Project Name: 2nd Avenue Watermain Trunk Construction
Date Reported As Of
2017-09-01T00:00:00.000
Pid
388
Project Name
2nd Avenue Watermain Trunk Construction
Description
Installation of trunk and distribution water mains for the 3rd water tunnel shaft 32B at 2nd Avenue.
Category
Water Supply
Borough
Manhattan
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2013-09-30T00:00:00.000
Budget Forecast
46482000.00
Latest Budget Changes
-2995000.00
Total Budget Changes
-7266000.00
Forecast Completion
2019-09-22T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2113
Queensboro Bridge Roadway Replacement over East River
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 594 • Project Name: Queensboro Bridge Roadway Replacement over East River
Date Reported As Of
2017-09-01T00:00:00.000
Pid
594
Project Name
Queensboro Bridge Roadway Replacement over East River
Description
This project includes the replacement of the upper roadway's deck on the main bridge along with steel repairs, fire standpipes, and lighting upgrades.
Category
Bridges, Streets and Roadways
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2015-04-09T00:00:00.000
Budget Forecast
373837381.00
Latest Budget Changes
11904147.67
Total Budget Changes
8567339.67
Forecast Completion
2019-04-08T00:00:00.000
Latest Schedule Changes
-30
Total Schedule Changes
1970
Coler Specialty Hospital Priority Mitigation Projects
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 544 • Project Name: Coler Specialty Hospital Priority Mitigation Projects
Date Reported As Of
2017-09-01T00:00:00.000
Pid
544
Project Name
Coler Specialty Hospital Priority Mitigation Projects
Description
The priority mitigation projects at Coler include key critical mitigation projects to improve the resiliency of the campus.
Category
Health and Hospitals
Borough
Manhattan
Managing Agency
EDC
Client Agency
H+H
Current Phase
Construction
Design Start
2014-09-01T00:00:00.000
Budget Forecast
21023561.26
Latest Budget Changes
-288855.74
Total Budget Changes
0.00
Forecast Completion
2018-12-31T00:00:00.000
Latest Schedule Changes
184
Total Schedule Changes
2085
STM & SAN SWR, WILLET PT BLVD WHITESTONE AREA, PH2
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 651 • Project Name: STM & SAN SWR, WILLET PT BLVD WHITESTONE AREA, PH2
Date Reported As Of
2017-09-01T00:00:00.000
Pid
651
Project Name
STM & SAN SWR, WILLET PT BLVD WHITESTONE AREA, PH2
Description
Whitestone Area, Willets Point Blvd, Queens
Category
Sewers
Borough
Queens
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2013-03-15T00:00:00.000
Budget Forecast
69282000.00
Total Budget Changes
41243000.00
Forecast Completion
2021-08-27T00:00:00.000
Total Schedule Changes
642
20th Avenue Storm and Sanitary Sewer Construction
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 432 • Project Name: 20th Avenue Storm and Sanitary Sewer Construction
Date Reported As Of
2017-09-01T00:00:00.000
Pid
432
Project Name
20th Avenue Storm and Sanitary Sewer Construction
Description
Construction of a new storm sewer in 20th Avenue between 126th Street and US Bulkhead.
Category
Sewers
Borough
Queens
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2012-07-10T00:00:00.000
Budget Forecast
126274000.00
Latest Budget Changes
-119000.00
Total Budget Changes
117177000.00
Forecast Completion
2021-06-29T00:00:00.000
Latest Schedule Changes
-777
Total Schedule Changes
2180
Ped Safety Upgrades on Atlantic Avenue, Phase 2
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 519 • Project Name: Ped Safety Upgrades on Atlantic Avenue, Phase 2
Date Reported As Of
2017-09-01T00:00:00.000
Pid
519
Project Name
Ped Safety Upgrades on Atlantic Avenue, Phase 2
Description
Safety Improvements on Atlantic Ave from Conduit Avenue to Rockaway Blvd, Phase 2, Brooklyn
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2016-08-04T00:00:00.000
Budget Forecast
39140000.00
Latest Budget Changes
1765000.00
Total Budget Changes
10136496.00
Forecast Completion
2021-02-27T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1400
Wyckoff Avenue Street Reconstruction
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 191 • Project Name: Wyckoff Avenue Street Reconstruction
Date Reported As Of
2017-09-01T00:00:00.000
Pid
191
Project Name
Wyckoff Avenue Street Reconstruction
Description
Reconstruction of Wyckoff Avenue from Flushing Avenue to Cooper Avenue, in the Boroughs of Brooklyn and Queens.
Category
Streets and Roadways
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Trans. & Env. Protection
Current Phase
Design
Design Start
2008-06-10T00:00:00.000
Budget Forecast
47099000.00
Latest Budget Changes
170000.00
Total Budget Changes
43926000.00
Forecast Completion
2030-01-13T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
226
DBCD South Site Cultural Fit-Out
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 484 • Project Name: DBCD South Site Cultural Fit-Out
Date Reported As Of
2017-09-01T00:00:00.000
Pid
484
Project Name
DBCD South Site Cultural Fit-Out
Description
Interior fit-out of the south site cultural unit.
Category
Arts and Culture
Borough
Brooklyn
Managing Agency
EDC
Client Agency
DCLA
Current Phase
Design
Design Start
2014-12-01T00:00:00.000
Budget Forecast
32833212.23
Latest Budget Changes
25507181.33
Total Budget Changes
36789601.16
Forecast Completion
2019-11-30T00:00:00.000
Latest Schedule Changes
91
Total Schedule Changes
1706
Hannah Street Pumping Station Construction
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 364 • Project Name: Hannah Street Pumping Station Construction
Date Reported As Of
2017-09-01T00:00:00.000
Pid
364
Project Name
Hannah Street Pumping Station Construction
Description
This project will reconstruct the Hannah St. Pumping Station, the largest City-owned wastewater collection and pumping station on Staten Island. Built in 1977, the facility has numerous deficiencies, needing a comprehensive upgrade.
Category
Wastewater Treatment
Borough
Staten Island
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2012-10-01T00:00:00.000
Budget Forecast
65920000.00
Latest Budget Changes
10920000.00
Total Budget Changes
67909196.80
Forecast Completion
2020-07-08T00:00:00.000
Latest Schedule Changes
28
Total Schedule Changes
3238
Pelham Parkway Bridge Reconstruction over Hutchinson Parkway
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 506 • Project Name: Pelham Parkway Bridge Reconstruction over Hutchinson Parkway
Date Reported As Of
2017-09-01T00:00:00.000
Pid
506
Project Name
Pelham Parkway Bridge Reconstruction over Hutchinson Parkway
Description
Replace the Pelham Parkway bridge over Hutchinson Parkway, Bronx.
Category
Bridges, Streets and Roadways
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-05-30T00:00:00.000
Budget Forecast
56521020.00
Latest Budget Changes
-274000.43
Total Budget Changes
10338071.57
Forecast Completion
2024-04-29T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1934
Emergency Communications Transformation Program (ECTP) Upgrades and Enhancements
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 267 • Project Name: Emergency Communications Transformation Program (ECTP) Upgrades and Enhancements
Date Reported As Of
2017-09-01T00:00:00.000
Pid
267
Project Name
Emergency Communications Transformation Program (ECTP) Upgrades and Enhancements
Description
Upgrade and enhancement of emergency technology infrastructure to improve interoperability and coordination among public safety agencies and improve call processing time to decrease overall response times.
Category
IT
Borough
Citywide
Managing Agency
DOITT
Client Agency
FDNY, NYPD
Current Phase
IT
Budget Forecast
2211709080.00
Latest Budget Changes
3174283.00
Total Budget Changes
73735148.87
Forecast Completion
2019-12-01T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2252
Primary Treatment Improvement at Wards Island WWTP
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 452 • Project Name: Primary Treatment Improvement at Wards Island WWTP
Date Reported As Of
2017-09-01T00:00:00.000
Pid
452
Project Name
Primary Treatment Improvement at Wards Island WWTP
Description
Replacement of internal mechanisms, concrete repairs, effluent weirs, scum troughs, grease pit collection system, electrical upgrades, HVAC upgrades, evaluation and improvement of cross collector drainage in 10 PST.
Category
Wastewater Treatment
Borough
Manhattan
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2017-06-30T00:00:00.000
Budget Forecast
68456631.00
Latest Budget Changes
22000000.00
Total Budget Changes
99651290.98
Forecast Completion
2020-07-22T00:00:00.000
Latest Schedule Changes
73
Total Schedule Changes
2142
West Tremont Avenue over Metro North Railroad
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 503 • Project Name: West Tremont Avenue over Metro North Railroad
Date Reported As Of
2017-09-01T00:00:00.000
Pid
503
Project Name
West Tremont Avenue over Metro North Railroad
Description
Repair the West Tremont Avenue bridge over the Metro North line, located in the Bronx.
Category
Bridges
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-05-30T00:00:00.000
Budget Forecast
54138000.00
Latest Budget Changes
147000.00
Total Budget Changes
37794543.00
Forecast Completion
2024-04-29T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1253
North River Wastewater Treatment Plant Cogeneration and Electrification
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 423 • Project Name: North River Wastewater Treatment Plant Cogeneration and Electrification
Date Reported As Of
2017-09-01T00:00:00.000
Pid
423
Project Name
North River Wastewater Treatment Plant Cogeneration and Electrification
Description
This project will remove the 10 existing pump and blower engines and add electric motors for the main sewage pumps, a new cogeneration facility consisting of 5 new dual fuel engines, electrical service upgrades and flood protection.
Category
Wastewater Treatment
Borough
New York
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2013-07-01T00:00:00.000
Budget Forecast
228432457.10
Latest Budget Changes
3271304.10
Total Budget Changes
134242052.88
Forecast Completion
2021-03-06T00:00:00.000
Latest Schedule Changes
26
Total Schedule Changes
1712
Broadway Bridge over Harlem River Replacement
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 106 • Project Name: Broadway Bridge over Harlem River Replacement
Date Reported As Of
2017-09-01T00:00:00.000
Pid
106
Project Name
Broadway Bridge over Harlem River Replacement
Description
Replace deteriorated members of lift span superstructure, concrete deck, lift electrical and mechanical systems, and fenders.
Category
Bridges
Borough
Bronx, Manhattan
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2005-04-01T00:00:00.000
Budget Forecast
191951546.00
Latest Budget Changes
23354089.28
Total Budget Changes
39724388.00
Forecast Completion
2021-10-17T00:00:00.000
Latest Schedule Changes
338
Total Schedule Changes
2797
49th Avenue Bridge Replacement
Date Reported As Of: 2017-09-01T00:00:00.000 • Pid: 131 • Project Name: 49th Avenue Bridge Replacement
Date Reported As Of
2017-09-01T00:00:00.000
Pid
131
Project Name
49th Avenue Bridge Replacement
Description
Replace the 49th Avenue bridge over Long Island Railroad and Amtrak in Hunters Point, Queens.
Category
Bridges, Streets and Roadways
Borough
Queens
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-08-15T00:00:00.000
Budget Forecast
81252000.00
Latest Budget Changes
0.00
Total Budget Changes
32902419.00
Forecast Completion
2023-02-02T00:00:00.000
Latest Schedule Changes
-634
Total Schedule Changes
1449
Dumbo and Vinegar Hill Area Roadway Reconstruction and Renovation
Date Reported As Of: 2017-04-01T00:00:00.000 • Pid: 193 • Project Name: Dumbo and Vinegar Hill Area Roadway Reconstruction and Renovation
Date Reported As Of
2017-04-01T00:00:00.000
Pid
193
Project Name
Dumbo and Vinegar Hill Area Roadway Reconstruction and Renovation
Description
Reconstruction and restoration of Belgian block roadways in the DUMBO and Vinegar Hill communities concurrent with installation of new water main, combined sewers and storm sewers, plus construction of the Pearl Street Triangle Plaza.
Category
Streets and Roadways
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2012-06-07T00:00:00.000
Budget Forecast
19553000.00
Latest Budget Changes
-41197000.00
Total Budget Changes
96724000.00
Forecast Completion
2019-04-25T00:00:00.000
Latest Schedule Changes
153
Total Schedule Changes
3253
West 59th Street Marine Transfer Station Construction, Phase 2
Date Reported As Of: 2017-04-01T00:00:00.000 • Pid: 347 • Project Name: West 59th Street Marine Transfer Station Construction, Phase 2
Date Reported As Of
2017-04-01T00:00:00.000
Pid
347
Project Name
West 59th Street Marine Transfer Station Construction, Phase 2
Description
Phase I repairs the inshore platform, replaces scales and control equipment, dredging around the pier, & site work. Phase 2 refurbishes existing pier building incl. pier structure, pile caps, fendering, construction of new emergency generator, etc.
Category
Sanitation
Borough
Manhattan
Managing Agency
DDC
Client Agency
Sanitation
Current Phase
Construction
Design Start
2012-01-17T00:00:00.000
Budget Forecast
84946000.00
Latest Budget Changes
-2617311.00
Total Budget Changes
126753576.46
Forecast Completion
2018-05-08T00:00:00.000
Latest Schedule Changes
49
Total Schedule Changes
1949
Riverside Drive/West 158th Street Bridge Rehabilitation
Date Reported As Of: 2017-04-01T00:00:00.000 • Pid: 113 • Project Name: Riverside Drive/West 158th Street Bridge Rehabilitation
Date Reported As Of
2017-04-01T00:00:00.000
Pid
113
Project Name
Riverside Drive/West 158th Street Bridge Rehabilitation
Description
Replace deck of the Riverside Drive viaduct/ bridge over West 158th Street.
Category
Bridges, Streets and Roadways
Borough
Manhattan
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2014-10-22T00:00:00.000
Budget Forecast
145663602.68
Latest Budget Changes
60307000.00
Total Budget Changes
96922794.00
Forecast Completion
2021-12-17T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2152
Emergency Communications Transformation Program (ECTP) Upgrades and Enhancements
Date Reported As Of: 2017-04-01T00:00:00.000 • Pid: 267 • Project Name: Emergency Communications Transformation Program (ECTP) Upgrades and Enhancements
Date Reported As Of
2017-04-01T00:00:00.000
Pid
267
Project Name
Emergency Communications Transformation Program (ECTP) Upgrades and Enhancements
Description
Upgrade and enhancement of emergency technology infrastructure to improve interoperability and coordination among public safety agencies and improve call processing time to decrease overall response times.
Category
IT
Borough
Citywide
Managing Agency
DOITT
Client Agency
FDNY, NYPD
Current Phase
IT
Budget Forecast
2208534797.00
Latest Budget Changes
1896049.00
Total Budget Changes
73735148.87
Forecast Completion
2019-12-01T00:00:00.000
Latest Schedule Changes
731
Total Schedule Changes
2252
Hannah Street Pumping Station Construction
Date Reported As Of: 2017-04-01T00:00:00.000 • Pid: 364 • Project Name: Hannah Street Pumping Station Construction
Date Reported As Of
2017-04-01T00:00:00.000
Pid
364
Project Name
Hannah Street Pumping Station Construction
Description
This project will reconstruct the Hannah St. Pumping Station, the largest City-owned wastewater collection and pumping station on Staten Island. Built in 1977, the facility has numerous deficiencies, needing a comprehensive upgrade.
Category
Wastewater Treatment
Borough
Staten Island
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2012-10-01T00:00:00.000
Budget Forecast
55000000.00
Latest Budget Changes
100000.00
Total Budget Changes
67909196.80
Forecast Completion
2020-06-10T00:00:00.000
Latest Schedule Changes
182
Total Schedule Changes
3238
Flatbush Avenue Trunk Watermain Replacement
Date Reported As Of: 2017-04-01T00:00:00.000 • Pid: 370 • Project Name: Flatbush Avenue Trunk Watermain Replacement
Date Reported As Of
2017-04-01T00:00:00.000
Pid
370
Project Name
Flatbush Avenue Trunk Watermain Replacement
Description
Replacement of trunk water main on Flatbush Avenue between Sterling place and 8th Avenue in addition to the distribution water main in 6th Avenue between Union Street and Park Place, and sections of adjoining streets.
Category
Wastewater Treatment
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction Procurement
Design Start
2014-12-02T00:00:00.000
Budget Forecast
51380000.00
Latest Budget Changes
23236000.00
Total Budget Changes
39272000.00
Forecast Completion
2019-07-01T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2266
2nd Avenue Watermain Trunk Construction
Date Reported As Of: 2017-04-01T00:00:00.000 • Pid: 388 • Project Name: 2nd Avenue Watermain Trunk Construction
Date Reported As Of
2017-04-01T00:00:00.000
Pid
388
Project Name
2nd Avenue Watermain Trunk Construction
Description
Installation of trunk and distribution water mains for the 3rd water tunnel shaft 32B at 2nd Avenue.
Category
Water Supply
Borough
Manhattan
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2013-09-30T00:00:00.000
Budget Forecast
49477000.00
Latest Budget Changes
0.00
Total Budget Changes
-7266000.00
Forecast Completion
2019-09-22T00:00:00.000
Latest Schedule Changes
191
Total Schedule Changes
2113
Bruckner Expressway Westchester Creek Bridge Reconstruction
Date Reported As Of: 2017-04-01T00:00:00.000 • Pid: 97 • Project Name: Bruckner Expressway Westchester Creek Bridge Reconstruction
Date Reported As Of
2017-04-01T00:00:00.000
Pid
97
Project Name
Bruckner Expressway Westchester Creek Bridge Reconstruction
Description
Replace the existing bridge with a new, wider double-leaf bascule bridge in the Bronx.
Category
Bridges, Streets and Roadways
Borough
Bronx
Managing Agency
DOT
Client Agency
DEP, DOT
Current Phase
Construction Procurement
Design Start
2012-07-23T00:00:00.000
Budget Forecast
324042014.70
Latest Budget Changes
-11722487.79
Total Budget Changes
142277136.00
Forecast Completion
2021-07-22T00:00:00.000
Latest Schedule Changes
140
Total Schedule Changes
2086
Madison Avenue Bridge Reconstruction
Date Reported As Of: 2017-04-01T00:00:00.000 • Pid: 114 • Project Name: Madison Avenue Bridge Reconstruction
Date Reported As Of
2017-04-01T00:00:00.000
Pid
114
Project Name
Madison Avenue Bridge Reconstruction
Description
Replace the electrical and mechanical systems of the Madison Avenue Bridge.
Category
Bridges
Borough
Manhattan, Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2011-02-14T00:00:00.000
Budget Forecast
55163089.93
Latest Budget Changes
2119000.00
Total Budget Changes
2036997.00
Forecast Completion
2019-07-03T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1628
Electronic Medical Records Upgrade
Date Reported As Of: 2017-04-01T00:00:00.000 • Pid: 403 • Project Name: Electronic Medical Records Upgrade
Date Reported As Of
2017-04-01T00:00:00.000
Pid
403
Project Name
Electronic Medical Records Upgrade
Description
The EPIC - EMR Program: Electronic Medical Records (EMR) System - a single enterprise-wide EMR to meet the needs of HHC's expansive size and improve patient care will replace the legacy EMR - QuadraMed, which is over 25 years old.
Category
Health and Hospitals, IT
Borough
Citywide
Managing Agency
HHC
Client Agency
H+H
Current Phase
IT
Budget Forecast
764063231.00
Latest Budget Changes
0.00
Total Budget Changes
15184947.00
Forecast Completion
2018-12-07T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2032
Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Date Reported As Of: 2017-04-01T00:00:00.000 • Pid: 112 • Project Name: Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Date Reported As Of
2017-04-01T00:00:00.000
Pid
112
Project Name
Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Description
Repair abutments, piers, approaches, and steel superstructure located in Pelham Bay, Bronx; replace reinforced concrete deck.
Category
Bridges, Streets and Roadways
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
1995-01-17T00:00:00.000
Budget Forecast
80133352.29
Latest Budget Changes
-43648816.71
Total Budget Changes
20945057.00
Forecast Completion
2021-09-13T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1592
Roma and Hett Avenue Storm and Sanitary Sewer Installation
Date Reported As Of: 2017-04-01T00:00:00.000 • Pid: 206 • Project Name: Roma and Hett Avenue Storm and Sanitary Sewer Installation
Date Reported As Of
2017-04-01T00:00:00.000
Pid
206
Project Name
Roma and Hett Avenue Storm and Sanitary Sewer Installation
Description
Roadway reconstruction and installation of new storm sewers and the replacement of sanitary sewers and water mains in the Midland Beach section, Staten Island.
Category
Sewers
Borough
Staten Island
Managing Agency
DDC
Client Agency
Trans. & Env. Protection
Current Phase
Design
Design Start
2008-06-19T00:00:00.000
Budget Forecast
62074000.00
Latest Budget Changes
-1841000.00
Total Budget Changes
62973000.00
Forecast Completion
2019-10-27T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
-8
Gilboa Dam Reconstruction, Phase III
Date Reported As Of: 2017-04-01T00:00:00.000 • Pid: 405 • Project Name: Gilboa Dam Reconstruction, Phase III
Date Reported As Of
2017-04-01T00:00:00.000
Pid
405
Project Name
Gilboa Dam Reconstruction, Phase III
Description
Gilboa Dam Reconstruction Project includes construction of a new low level outlet (LLO) consisting of 2,000 feet of tunneling, an access shaft, oulet structure and gate valve controls.
Category
Water Supply
Borough
Upstate
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2004-03-18T00:00:00.000
Budget Forecast
204690536.30
Latest Budget Changes
-846314.00
Total Budget Changes
10376533.49
Forecast Completion
2020-07-27T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1113