Capital Projects

All major infrastructure and information technology projects with a budget of $25 million or more that are currently active (in the design, procurement, or construction phase).

City Government Mayor's Office of Operations (OPS) Dataset n7gv-k5yt 16 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
20th Avenue Storm and Sanitary Sewer Construction
Date Reported As Of: 2016-01-01T00:00:00.000 • Pid: 432 • Project Name: 20th Avenue Storm and Sanitary Sewer Construction
Date Reported As Of
2016-01-01T00:00:00.000
Pid
432
Project Name
20th Avenue Storm and Sanitary Sewer Construction
Description
Construction of a new storm sewer in 20th Avenue between 126th Street and US Bulkhead.
Category
Sewers
Borough
Queens
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction Procurement
Design Start
2012-07-10T00:00:00.000
Budget Forecast
95653000.00
Latest Budget Changes
287000.00
Total Budget Changes
117177000.00
Forecast Completion
2018-07-23T00:00:00.000
Latest Schedule Changes
112
Total Schedule Changes
2180
Roma and Hett Avenue Storm and Sanitary Sewer Installation
Date Reported As Of: 2016-01-01T00:00:00.000 • Pid: 206 • Project Name: Roma and Hett Avenue Storm and Sanitary Sewer Installation
Date Reported As Of
2016-01-01T00:00:00.000
Pid
206
Project Name
Roma and Hett Avenue Storm and Sanitary Sewer Installation
Description
Roadway reconstruction and installation of new storm sewers and the replacement of sanitary sewers and water mains in the Midland Beach section, Staten Island.
Category
Sewers
Borough
Staten Island
Managing Agency
DDC
Client Agency
Trans. & Env. Protection
Current Phase
Design
Design Start
2008-06-19T00:00:00.000
Budget Forecast
43545000.00
Latest Budget Changes
752000.00
Total Budget Changes
62973000.00
Forecast Completion
2019-10-27T00:00:00.000
Latest Schedule Changes
350
Total Schedule Changes
-8
Emergency Communications Transformation Program (ECTP) Upgrades and Enhancements
Date Reported As Of: 2016-01-01T00:00:00.000 • Pid: 267 • Project Name: Emergency Communications Transformation Program (ECTP) Upgrades and Enhancements
Date Reported As Of
2016-01-01T00:00:00.000
Pid
267
Project Name
Emergency Communications Transformation Program (ECTP) Upgrades and Enhancements
Description
Upgrade and enhancement of emergency technology infrastructure to improve interoperability and coordination among public safety agencies and improve call processing time to decrease overall response times.
Category
IT
Borough
Citywide
Managing Agency
DOITT
Client Agency
FDNY, NYPD
Current Phase
IT
Budget Forecast
2146517283.00
Latest Budget Changes
-10795429.00
Total Budget Changes
73735148.87
Forecast Completion
2017-11-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2252
2nd Avenue Watermain Trunk Construction
Date Reported As Of: 2016-01-01T00:00:00.000 • Pid: 388 • Project Name: 2nd Avenue Watermain Trunk Construction
Date Reported As Of
2016-01-01T00:00:00.000
Pid
388
Project Name
2nd Avenue Watermain Trunk Construction
Description
Installation of trunk and distribution water mains for the 3rd water tunnel shaft 32B at 2nd Avenue.
Category
Water Supply
Borough
Manhattan
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction Procurement
Design Start
2013-09-30T00:00:00.000
Budget Forecast
60802000.00
Latest Budget Changes
0.00
Total Budget Changes
-7266000.00
Forecast Completion
2018-06-15T00:00:00.000
Latest Schedule Changes
-31
Total Schedule Changes
2113
Madison Avenue Bridge Reconstruction
Date Reported As Of: 2016-01-01T00:00:00.000 • Pid: 114 • Project Name: Madison Avenue Bridge Reconstruction
Date Reported As Of
2016-01-01T00:00:00.000
Pid
114
Project Name
Madison Avenue Bridge Reconstruction
Description
Replace the electrical and mechanical systems of the Madison Avenue Bridge.
Category
Bridges
Borough
Manhattan, Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2011-02-14T00:00:00.000
Budget Forecast
53092095.93
Latest Budget Changes
-1417209.07
Total Budget Changes
2036997.00
Forecast Completion
2019-07-03T00:00:00.000
Latest Schedule Changes
320
Total Schedule Changes
1628
Roosevelt Avenue Bridge Superstructure and Substructure Repairs
Date Reported As Of: 2015-08-01T00:00:00.000 • Pid: 101 • Project Name: Roosevelt Avenue Bridge Superstructure and Substructure Repairs
Date Reported As Of
2015-08-01T00:00:00.000
Pid
101
Project Name
Roosevelt Avenue Bridge Superstructure and Substructure Repairs
Description
Repair the bridge superstructure and substructure and install a new concrete-filled steel grid deck.
Category
Bridges
Borough
Queens
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2003-03-10T00:00:00.000
Budget Forecast
201932563.81
Latest Budget Changes
59835223.81
Total Budget Changes
23798213.00
Forecast Completion
2019-05-07T00:00:00.000
Latest Schedule Changes
-1345
Total Schedule Changes
2003
Dumbo and Vinegar Hill Area Roadway Reconstruction and Renovation
Date Reported As Of: 2015-08-01T00:00:00.000 • Pid: 193 • Project Name: Dumbo and Vinegar Hill Area Roadway Reconstruction and Renovation
Date Reported As Of
2015-08-01T00:00:00.000
Pid
193
Project Name
Dumbo and Vinegar Hill Area Roadway Reconstruction and Renovation
Description
Reconstruction and restoration of Belgian block roadways in the DUMBO and Vinegar Hill communities concurrent with installation of new water main, combined sewers and storm sewers, plus construction of the Pearl Street Triangle Plaza.
Category
Streets and Roadways
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2012-06-07T00:00:00.000
Budget Forecast
48317000.00
Latest Budget Changes
-1000000.00
Total Budget Changes
96724000.00
Forecast Completion
2017-11-08T00:00:00.000
Latest Schedule Changes
213
Total Schedule Changes
3253
Wyckoff Avenue Street Reconstruction
Date Reported As Of: 2015-08-01T00:00:00.000 • Pid: 191 • Project Name: Wyckoff Avenue Street Reconstruction
Date Reported As Of
2015-08-01T00:00:00.000
Pid
191
Project Name
Wyckoff Avenue Street Reconstruction
Description
Reconstruction of Wyckoff Avenue from Flushing Avenue to Cooper Avenue, in the Boroughs of Brooklyn and Queens.
Category
Streets and Roadways
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Trans. & Env. Protection
Current Phase
Design
Design Start
2008-06-10T00:00:00.000
Budget Forecast
37230000.00
Latest Budget Changes
50000.00
Total Budget Changes
43926000.00
Forecast Completion
2028-05-31T00:00:00.000
Latest Schedule Changes
-2784
Total Schedule Changes
226
Bainbridge Avenue Trunk Water Main
Date Reported As Of: 2015-08-01T00:00:00.000 • Pid: 454 • Project Name: Bainbridge Avenue Trunk Water Main
Date Reported As Of
2015-08-01T00:00:00.000
Pid
454
Project Name
Bainbridge Avenue Trunk Water Main
Description
Replacement Trunk Water Main in Bainbridge Ave, Bronx
Category
Water Supply
Borough
Bronx
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction Procurement
Design Start
2014-03-17T00:00:00.000
Budget Forecast
46802000.00
Total Budget Changes
25547000.00
Forecast Completion
2018-11-16T00:00:00.000
Total Schedule Changes
1687
Electronic Medical Records Upgrade
Date Reported As Of: 2015-08-01T00:00:00.000 • Pid: 403 • Project Name: Electronic Medical Records Upgrade
Date Reported As Of
2015-08-01T00:00:00.000
Pid
403
Project Name
Electronic Medical Records Upgrade
Description
The EPIC - EMR Program: Electronic Medical Records (EMR) System - a single enterprise-wide EMR to meet the needs of HHC's expansive size and improve patient care will replace the legacy EMR - QuadraMed, which is over 25 years old.
Category
Health and Hospitals, IT
Borough
Citywide
Managing Agency
HHC
Client Agency
H+H
Current Phase
IT
Budget Forecast
764063231.00
Latest Budget Changes
0.00
Total Budget Changes
15184947.00
Forecast Completion
2018-12-20T00:00:00.000
Latest Schedule Changes
-11
Total Schedule Changes
2032
Gilboa Dam Reconstruction, Phase III
Date Reported As Of: 2015-08-01T00:00:00.000 • Pid: 405 • Project Name: Gilboa Dam Reconstruction, Phase III
Date Reported As Of
2015-08-01T00:00:00.000
Pid
405
Project Name
Gilboa Dam Reconstruction, Phase III
Description
Gilboa Dam Reconstruction Project includes construction of a new low level outlet (LLO) consisting of 2,000 feet of tunneling, an access shaft, oulet structure and gate valve controls.
Category
Water Supply
Borough
Upstate
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2004-03-18T00:00:00.000
Budget Forecast
195762213.00
Latest Budget Changes
-30962278.00
Total Budget Changes
10376533.49
Forecast Completion
2020-06-28T00:00:00.000
Latest Schedule Changes
-22
Total Schedule Changes
1113
Pelham Parkway Roadway Reconstruction, Phase 2
Date Reported As Of: 2015-08-01T00:00:00.000 • Pid: 180 • Project Name: Pelham Parkway Roadway Reconstruction, Phase 2
Date Reported As Of
2015-08-01T00:00:00.000
Pid
180
Project Name
Pelham Parkway Roadway Reconstruction, Phase 2
Description
Reconstruction of Pelham Parkway from the Bronx River Parkway to the Hutchinson River Parkway, including the north service road from Bronx Park East to Eastchester Road.
Category
Streets and Roadways
Borough
Bronx
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2002-02-20T00:00:00.000
Budget Forecast
33814000.00
Latest Budget Changes
-2693404.00
Total Budget Changes
125164000.00
Forecast Completion
2018-01-09T00:00:00.000
Latest Schedule Changes
239
Total Schedule Changes
2869
Bergen Avenue Street Reconstruction
Date Reported As Of: 2015-08-01T00:00:00.000 • Pid: 170 • Project Name: Bergen Avenue Street Reconstruction
Date Reported As Of
2015-08-01T00:00:00.000
Pid
170
Project Name
Bergen Avenue Street Reconstruction
Description
Roadway reconstruction Bergen Avenue and vicinity, includes sections of: Avenues N, T, U, V, W, X and Y; 66th Street and 69th through 75th Streets; Veterans Avenue and Royce Street.
Category
Streets and Roadways
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2012-12-03T00:00:00.000
Budget Forecast
20390000.00
Latest Budget Changes
518000.00
Total Budget Changes
45837000.00
Forecast Completion
2025-07-18T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
-388
Broadway Bridge over Harlem River Replacement
Date Reported As Of: 2015-08-01T00:00:00.000 • Pid: 106 • Project Name: Broadway Bridge over Harlem River Replacement
Date Reported As Of
2015-08-01T00:00:00.000
Pid
106
Project Name
Broadway Bridge over Harlem River Replacement
Description
Replace deteriorated members of lift span superstructure, concrete deck, lift electrical and mechanical systems, and fenders.
Category
Bridges
Borough
Bronx, Manhattan
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2005-04-01T00:00:00.000
Budget Forecast
109294563.00
Latest Budget Changes
79000.00
Total Budget Changes
39724388.00
Forecast Completion
2021-01-12T00:00:00.000
Latest Schedule Changes
60
Total Schedule Changes
2797
Edgewood Triangle Roadway Reconstruction
Date Reported As Of: 2015-08-01T00:00:00.000 • Pid: 204 • Project Name: Edgewood Triangle Roadway Reconstruction
Date Reported As Of
2015-08-01T00:00:00.000
Pid
204
Project Name
Edgewood Triangle Roadway Reconstruction
Description
Reconstruct roadway and extend storm and sanitary sewers in portions of Brookville Boulevard, Edgewood Street, 147th Avenue, and adjacent streets west of 241st Street.
Category
Streets and Roadways
Borough
Queens
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2013-02-13T00:00:00.000
Budget Forecast
29883000.00
Latest Budget Changes
496000.00
Total Budget Changes
106503000.00
Forecast Completion
2019-09-26T00:00:00.000
Latest Schedule Changes
19
Total Schedule Changes
3597
Hannah Street Pumping Station Construction
Date Reported As Of: 2015-08-01T00:00:00.000 • Pid: 364 • Project Name: Hannah Street Pumping Station Construction
Date Reported As Of
2015-08-01T00:00:00.000
Pid
364
Project Name
Hannah Street Pumping Station Construction
Description
This project will reconstruct the Hannah St. Pumping Station, the largest City-owned wastewater collection and pumping station on Staten Island. Built in 1977, the facility has numerous deficiencies, needing a comprehensive upgrade.
Category
Wastewater Treatment
Borough
Staten Island
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2012-10-01T00:00:00.000
Budget Forecast
53900000.00
Latest Budget Changes
-300000.00
Total Budget Changes
67909196.80
Forecast Completion
2019-03-12T00:00:00.000
Latest Schedule Changes
366
Total Schedule Changes
3238
Reconstruction of the Port Jervis Wastewater Treatment Plant
Date Reported As Of: 2015-08-01T00:00:00.000 • Pid: 444 • Project Name: Reconstruction of the Port Jervis Wastewater Treatment Plant
Date Reported As Of
2015-08-01T00:00:00.000
Pid
444
Project Name
Reconstruction of the Port Jervis Wastewater Treatment Plant
Description
Reconstruction of the Port Jervis WWTP as required based on the effluent limits proposed by the Delaware River Basin Commission (DRBC)
Category
Wastewater Treatment
Borough
Port Jervis
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2014-06-17T00:00:00.000
Budget Forecast
42918306.30
Latest Budget Changes
-8278171.70
Total Budget Changes
9428438.55
Forecast Completion
2020-01-24T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2445
West 59th Street Marine Transfer Station Construction, Phase 2
Date Reported As Of: 2015-08-01T00:00:00.000 • Pid: 347 • Project Name: West 59th Street Marine Transfer Station Construction, Phase 2
Date Reported As Of
2015-08-01T00:00:00.000
Pid
347
Project Name
West 59th Street Marine Transfer Station Construction, Phase 2
Description
Phase I repairs the inshore platform, replaces scales and control equipment, dredging around the pier, & site work. Phase 2 refurbishes existing pier building incl. pier structure, pile caps, fendering, construction of new emergency generator, etc.
Category
Sanitation
Borough
Manhattan
Managing Agency
DDC
Client Agency
Sanitation
Current Phase
Construction
Design Start
2012-01-17T00:00:00.000
Budget Forecast
89734000.00
Latest Budget Changes
0.00
Total Budget Changes
126753576.46
Forecast Completion
2017-05-18T00:00:00.000
Latest Schedule Changes
-457
Total Schedule Changes
1949
Riverside Drive/West 158th Street Bridge Rehabilitation
Date Reported As Of: 2015-08-01T00:00:00.000 • Pid: 113 • Project Name: Riverside Drive/West 158th Street Bridge Rehabilitation
Date Reported As Of
2015-08-01T00:00:00.000
Pid
113
Project Name
Riverside Drive/West 158th Street Bridge Rehabilitation
Description
Deck replacement of the Riverside Drive Viaduct / Bridge over W. 158th Street.
Category
Bridges, Streets and Roadways
Borough
Manhattan
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2014-10-22T00:00:00.000
Budget Forecast
64057424.18
Latest Budget Changes
2550000.18
Total Budget Changes
96922794.00
Forecast Completion
2021-12-17T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2152
Roma and Hett Avenue Storm and Sanitary Sewer Installation
Date Reported As Of: 2015-08-01T00:00:00.000 • Pid: 206 • Project Name: Roma and Hett Avenue Storm and Sanitary Sewer Installation
Date Reported As Of
2015-08-01T00:00:00.000
Pid
206
Project Name
Roma and Hett Avenue Storm and Sanitary Sewer Installation
Description
Roadway reconstruction and installation of new storm sewers and the replacement of sanitary sewers and water mains in the Midland Beach section, Staten Island.
Category
Sewers
Borough
Staten Island
Managing Agency
DDC
Client Agency
Trans. & Env. Protection
Current Phase
Design
Design Start
2008-06-19T00:00:00.000
Budget Forecast
42793000.00
Latest Budget Changes
372000.00
Total Budget Changes
62973000.00
Forecast Completion
2018-11-11T00:00:00.000
Latest Schedule Changes
309
Total Schedule Changes
-8
Rondout-West Branch Bypass Tunnel Construction Project 2
Date Reported As Of: 2015-08-01T00:00:00.000 • Pid: 409 • Project Name: Rondout-West Branch Bypass Tunnel Construction Project 2
Date Reported As Of
2015-08-01T00:00:00.000
Pid
409
Project Name
Rondout-West Branch Bypass Tunnel Construction Project 2
Description
To address existing leaks in the Delaware Aqueduct, a 3-mile bypass tunnel will be constructed near the town of Roseton and the existing tunnel will be repaired near the town of Wawarsing.
Category
Water Supply
Borough
Marlboro
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2012-03-23T00:00:00.000
Budget Forecast
866526960.00
Latest Budget Changes
135269105.00
Total Budget Changes
202552329.25
Forecast Completion
2025-12-05T00:00:00.000
Latest Schedule Changes
463
Total Schedule Changes
256
New Ferry Boat Construction
Date Reported As Of: 2015-08-01T00:00:00.000 • Pid: 94 • Project Name: New Ferry Boat Construction
Date Reported As Of
2015-08-01T00:00:00.000
Pid
94
Project Name
New Ferry Boat Construction
Description
Replace one Barberi class boat and the John F. Kennedy boat which are approaching the end of their useful lives with new Staten Island ferries. Replacement is needed to continue reliable service.
Category
Ferries
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2014-09-15T00:00:00.000
Budget Forecast
327552000.00
Latest Budget Changes
83234948.00
Total Budget Changes
-238419180.00
Forecast Completion
2020-02-11T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
549
Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Date Reported As Of: 2015-08-01T00:00:00.000 • Pid: 112 • Project Name: Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Date Reported As Of
2015-08-01T00:00:00.000
Pid
112
Project Name
Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Description
Repair abutments, piers, approaches, and the steel superstructure. Replace reinforced concrete deck.
Category
Bridges, Streets and Roadways
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
1995-01-17T00:00:00.000
Budget Forecast
63911397.37
Latest Budget Changes
1309733.37
Total Budget Changes
20945057.00
Forecast Completion
2020-05-01T00:00:00.000
Latest Schedule Changes
305
Total Schedule Changes
1592
Dutch Kills and Lower Newtown Creek Enhanced Aeration Work
Date Reported As Of: 2015-08-01T00:00:00.000 • Pid: 313 • Project Name: Dutch Kills and Lower Newtown Creek Enhanced Aeration Work
Date Reported As Of
2015-08-01T00:00:00.000
Pid
313
Project Name
Dutch Kills and Lower Newtown Creek Enhanced Aeration Work
Description
This project will construct a blower facility and install a diffused aeration system in Dutch Kills and Newtown Creek to increase dissolved oxygen content in the project area to meet DEC standards for the water body.
Category
Wastewater Treatment
Borough
Queens
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2014-01-01T00:00:00.000
Budget Forecast
40484222.00
Latest Budget Changes
5585199.00
Total Budget Changes
-4338327.57
Forecast Completion
2019-04-14T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1891
Flatbush Avenue Trunk Watermain Replacement
Date Reported As Of: 2015-08-01T00:00:00.000 • Pid: 370 • Project Name: Flatbush Avenue Trunk Watermain Replacement
Date Reported As Of
2015-08-01T00:00:00.000
Pid
370
Project Name
Flatbush Avenue Trunk Watermain Replacement
Description
Replacement of trunk water main on Flatbush Avenue between Sterling place and 8th Avenue in addition to the distribution water main in 6th Avenue between Union Street and Park Place, and sections of adjoining streets.
Category
Wastewater Treatment
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2014-12-02T00:00:00.000
Budget Forecast
27688000.00
Latest Budget Changes
1884000.00
Total Budget Changes
39272000.00
Forecast Completion
2018-11-29T00:00:00.000
Latest Schedule Changes
52
Total Schedule Changes
2266
North River Wastewater Treatment Plant Cogeneration and Electrification
Date Reported As Of: 2015-08-01T00:00:00.000 • Pid: 423 • Project Name: North River Wastewater Treatment Plant Cogeneration and Electrification
Date Reported As Of
2015-08-01T00:00:00.000
Pid
423
Project Name
North River Wastewater Treatment Plant Cogeneration and Electrification
Description
This project will replace the 10 existing pump and blower engines with electric motors for the main sewage pumps and a new cogeneration facility consisting of 5 new dual fuel engines and electrical service distribution upgrades.
Category
Wastewater Treatment
Borough
New York
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2013-07-01T00:00:00.000
Budget Forecast
194860876.00
Latest Budget Changes
40404281.00
Total Budget Changes
134242052.88
Forecast Completion
2020-09-13T00:00:00.000
Latest Schedule Changes
148
Total Schedule Changes
1712
Bruckner Expressway Westchester Creek Bridge Reconstruction
Date Reported As Of: 2015-08-01T00:00:00.000 • Pid: 97 • Project Name: Bruckner Expressway Westchester Creek Bridge Reconstruction
Date Reported As Of
2015-08-01T00:00:00.000
Pid
97
Project Name
Bruckner Expressway Westchester Creek Bridge Reconstruction
Description
This project will replace the existing bridge with a new, wider double-leaf bascule bridge.
Category
Bridges, Streets and Roadways
Borough
Bronx
Managing Agency
DOT
Client Agency
DEP, DOT
Current Phase
Design
Design Start
2012-07-23T00:00:00.000
Budget Forecast
198843972.62
Latest Budget Changes
274011.62
Total Budget Changes
142277136.00
Forecast Completion
2020-08-17T00:00:00.000
Latest Schedule Changes
-58
Total Schedule Changes
2086
Grand Concourse Metro North Railroad Bridge Construction
Date Reported As Of: 2015-08-01T00:00:00.000 • Pid: 120 • Project Name: Grand Concourse Metro North Railroad Bridge Construction
Date Reported As Of
2015-08-01T00:00:00.000
Pid
120
Project Name
Grand Concourse Metro North Railroad Bridge Construction
Description
Repair the existing bridge and separate the NYCDOT and NYCT components. Includes new steel plate girders, concrete deck, pedestals, backwalls, sidewalks, and bridge railing.
Category
Bridges
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2000-02-14T00:00:00.000
Budget Forecast
65710551.35
Latest Budget Changes
12062000.35
Total Budget Changes
22682117.00
Forecast Completion
2020-12-17T00:00:00.000
Latest Schedule Changes
222
Total Schedule Changes
836
2nd Avenue Watermain Trunk Construction
Date Reported As Of: 2015-08-01T00:00:00.000 • Pid: 388 • Project Name: 2nd Avenue Watermain Trunk Construction
Date Reported As Of
2015-08-01T00:00:00.000
Pid
388
Project Name
2nd Avenue Watermain Trunk Construction
Description
Installation of trunk and distribution water mains for the 3rd water tunnel shaft 32B at 2nd Avenue.
Category
Water Supply
Borough
Manhattan
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2013-09-30T00:00:00.000
Budget Forecast
60802000.00
Latest Budget Changes
846000.00
Total Budget Changes
-7266000.00
Forecast Completion
2018-07-16T00:00:00.000
Latest Schedule Changes
31
Total Schedule Changes
2113
Gilboa Dam Reconstruction, Phase IV
Date Reported As Of: 2015-08-01T00:00:00.000 • Pid: 406 • Project Name: Gilboa Dam Reconstruction, Phase IV
Date Reported As Of
2015-08-01T00:00:00.000
Pid
406
Project Name
Gilboa Dam Reconstruction, Phase IV
Description
This project will rehabilitate the mechanics and the architecture of the Shandaken Tunnel Intake Chamber, which includes the replacement of gates and general site improvements.
Category
Water Supply
Borough
Upstate
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2008-12-01T00:00:00.000
Budget Forecast
45128381.00
Latest Budget Changes
-519858.00
Total Budget Changes
33535991.20
Forecast Completion
2020-04-03T00:00:00.000
Latest Schedule Changes
145
Total Schedule Changes
1684
Emergency Communications Transformation Program (ECTP) Upgrades and Enhancements
Date Reported As Of: 2015-08-01T00:00:00.000 • Pid: 267 • Project Name: Emergency Communications Transformation Program (ECTP) Upgrades and Enhancements
Date Reported As Of
2015-08-01T00:00:00.000
Pid
267
Project Name
Emergency Communications Transformation Program (ECTP) Upgrades and Enhancements
Description
Upgrade and enhancement of emergency technology infrastructure to improve interoperability and coordination among public safety agencies and improve call processing time to decrease overall response times.
Category
IT
Borough
Citywide
Managing Agency
DOITT
Client Agency
FDNY, NYPD
Current Phase
IT
Budget Forecast
2157312712.00
Latest Budget Changes
-113686995.00
Total Budget Changes
73735148.87
Forecast Completion
2017-11-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2252
20th Avenue Storm and Sanitary Sewer Construction
Date Reported As Of: 2015-08-01T00:00:00.000 • Pid: 432 • Project Name: 20th Avenue Storm and Sanitary Sewer Construction
Date Reported As Of
2015-08-01T00:00:00.000
Pid
432
Project Name
20th Avenue Storm and Sanitary Sewer Construction
Description
Construction of a new storm sewer in 20th Avenue between 126th Street and US Bulkhead.
Category
Sewers
Borough
Queens
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction Procurement
Design Start
2012-07-10T00:00:00.000
Budget Forecast
95366000.00
Latest Budget Changes
41119000.00
Total Budget Changes
117177000.00
Forecast Completion
2018-04-02T00:00:00.000
Latest Schedule Changes
80
Total Schedule Changes
2180
Emergency Communications Transformation Program (ECTP) Upgrades and Enhancements
Date Reported As Of: 2015-02-01T00:00:00.000 • Pid: 267 • Project Name: Emergency Communications Transformation Program (ECTP) Upgrades and Enhancements
Date Reported As Of
2015-02-01T00:00:00.000
Pid
267
Project Name
Emergency Communications Transformation Program (ECTP) Upgrades and Enhancements
Description
Upgrade and enhancement of emergency technology infrastructure to improve interoperability and coordination among public safety agencies and improve call processing time to decrease overall response times.
Category
IT
Borough
Citywide
Managing Agency
DOITT
Client Agency
FDNY, NYPD
Current Phase
IT
Budget Forecast
2270999707.00
Latest Budget Changes
-409480.00
Total Budget Changes
73735148.87
Forecast Completion
2017-11-30T00:00:00.000
Latest Schedule Changes
-31
Total Schedule Changes
2252
Edgewood Triangle Roadway Reconstruction
Date Reported As Of: 2015-02-01T00:00:00.000 • Pid: 204 • Project Name: Edgewood Triangle Roadway Reconstruction
Date Reported As Of
2015-02-01T00:00:00.000
Pid
204
Project Name
Edgewood Triangle Roadway Reconstruction
Description
Reconstruct roadway and extend storm and sanitary sewers in portions of Brookville Boulevard, Edgewood Street, 147th Avenue, and adjacent streets west of 241st Street.
Category
Streets and Roadways
Borough
Queens
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2013-02-13T00:00:00.000
Budget Forecast
29387000.00
Latest Budget Changes
816000.00
Total Budget Changes
106503000.00
Forecast Completion
2019-09-07T00:00:00.000
Latest Schedule Changes
332
Total Schedule Changes
3597
Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Date Reported As Of: 2015-02-01T00:00:00.000 • Pid: 112 • Project Name: Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Date Reported As Of
2015-02-01T00:00:00.000
Pid
112
Project Name
Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Description
Repair abutments, piers, approaches, and the steel superstructure. Replace reinforced concrete deck.
Category
Bridges, Streets and Roadways
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
1995-01-17T00:00:00.000
Budget Forecast
62601664.00
Latest Budget Changes
101528.00
Total Budget Changes
20945057.00
Forecast Completion
2019-07-01T00:00:00.000
Latest Schedule Changes
-305
Total Schedule Changes
1592
20th Avenue Storm and Sanitary Sewer Construction
Date Reported As Of: 2015-02-01T00:00:00.000 • Pid: 432 • Project Name: 20th Avenue Storm and Sanitary Sewer Construction
Date Reported As Of
2015-02-01T00:00:00.000
Pid
432
Project Name
20th Avenue Storm and Sanitary Sewer Construction
Description
Construction of a new storm sewer in 20th Avenue between 126th Street and US Bulkhead.
Category
Sewers
Borough
Queens
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2012-07-10T00:00:00.000
Budget Forecast
54247000.00
Latest Budget Changes
29558000.00
Total Budget Changes
117177000.00
Forecast Completion
2018-01-12T00:00:00.000
Latest Schedule Changes
196
Total Schedule Changes
2180
Roosevelt Avenue Bridge Superstructure and Substructure Repairs
Date Reported As Of: 2015-02-01T00:00:00.000 • Pid: 101 • Project Name: Roosevelt Avenue Bridge Superstructure and Substructure Repairs
Date Reported As Of
2015-02-01T00:00:00.000
Pid
101
Project Name
Roosevelt Avenue Bridge Superstructure and Substructure Repairs
Description
Repair the bridge superstructure and substructure and install a new concrete-filled steel grid deck.
Category
Bridges
Borough
Queens
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction Procurement
Design Start
2003-03-10T00:00:00.000
Budget Forecast
142097340.00
Latest Budget Changes
-5710999.00
Total Budget Changes
23798213.00
Forecast Completion
2023-01-11T00:00:00.000
Latest Schedule Changes
1749
Total Schedule Changes
2003
Bergen Avenue Street Reconstruction
Date Reported As Of: 2015-02-01T00:00:00.000 • Pid: 170 • Project Name: Bergen Avenue Street Reconstruction
Date Reported As Of
2015-02-01T00:00:00.000
Pid
170
Project Name
Bergen Avenue Street Reconstruction
Description
Roadway reconstruction Bergen Avenue and vicinity, includes sections of: Avenues N, T, U, V, W, X and Y; 66th Street and 69th through 75th Streets; Veterans Avenue and Royce Street.
Category
Streets and Roadways
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2012-12-03T00:00:00.000
Budget Forecast
19872000.00
Latest Budget Changes
-13124000.00
Total Budget Changes
45837000.00
Forecast Completion
2025-07-18T00:00:00.000
Latest Schedule Changes
367
Total Schedule Changes
-388
Gilboa Dam Reconstruction, Phase IV
Date Reported As Of: 2015-02-01T00:00:00.000 • Pid: 406 • Project Name: Gilboa Dam Reconstruction, Phase IV
Date Reported As Of
2015-02-01T00:00:00.000
Pid
406
Project Name
Gilboa Dam Reconstruction, Phase IV
Description
This project will rehabilitate the mechanics and the architecture of the Shandaken Tunnel Intake Chamber, which includes the replacement of gates and general site improvements.
Category
Water Supply
Borough
Upstate
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2008-12-01T00:00:00.000
Budget Forecast
45648239.00
Latest Budget Changes
-1369256.00
Total Budget Changes
33535991.20
Forecast Completion
2019-11-10T00:00:00.000
Latest Schedule Changes
133
Total Schedule Changes
1684
Wyckoff Avenue Street Reconstruction
Date Reported As Of: 2015-02-01T00:00:00.000 • Pid: 191 • Project Name: Wyckoff Avenue Street Reconstruction
Date Reported As Of
2015-02-01T00:00:00.000
Pid
191
Project Name
Wyckoff Avenue Street Reconstruction
Description
Reconstruction of Wyckoff Avenue from Flushing Avenue to Cooper Avenue, in the Boroughs of Brooklyn and Queens.
Category
Streets and Roadways
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Trans. & Env. Protection
Current Phase
Design
Design Start
2008-06-10T00:00:00.000
Budget Forecast
37180000.00
Latest Budget Changes
8393000.00
Total Budget Changes
43926000.00
Forecast Completion
2036-01-14T00:00:00.000
Latest Schedule Changes
182
Total Schedule Changes
226
Broadway Bridge over Harlem River Replacement
Date Reported As Of: 2015-02-01T00:00:00.000 • Pid: 106 • Project Name: Broadway Bridge over Harlem River Replacement
Date Reported As Of
2015-02-01T00:00:00.000
Pid
106
Project Name
Broadway Bridge over Harlem River Replacement
Description
Replace deteriorated members of lift span superstructure, concrete deck, lift electrical and mechanical systems, and fenders.
Category
Bridges
Borough
Bronx, Manhattan
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2005-04-01T00:00:00.000
Budget Forecast
109215563.00
Latest Budget Changes
-1110000.00
Total Budget Changes
39724388.00
Forecast Completion
2020-11-13T00:00:00.000
Latest Schedule Changes
466
Total Schedule Changes
2797
Reconstruction of the Port Jervis Wastewater Treatment Plant
Date Reported As Of: 2015-02-01T00:00:00.000 • Pid: 444 • Project Name: Reconstruction of the Port Jervis Wastewater Treatment Plant
Date Reported As Of
2015-02-01T00:00:00.000
Pid
444
Project Name
Reconstruction of the Port Jervis Wastewater Treatment Plant
Description
Reconstruction of the Port Jervis WWTP as required based on the effluent limits proposed by the Delaware River Basin Commission (DRBC)
Category
Wastewater Treatment
Borough
Port Jervis
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2014-06-17T00:00:00.000
Budget Forecast
51196478.00
Total Budget Changes
9428438.55
Forecast Completion
2020-01-24T00:00:00.000
Total Schedule Changes
2445
Dutch Kills and Lower Newtown Creek Enhanced Aeration Work
Date Reported As Of: 2015-02-01T00:00:00.000 • Pid: 313 • Project Name: Dutch Kills and Lower Newtown Creek Enhanced Aeration Work
Date Reported As Of
2015-02-01T00:00:00.000
Pid
313
Project Name
Dutch Kills and Lower Newtown Creek Enhanced Aeration Work
Description
This project will construct a blower facility and install a diffused aeration system in Dutch Kills and Newtown Creek to increase dissolved oxygen content in the project area to meet DEC standards for the water body.
Category
Wastewater Treatment
Borough
Queens
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2010-06-14T00:00:00.000
Budget Forecast
34899023.00
Latest Budget Changes
0.00
Total Budget Changes
-4338327.57
Forecast Completion
2019-04-14T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1891
Roma and Hett Avenue Storm and Sanitary Sewer Installation
Date Reported As Of: 2015-02-01T00:00:00.000 • Pid: 206 • Project Name: Roma and Hett Avenue Storm and Sanitary Sewer Installation
Date Reported As Of
2015-02-01T00:00:00.000
Pid
206
Project Name
Roma and Hett Avenue Storm and Sanitary Sewer Installation
Description
Roadway reconstruction and installation of new storm sewers and the replacement of sanitary sewers and water mains in the Midland Beach section, Staten Island.
Category
Sewers
Borough
Staten Island
Managing Agency
DDC
Client Agency
Trans. & Env. Protection
Current Phase
Design
Design Start
2008-06-19T00:00:00.000
Budget Forecast
42421000.00
Latest Budget Changes
-4739000.00
Total Budget Changes
62973000.00
Forecast Completion
2018-01-06T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
-8
Gilboa Dam Reconstruction, Phase III
Date Reported As Of: 2015-02-01T00:00:00.000 • Pid: 405 • Project Name: Gilboa Dam Reconstruction, Phase III
Date Reported As Of
2015-02-01T00:00:00.000
Pid
405
Project Name
Gilboa Dam Reconstruction, Phase III
Description
Gilboa Dam Reconstruction Project includes construction of a new low level outlet (LLO) consisting of 2,000 feet of tunneling, an access shaft, oulet structure and gate valve controls.
Category
Water Supply
Borough
Upstate
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction Procurement
Design Start
2004-03-18T00:00:00.000
Budget Forecast
226724491.00
Latest Budget Changes
3503278.00
Total Budget Changes
10376533.49
Forecast Completion
2020-07-20T00:00:00.000
Latest Schedule Changes
79
Total Schedule Changes
1113
Electronic Medical Records Upgrade
Date Reported As Of: 2015-02-01T00:00:00.000 • Pid: 403 • Project Name: Electronic Medical Records Upgrade
Date Reported As Of
2015-02-01T00:00:00.000
Pid
403
Project Name
Electronic Medical Records Upgrade
Description
Integrated Clinical Information System (ICIS) Program: Electronic Medical Records (EMR) System - a single enterprise-wide EMR to meet the needs of HHC's expansive size and improve patient care will replace the legacy EMR, which is over 25 years old.
Category
Health and Hospitals, IT
Borough
Citywide
Managing Agency
HHC
Client Agency
H+H
Current Phase
IT
Budget Forecast
764063231.00
Latest Budget Changes
15184947.00
Total Budget Changes
15184947.00
Forecast Completion
2018-12-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2032
West 59th Street Marine Transfer Station Construction, Phase 2
Date Reported As Of: 2015-02-01T00:00:00.000 • Pid: 347 • Project Name: West 59th Street Marine Transfer Station Construction, Phase 2
Date Reported As Of
2015-02-01T00:00:00.000
Pid
347
Project Name
West 59th Street Marine Transfer Station Construction, Phase 2
Description
Phase I repairs the inshore platform, replaces scales and control equipment, dredging around the pier, & site work. Phase 2 refurbishes existing pier building incl. pier structure, pile caps, fendering, construction of new emergency generator, etc.
Category
Sanitation
Borough
Manhattan
Managing Agency
DDC
Client Agency
Sanitation
Current Phase
Construction Procurement
Design Start
2012-01-17T00:00:00.000
Budget Forecast
89734000.00
Latest Budget Changes
0.00
Total Budget Changes
126753576.46
Forecast Completion
2018-08-18T00:00:00.000
Latest Schedule Changes
294
Total Schedule Changes
1949
Pelham Parkway Roadway Reconstruction, Phase 2
Date Reported As Of: 2015-02-01T00:00:00.000 • Pid: 180 • Project Name: Pelham Parkway Roadway Reconstruction, Phase 2
Date Reported As Of
2015-02-01T00:00:00.000
Pid
180
Project Name
Pelham Parkway Roadway Reconstruction, Phase 2
Description
Reconstruction of Pelham Parkway from the Bronx River Parkway to the Hutchinson River Parkway, including the north service road from Bronx Park East to Eastchester Road.
Category
Streets and Roadways
Borough
Bronx
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2002-02-20T00:00:00.000
Budget Forecast
36507404.00
Latest Budget Changes
2843404.00
Total Budget Changes
125164000.00
Forecast Completion
2017-05-15T00:00:00.000
Latest Schedule Changes
92
Total Schedule Changes
2869
Hannah Street Pumping Station Construction
Date Reported As Of: 2015-02-01T00:00:00.000 • Pid: 364 • Project Name: Hannah Street Pumping Station Construction
Date Reported As Of
2015-02-01T00:00:00.000
Pid
364
Project Name
Hannah Street Pumping Station Construction
Description
This project will reconstruct the Hannah St. Pumping Station, the largest City-owned wastewater collection and pumping station on Staten Island. Built in 1977, the facility has numerous deficiencies, needing a comprehensive upgrade.
Category
Wastewater Treatment
Borough
Staten Island
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2012-08-03T00:00:00.000
Budget Forecast
54200000.00
Latest Budget Changes
12060000.00
Total Budget Changes
67909196.80
Forecast Completion
2018-03-11T00:00:00.000
Latest Schedule Changes
39
Total Schedule Changes
3238
2nd Avenue Watermain Trunk Construction
Date Reported As Of: 2015-02-01T00:00:00.000 • Pid: 388 • Project Name: 2nd Avenue Watermain Trunk Construction
Date Reported As Of
2015-02-01T00:00:00.000
Pid
388
Project Name
2nd Avenue Watermain Trunk Construction
Description
Installation of trunk and distribution water mains for the 3rd water tunnel shaft 32B at 2nd Avenue.
Category
Water Supply
Borough
Manhattan
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2013-09-30T00:00:00.000
Budget Forecast
59956000.00
Latest Budget Changes
-362000.00
Total Budget Changes
-7266000.00
Forecast Completion
2018-06-15T00:00:00.000
Latest Schedule Changes
245
Total Schedule Changes
2113