All major infrastructure and information technology projects with a budget of $25 million or more that are currently active (in the design, procurement, or construction phase).
City GovernmentMayor's Office of Operations (OPS)
Dataset n7gv-k5yt
16 fields
Investigation and Remediation of Corrosion in Water Tunnel Facilities
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 457 • Project Name: Investigation and Remediation of Corrosion in Water Tunnel Facilities
Date Reported As Of
2023-01-01T00:00:00.000
Pid
457
Project Name
Investigation and Remediation of Corrosion in Water Tunnel Facilities
Description
Design Services for Investigation and Remediation of Corrosion in Water Tunnel Facilities
Category
Water Supply
Borough
Citywide
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2022-07-12T00:00:00.000
Budget Forecast
56020208.84
Latest Budget Changes
0.00
Total Budget Changes
0.00
Forecast Completion
2029-05-31T00:00:00.000
Latest Schedule Changes
335
Total Schedule Changes
335
Brooklyn Supreme Court Fire Alarm System Upgrade
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 510 • Project Name: Brooklyn Supreme Court Fire Alarm System Upgrade
Date Reported As Of
2023-01-01T00:00:00.000
Pid
510
Project Name
Brooklyn Supreme Court Fire Alarm System Upgrade
Description
Brooklyn Supreme Court, Fire Alarm, Sprinkler, 360 Adams Street - New addressable fire detection and alarm system and new sprinkler system.
Category
Public Safety and Criminal Justice
Borough
Brooklyn
Managing Agency
DDC
Client Agency
DCAS
Current Phase
Design
Design Start
2017-03-31T00:00:00.000
Budget Forecast
90313000.00
Latest Budget Changes
0.00
Total Budget Changes
47003000.00
Forecast Completion
2027-01-12T00:00:00.000
Latest Schedule Changes
105
Total Schedule Changes
1533
Replacement of the Esopus & Route 28A Railroad Bridges
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 443 • Project Name: Replacement of the Esopus & Route 28A Railroad Bridges
Date Reported As Of
2023-01-01T00:00:00.000
Pid
443
Project Name
Replacement of the Esopus & Route 28A Railroad Bridges
Description
Replacement of the Esopus & Route 28A Railroad Bridges
Category
Bridges
Borough
Olive
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2016-10-11T00:00:00.000
Budget Forecast
51873522.24
Latest Budget Changes
663242.28
Total Budget Changes
-50461071.35
Forecast Completion
2025-11-09T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
714
Gilboa Dam Reconstruction, Phase V
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 456 • Project Name: Gilboa Dam Reconstruction, Phase V
Date Reported As Of
2023-01-01T00:00:00.000
Pid
456
Project Name
Gilboa Dam Reconstruction, Phase V
Description
This is the final phase of the Gilboa Dam reconstruction project and includes reforestation, final site stabilization and wetlands mitigation measures.
Category
Water Supply
Borough
Upstate
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2020-12-30T00:00:00.000
Budget Forecast
36492236.00
Latest Budget Changes
-246464.00
Total Budget Changes
-3079490.00
Forecast Completion
2026-04-16T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
503
West Tremont Avenue over Metro North Railroad
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 503 • Project Name: West Tremont Avenue over Metro North Railroad
Date Reported As Of
2023-01-01T00:00:00.000
Pid
503
Project Name
West Tremont Avenue over Metro North Railroad
Description
Replace/Rehab the West Tremont Avenue bridge over the Metro North line, located in the Bronx.
Category
Bridges
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2018-01-16T00:00:00.000
Budget Forecast
91785543.00
Latest Budget Changes
-564000.00
Total Budget Changes
37794543.00
Forecast Completion
2027-10-04T00:00:00.000
Latest Schedule Changes
57
Total Schedule Changes
1253
Brooklyn Civil Court move to 210 Joralemon St
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 509 • Project Name: Brooklyn Civil Court move to 210 Joralemon St
Date Reported As Of
2023-01-01T00:00:00.000
Pid
509
Project Name
Brooklyn Civil Court move to 210 Joralemon St
Description
Relocation of Brooklyn Civil and Housing Court to 210 Joralemon St
Category
Public Safety and Criminal Justice
Borough
Brooklyn
Managing Agency
DCAS
Client Agency
DCAS
Current Phase
Construction
Design Start
2016-07-27T00:00:00.000
Budget Forecast
281430011.96
Latest Budget Changes
0.00
Total Budget Changes
200931011.96
Forecast Completion
2026-03-31T00:00:00.000
Latest Schedule Changes
301
Total Schedule Changes
1977
Rondout-West Branch Bypass Tunnel Construction Project 2
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 409 • Project Name: Rondout-West Branch Bypass Tunnel Construction Project 2
Date Reported As Of
2023-01-01T00:00:00.000
Pid
409
Project Name
Rondout-West Branch Bypass Tunnel Construction Project 2
Description
To address existing leaks in the Delaware Aqueduct, a 3-mile bypass tunnel will be constructed near the town of Roseton and the existing tunnel will be repaired near the town of Wawarsing.
Category
Water Supply
Borough
Marlboro
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2012-03-23T00:00:00.000
Budget Forecast
908466371.25
Latest Budget Changes
1376538.49
Total Budget Changes
202552329.25
Forecast Completion
2024-11-11T00:00:00.000
Latest Schedule Changes
28
Total Schedule Changes
256
20th Avenue Storm and Sanitary Sewer Construction
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 432 • Project Name: 20th Avenue Storm and Sanitary Sewer Construction
Date Reported As Of
2023-01-01T00:00:00.000
Pid
432
Project Name
20th Avenue Storm and Sanitary Sewer Construction
Description
Storm and sanitary sewers in 20th Ave between 126th Street and U.S. Bulkhead Line, etc. Water main works.
Category
Sewers
Borough
Queens
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2012-07-10T00:00:00.000
Budget Forecast
141866000.00
Latest Budget Changes
-10000.00
Total Budget Changes
117177000.00
Forecast Completion
2023-06-19T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2180
Oakwood Beach WWTP Sludge Thickening Improvements
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 449 • Project Name: Oakwood Beach WWTP Sludge Thickening Improvements
Date Reported As Of
2023-01-01T00:00:00.000
Pid
449
Project Name
Oakwood Beach WWTP Sludge Thickening Improvements
Description
Replacement of thickener pumps and associated controls/piping, digested sludge pumps, sludge mixing pumps, sludge recirculation pumps, spray water pumps, and seal water pumps
Category
Wastewater Treatment
Borough
Staten Island
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction Procurement
Design Start
2018-08-02T00:00:00.000
Budget Forecast
100168119.30
Latest Budget Changes
12287925.19
Total Budget Changes
57138101.30
Forecast Completion
2027-04-27T00:00:00.000
Latest Schedule Changes
259
Total Schedule Changes
3241
Bainbridge Avenue Trunk Water Main
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 454 • Project Name: Bainbridge Avenue Trunk Water Main
Date Reported As Of
2023-01-01T00:00:00.000
Pid
454
Project Name
Bainbridge Avenue Trunk Water Main
Description
Replacement of Trunk Water Main in Bainbridge Avenue Between Gunhill Road and Holly Lane and in Jerome Avenue Between Holly Lane and E233th Street, etc. Also, New 36" WM in West Burnside Avenue & Phelan Place
Category
Water Supply
Borough
Bronx
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2014-03-17T00:00:00.000
Budget Forecast
72349000.00
Latest Budget Changes
400000.00
Total Budget Changes
25547000.00
Forecast Completion
2023-06-30T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1687
FDR Rehabilitation, Northbound (East 42nd to 49th Streets)
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 502 • Project Name: FDR Rehabilitation, Northbound (East 42nd to 49th Streets)
Date Reported As Of
2023-01-01T00:00:00.000
Pid
502
Project Name
FDR Rehabilitation, Northbound (East 42nd to 49th Streets)
Description
Repair the northbound FDR from East 42nd to 49th Streets.
Category
Bridges
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2016-08-30T00:00:00.000
Budget Forecast
94710178.00
Latest Budget Changes
7630000.00
Total Budget Changes
-2802822.00
Forecast Completion
2030-03-22T00:00:00.000
Latest Schedule Changes
222
Total Schedule Changes
1816
Hannah Street Pumping Station Construction
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 364 • Project Name: Hannah Street Pumping Station Construction
Date Reported As Of
2023-01-01T00:00:00.000
Pid
364
Project Name
Hannah Street Pumping Station Construction
Description
This project will reconstruct the Hannah St. Pumping Station, the largest City-owned wastewater collection and pumping station on Staten Island. Built in 1977, the facility has numerous deficiencies, needing a comprehensive upgrade.
Category
Wastewater Treatment
Borough
Staten Island
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2012-08-03T00:00:00.000
Budget Forecast
109709196.80
Latest Budget Changes
6717034.57
Total Budget Changes
67909196.80
Forecast Completion
2026-06-23T00:00:00.000
Latest Schedule Changes
174
Total Schedule Changes
3238
2nd Avenue Watermain Trunk Construction
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 388 • Project Name: 2nd Avenue Watermain Trunk Construction
Date Reported As Of
2023-01-01T00:00:00.000
Pid
388
Project Name
2nd Avenue Watermain Trunk Construction
Description
Trunk and Distribution Main Connection to shaft 32B in 2nd Ave., etc., together with all work incidental thereto, Borough of Manhattan. 2nd Avenue from East 33rd Street to East 37th Street
Category
Water Supply
Borough
Manhattan
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2013-09-30T00:00:00.000
Budget Forecast
52942000.00
Latest Budget Changes
0.00
Total Budget Changes
-7266000.00
Forecast Completion
2023-07-27T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2113
Pelham Parkway Bridge Reconstruction over Hutchinson Parkway
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 506 • Project Name: Pelham Parkway Bridge Reconstruction over Hutchinson Parkway
Date Reported As Of
2023-01-01T00:00:00.000
Pid
506
Project Name
Pelham Parkway Bridge Reconstruction over Hutchinson Parkway
Description
Replace/Rehab the Pelham Parkway bridge over Hutchinson River Parkway, Bronx.
Category
Bridges, Streets and Roadways
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-11-08T00:00:00.000
Budget Forecast
67133092.00
Latest Budget Changes
350000.00
Total Budget Changes
10338071.57
Forecast Completion
2029-08-15T00:00:00.000
Latest Schedule Changes
60
Total Schedule Changes
1934
Electronic Medical Records Upgrade
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 403 • Project Name: Electronic Medical Records Upgrade
Date Reported As Of
2023-01-01T00:00:00.000
Pid
403
Project Name
Electronic Medical Records Upgrade
Description
The EPIC - EMR Program: Electronic Medical Records (EMR) System - a single enterprise-wide EMR to meet the needs of HHC's expansive size and improve patient care will replace the legacy EMR - QuadraMed, which is over 25 years old.
Category
Health and Hospitals, IT
Borough
Citywide
Managing Agency
HHC
Client Agency
H+H
Current Phase
IT
Budget Forecast
764063231.00
Latest Budget Changes
0.00
Total Budget Changes
15184947.00
Forecast Completion
2023-12-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2032
Gilboa Dam Reconstruction, Phase IV
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 406 • Project Name: Gilboa Dam Reconstruction, Phase IV
Date Reported As Of
2023-01-01T00:00:00.000
Pid
406
Project Name
Gilboa Dam Reconstruction, Phase IV
Description
This project will rehabilitate the mechanics and the architecture of the Shandaken Tunnel Intake Chamber, which includes the replacement of gates and general site improvements.
Category
Water Supply
Borough
Upstate
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2008-12-01T00:00:00.000
Budget Forecast
71013192.20
Latest Budget Changes
-33000.00
Total Budget Changes
33535991.20
Forecast Completion
2023-03-27T00:00:00.000
Latest Schedule Changes
120
Total Schedule Changes
1684
GI - GRAVESEND BAY CSO - PHASE II
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 1198 • Project Name: GI - GRAVESEND BAY CSO - PHASE II
Date Reported As Of
2023-01-01T00:00:00.000
Pid
1198
Project Name
GI - GRAVESEND BAY CSO - PHASE II
Description
GREEN INFRASTRUCTURE IN OH-015 GRAVESEND BAY CSO PH 2
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction Procurement
Design Start
2017-10-30T00:00:00.000
Budget Forecast
55026000.00
Latest Budget Changes
0.00
Total Budget Changes
13699000.00
Forecast Completion
2024-12-09T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
29
North River Wastewater Treatment Plant Cogeneration and Electrification
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 423 • Project Name: North River Wastewater Treatment Plant Cogeneration and Electrification
Date Reported As Of
2023-01-01T00:00:00.000
Pid
423
Project Name
North River Wastewater Treatment Plant Cogeneration and Electrification
Description
This project will replace the 10 existing pump and blower engines with electric motors for the main sewage pumps and a new cogeneration facility consisting of 5 new dual fuel engines and electrical service distribution upgrades.
Category
Wastewater Treatment
Borough
New York
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2013-07-01T00:00:00.000
Budget Forecast
287224972.88
Latest Budget Changes
1560089.01
Total Budget Changes
134242052.88
Forecast Completion
2024-01-13T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1712
Reconstruction of the Port Jervis Wastewater Treatment Plant
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 444 • Project Name: Reconstruction of the Port Jervis Wastewater Treatment Plant
Date Reported As Of
2023-01-01T00:00:00.000
Pid
444
Project Name
Reconstruction of the Port Jervis Wastewater Treatment Plant
Description
Reconstruction of the Port Jervis WWTP as required based on the effluent limits proposed by the Delaware River Basin Commission (DRBC)
Category
Wastewater Treatment
Borough
Port Jervis
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2014-06-17T00:00:00.000
Budget Forecast
60624916.55
Latest Budget Changes
0.00
Total Budget Changes
9428438.55
Forecast Completion
2026-10-04T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2445
Jerome Reservoir and Aqueduct Rehabilitation
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 448 • Project Name: Jerome Reservoir and Aqueduct Rehabilitation
Date Reported As Of
2023-01-01T00:00:00.000
Pid
448
Project Name
Jerome Reservoir and Aqueduct Rehabilitation
Description
Improvements to: fencing, vegetation, roadway, drainage, ext. above-ground retaining walls. Including repair of dam inlet archway & wingwall, re-pointing of stones & reinforcement of east reservoir wall, & leakage/seepage protection within OCA.
Category
Water Supply
Borough
Bronx
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2016-02-24T00:00:00.000
Budget Forecast
57966722.86
Latest Budget Changes
0.00
Total Budget Changes
-833277.14
Forecast Completion
2026-12-29T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2363
Oakwood Beach WWTP Headworks Improvements
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 450 • Project Name: Oakwood Beach WWTP Headworks Improvements
Date Reported As Of
2023-01-01T00:00:00.000
Pid
450
Project Name
Oakwood Beach WWTP Headworks Improvements
Description
Replacement of six bar screens, grit bin vibrator, six ring flushing pumps, six main sewage pumps and assoc. piping/valves and motor control center, replacement of four exhaust fans, gas and oxygen detectors and a 15 KVA transformer
Category
Wastewater Treatment
Borough
Staten Island
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2023-02-01T00:00:00.000
Budget Forecast
83229440.00
Latest Budget Changes
0.00
Total Budget Changes
31867440.00
Forecast Completion
2029-04-25T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2857
Reconstruction of Power Distribution at Wards Island WWTP
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 453 • Project Name: Reconstruction of Power Distribution at Wards Island WWTP
Date Reported As Of
2023-01-01T00:00:00.000
Pid
453
Project Name
Reconstruction of Power Distribution at Wards Island WWTP
Description
Upgrades significant portions of the electrical distribution infrastructure including 3 power center installations, 15 motor control centers, 6 automatic transfer switches and 20 transformers throughout the plant
Category
Wastewater Treatment
Borough
Manhattan
Managing Agency
DEP
Client Agency
DEP
Current Phase
Design
Design Start
2019-06-04T00:00:00.000
Budget Forecast
149106268.26
Latest Budget Changes
0.00
Total Budget Changes
33489860.26
Forecast Completion
2028-03-04T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1147
Catskill Aqueduct Repair and Rehabilitation
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 478 • Project Name: Catskill Aqueduct Repair and Rehabilitation
Date Reported As Of
2023-01-01T00:00:00.000
Pid
478
Project Name
Catskill Aqueduct Repair and Rehabilitation
Description
Project to ensure the reliability of the 74 mile upper Catskill Aqueduct, including replacement of mechanical components, leak mitigation, and biofilm removal/condition assessment.
Category
Water Supply
Borough
Citywide
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2015-06-19T00:00:00.000
Budget Forecast
237517401.68
Latest Budget Changes
-4752101.50
Total Budget Changes
9642889.68
Forecast Completion
2022-11-30T00:00:00.000
Latest Schedule Changes
15
Total Schedule Changes
1517
DBCD South Site Cultural Fit-Out
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 484 • Project Name: DBCD South Site Cultural Fit-Out
Date Reported As Of
2023-01-01T00:00:00.000
Pid
484
Project Name
DBCD South Site Cultural Fit-Out
Description
Interior fit-out of the south site cultural unit.
Category
Arts and Culture
Borough
Brooklyn
Managing Agency
EDC
Client Agency
DCLA
Current Phase
Construction
Design Start
2014-12-01T00:00:00.000
Budget Forecast
71317591.86
Latest Budget Changes
800642.00
Total Budget Changes
36789601.16
Forecast Completion
2023-09-02T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1706
Edgewood Triangle Roadway Reconstruction
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 204 • Project Name: Edgewood Triangle Roadway Reconstruction
Date Reported As Of
2023-01-01T00:00:00.000
Pid
204
Project Name
Edgewood Triangle Roadway Reconstruction
Description
Reconstruct roadway and extend storm and sanitary sewers in portions of Brookville Boulevard, Edgewood Street, 147th Avenue, and adjacent streets west of 241st Street.
Category
Streets and Roadways
Borough
Queens
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Design
Design Start
2012-08-17T00:00:00.000
Budget Forecast
134639000.00
Latest Budget Changes
0.00
Total Budget Changes
106503000.00
Forecast Completion
2028-08-15T00:00:00.000
Latest Schedule Changes
86
Total Schedule Changes
3597
Pelham Parkway Roadway Reconstruction, Phase 2
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 180 • Project Name: Pelham Parkway Roadway Reconstruction, Phase 2
Date Reported As Of
2023-01-01T00:00:00.000
Pid
180
Project Name
Pelham Parkway Roadway Reconstruction, Phase 2
Description
Pelham Pkwy main road W/B from Bronx River Pkwy to Hutchinson River Pkwy Pelham Pkwy North Service Rd. (S/R) from Bronx Park East to Eastchester Rd. Stillwell Ave from westbound mainline to north service road
Category
Streets and Roadways
Borough
Bronx
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction
Design Start
2002-02-15T00:00:00.000
Budget Forecast
158533000.00
Latest Budget Changes
0.00
Total Budget Changes
125164000.00
Forecast Completion
2023-12-22T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2869
Riverside Drive/West 158th Street Bridge Rehabilitation
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 113 • Project Name: Riverside Drive/West 158th Street Bridge Rehabilitation
Date Reported As Of
2023-01-01T00:00:00.000
Pid
113
Project Name
Riverside Drive/West 158th Street Bridge Rehabilitation
Description
Replace deck of the Riverside Drive viaduct/ bridge over West 158th Street.
Category
Bridges, Streets and Roadways
Borough
Manhattan
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2014-10-22T00:00:00.000
Budget Forecast
151628794.00
Latest Budget Changes
7058936.00
Total Budget Changes
96922794.00
Forecast Completion
2025-05-21T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2152
Grand Concourse Metro North Railroad Bridge Construction
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 120 • Project Name: Grand Concourse Metro North Railroad Bridge Construction
Date Reported As Of
2023-01-01T00:00:00.000
Pid
120
Project Name
Grand Concourse Metro North Railroad Bridge Construction
Description
Repair the existing bridge and separate the NYCDOT and NYCT components. Includes new steel plate girders, concrete deck, pedestals, backwalls, sidewalks, and bridge railing.
Category
Bridges
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2000-02-14T00:00:00.000
Budget Forecast
72968117.00
Latest Budget Changes
-532000.00
Total Budget Changes
22682117.00
Forecast Completion
2023-01-16T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
836
Flatbush Avenue Trunk Watermain Replacement
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 370 • Project Name: Flatbush Avenue Trunk Watermain Replacement
Date Reported As Of
2023-01-01T00:00:00.000
Pid
370
Project Name
Flatbush Avenue Trunk Watermain Replacement
Description
72" Trunk Water Main and Combined Sewer Replacement in Flatbush Ave. between Sterling Pl. and 8th Ave., etc., Borough of Brooklyn.
Category
Wastewater Treatment
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Construction
Design Start
2014-11-24T00:00:00.000
Budget Forecast
59124000.00
Latest Budget Changes
200000.00
Total Budget Changes
39272000.00
Forecast Completion
2023-09-29T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2266
5th Avenue Bridge Reconstruction over LIRR and Sea Beach, Brooklyn
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 504 • Project Name: 5th Avenue Bridge Reconstruction over LIRR and Sea Beach, Brooklyn
Date Reported As Of
2023-01-01T00:00:00.000
Pid
504
Project Name
5th Avenue Bridge Reconstruction over LIRR and Sea Beach, Brooklyn
Description
Replace the 5th Avenue Bridge over LIRR & Sea Beach, Brooklyn.
Category
Bridges
Borough
Brooklyn
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction Procurement
Design Start
2017-11-30T00:00:00.000
Budget Forecast
83778580.00
Latest Budget Changes
-2732781.00
Total Budget Changes
36577693.00
Forecast Completion
2027-07-01T00:00:00.000
Latest Schedule Changes
-135
Total Schedule Changes
969
Emergency Communications Transformation Program (ECTP) Upgrades and Enhancements
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 267 • Project Name: Emergency Communications Transformation Program (ECTP) Upgrades and Enhancements
Date Reported As Of
2023-01-01T00:00:00.000
Pid
267
Project Name
Emergency Communications Transformation Program (ECTP) Upgrades and Enhancements
Description
Upgrade and enhancement of emergency technology infrastructure to improve interoperability and coordination among public safety agencies and improve call processing time to decrease overall response times.
Category
IT
Borough
Citywide
Managing Agency
DOITT
Client Agency
FDNY, NYPD
Current Phase
IT
Budget Forecast
2325426529.98
Latest Budget Changes
-1174838.83
Total Budget Changes
73735148.87
Forecast Completion
2024-03-01T00:00:00.000
Latest Schedule Changes
337
Total Schedule Changes
2252
GI-OWLS HEAD TRIBUTARY DRAINAGE AREAS, BROOKLYN
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 1200 • Project Name: GI-OWLS HEAD TRIBUTARY DRAINAGE AREAS, BROOKLYN
Date Reported As Of
2023-01-01T00:00:00.000
Pid
1200
Project Name
GI-OWLS HEAD TRIBUTARY DRAINAGE AREAS, BROOKLYN
Description
GREEN INFRASTRUCTURE IN OWLS HEAD TRIBUTARY DRAINAGE AREAS, BROOKLYN
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2019-01-02T00:00:00.000
Budget Forecast
60387000.00
Latest Budget Changes
300000.00
Total Budget Changes
24278000.00
Forecast Completion
2027-07-02T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
396
Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 112 • Project Name: Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Date Reported As Of
2023-01-01T00:00:00.000
Pid
112
Project Name
Westchester Avenue Bridge over Hutch River Parkway Rehabilitation
Description
Repair abutments, piers, approaches, and steel superstructure located in Pelham Bay, Bronx; replace reinforced concrete deck.
Category
Bridges, Streets and Roadways
Borough
Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
1995-01-17T00:00:00.000
Budget Forecast
79204057.00
Latest Budget Changes
471000.00
Total Budget Changes
20945057.00
Forecast Completion
2023-07-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1592
Gilboa Dam Reconstruction, Phase III
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 405 • Project Name: Gilboa Dam Reconstruction, Phase III
Date Reported As Of
2023-01-01T00:00:00.000
Pid
405
Project Name
Gilboa Dam Reconstruction, Phase III
Description
Gilboa Dam Reconstruction Project includes construction of a new low level outlet (LLO) consisting of 2,000 feet of tunneling , an access shaft, oulet structure and gate valve controls.
Category
Water Supply
Borough
Upstate
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2004-03-18T00:00:00.000
Budget Forecast
199398344.49
Latest Budget Changes
-1313992.21
Total Budget Changes
10376533.49
Forecast Completion
2023-06-15T00:00:00.000
Latest Schedule Changes
81
Total Schedule Changes
1113
Bergen Avenue Street Reconstruction
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 170 • Project Name: Bergen Avenue Street Reconstruction
Date Reported As Of
2023-01-01T00:00:00.000
Pid
170
Project Name
Bergen Avenue Street Reconstruction
Description
Reconstruction of Bergen Avenue Area, including Storm Sewers, Water Mains, Street Lighting, Traffic Signal Work, and reconstruction of new outfall at East Mill Basin.
Category
Streets and Roadways
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction
Design Start
2012-12-03T00:00:00.000
Budget Forecast
79564000.00
Latest Budget Changes
0.00
Total Budget Changes
45837000.00
Forecast Completion
2023-06-24T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
-388
Broadway Bridge over Harlem River Replacement
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 106 • Project Name: Broadway Bridge over Harlem River Replacement
Date Reported As Of
2023-01-01T00:00:00.000
Pid
106
Project Name
Broadway Bridge over Harlem River Replacement
Description
Replace deteriorated members of lift span superstructure, concrete deck, lift electrical and mechanical systems, and fenders.
Category
Bridges
Borough
Bronx, Manhattan
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2005-04-01T00:00:00.000
Budget Forecast
148960388.00
Latest Budget Changes
-1088222.00
Total Budget Changes
39724388.00
Forecast Completion
2027-04-02T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2797
Wyckoff Avenue Street Reconstruction
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 191 • Project Name: Wyckoff Avenue Street Reconstruction
Date Reported As Of
2023-01-01T00:00:00.000
Pid
191
Project Name
Wyckoff Avenue Street Reconstruction
Description
Reconstruction of Wyckoff Avenue from Flushing Avenue to Cooper Avenue, in the Boroughs of Brooklyn and Queens..
Category
Streets and Roadways
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Trans. & Env. Protection
Current Phase
Design
Design Start
2017-03-29T00:00:00.000
Budget Forecast
77097000.00
Latest Budget Changes
0.00
Total Budget Changes
43926000.00
Forecast Completion
2027-02-27T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
226
Roma and Hett Avenue Storm and Sanitary Sewer Installation
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 206 • Project Name: Roma and Hett Avenue Storm and Sanitary Sewer Installation
Date Reported As Of
2023-01-01T00:00:00.000
Pid
206
Project Name
Roma and Hett Avenue Storm and Sanitary Sewer Installation
Description
Installation of Storm, Sanitary Sewers in the following Streets:=================================1- Cedar Grove Avenue between Ebbitts Street and new Dorp Lane.2- Milton Avenue between Ebbitts Street and new Dorp Lane.3- Finley Avenue between Ebbitts Street and new Dorp Lane.4- Roma Avenue between Ebbitts Street and new Dorp Lane.5- Hett Avenue between Ebbitts Street and new Dorp Lane.6- Marine Way between Cedar Grove and Milton Avenue7- Beacon Avenue between Roma Avenue and Milton Avenue.8- Dustan Avenue between Marine way and Milton Avenue.9- Garibaldi Avenue between Roma Avenue and Cedar Grove Avenue.10- Cedar Grove Court between Cedar Grove Avenue and Dustan Street.11- Topping Street between Cedar Grove Avenue and Dustan Street.12- Center Way between Cedar Grove Avenue and Dustan Street.13- Neptune Street between Cedar Grove Avenue and Dustan Street.14- Seafoam Street between Cedar Grove Avenue and Dustan Street.15- Waterside Street between Cedar Grove Avenue and Dustan Street.16- Maple Terrace between Cedar Grove Avenue and Dustan Street.17- Herman Street between Cedar Grove Avenue and Dustan Street.18- Neutral Avenue between Cedar Grove Avenue and Dustan Street.19- Milbank Drive between Cedar Grove Avenue and Dustan Street.
Category
Sewers
Borough
Staten Island
Managing Agency
DDC
Client Agency
Trans. & Env. Protection
Current Phase
Construction
Design Start
2014-10-15T00:00:00.000
Budget Forecast
94191000.00
Latest Budget Changes
0.00
Total Budget Changes
62973000.00
Forecast Completion
2023-12-22T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
-8
West 59th Street Marine Transfer Station Construction, Phase 2
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 347 • Project Name: West 59th Street Marine Transfer Station Construction, Phase 2
Date Reported As Of
2023-01-01T00:00:00.000
Pid
347
Project Name
West 59th Street Marine Transfer Station Construction, Phase 2
Description
Project 2 Scope: Refurbishment of the existing pier building including: repair of existing pier structure including pile caps and fendering; construction of new emergency generator, electrical, mechanical, fire pump and fire valve rooms; new exit passageway construction and existing exit passageway refurbishment; re-arrangement and refurbishment of the Operations Building interiors; replacement of fire suppression system throughout the entire pier structure; mechanical, electrical and plumbing system upgrades; refurbishment and painting the existing pier interior steel framing and wall/roof surfaces; recoating the structure's exterior cladding systems including metal wall and roof panel system and translucent panel wall cladding system.
Category
Sanitation
Borough
Manhattan
Managing Agency
DDC
Client Agency
Sanitation
Current Phase
Construction
Design Start
2012-01-17T00:00:00.000
Budget Forecast
187830576.46
Latest Budget Changes
0.00
Total Budget Changes
126753576.46
Forecast Completion
2023-05-31T00:00:00.000
Latest Schedule Changes
215
Total Schedule Changes
1949
Bruckner Expressway Westchester Creek Bridge Reconstruction
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 97 • Project Name: Bruckner Expressway Westchester Creek Bridge Reconstruction
Date Reported As Of
2023-01-01T00:00:00.000
Pid
97
Project Name
Bruckner Expressway Westchester Creek Bridge Reconstruction
Description
Replace the existing bridge with a new, wider double-leaf bascule bridge in the Bronx.
Category
Bridges, Streets and Roadways
Borough
Bronx
Managing Agency
DOT
Client Agency
DEP, DOT
Current Phase
Construction
Design Start
2012-07-23T00:00:00.000
Budget Forecast
297884658.00
Latest Budget Changes
6225760.00
Total Budget Changes
142277136.00
Forecast Completion
2023-12-27T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2086
New Ferry Boat Construction
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 94 • Project Name: New Ferry Boat Construction
Date Reported As Of
2023-01-01T00:00:00.000
Pid
94
Project Name
New Ferry Boat Construction
Description
Replace one Barberi class boat and the John F. Kennedy boat which are approaching the end of their useful lives with new Staten Island ferries. Replacement is needed to continue reliable service.
Category
Ferries
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2014-09-15T00:00:00.000
Budget Forecast
22204190.00
Latest Budget Changes
34000.00
Total Budget Changes
-238419180.00
Total Schedule Changes
549
Roosevelt Avenue Bridge Superstructure and Substructure Repairs
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 101 • Project Name: Roosevelt Avenue Bridge Superstructure and Substructure Repairs
Date Reported As Of
2023-01-01T00:00:00.000
Pid
101
Project Name
Roosevelt Avenue Bridge Superstructure and Substructure Repairs
Description
Repair the bridge superstructure and substructure and install a new concrete-filled steel grid deck.
Category
Bridges
Borough
Queens
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2003-03-10T00:00:00.000
Budget Forecast
147182213.00
Latest Budget Changes
-14677352.00
Total Budget Changes
23798213.00
Forecast Completion
2023-08-07T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2003
Dumbo and Vinegar Hill Area Roadway Reconstruction and Renovation
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 193 • Project Name: Dumbo and Vinegar Hill Area Roadway Reconstruction and Renovation
Date Reported As Of
2023-01-01T00:00:00.000
Pid
193
Project Name
Dumbo and Vinegar Hill Area Roadway Reconstruction and Renovation
Description
Reconstruction DUMBO/Vinegar Hill Area including Trunk and Distribution water main replacement; Installation of HLSS and Combined Sewer replacement; Restoration of Belgian block in Water Street; Street lighting and Traffic Signal work.
Category
Streets and Roadways
Borough
Brooklyn
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction
Design Start
2012-06-07T00:00:00.000
Budget Forecast
130324000.00
Latest Budget Changes
-1015000.00
Total Budget Changes
96724000.00
Forecast Completion
2024-06-04T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
3253
Dutch Kills and Lower Newtown Creek Enhanced Aeration Work
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 313 • Project Name: Dutch Kills and Lower Newtown Creek Enhanced Aeration Work
Date Reported As Of
2023-01-01T00:00:00.000
Pid
313
Project Name
Dutch Kills and Lower Newtown Creek Enhanced Aeration Work
Description
This project will upgrade the Borden Ave Pump Station. Footprint of the PS will be increased to ~ 2750 square feet. Convert dry well into wet well. Replace existing non-submersible pumps with submersible pumps while maintaining PS capacity of 3.9 MGD. Provide emergency portable diesel driven 4.5 MGD pump. Installation of new electrical, controls (SCADA), mechanical & HVAC systems. Provisions to support a future project to expand capacity of the PS from 3.9 MGD to 26 MGD. Upgrade resiliency per BWT guidelines. Line existing 14" Force Main
Category
Wastewater Treatment
Borough
Queens
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2014-01-01T00:00:00.000
Budget Forecast
33485716.43
Latest Budget Changes
0.00
Total Budget Changes
-4338327.57
Forecast Completion
2024-06-18T00:00:00.000
Latest Schedule Changes
19
Total Schedule Changes
1891
49th Avenue Bridge Replacement
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 131 • Project Name: 49th Avenue Bridge Replacement
Date Reported As Of
2023-01-01T00:00:00.000
Pid
131
Project Name
49th Avenue Bridge Replacement
Description
Replace the 49th Avenue bridge over Long Island Railroad and Amtrak in Hunters Point, Queens.
Category
Bridges, Streets and Roadways
Borough
Queens
Managing Agency
DOT
Client Agency
DOT
Current Phase
Design
Design Start
2017-08-15T00:00:00.000
Budget Forecast
114154419.00
Latest Budget Changes
530000.00
Total Budget Changes
32902419.00
Forecast Completion
2028-10-16T00:00:00.000
Latest Schedule Changes
100
Total Schedule Changes
1449
Primary Treatment Improvement at Wards Island WWTP
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 452 • Project Name: Primary Treatment Improvement at Wards Island WWTP
Date Reported As Of
2023-01-01T00:00:00.000
Pid
452
Project Name
Primary Treatment Improvement at Wards Island WWTP
Description
Replacement of collector drives, scum trough dipping weirs and dump valves for ten primary settling tanks. Also included are Influent channel mixing and seal water system for the primary sludge pumps and concrete repairs.
Category
Wastewater Treatment
Borough
Manhattan
Managing Agency
DEP
Client Agency
DEP
Current Phase
Construction
Design Start
2017-11-06T00:00:00.000
Budget Forecast
146107921.98
Latest Budget Changes
2277592.62
Total Budget Changes
99651290.98
Forecast Completion
2027-04-09T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
2142
Madison Avenue Bridge Reconstruction
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 114 • Project Name: Madison Avenue Bridge Reconstruction
Date Reported As Of
2023-01-01T00:00:00.000
Pid
114
Project Name
Madison Avenue Bridge Reconstruction
Description
Replace the electrical and mechanical systems of the Madison Avenue Bridge.
Category
Bridges
Borough
Manhattan, Bronx
Managing Agency
DOT
Client Agency
DOT
Current Phase
Construction
Design Start
2011-02-14T00:00:00.000
Budget Forecast
56546302.00
Latest Budget Changes
1121903.00
Total Budget Changes
2036997.00
Forecast Completion
2023-01-31T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1628
Grand Concourse Reconstruction, Phase 4 (Great Streets)
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 476 • Project Name: Grand Concourse Reconstruction, Phase 4 (Great Streets)
Date Reported As Of
2023-01-01T00:00:00.000
Pid
476
Project Name
Grand Concourse Reconstruction, Phase 4 (Great Streets)
Description
RECONSTRUCTION OF GRAND CONCOURSE FROM E 175 ST TO EAST FORDHAM RD- PHASE 4, BX
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Transportation
Current Phase
Construction
Design Start
2016-07-19T00:00:00.000
Budget Forecast
96108000.00
Latest Budget Changes
0.00
Total Budget Changes
57634000.00
Forecast Completion
2023-06-13T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
1448
GI - GRAVESEND BAY CSO - PHASE III
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 1199 • Project Name: GI - GRAVESEND BAY CSO - PHASE III
Date Reported As Of
2023-01-01T00:00:00.000
Pid
1199
Project Name
GI - GRAVESEND BAY CSO - PHASE III
Description
GREEN INFRASTRUCTURE IN OH-015 GRAVESEND BAY CSO PH 3
Category
Streets and Roadways
Managing Agency
DDC
Client Agency
Environmental Protection
Current Phase
Design
Design Start
2017-08-01T00:00:00.000
Budget Forecast
49132000.00
Latest Budget Changes
0.00
Total Budget Changes
-372000.00
Forecast Completion
2025-11-19T00:00:00.000
Latest Schedule Changes
0
Total Schedule Changes
189
Coney Island Area, Phase 3A
Date Reported As Of: 2023-01-01T00:00:00.000 • Pid: 516 • Project Name: Coney Island Area, Phase 3A
Date Reported As Of
2023-01-01T00:00:00.000
Pid
516
Project Name
Coney Island Area, Phase 3A
Description
Reconstruction of Storm and Sanitary sewer, Trunk and distribution water main in Coney Island area - Phase 3A, Borough of Brooklyn