Dataset nfz9-tzba
14 fields
DOWNLOAD CSV
SEARCH RECORDS
Dataset fields
Sited
Leased
District
Project #
School
Boro
Forecast Capacity
Design Start
Construction Start
Actual Est. Comp
Total Est.Cost
Previous Appropriations
Funding Req'd FY 25-29
Needed toComplete
Showing field:
SHOW ALL FIELDS
Showing 1 real records
YES
Existing Site Identified: YES • Proposed Leased Facility: YES • District: 20
Existing Site Identified
YES
Proposed Leased Facility
YES
District
20
Project
DSF0000866170
School
PRE-K CENTER @ 412 63 STREET
Boro
BROOKLYN
Forecast Capacity
90
Design Start
16-Nov
Constr Start
25-May
Actual Est Compl
26-Dec
Total Est Cost
12.65
Previousappropriations
1.53
Fundingreq Dfy 15 19
11.11
Needed Tocomplete
0