SCA
Vote Year: 2016 • Fiscal Year: FY17 • District: 32
Vote Year
2016
Fiscal Year
FY17
District
32
Project
Upgrades to 6 Schools- BEACH CHANNEL EDUCATION CAMPUS (Site 5 of 6)
Ballot Price
435000.00
Subproject Cost
150000.00
Total Appropriated
435000.00
Number Of Subprojects
6
Agency
SCA
Non City
N
Description
P.S. 47 – Tech equipment ($45,000) // P.S. 317 – Tech equipment ($45,000) // P.S. 114 – Auditorium upgrades ($75,000) // Beach Channel Campus – mobile earth science lab cart RCHS ($60,000) // Beach Channel Campus – New exercise room with updated equipment ($150,000) // Scholar’s Academy – Bathroom updates ($60,000)
Installation Location
100-00 Beach Channel Dr, Rockaway Park
Mapping Location
40.586717, -73.823441
Status Summary
Part of Capital Plan- Funding Approved
Postcode
11694
Borough
QUEENS
Community Board
14
Census Tract
94201
Bin
4303773
Bbl
4161670099
Nta
Breezy Point-Belle Harbor-Rockaway Park-Broad Channel
SCA
Vote Year: 2016 • Fiscal Year: FY17 • District: 35
Vote Year
2016
Fiscal Year
FY17
District
35
Project
Learning Walls for P.S. 20
Ballot Price
36500.00
Subproject Cost
36500.00
Total Appropriated
37000.00
Agency
SCA
Non City
N
Description
Install pin-able writable walls in 20 classrooms for students and teachers to actively co-create learning. 5 temporary walls already increasing learning, initiation, critical thinking and cooperation.
Installation Location
PS 20 The Clinton Hill School 225 Adelphi Street
Mapping Location
40.691343, -73.971280
Status Summary
Part of Capital Plan- Funding Approved
SCA
Vote Year: 2016 • Fiscal Year: FY17 • District: 32
Vote Year
2016
Fiscal Year
FY17
District
32
Project
Upgrades to 6 Schools- SCHOLARS ACADEMY (Site 6 of 6)
Ballot Price
435000.00
Subproject Cost
60000.00
Total Appropriated
435000.00
Number Of Subprojects
6
Agency
SCA
Non City
N
Description
P.S. 47 – Tech equipment ($45,000) // P.S. 317 – Tech equipment ($45,000) // P.S. 114 – Auditorium upgrades ($75,000) // Beach Channel Campus – mobile earth science lab cart RCHS ($60,000) // Beach Channel Campus – New exercise room with updated equipment ($150,000) // Scholar’s Academy – Bathroom updates ($60,000)
Installation Location
320 Beach 104th St, Rockaway Park
Mapping Location
40.584309, -73.825176
Status Summary
Part of Capital Plan- Funding Approved
Postcode
11694
Borough
QUEENS
Community Board
14
Census Tract
938
Bin
4303722
Bbl
4161590012
Nta
Breezy Point-Belle Harbor-Rockaway Park-Broad Channel
DPR
Vote Year: 2016 • Fiscal Year: FY17 • District: 32
Vote Year
2016
Fiscal Year
FY17
District
32
Project
Boardwalk Amenities
Ballot Price
50000.00
Subproject Cost
50000.00
Total Appropriated
50000.00
Agency
DPR
Non City
N
Description
Boardwalk amenities including mile markers, storyboards, and information boards along Rockaway Boardwalk
Installation Location
Rockaway Boardwalk
Mapping Location
40.580055, -73.827447
Status Summary
Part of Capital Plan- Funding Approved
DPR
Vote Year: 2016 • Fiscal Year: FY17 • District: 32
Vote Year
2016
Fiscal Year
FY17
District
32
Project
Upgrades to All-American Park/Sunset Cove
Ballot Price
200000.00
Subproject Cost
200000.00
Total Appropriated
200000.00
Agency
DPR
Non City
N
Description
Upgrades to All-American Park/Sunset Cove in Broad Channel
Installation Location
All-American Park and Sunset Cove Park
Mapping Location
40.596252, -73.823351
Status Summary
Part of Capital Plan- Funding Approved
DPR
Vote Year: 2016 • Fiscal Year: FY17 • District: 32
Vote Year
2016
Fiscal Year
FY17
District
32
Project
Upgrades to 17th Road Park
Ballot Price
250000.00
Subproject Cost
250000.00
Total Appropriated
250000.00
Agency
DPR
Non City
N
Description
Equipment upgrades and amenities to 17th Road Park in Broad Channel
Installation Location
17th Road Park
Mapping Location
40.601162, -73.822070
Status Summary
Part of Capital Plan- Funding Approved
SCA
Vote Year: 2016 • Fiscal Year: FY17 • District: 33
Vote Year
2016
Fiscal Year
FY17
District
33
Project
Essential STEM Labs at I.S 318 and P.S 34
Ballot Price
500000.00
Subproject Cost
500000.00
Total Appropriated
500000.00
Agency
SCA
Non City
N
Description
Let’s bridge the technology gap and invest in the future for 2,000+ students at two amazing but underserved schools by funding essential STEM (Science, Tech, Engineering & Math) labs at both schools!
Installation Location
IS 318, East Williamsburg; PS 34, Greenpoint
Mapping Location
40.703571, -73.948411
Status Summary
Part of Capital Plan- Funding Approved
NYCHA
Vote Year: 2016 • Fiscal Year: FY17 • District: 33
Vote Year
2016
Fiscal Year
FY17
District
33
Project
Hear the Beat! Community Sound Studio
Ballot Price
100000.00
Subproject Cost
100000.00
Total Appropriated
100000.00
Agency
NYCHA
Non City
N
Description
This project will outfit an existing computer lab as a recording studio, so youth/adults could be trained for music/audio professions. Includes upgrades to the space and all needed audio equipment.
Installation Location
114 Taylor St., Independence Towers, W’burg
Mapping Location
40.705437, -73.963313
Status Summary
Part of Capital Plan- Funding Approved
DPR
Vote Year: 2016 • Fiscal Year: FY17 • District: 33
Vote Year
2016
Fiscal Year
FY17
District
33
Project
Make Msgr. McGolrick Park Safer
Ballot Price
500000.00
Subproject Cost
500000.00
Total Appropriated
500000.00
Agency
DPR
Non City
N
Description
This project focuses on repaving some of the sidewalks along the park and replacing fencing. Current sidewalks are cracked, unsafe for children, and hazardous for wheelchair and stroller access.
Installation Location
Driggs Avenue, Greenpoint
Mapping Location
40.724696, -73.943412
Status Summary
Part of Capital Plan- Funding Approved
SCA
Vote Year: 2016 • Fiscal Year: FY17 • District: 33
Vote Year
2016
Fiscal Year
FY17
District
33
Project
Make Our School Cool! M.S. 126
Ballot Price
400000.00
Subproject Cost
400000.00
Total Appropriated
400000.00
Agency
SCA
Non City
N
Description
Our building serves 3 schools and 1200 kids and needs wiring for AC in the classrooms and Auditorium! It’s hard to concentrate and be good students when you’re too hot! Give them a chance to succeed!
Installation Location
424 Leonard Street, Williamsburg
Mapping Location
40.719786, -73.947829
Status Summary
Part of Capital Plan- Funding Approved
Postcode
11222
Borough
BROOKLYN
Community Board
1
Census Tract
499
Bin
3067788
Bbl
3027120001
Nta
Greenpoint
SCA
Vote Year: 2016 • Fiscal Year: FY17 • District: 33
Vote Year
2016
Fiscal Year
FY17
District
33
Project
Finish the Upgrades with P.S. 261 Computer Carts
Ballot Price
140000.00
Subproject Cost
40000.00
Brooklyn Borough President Funding
100000.00
Total Appropriated
40000.00
Agency
SCA
Non City
N
Description
P.S. 261 is a K-5 school with 800 students. Their wiring was upgraded but to utilize the improvements the students need new computers; four new carts will give them what they need!
Installation Location
314 Pacific Street, Boerum Hill
Mapping Location
40.687390, -73.988267
Status Summary
Part of Capital Plan- Funding Approved
Postcode
11201
Borough
BROOKLYN
Community Board
2
Census Tract
43
Bin
3001070
Bbl
3001880014
Nta
DUMBO-Vinegar Hill-Downtown Brooklyn-Boerum Hill
SCA
Vote Year: 2016 • Fiscal Year: FY17 • District: 34
Vote Year
2016
Fiscal Year
FY17
District
34
Project
Technology Upgrades at P.S. 239 and P.S. 18: P.S. 239 (Site 1 of 2)
Ballot Price
400000.00
Subproject Cost
250000.00
Total Appropriated
400000.00
Number Of Subprojects
2
Agency
SCA
Non City
N
Description
Includes two new laptop carts, two smart tables, a 3-D printers, six smart boards, and forty-two desktops.
Installation Location
15-17 Weirfield Street
Mapping Location
40.699525, -73.903855
Status Summary
Part of Capital Plan- Funding Approved
SCA
Vote Year: 2016 • Fiscal Year: FY17 • District: 34
Vote Year
2016
Fiscal Year
FY17
District
34
Project
Technology Upgrades at P.S. 239 and P.S. 18: P.S. 18 (Site 2 of 2)
Ballot Price
400000.00
Subproject Cost
150000.00
Total Appropriated
400000.00
Number Of Subprojects
2
Agency
SCA
Non City
N
Description
Includes two new laptop carts, two smart tables, a 3-D printers, six smart boards, and forty-two desktops.
Installation Location
101 Maujer Street
Mapping Location
40.710762, -73.947038
Status Summary
Part of Capital Plan- Funding Approved
Postcode
11206
Borough
BROOKLYN
Community Board
1
Census Tract
503
Bin
3069559
Bbl
3027870001
Nta
East Williamsburg
SCA
Vote Year: 2016 • Fiscal Year: FY17 • District: 34
Vote Year
2016
Fiscal Year
FY17
District
34
Project
21st Century Technology at P.S. 120 and P.S. 132: P.S. 120 (Site 1 of 2)
Ballot Price
285000.00
Subproject Cost
200000.00
Total Appropriated
285000.00
Number Of Subprojects
2
Agency
SCA
Non City
N
Description
Includes smart boards, laptops, smart tables, a 3-D Printer, a green wall, and solar & weather panels.
Installation Location
18 Beaver Street
Mapping Location
40.700641, -73.937763
Status Summary
Part of Capital Plan- Funding Approved
Postcode
11206
Borough
BROOKLYN
Community Board
4
Census Tract
389
Bin
3071806
Bbl
3031370026
Nta
Bushwick South
SCA
Vote Year: 2016 • Fiscal Year: FY17 • District: 34
Vote Year
2016
Fiscal Year
FY17
District
34
Project
21st Century Technology at P.S. 120 and P.S. 132: P.S. 132 (Site 2 of 2)
Ballot Price
285000.00
Subproject Cost
185000.00
Total Appropriated
285000.00
Number Of Subprojects
2
Agency
SCA
Non City
N
Description
Includes smart boards, laptops, smart tables, a 3-D Printer, a green wall, and solar & weather panels.
Installation Location
320 Manhattan Avenue
Mapping Location
40.714822, -73.945857
Status Summary
Part of Capital Plan- Funding Approved
Postcode
11211
Borough
BROOKLYN
Community Board
1
Census Tract
497
Bin
3068728
Bbl
3027590001
Nta
East Williamsburg
NYCHA
Vote Year: 2016 • Fiscal Year: FY17 • District: 34
Vote Year
2016
Fiscal Year
FY17
District
34
Project
Playground Upgrade at Williamsburg Houses
Ballot Price
350000.00
Subproject Cost
350000.00
Total Appropriated
350000.00
Agency
NYCHA
Non City
N
Description
This playground will get new benches, play equipment, and a sprinkler system.
Installation Location
176 Maujer Street – Block 1
Mapping Location
40.710785, -73.942652
Status Summary
Part of Capital Plan- Funding Approved
Postcode
11206
Borough
BROOKLYN
Community Board
1
Census Tract
493
Bin
3327889
Bbl
3030260001
Nta
Bushwick South
SCA
Vote Year: 2016 • Fiscal Year: FY17 • District: 34
Vote Year
2016
Fiscal Year
FY17
District
34
Project
A Cool Gym at P.S. 257
Ballot Price
250000.00
Subproject Cost
150000.00
Brooklyn Borough President Funding
100000.00
Total Appropriated
250000.00
Agency
SCA
Non City
N
Description
An air conditioner in the school gym, which is used throughout the school year and summer programming.
Installation Location
60 Cook Street
Mapping Location
40.702845, -73.941728
Status Summary
Part of Capital Plan- Funding Approved
Postcode
11206
Borough
BROOKLYN
Community Board
1
Census Tract
491
Bin
3071571
Bbl
3031140011
Nta
East Williamsburg
DOT
Vote Year: 2016 • Fiscal Year: FY17 • District: 34
Vote Year
2016
Fiscal Year
FY17
District
34
Project
Real Time Passenger Boards
Ballot Price
60000.00
Subproject Cost
60000.00
Total Appropriated
60000.00
Agency
DOT
Non City
N
Description
Real Time Passenger Information in Council District 34. DOT will choose site locations with the City Council office post budget adoption.
Installation Location
Ridgewood, Bushwick, and Williamsburg
Mapping Location
40.701137, -73.926349
Status Summary
Part of Capital Plan- Funding Approved
BPL
Vote Year: 2016 • Fiscal Year: FY17 • District: 36
Vote Year
2016
Fiscal Year
FY17
District
36
Project
Renovate and Upgrade Marcy Library Auditorium
Ballot Price
350000.00
Subproject Cost
350000.00
Total Appropriated
350000.00
Agency
BPL
Non City
N
Description
Upgrade the multi-purpose room/ auditorium of the Marcy Branch of the Brooklyn Public Library with new electrical, lighting, flooring & shelving.
Installation Location
617 Dekalb Avenue
Mapping Location
40.691631, -73.951296
Status Summary
Part of Capital Plan- Funding Approved
Postcode
11216
Borough
BROOKLYN
Community Board
3
Census Tract
253
Bin
3049472
Bbl
3017740081
Nta
Bedford
SCA
Vote Year: 2016 • Fiscal Year: FY17 • District: 36
Vote Year
2016
Fiscal Year
FY17
District
36
Project
4 Science Carts for Bed-Stuy New Beginnings
Ballot Price
248000.00
Subproject Cost
248000.00
Total Appropriated
248000.00
Agency
SCA
Non City
N
Description
Each Science Cart costs $62,000
Installation Location
82 Lewis Ave
Mapping Location
40.694713, -73.937539
Status Summary
Part of Capital Plan- Funding Approved
Postcode
11206
Borough
BROOKLYN
Community Board
3
Census Tract
283
Bin
3043017
Bbl
3015910045
Nta
Stuyvesant Heights
SCA
Vote Year: 2016 • Fiscal Year: FY17 • District: 36
Vote Year
2016
Fiscal Year
FY17
District
36
Project
New Laptops for P.S. 59
Ballot Price
70000.00
Subproject Cost
70000.00
Total Appropriated
70000.00
Agency
SCA
Non City
N
Description
2 laptop carts w/ 30-35 Lenovo laptops each
Installation Location
211 Throop Avenue
Mapping Location
40.697715, -73.943148
Status Summary
Part of Capital Plan- Funding Approved
Postcode
11206
Borough
BROOKLYN
Community Board
3
Census Tract
28502
Bin
3048546
Bbl
3017490001
Nta
Stuyvesant Heights
SCA
Vote Year: 2016 • Fiscal Year: FY17 • District: 36
Vote Year
2016
Fiscal Year
FY17
District
36
Project
Smartboards for Smart Kids!
Ballot Price
320000.00
Subproject Cost
320000.00
Total Appropriated
320000.00
Agency
SCA
Non City
N
Description
New smartboards for five D36 schools — PS 289, PS 138, PS 93, PS 243 & Bedford Academy. $64K will fund 8 smartboards per school. Includes required electrical & data.
Installation Location
PS 289, PS 138, PS 93, PS 243 & Bedford Acdmy
Mapping Location
40.674183, -73.942409
Status Summary
Part of Capital Plan- Funding Approved
DPR
Vote Year: 2016 • Fiscal Year: FY17 • District: 36
Vote Year
2016
Fiscal Year
FY17
District
36
Project
Upgrade Brower Park Basketball Courts
Ballot Price
600000.00
Subproject Cost
500000.00
Brooklyn Borough President Funding
100000.00
Total Appropriated
600000.00
Agency
DPR
Non City
N
Description
Provide beautiful new surfaces for two of the four basketball courts in Brower Park, including new drainage, pavement and lines.
Installation Location
Brower Park
Mapping Location
40.673561, -73.943241
Status Summary
Part of Capital Plan- Funding Approved
DPR
Vote Year: 2016 • Fiscal Year: FY17 • District: 38
Vote Year
2016
Fiscal Year
FY17
District
38
Project
Sunset Park Renovation
Ballot Price
500000.00
Subproject Cost
400000.00
Brooklyn Borough President Funding
100000.00
Total Appropriated
500000.00
Agency
DPR
Non City
N
Description
Repaving, installation of 20 new benches, replacement of existing dilapidated chain-link fences, and adding in picnic tables.
Installation Location
Sunset Park
Mapping Location
40.648052, -74.003732
Status Summary
Part of Capital Plan- Funding Approved
SCA
Vote Year: 2016 • Fiscal Year: FY17 • District: 38
Vote Year
2016
Fiscal Year
FY17
District
38
Project
Library Update
Ballot Price
450000.00
Subproject Cost
450000.00
Total Appropriated
450000.00
Agency
SCA
Non City
N
Description
The project would involve the renovation of Middle School 88 and Sunset Park High School’s library media center, currently equipped with highly outdated and non-functioning technology.
Installation Location
M.S. 88 and Sunset Park High School
Mapping Location
40.655164, -74.004114
Status Summary
Part of Capital Plan- Funding Approved
DOT
Vote Year: 2016 • Fiscal Year: FY17 • District: 38
Vote Year
2016
Fiscal Year
FY17
District
38
Project
Electronic "Locator" Sign Throughout the District
Ballot Price
600000.00
Subproject Cost
600000.00
Total Appropriated
600000.00
Agency
DOT
Non City
N
Description
Install electronic bus signs along the B70, B63, B35, B11, B9, B57 & B61 bus routes. The signs will be posted at busy bus stops. The signs will tell riders the location and arrival time of their bus.
Installation Location
District-Wide
Mapping Location
40.653130, -74.002178
Status Summary
Part of Capital Plan- Funding Approved
DPR
Vote Year: 2016 • Fiscal Year: FY17 • District: 40
Vote Year
2016
Fiscal Year
FY17
District
40
Project
Replacement of “Lake Mess Monster”
Ballot Price
140000.00
Subproject Cost
140000.00
Total Appropriated
140000.00
Agency
DPR
Non City
N
Description
A vessel that would grind up duck weed and other contaminants that cause visible pollution in the Prospect Park Lake.
Installation Location
Prospect Park Lake
Mapping Location
40.655162, -73.970510
Status Summary
Part of Capital Plan- Funding Approved
SCA
Vote Year: 2016 • Fiscal Year: FY17 • District: 38
Vote Year
2016
Fiscal Year
FY17
District
38
Project
South Brooklyn Community H.S.& P.S.169 Upgrades
Ballot Price
380000.00
Subproject Cost
380000.00
Total Appropriated
380000.00
Agency
SCA
Non City
N
Description
There are no lockers, and thus students are required to carry their belongings, books, etc., throughout the day at SBHS. P.S.169 needs renovations of bathrooms that are in a state of disrepair.
Installation Location
173 Conover St & 4305 7th Avenue
Mapping Location
40.677865, -74.014179
Status Summary
Part of Capital Plan- Funding Approved
SCA
Vote Year: 2016 • Fiscal Year: FY17 • District: 38
Vote Year
2016
Fiscal Year
FY17
District
38
Project
Auditorium Upgrade for M.S. 88 and M.S.136
Ballot Price
375000.00
Subproject Cost
375000.00
Total Appropriated
375000.00
Agency
SCA
Non City
N
Description
These auditoriums are multi-purpose, handicapped-accessible community spaces. The spaces are currently outdated and need upgrades to better serve each school’s internal and local community members.
Installation Location
M.S.88, Sunset Park Prep, I.S.136
Mapping Location
40.660686, -73.988515
Status Summary
Part of Capital Plan- Funding Approved
DPR
Vote Year: 2016 • Fiscal Year: FY17 • District: 39
Vote Year
2016
Fiscal Year
FY17
District
39
Project
New “Lake Mess Monster,” an Aquatic Weed Harvester
Ballot Price
140000.00
Subproject Cost
70000.00
Total Appropriated
70000.00
Agency
DPR
Non City
N
Description
Prospect Park needs a new aquatic weed harvester (aka “Lake Mess Monster”) to remove scum from the lake. Without it, the scum will sink and proceed to rot, causing the water to become toxic.
Installation Location
Prospect Park Lake
Mapping Location
40.655162, -73.970510
Status Summary
Part of Capital Plan- Funding Approved
DPR
Vote Year: 2016 • Fiscal Year: FY17 • District: 39
Vote Year
2016
Fiscal Year
FY17
District
39
Project
Year-Round, Freeze-Resistant Drinking Fountains
Ballot Price
175000.00
Subproject Cost
175000.00
Total Appropriated
175000.00
Agency
DPR
Non City
N
Description
The water fountains in Prospect Park are not available to use during the winter months. This upgrade would make 5 fountains along the Prospect Park Drive freeze-resistant and available year-round.
Installation Location
Prospect Park, 5 Locations along the Drive
Mapping Location
40.655701, -73.972649
Status Summary
Part of Capital Plan- Funding Approved
DOT
Vote Year: 2016 • Fiscal Year: FY17 • District: 39
Vote Year
2016
Fiscal Year
FY17
District
39
Project
Bus Clocks on B67/B69: Know When Bus Arrives!
Ballot Price
240000.00
Subproject Cost
240000.00
Total Appropriated
240000.00
Agency
DOT
Non City
N
Description
Install bus countdown clocks that display real-time information about bus location at 12 B67/B69 stops. This will help mass transit users estimate wait times and make better travel decisions.
Installation Location
McDonald, 7th and Flatbush Avenues
Mapping Location
40.649999, -73.980680
Status Summary
Part of Capital Plan- Funding Approved
BPL
Vote Year: 2016 • Fiscal Year: FY17 • District: 39
Vote Year
2016
Fiscal Year
FY17
District
39
Project
Create Teen Space at Carroll Gardens Library
Ballot Price
350000.00
Subproject Cost
350000.00
Total Appropriated
350000.00
Agency
BPL
Non City
N
Description
Revamp the library’s mezzanine-level to create more space and add comfortable furniture, outlets, and new lighting – to create an inviting space for teens to use after-school and on weekends
Installation Location
396 Clinton St, between Union and Sackett Sts
Mapping Location
40.683235, -73.997891
Status Summary
Part of Capital Plan- Funding Approved
Postcode
11231
Borough
BROOKLYN
Community Board
6
Census Tract
67
Bin
3004336
Bbl
3003380033
Nta
Carroll Gardens-Columbia Street-Red Hook
SCA
Vote Year: 2016 • Fiscal Year: FY17 • District: 39
Vote Year
2016
Fiscal Year
FY17
District
39
Project
West Brooklyn Community HS Portable Laptop Lab
Ballot Price
105000.00
Subproject Cost
105000.00
Total Appropriated
105000.00
Agency
SCA
Non City
N
Description
Three mobile carts with 25 laptops each will travel among classrooms to support instruction and foster IT skills. West Brooklyn Community HS is a transfer high school offering a second chance to high-needs students.
Installation Location
1053 41st Street, Borough Park
Mapping Location
40.642837, -73.992528
Status Summary
Part of Capital Plan- Funding Approved
Postcode
11219
Borough
BROOKLYN
Community Board
12
Census Tract
110
Bin
3328583
Bbl
3055870038
Nta
Sunset Park East
DCA
Vote Year: 2016 • Fiscal Year: FY17 • District: 39
Vote Year
2016
Fiscal Year
FY17
District
39
Project
"Mobile Studios" for Artists and Orgs in Gowanus
Ballot Price
150000.00
Subproject Cost
50000.00
Total Appropriated
150000.00
Agency
DCA
Non City
Y
Description
Three “mobile studios” – small, mobile workplaces – for artists and community organizations that will enliven underused areas and engage the public on local issues like displacement and resiliency.
Installation Location
Parks, Plazas, and Street-ends in Gowanus
Mapping Location
40.677554, -73.991322
Status Summary
Part of Capital Plan- Funding Approved
DOT
Vote Year: 2016 • Fiscal Year: FY17 • District: 39
Vote Year
2016
Fiscal Year
FY17
District
39
Project
Curb Extension & Safer Crossing- Carroll Park
Ballot Price
150000.00
Subproject Cost
150000.00
Total Appropriated
150000.00
Agency
DOT
Non City
N
Description
The installation of a curb extension at this very busy intersection would shorten the crossing distance and promote pedestrian safety for families and residents using Carroll Park.
Installation Location
Intersection of Carroll and Court Streets
Mapping Location
40.681104, -73.996569
Status Summary
Part of Capital Plan- Funding Approved
SCA
Vote Year: 2016 • Fiscal Year: FY17 • District: 39
Vote Year
2016
Fiscal Year
FY17
District
39
Project
Retrofit 75 Auditorium Lights for Safety
Ballot Price
200000.00
Subproject Cost
200000.00
Total Appropriated
200000.00
Agency
SCA
Non City
N
Description
School and after-school groups use auditorium daily. Current lights cast shadows, making steep floor unsafe, and use expensive short-life bulbs. New LED retrofit will fix safety and cost issues.
Installation Location
PS 282, 180 6th Avenue, Park Slope
Mapping Location
40.676637, -73.977787
Status Summary
Part of Capital Plan- Funding Approved
Postcode
11217
Borough
BROOKLYN
Community Board
6
Census Tract
131
Bin
3019597
Bbl
3009500024
Nta
Park Slope-Gowanus
DPR
Vote Year: 2016 • Fiscal Year: FY17 • District: 39
Vote Year
2016
Fiscal Year
FY17
District
39
Project
Brand New Dog Run: Areas for Big and Small Dogs
Ballot Price
135000.00
Subproject Cost
35000.00
Brooklyn Borough President Funding
100000.00
Total Appropriated
35000.00
Agency
DPR
Non City
N
Description
Many Kensington and Windsor Terrace dog owners do not have access to fenced-in space where their pups can exercise and socialize. Project is shared with Council Member Eugene & Borough President Adams
Installation Location
Parade Grounds (at unused southwest corner)
Mapping Location
40.651667, -73.968909
Status Summary
Part of Capital Plan- Funding Approved
SCA
Vote Year: 2016 • Fiscal Year: FY17 • District: 39E
Vote Year
2016
Fiscal Year
FY17
District
39E
Project
Translation Equipment for Multi-Lingual Schools
Ballot Price
25000.00
Subproject Cost
25000.00
Total Appropriated
25000.00
Agency
SCA
Non City
N
Description
Allows interpreters to provide live translation during school events. Non-English speaking audience members listen through headsets. Equipment accommodates up to 8 languages and 2,000 receivers.
Installation Location
PS 130, PS 131, PS 179, PS 230, and MS 839
Mapping Location
40.649051, -73.975837
Status Summary
Part of Capital Plan- Funding Approved
BPL
Vote Year: 2016 • Fiscal Year: FY17 • District: 39E
Vote Year
2016
Fiscal Year
FY17
District
39E
Project
Overnight Book Drops at Three Library Branches
Ballot Price
24000.00
Subproject Cost
24000.00
Total Appropriated
24000.00
Agency
BPL
Non City
N
Description
Installation of overnight book drops at three district library branches to enable after-hours library returns. The drops will make utilizing the library easier and help people avoid fines.
Installation Location
Carroll Gardens, Windsor Terrace & Borough Park
Mapping Location
40.683230, -73.997892
Status Summary
Part of Capital Plan- Funding Approved
DFTA
Vote Year: 2016 • Fiscal Year: FY17 • District: 39E
Vote Year
2016
Fiscal Year
FY17
District
39E
Project
Music Equipment for Three Centers
Ballot Price
5000.00
Subproject Cost
5000.00
Total Appropriated
5000.00
Agency
DFTA
Non City
N
Description
Music equipment for three district senior centers, including guitars and keyboards, to enhance current music programming and to facilitate new programs such as keyboard classes and karaoke.
Installation Location
Prospect Hill, Eileen Dugan & Park Slope Centers
Mapping Location
40.663424, -73.988914
Status Summary
Part of Capital Plan- Funding Approved
SCA
Vote Year: 2016 • Fiscal Year: FY17 • District: 40
Vote Year
2016
Fiscal Year
FY17
District
40
Project
Computer Lab Updates for Local Schools
Ballot Price
140000.00
Subproject Cost
140000.00
Total Appropriated
140000.00
Agency
SCA
Non City
N
Description
General technology updates at P.S. 249, P.S. 245, P.S. 139, and P.S. 6
Installation Location
PS 249, PS 245, PS 139, PS 6
Mapping Location
40.649822, -73.966215
Status Summary
Part of Capital Plan- Funding Approved
DPR
Vote Year: 2016 • Fiscal Year: FY17 • District: 40
Vote Year
2016
Fiscal Year
FY17
District
40
Project
Community Barbecue Sites in Prospect Park
Ballot Price
80000.00
Subproject Cost
80000.00
Total Appropriated
80000.00
Agency
DPR
Non City
N
Description
New-style municipal grills, which are similar to those at Brooklyn Bridge Park Picnic Peninsula.
Installation Location
Lincoln Rd & E Drive; Parkside Ave & E Drive
Mapping Location
40.660511, -73.962838
Status Summary
Part of Capital Plan- Funding Approved
SCA
Vote Year: 2016 • Fiscal Year: FY17 • District: 40
Vote Year
2016
Fiscal Year
FY17
District
40
Project
Gymnasium Upgrades at Erasmus High School
Ballot Price
150000.00
Subproject Cost
150000.00
Total Appropriated
150000.00
Agency
SCA
Non City
N
Description
Physical upgrades to the gymnasium
Installation Location
911 Flatbush Avenue
Mapping Location
40.649603, -73.958200
Status Summary
Part of Capital Plan- Funding Approved
Postcode
11226
Borough
BROOKLYN
Community Board
14
Census Tract
794
Bin
3336215
Bbl
3051030010
Nta
Erasmus
SCA
Vote Year: 2016 • Fiscal Year: FY17 • District: 40
Vote Year
2016
Fiscal Year
FY17
District
40
Project
Technology Updates for M.S. 2 Parkside Academy
Ballot Price
35000.00
Subproject Cost
35000.00
Total Appropriated
35000.00
Agency
SCA
Non City
N
Description
Various technological updates at M.S. 2 Parkside Academy
Installation Location
655 Parkside Avenue
Mapping Location
40.656408, -73.951463
Status Summary
Part of Capital Plan- Funding Approved
Postcode
11226
Borough
BROOKLYN
Community Board
9
Census Tract
802
Bin
3378201
Bbl
3050500051
Nta
Prospect Lefferts Gardens-Wingate
SCA
Vote Year: 2016 • Fiscal Year: FY17 • District: 40
Vote Year
2016
Fiscal Year
FY17
District
40
Project
Smartboards for P.S. 92
Ballot Price
175000.00
Subproject Cost
175000.00
Total Appropriated
175000.00
Agency
SCA
Non City
N
Description
Twenty-nine smartboards are needed for PS 92.
Installation Location
601 Parkside Avenue
Mapping Location
40.656245, -73.953793
Status Summary
Part of Capital Plan- Funding Approved
Postcode
11226
Borough
BROOKLYN
Community Board
9
Census Tract
802
Bin
3115866
Bbl
3050490055
Nta
Prospect Lefferts Gardens-Wingate
DOT
Vote Year: 2016 • Fiscal Year: FY17 • District: 40
Vote Year
2016
Fiscal Year
FY17
District
40
Project
Real-Time Passenger Information
Ballot Price
40000.00
Subproject Cost
40000.00
Total Appropriated
40000.00
Agency
DOT
Non City
N
Description
Bus display signs that are visible from a distance and inform riders when their bus will arrive.
Installation Location
Lincoln Road entrance; Church Avenue B35 stop
Mapping Location
40.650113, -73.961470
Status Summary
Part of Capital Plan- Funding Approved
DPR
Vote Year: 2016 • Fiscal Year: FY17 • District: 40
Vote Year
2016
Fiscal Year
FY17
District
40
Project
Kensington Dog Run
Ballot Price
135000.00
Subproject Cost
135000.00
Total Appropriated
135000.00
Agency
DPR
Non City
N
Description
An enclosed Dog Run at the Parade Grounds
Installation Location
Parade Grounds
Mapping Location
40.651648, -73.968881
Status Summary
Part of Capital Plan- Funding Approved
DOT
Vote Year: 2016 • Fiscal Year: FY17 • District: 40
Vote Year
2016
Fiscal Year
FY17
District
40
Project
Little Red Riding Hood Pre-K Sidewalk Extension
Ballot Price
300000.00
Subproject Cost
200000.00
Brooklyn Borough President Funding
100000.00
Total Appropriated
300000.00
Agency
DOT
Non City
N
Description
Sidewalk extensions at this corner paired with heavy-duty bollards
Installation Location
NE corner of Rogers Ave. and Lefferts Ave.
Mapping Location
40.662392, -73.953454
Status Summary
Part of Capital Plan- Funding Approved
DOT
Vote Year: 2016 • Fiscal Year: FY17 • District: 44
Vote Year
2016
Fiscal Year
FY17
District
44
Project
Street Resurfacing
Ballot Price
200000.00
Subproject Cost
200000.00
Total Appropriated
200000.00
Agency
DOT
Non City
N
Description
Repair and resurface roadways that have been identified as dangerous due to potholes, ridges and other holes.
Installation Location
District Wide
Mapping Location
40.633564, -73.983334
Status Summary
Part of Capital Plan- Funding Approved