List of all approved construction permits in DOB NOW except for Electrical, Elevator, and Limited Alteration Application (LAA) which have their own datasets.
Housing & DevelopmentDepartment of Buildings (DOB)
Dataset rbx6-tga4
46 fields
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. LIVE LOAD 300PSF.
INSTALLATION OF OVERHEAD PROTECTION AND ROOF PROTECTION AT ADJACENT BUILDING AS SHOW HEREIN IN CONJUNCTION WITH FACADE JOB# M01355711. NO CHANGE IN USE EGRESS OR OCCUPACNY. WE SHALL COMPLY WITH CHOATER 33 OF 2022 B.C
HORIZONTIAL ENLARGEMENT OF THE EXISTING 2-STORY 2-FAMILY BUILDING WITH CELLAR. INTERIOR RENOVATION AS PER PLAN. FILED TO RESOLVE DOB VIOLATIONS AND VAC Q159/2023. FILED TO SUPERSEDE #Q00975539-I1.
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. LIVE LOAD 300PSF.
HORIZINTAL ENLARGEMENT OF AN EXISTING 3-STORY 1-FAMILY BUILDING WITH BASEMENT AND CELLAR, CONVERSION FROM SRO's AND DWELLING TO A TWO-FAMILY DWELLING AS SHOWN IN PLANS. INSTALL A METAL DECK AT REAR. OBTAIN A NEW CofO.
Installation of a temporarily supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
INTERIOR RENOVATION AND ADDRESS DOB VIOLATION#092524CRTGCO1, 092524CRTGC02;092524CRTGC03 AND ECB VIOLATION # 35683114L, 35683115N; 35683116P DUE TO WORK WITHOUT THE PERMIT IN APARTMENT E7 AT 5TH FLOOR. NO CHANGE IN USE, OCCUPANCY, BULK, OR EGRESS
Filling for the interior renovation work and the replacement of the windows. The interior work includes removal and installation of non load bearing interior partitions, finishes etc.
Building 1P: install new plumbing fixtures and replace sprinkler heads to accommodate bathroom renovations on 1st floor in the existing in college building.
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
PLUMBING WORK IN THE CELLAR, PLUMBING WORK INCLUDES INSTALLATION OF NEW FIXTURES AND ASSOCIATED PIPING AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD 300 LBS PER SQUARE FEET. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
ADDITION OF A PORTION OF GOLDFINE PAVILION GROUND FLOORTO STOLZ PAVILION'S CERTIFICATION OF OCCUPANCY. THE SPECIFIED AREA OF GOLDFINE IS NOTSUBJECT TO CHANGE OF USE OR OCCUPANCY. GOLDFINE PAVILION DEMOLITION TO BE FILEDUNDER SEPARATE APPLICATION.
Interior remodeling of the cellar commercial space to address ECB violation 39069360M. Erecting partial partitions, flooring, and ceilings, and adding a new mini split unit.