Capital Project Detail Data - Milestones

This dataset contains capital commitment plan data by managing agency, project identification number and project schedules. The dataset was updated three times a year during the Preliminary, Executive and Adopted Capital Commitment Plans. Starting in January 2024, OMB will no longer update this dataset. It is being replaced by the Capital Projects Dashboard administered by the Mayor's Office of Operations.

City Government Mayor’s Office of Management and Budget (OMB) Dataset s7yh-frbm 12 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV235AMER
Project Descr
BMA - Brooklyn Museum - American Gallery Renovations
Seq Number
6
Task Description
CONSTRUCTION TO 50%
Orig Start Date
2027-02-01T00:00:00.000
Orig End Date
2027-06-01T00:00:00.000
Task Start Date
2026-02-01T00:00:00.000
Task End Date
2026-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV235AMER
Project Descr
BMA - Brooklyn Museum - American Gallery Renovations
Seq Number
7
Task Description
CONSTRUCTION TO 75%
Orig Start Date
2027-06-01T00:00:00.000
Orig End Date
2027-10-01T00:00:00.000
Task Start Date
2026-06-01T00:00:00.000
Task End Date
2026-10-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV235AMER
Project Descr
BMA - Brooklyn Museum - American Gallery Renovations
Seq Number
8
Task Description
ORIGINAL EQUIP & FURNISHING
Orig Start Date
2027-10-01T00:00:00.000
Orig End Date
2028-01-01T00:00:00.000
Task Start Date
2026-10-01T00:00:00.000
Task End Date
2027-01-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV235AMER
Project Descr
BMA - Brooklyn Museum - American Gallery Renovations
Seq Number
9
Task Description
SUBSTANTIAL COMPLETION
Orig Start Date
2028-01-01T00:00:00.000
Orig End Date
2028-03-01T00:00:00.000
Task Start Date
2027-01-01T00:00:00.000
Task End Date
2027-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV235AMER
Project Descr
BMA - Brooklyn Museum - American Gallery Renovations
Seq Number
10
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2028-03-01T00:00:00.000
Orig End Date
2028-04-01T00:00:00.000
Task Start Date
2027-03-01T00:00:00.000
Task End Date
2027-04-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV235EDUC
Project Descr
BMA - Brooklyn Museum - Education Space
Seq Number
1
Task Description
DEVELOP SCOPE
Orig Start Date
2014-11-01T00:00:00.000
Orig End Date
2015-02-01T00:00:00.000
Task Start Date
2023-07-01T00:00:00.000
Task End Date
2024-07-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV235EDUC
Project Descr
BMA - Brooklyn Museum - Education Space
Seq Number
2
Task Description
PRELIMINARY DESIGN
Orig Start Date
2015-02-01T00:00:00.000
Orig End Date
2015-06-01T00:00:00.000
Task Start Date
2024-07-01T00:00:00.000
Task End Date
2024-10-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV235EDUC
Project Descr
BMA - Brooklyn Museum - Education Space
Seq Number
3
Task Description
FINAL DESIGN
Orig Start Date
2015-06-01T00:00:00.000
Orig End Date
2015-12-01T00:00:00.000
Task Start Date
2024-10-01T00:00:00.000
Task End Date
2025-04-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV235EDUC
Project Descr
BMA - Brooklyn Museum - Education Space
Seq Number
4
Task Description
BID AWARD AND REGISTER CONTRCT
Orig Start Date
2015-12-01T00:00:00.000
Orig End Date
2016-03-01T00:00:00.000
Task Start Date
2025-04-01T00:00:00.000
Task End Date
2025-07-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV235EDUC
Project Descr
BMA - Brooklyn Museum - Education Space
Seq Number
5
Task Description
CONSTRUCTION TO 25%
Orig Start Date
2016-03-01T00:00:00.000
Orig End Date
2016-07-01T00:00:00.000
Task Start Date
2025-07-01T00:00:00.000
Task End Date
2025-11-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV235EDUC
Project Descr
BMA - Brooklyn Museum - Education Space
Seq Number
6
Task Description
CONSTRUCTION TO 50%
Orig Start Date
2016-07-01T00:00:00.000
Orig End Date
2016-11-01T00:00:00.000
Task Start Date
2025-11-01T00:00:00.000
Task End Date
2026-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV235EDUC
Project Descr
BMA - Brooklyn Museum - Education Space
Seq Number
7
Task Description
CONSTRUCTION TO 75%
Orig Start Date
2016-11-01T00:00:00.000
Orig End Date
2017-03-01T00:00:00.000
Task Start Date
2026-03-01T00:00:00.000
Task End Date
2026-07-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV235EDUC
Project Descr
BMA - Brooklyn Museum - Education Space
Seq Number
8
Task Description
ORIGINAL EQUIP & FURNISHING
Orig Start Date
2017-03-01T00:00:00.000
Orig End Date
2017-06-01T00:00:00.000
Task Start Date
2026-07-01T00:00:00.000
Task End Date
2026-10-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV235EDUC
Project Descr
BMA - Brooklyn Museum - Education Space
Seq Number
9
Task Description
SUBSTANTIAL COMPLETION
Orig Start Date
2017-06-01T00:00:00.000
Orig End Date
2017-07-01T00:00:00.000
Task Start Date
2026-10-01T00:00:00.000
Task End Date
2026-12-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV235EDUC
Project Descr
BMA - Brooklyn Museum - Education Space
Seq Number
10
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2017-08-01T00:00:00.000
Orig End Date
2017-08-01T00:00:00.000
Task Start Date
2026-12-01T00:00:00.000
Task End Date
2027-01-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV236AUDI
Project Descr
BBG - Auditorium Renovations
Seq Number
1
Task Description
DEVELOP SCOPE
Orig Start Date
2010-12-01T00:00:00.000
Orig End Date
2011-02-01T00:00:00.000
Task Start Date
2023-06-01T00:00:00.000
Task End Date
2023-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV236AUDI
Project Descr
BBG - Auditorium Renovations
Seq Number
2
Task Description
PRELIMINARY DESIGN
Orig Start Date
2011-03-01T00:00:00.000
Orig End Date
2011-06-01T00:00:00.000
Task Start Date
2023-09-01T00:00:00.000
Task End Date
2024-01-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV236AUDI
Project Descr
BBG - Auditorium Renovations
Seq Number
3
Task Description
FINAL DESIGN
Orig Start Date
2011-06-01T00:00:00.000
Orig End Date
2011-12-01T00:00:00.000
Task Start Date
2024-01-01T00:00:00.000
Task End Date
2024-07-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV236AUDI
Project Descr
BBG - Auditorium Renovations
Seq Number
4
Task Description
BID AWARD AND REGISTER CONTRCT
Orig Start Date
2011-12-01T00:00:00.000
Orig End Date
2012-03-01T00:00:00.000
Task Start Date
2024-07-01T00:00:00.000
Task End Date
2024-10-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV236AUDI
Project Descr
BBG - Auditorium Renovations
Seq Number
5
Task Description
CONSTRUCTION TO 25%
Orig Start Date
2012-03-01T00:00:00.000
Orig End Date
2012-07-01T00:00:00.000
Task Start Date
2024-10-01T00:00:00.000
Task End Date
2025-02-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV236AUDI
Project Descr
BBG - Auditorium Renovations
Seq Number
6
Task Description
CONSTRUCTION TO 50%
Orig Start Date
2012-07-01T00:00:00.000
Orig End Date
2012-11-01T00:00:00.000
Task Start Date
2025-02-01T00:00:00.000
Task End Date
2025-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV236AUDI
Project Descr
BBG - Auditorium Renovations
Seq Number
7
Task Description
CONSTRUCTION TO 75%
Orig Start Date
2012-11-01T00:00:00.000
Orig End Date
2013-03-01T00:00:00.000
Task Start Date
2025-06-01T00:00:00.000
Task End Date
2025-10-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV236AUDI
Project Descr
BBG - Auditorium Renovations
Seq Number
8
Task Description
ORIGINAL EQUIP & FURNISHING
Orig Start Date
2013-03-01T00:00:00.000
Orig End Date
2013-06-01T00:00:00.000
Task Start Date
2025-10-01T00:00:00.000
Task End Date
2026-01-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV236AUDI
Project Descr
BBG - Auditorium Renovations
Seq Number
9
Task Description
SUBSTANTIAL COMPLETION
Orig Start Date
2013-06-01T00:00:00.000
Orig End Date
2013-08-01T00:00:00.000
Task Start Date
2026-01-01T00:00:00.000
Task End Date
2026-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV236AUDI
Project Descr
BBG - Auditorium Renovations
Seq Number
10
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2013-08-01T00:00:00.000
Orig End Date
2013-09-01T00:00:00.000
Task Start Date
2026-03-01T00:00:00.000
Task End Date
2026-04-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV236BCSG
Project Descr
BBG - Brooklyn Botanic Garden - Sustainable Gardening Center
Seq Number
1
Task Description
CONSTRUCTION
Orig Start Date
2016-09-01T00:00:00.000
Orig End Date
2017-09-01T00:00:00.000
Task Start Date
2023-06-01T00:00:00.000
Task End Date
2023-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV236BCSG
Project Descr
BBG - Brooklyn Botanic Garden - Sustainable Gardening Center
Seq Number
2
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2017-09-01T00:00:00.000
Orig End Date
2018-09-01T00:00:00.000
Task Start Date
2023-09-01T00:00:00.000
Task End Date
2024-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV236BCSG
Project Descr
BBG - Brooklyn Botanic Garden - Sustainable Gardening Center
Seq Number
3
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2017-09-01T00:00:00.000
Orig End Date
2018-09-01T00:00:00.000
Task Start Date
2024-09-01T00:00:00.000
Task End Date
2025-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV236-NSY
Project Descr
BBG - North Service Yard
Seq Number
1
Task Description
DEVELOP SCOPE
Orig Start Date
2025-07-01T00:00:00.000
Orig End Date
2025-09-01T00:00:00.000
Task Start Date
2025-06-01T00:00:00.000
Task End Date
2025-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV236-NSY
Project Descr
BBG - North Service Yard
Seq Number
2
Task Description
PRELIMINARY DESIGN
Orig Start Date
2025-09-01T00:00:00.000
Orig End Date
2026-01-01T00:00:00.000
Task Start Date
2025-09-01T00:00:00.000
Task End Date
2026-01-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV236-NSY
Project Descr
BBG - North Service Yard
Seq Number
3
Task Description
FINAL DESIGN
Orig Start Date
2026-01-01T00:00:00.000
Orig End Date
2026-07-01T00:00:00.000
Task Start Date
2026-01-01T00:00:00.000
Task End Date
2026-07-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV236-NSY
Project Descr
BBG - North Service Yard
Seq Number
4
Task Description
BID AWARD AND REGISTER CONTRCT
Orig Start Date
2026-07-01T00:00:00.000
Orig End Date
2026-10-01T00:00:00.000
Task Start Date
2026-07-01T00:00:00.000
Task End Date
2026-10-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV236-NSY
Project Descr
BBG - North Service Yard
Seq Number
5
Task Description
CONSTRUCTION TO 25%
Orig Start Date
2026-10-01T00:00:00.000
Orig End Date
2027-02-01T00:00:00.000
Task Start Date
2026-10-01T00:00:00.000
Task End Date
2027-02-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV236-NSY
Project Descr
BBG - North Service Yard
Seq Number
6
Task Description
CONSTRUCTION TO 50%
Orig Start Date
2027-02-01T00:00:00.000
Orig End Date
2027-06-01T00:00:00.000
Task Start Date
2027-02-01T00:00:00.000
Task End Date
2027-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV236-NSY
Project Descr
BBG - North Service Yard
Seq Number
7
Task Description
CONSTRUCTION TO 75%
Orig Start Date
2027-06-01T00:00:00.000
Orig End Date
2027-10-01T00:00:00.000
Task Start Date
2027-06-01T00:00:00.000
Task End Date
2027-10-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV236-NSY
Project Descr
BBG - North Service Yard
Seq Number
8
Task Description
ORIGINAL EQUIP & FURNISHING
Orig Start Date
2027-10-01T00:00:00.000
Orig End Date
2028-01-01T00:00:00.000
Task Start Date
2027-10-01T00:00:00.000
Task End Date
2028-01-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV236-NSY
Project Descr
BBG - North Service Yard
Seq Number
9
Task Description
SUBSTANTIAL COMPLETION
Orig Start Date
2028-01-01T00:00:00.000
Orig End Date
2028-03-01T00:00:00.000
Task Start Date
2028-01-01T00:00:00.000
Task End Date
2028-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV236-NSY
Project Descr
BBG - North Service Yard
Seq Number
10
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2028-03-01T00:00:00.000
Orig End Date
2028-04-01T00:00:00.000
Task Start Date
2028-03-01T00:00:00.000
Task End Date
2028-04-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV236ROSE
Project Descr
BBG -Brooklyn Botanic Garden - Accessibility Improvements
Seq Number
1
Task Description
DEVELOP SCOPE
Orig Start Date
2021-06-01T00:00:00.000
Orig End Date
2021-09-01T00:00:00.000
Task Start Date
2024-06-01T00:00:00.000
Task End Date
2024-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV236ROSE
Project Descr
BBG -Brooklyn Botanic Garden - Accessibility Improvements
Seq Number
2
Task Description
BID AWARD AND REGISTER CONTRCT
Orig Start Date
2021-09-01T00:00:00.000
Orig End Date
2021-12-01T00:00:00.000
Task Start Date
2024-09-01T00:00:00.000
Task End Date
2024-12-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV236ROSE
Project Descr
BBG -Brooklyn Botanic Garden - Accessibility Improvements
Seq Number
3
Task Description
CONSTRUCTION TO 50%
Orig Start Date
2021-12-01T00:00:00.000
Orig End Date
2022-04-01T00:00:00.000
Task Start Date
2024-12-01T00:00:00.000
Task End Date
2025-04-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV236ROSE
Project Descr
BBG -Brooklyn Botanic Garden - Accessibility Improvements
Seq Number
4
Task Description
CONSTRUCTION TO 75%
Orig Start Date
2022-04-01T00:00:00.000
Orig End Date
2022-06-01T00:00:00.000
Task Start Date
2025-04-01T00:00:00.000
Task End Date
2025-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV236ROSE
Project Descr
BBG -Brooklyn Botanic Garden - Accessibility Improvements
Seq Number
5
Task Description
SUBSTANTIAL COMPLETION
Orig Start Date
2022-06-01T00:00:00.000
Orig End Date
2022-08-01T00:00:00.000
Task Start Date
2025-06-01T00:00:00.000
Task End Date
2025-08-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV236ROSE
Project Descr
BBG -Brooklyn Botanic Garden - Accessibility Improvements
Seq Number
6
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2022-08-01T00:00:00.000
Orig End Date
2022-09-01T00:00:00.000
Task Start Date
2025-08-01T00:00:00.000
Task End Date
2025-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV262HOLD
Project Descr
BCM - Brooklyn Children's Museum - HOLD
Seq Number
1
Task Description
DEVELOP SCOPE
Orig Start Date
2026-09-01T00:00:00.000
Orig End Date
2026-12-01T00:00:00.000
Task Start Date
2026-06-01T00:00:00.000
Task End Date
2026-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV262HOLD
Project Descr
BCM - Brooklyn Children's Museum - HOLD
Seq Number
2
Task Description
PRELIMINARY DESIGN
Orig Start Date
2026-12-01T00:00:00.000
Orig End Date
2027-04-01T00:00:00.000
Task Start Date
2026-09-01T00:00:00.000
Task End Date
2027-01-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV262HOLD
Project Descr
BCM - Brooklyn Children's Museum - HOLD
Seq Number
3
Task Description
FINAL DESIGN
Orig Start Date
2027-04-01T00:00:00.000
Orig End Date
2027-10-01T00:00:00.000
Task Start Date
2027-01-01T00:00:00.000
Task End Date
2027-07-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV262HOLD
Project Descr
BCM - Brooklyn Children's Museum - HOLD
Seq Number
4
Task Description
BID AWARD AND REGISTER CONTRCT
Orig Start Date
2027-10-01T00:00:00.000
Orig End Date
2028-01-01T00:00:00.000
Task Start Date
2027-07-01T00:00:00.000
Task End Date
2027-10-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV262HOLD
Project Descr
BCM - Brooklyn Children's Museum - HOLD
Seq Number
5
Task Description
CONSTRUCTION TO 25%
Orig Start Date
2028-01-01T00:00:00.000
Orig End Date
2028-05-01T00:00:00.000
Task Start Date
2027-10-01T00:00:00.000
Task End Date
2028-02-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 126
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
126
Managing Agcy
DEPARTMENT OF CULTURAL AFFAIRS
Project Id
PV262HOLD
Project Descr
BCM - Brooklyn Children's Museum - HOLD
Seq Number
6
Task Description
CONSTRUCTION TO 50%
Orig Start Date
2028-05-01T00:00:00.000
Orig End Date
2028-09-01T00:00:00.000
Task Start Date
2028-02-01T00:00:00.000
Task End Date
2028-06-01T00:00:00.000