Capital Project Detail Data - Milestones

This dataset contains capital commitment plan data by managing agency, project identification number and project schedules. The dataset was updated three times a year during the Preliminary, Executive and Adopted Capital Commitment Plans. Starting in January 2024, OMB will no longer update this dataset. It is being replaced by the Capital Projects Dashboard administered by the Mayor's Office of Operations.

City Government Mayor’s Office of Management and Budget (OMB) Dataset s7yh-frbm 12 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SAND2601C
Project Descr
CIH: RELOCATE OUTPATIENT RADIOLOGIC IMAGING SERVICES
Seq Number
4
Task Description
ORIGINAL EQUIP & FURNISHING
Orig Start Date
2020-04-01T00:00:00.000
Orig End Date
2020-03-01T00:00:00.000
Task Start Date
2023-04-01T00:00:00.000
Task End Date
2023-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SAND2601C
Project Descr
CIH: RELOCATE OUTPATIENT RADIOLOGIC IMAGING SERVICES
Seq Number
5
Task Description
SUBSTANTIAL COMPLETION
Orig Start Date
2020-04-01T00:00:00.000
Orig End Date
2020-03-01T00:00:00.000
Task Start Date
2023-04-01T00:00:00.000
Task End Date
2023-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SAND2601C
Project Descr
CIH: RELOCATE OUTPATIENT RADIOLOGIC IMAGING SERVICES
Seq Number
6
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2020-04-01T00:00:00.000
Orig End Date
2020-04-01T00:00:00.000
Task Start Date
2023-04-01T00:00:00.000
Task End Date
2028-04-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SAND2603C
Project Descr
CIH: RENOVATE VACANT SPACE ON FIRST FL MAIN HOSPITAL BLG.
Seq Number
1
Task Description
DESIGN
Orig Start Date
2015-10-01T00:00:00.000
Orig End Date
2020-03-01T00:00:00.000
Task Start Date
2015-10-01T00:00:00.000
Task End Date
2020-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SAND2603C
Project Descr
CIH: RENOVATE VACANT SPACE ON FIRST FL MAIN HOSPITAL BLG.
Seq Number
2
Task Description
BID AWARD AND REGISTER CONTRCT
Orig Start Date
2020-04-01T00:00:00.000
Orig End Date
2020-03-01T00:00:00.000
Task Start Date
2020-04-01T00:00:00.000
Task End Date
2020-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SAND2603C
Project Descr
CIH: RENOVATE VACANT SPACE ON FIRST FL MAIN HOSPITAL BLG.
Seq Number
3
Task Description
CONSTRUCTION
Orig Start Date
2020-04-01T00:00:00.000
Orig End Date
2020-03-01T00:00:00.000
Task Start Date
2020-04-01T00:00:00.000
Task End Date
2020-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SAND2603C
Project Descr
CIH: RENOVATE VACANT SPACE ON FIRST FL MAIN HOSPITAL BLG.
Seq Number
4
Task Description
ORIGINAL EQUIP & FURNISHING
Orig Start Date
2020-04-01T00:00:00.000
Orig End Date
2020-03-01T00:00:00.000
Task Start Date
2020-04-01T00:00:00.000
Task End Date
2020-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SAND2603C
Project Descr
CIH: RENOVATE VACANT SPACE ON FIRST FL MAIN HOSPITAL BLG.
Seq Number
5
Task Description
SUBSTANTIAL COMPLETION
Orig Start Date
2020-04-01T00:00:00.000
Orig End Date
2020-03-01T00:00:00.000
Task Start Date
2020-04-01T00:00:00.000
Task End Date
2020-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SAND2603C
Project Descr
CIH: RENOVATE VACANT SPACE ON FIRST FL MAIN HOSPITAL BLG.
Seq Number
6
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2020-04-01T00:00:00.000
Orig End Date
2020-04-01T00:00:00.000
Task Start Date
2020-04-01T00:00:00.000
Task End Date
2025-04-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SAND2605
Project Descr
CIH: DESIGN & CONSTRUCTION MANAGEMENT FOR HOSPITAL CAMPUS
Seq Number
1
Task Description
DESIGN
Orig Start Date
2017-07-01T00:00:00.000
Orig End Date
2017-07-01T00:00:00.000
Task Start Date
2018-03-01T00:00:00.000
Task End Date
2018-04-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SAND2605
Project Descr
CIH: DESIGN & CONSTRUCTION MANAGEMENT FOR HOSPITAL CAMPUS
Seq Number
2
Task Description
BID AWARD AND REGISTER CONTRCT
Orig Start Date
2017-07-01T00:00:00.000
Orig End Date
2017-08-01T00:00:00.000
Task Start Date
2018-04-01T00:00:00.000
Task End Date
2018-04-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SAND2605
Project Descr
CIH: DESIGN & CONSTRUCTION MANAGEMENT FOR HOSPITAL CAMPUS
Seq Number
3
Task Description
CONSTRUCTION
Orig Start Date
2017-08-01T00:00:00.000
Orig End Date
2017-09-01T00:00:00.000
Task Start Date
2018-04-01T00:00:00.000
Task End Date
2018-05-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SAND2605
Project Descr
CIH: DESIGN & CONSTRUCTION MANAGEMENT FOR HOSPITAL CAMPUS
Seq Number
4
Task Description
ORIGINAL EQUIP & FURNISHING
Orig Start Date
2017-09-01T00:00:00.000
Orig End Date
2017-09-01T00:00:00.000
Task Start Date
2018-06-01T00:00:00.000
Task End Date
2018-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SAND2605
Project Descr
CIH: DESIGN & CONSTRUCTION MANAGEMENT FOR HOSPITAL CAMPUS
Seq Number
5
Task Description
SUBSTANTIAL COMPLETION
Orig Start Date
2017-09-01T00:00:00.000
Orig End Date
2017-10-01T00:00:00.000
Task Start Date
2018-06-01T00:00:00.000
Task End Date
2018-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SAND2605
Project Descr
CIH: DESIGN & CONSTRUCTION MANAGEMENT FOR HOSPITAL CAMPUS
Seq Number
6
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2017-10-01T00:00:00.000
Orig End Date
2017-10-01T00:00:00.000
Task Start Date
2018-06-01T00:00:00.000
Task End Date
2023-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SANDB3416
Project Descr
Sandy - BNYDC - PW 3416 - Berth 6 Concrete Slab
Seq Number
1
Task Description
DESIGN
Orig Start Date
2019-01-01T00:00:00.000
Orig End Date
2019-07-01T00:00:00.000
Task Start Date
2019-01-01T00:00:00.000
Task End Date
2020-07-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SANDB3416
Project Descr
Sandy - BNYDC - PW 3416 - Berth 6 Concrete Slab
Seq Number
2
Task Description
CONSTRUCTION
Orig Start Date
2019-07-01T00:00:00.000
Orig End Date
2020-11-01T00:00:00.000
Task Start Date
2019-01-01T00:00:00.000
Task End Date
2020-07-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SANDB3416
Project Descr
Sandy - BNYDC - PW 3416 - Berth 6 Concrete Slab
Seq Number
3
Task Description
SUBSTANTIAL COMPLETION
Orig Start Date
2020-11-01T00:00:00.000
Orig End Date
2021-01-01T00:00:00.000
Task Start Date
2020-07-01T00:00:00.000
Task End Date
2021-11-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SANDB3416
Project Descr
Sandy - BNYDC - PW 3416 - Berth 6 Concrete Slab
Seq Number
4
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2021-01-01T00:00:00.000
Orig End Date
2021-01-01T00:00:00.000
Task Start Date
2020-07-01T00:00:00.000
Task End Date
2021-11-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SANDB3416
Project Descr
Sandy - BNYDC - PW 3416 - Berth 6 Concrete Slab
Seq Number
5
Task Description
SUBSTANTIAL COMPLETION
Orig Start Date
2021-01-01T00:00:00.000
Orig End Date
2021-01-01T00:00:00.000
Task Start Date
2021-11-01T00:00:00.000
Task End Date
2022-01-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SANDB3416
Project Descr
Sandy - BNYDC - PW 3416 - Berth 6 Concrete Slab
Seq Number
6
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2021-01-01T00:00:00.000
Orig End Date
2021-01-01T00:00:00.000
Task Start Date
2022-01-01T00:00:00.000
Task End Date
2022-01-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SANDB4123
Project Descr
Sandy - BNYDC - PW 4123 Rehabilitation
Seq Number
1
Task Description
DESIGN
Orig Start Date
2021-05-01T00:00:00.000
Orig End Date
2021-06-01T00:00:00.000
Task Start Date
2021-05-01T00:00:00.000
Task End Date
2021-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SANDB4123
Project Descr
Sandy - BNYDC - PW 4123 Rehabilitation
Seq Number
2
Task Description
CONSTRUCTION
Orig Start Date
2021-06-01T00:00:00.000
Orig End Date
2023-02-01T00:00:00.000
Task Start Date
2021-05-01T00:00:00.000
Task End Date
2021-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SANDB4123
Project Descr
Sandy - BNYDC - PW 4123 Rehabilitation
Seq Number
3
Task Description
SUBSTANTIAL COMPLETION
Orig Start Date
2023-02-01T00:00:00.000
Orig End Date
2023-04-01T00:00:00.000
Task Start Date
2021-06-01T00:00:00.000
Task End Date
2023-02-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SANDB4123
Project Descr
Sandy - BNYDC - PW 4123 Rehabilitation
Seq Number
4
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2023-04-01T00:00:00.000
Orig End Date
2023-04-01T00:00:00.000
Task Start Date
2021-06-01T00:00:00.000
Task End Date
2023-02-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SANDB4123
Project Descr
Sandy - BNYDC - PW 4123 Rehabilitation
Seq Number
5
Task Description
SUBSTANTIAL COMPLETION
Orig Start Date
2023-04-01T00:00:00.000
Orig End Date
2023-04-01T00:00:00.000
Task Start Date
2023-02-01T00:00:00.000
Task End Date
2023-04-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SANDB4123
Project Descr
Sandy - BNYDC - PW 4123 Rehabilitation
Seq Number
6
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2023-04-01T00:00:00.000
Orig End Date
2023-04-01T00:00:00.000
Task Start Date
2023-04-01T00:00:00.000
Task End Date
2023-04-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SANDB4225
Project Descr
Sandy - BNYDC - PW 4225 Dry-Dock/Caisson Gate 5,6, PWell 156
Seq Number
1
Task Description
DESIGN
Orig Start Date
2019-01-01T00:00:00.000
Orig End Date
2019-04-01T00:00:00.000
Task Start Date
2019-01-01T00:00:00.000
Task End Date
2020-04-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SANDB4225
Project Descr
Sandy - BNYDC - PW 4225 Dry-Dock/Caisson Gate 5,6, PWell 156
Seq Number
2
Task Description
CONSTRUCTION
Orig Start Date
2019-04-01T00:00:00.000
Orig End Date
2020-04-01T00:00:00.000
Task Start Date
2019-01-01T00:00:00.000
Task End Date
2020-04-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SANDB4225
Project Descr
Sandy - BNYDC - PW 4225 Dry-Dock/Caisson Gate 5,6, PWell 156
Seq Number
3
Task Description
SUBSTANTIAL COMPLETION
Orig Start Date
2020-04-01T00:00:00.000
Orig End Date
2020-06-01T00:00:00.000
Task Start Date
2020-04-01T00:00:00.000
Task End Date
2024-05-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SANDB4225
Project Descr
Sandy - BNYDC - PW 4225 Dry-Dock/Caisson Gate 5,6, PWell 156
Seq Number
4
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2020-06-01T00:00:00.000
Orig End Date
2020-06-01T00:00:00.000
Task Start Date
2020-04-01T00:00:00.000
Task End Date
2024-05-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SANDB4225
Project Descr
Sandy - BNYDC - PW 4225 Dry-Dock/Caisson Gate 5,6, PWell 156
Seq Number
5
Task Description
SUBSTANTIAL COMPLETION
Orig Start Date
2020-06-01T00:00:00.000
Orig End Date
2020-06-01T00:00:00.000
Task Start Date
2024-05-01T00:00:00.000
Task End Date
2024-07-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SANDB4225
Project Descr
Sandy - BNYDC - PW 4225 Dry-Dock/Caisson Gate 5,6, PWell 156
Seq Number
6
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2020-06-01T00:00:00.000
Orig End Date
2020-06-01T00:00:00.000
Task Start Date
2024-07-01T00:00:00.000
Task End Date
2024-07-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SANDB4269
Project Descr
BNYDC Sandy - PW 4269 - B270 Boilers
Seq Number
1
Task Description
DESIGN
Orig Start Date
2023-01-01T00:00:00.000
Orig End Date
2023-03-01T00:00:00.000
Task Start Date
2022-06-01T00:00:00.000
Task End Date
2023-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SANDB4269
Project Descr
BNYDC Sandy - PW 4269 - B270 Boilers
Seq Number
2
Task Description
CONSTRUCTION
Orig Start Date
2023-03-01T00:00:00.000
Orig End Date
2024-04-01T00:00:00.000
Task Start Date
2022-06-01T00:00:00.000
Task End Date
2023-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SANDB4269
Project Descr
BNYDC Sandy - PW 4269 - B270 Boilers
Seq Number
3
Task Description
CONSTRUCTION
Orig Start Date
2024-04-01T00:00:00.000
Orig End Date
2024-06-01T00:00:00.000
Task Start Date
2023-03-01T00:00:00.000
Task End Date
2024-04-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SANDB4269
Project Descr
BNYDC Sandy - PW 4269 - B270 Boilers
Seq Number
4
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2024-06-01T00:00:00.000
Orig End Date
2024-06-01T00:00:00.000
Task Start Date
2023-03-01T00:00:00.000
Task End Date
2024-04-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SANDB4269
Project Descr
BNYDC Sandy - PW 4269 - B270 Boilers
Seq Number
5
Task Description
SUBSTANTIAL COMPLETION
Orig Start Date
2024-06-01T00:00:00.000
Orig End Date
2024-06-01T00:00:00.000
Task Start Date
2024-04-01T00:00:00.000
Task End Date
2024-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SANDB4269
Project Descr
BNYDC Sandy - PW 4269 - B270 Boilers
Seq Number
6
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2024-06-01T00:00:00.000
Orig End Date
2024-06-01T00:00:00.000
Task Start Date
2024-06-01T00:00:00.000
Task End Date
2024-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SANDB4270
Project Descr
Sandy - BNYDC - PW 4270 - BNYDC SITE-WIDE CONDUIT - PAAP
Seq Number
1
Task Description
DESIGN
Orig Start Date
2019-03-01T00:00:00.000
Orig End Date
2019-07-01T00:00:00.000
Task Start Date
2019-03-01T00:00:00.000
Task End Date
2020-07-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SANDB4270
Project Descr
Sandy - BNYDC - PW 4270 - BNYDC SITE-WIDE CONDUIT - PAAP
Seq Number
2
Task Description
CONSTRUCTION
Orig Start Date
2019-07-01T00:00:00.000
Orig End Date
2020-04-01T00:00:00.000
Task Start Date
2019-03-01T00:00:00.000
Task End Date
2020-07-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SANDB4270
Project Descr
Sandy - BNYDC - PW 4270 - BNYDC SITE-WIDE CONDUIT - PAAP
Seq Number
3
Task Description
SUBSTANTIAL COMPLETION
Orig Start Date
2020-04-01T00:00:00.000
Orig End Date
2020-06-01T00:00:00.000
Task Start Date
2020-07-01T00:00:00.000
Task End Date
2024-08-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SANDB4270
Project Descr
Sandy - BNYDC - PW 4270 - BNYDC SITE-WIDE CONDUIT - PAAP
Seq Number
4
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2020-06-01T00:00:00.000
Orig End Date
2020-06-01T00:00:00.000
Task Start Date
2020-07-01T00:00:00.000
Task End Date
2024-08-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SANDB4270
Project Descr
Sandy - BNYDC - PW 4270 - BNYDC SITE-WIDE CONDUIT - PAAP
Seq Number
5
Task Description
SUBSTANTIAL COMPLETION
Orig Start Date
2020-06-01T00:00:00.000
Orig End Date
2020-06-01T00:00:00.000
Task Start Date
2024-08-01T00:00:00.000
Task End Date
2024-11-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SANDB4270
Project Descr
Sandy - BNYDC - PW 4270 - BNYDC SITE-WIDE CONDUIT - PAAP
Seq Number
6
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2020-06-01T00:00:00.000
Orig End Date
2020-06-01T00:00:00.000
Task Start Date
2024-11-01T00:00:00.000
Task End Date
2024-11-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SANDB4271
Project Descr
Sandy - BNYDC - PW 4271 - Substations No. 292 and No. 542
Seq Number
1
Task Description
DESIGN
Orig Start Date
2019-03-01T00:00:00.000
Orig End Date
2019-07-01T00:00:00.000
Task Start Date
2019-03-01T00:00:00.000
Task End Date
2020-07-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SANDB4271
Project Descr
Sandy - BNYDC - PW 4271 - Substations No. 292 and No. 542
Seq Number
2
Task Description
CONSTRUCTION
Orig Start Date
2019-07-01T00:00:00.000
Orig End Date
2020-03-01T00:00:00.000
Task Start Date
2019-03-01T00:00:00.000
Task End Date
2020-07-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SANDB4271
Project Descr
Sandy - BNYDC - PW 4271 - Substations No. 292 and No. 542
Seq Number
3
Task Description
SUBSTANTIAL COMPLETION
Orig Start Date
2020-04-01T00:00:00.000
Orig End Date
2020-06-01T00:00:00.000
Task Start Date
2020-07-01T00:00:00.000
Task End Date
2022-04-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SANDB4271
Project Descr
Sandy - BNYDC - PW 4271 - Substations No. 292 and No. 542
Seq Number
4
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2020-06-01T00:00:00.000
Orig End Date
2020-06-01T00:00:00.000
Task Start Date
2020-07-01T00:00:00.000
Task End Date
2022-04-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 801
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
801
Managing Agcy
DEPT OF SMALL BUSINESS SERVICES
Project Id
SANDB4271
Project Descr
Sandy - BNYDC - PW 4271 - Substations No. 292 and No. 542
Seq Number
5
Task Description
SUBSTANTIAL COMPLETION
Orig Start Date
2020-06-01T00:00:00.000
Orig End Date
2020-06-01T00:00:00.000
Task Start Date
2022-04-01T00:00:00.000
Task End Date
2022-06-01T00:00:00.000