Capital Project Detail Data - Milestones

This dataset contains capital commitment plan data by managing agency, project identification number and project schedules. The dataset was updated three times a year during the Preliminary, Executive and Adopted Capital Commitment Plans. Starting in January 2024, OMB will no longer update this dataset. It is being replaced by the Capital Projects Dashboard administered by the Mayor's Office of Operations.

City Government Mayor’s Office of Management and Budget (OMB) Dataset s7yh-frbm 12 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
S216-403C
Project Descr
Hamilton Avenue MTS Rehab
Seq Number
5
Task Description
CONSTRUCTION TO 25%
Orig Start Date
2021-07-01T00:00:00.000
Orig End Date
2021-12-01T00:00:00.000
Task Start Date
2021-07-01T00:00:00.000
Task End Date
2021-12-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
S216-403C
Project Descr
Hamilton Avenue MTS Rehab
Seq Number
6
Task Description
CONSTRUCTION TO 50%
Orig Start Date
2021-12-01T00:00:00.000
Orig End Date
2022-06-01T00:00:00.000
Task Start Date
2021-12-01T00:00:00.000
Task End Date
2022-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
S216-403C
Project Descr
Hamilton Avenue MTS Rehab
Seq Number
7
Task Description
CONSTRUCTION TO 75%
Orig Start Date
2022-06-01T00:00:00.000
Orig End Date
2022-12-01T00:00:00.000
Task Start Date
2022-06-01T00:00:00.000
Task End Date
2022-12-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
S216-403C
Project Descr
Hamilton Avenue MTS Rehab
Seq Number
8
Task Description
SUBSTANTIAL COMPLETION
Orig Start Date
2022-12-01T00:00:00.000
Orig End Date
2024-01-01T00:00:00.000
Task Start Date
2022-12-01T00:00:00.000
Task End Date
2024-01-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
S216-403C
Project Descr
Hamilton Avenue MTS Rehab
Seq Number
9
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2024-01-01T00:00:00.000
Orig End Date
2025-03-01T00:00:00.000
Task Start Date
2024-01-01T00:00:00.000
Task End Date
2025-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDBK11C
Project Descr
Hurricane Sandy Brooklyn 11 Conduit Replacement
Seq Number
1
Task Description
DEVELOP SCOPE
Orig Start Date
2015-08-01T00:00:00.000
Orig End Date
2018-02-01T00:00:00.000
Task Start Date
2015-08-01T00:00:00.000
Task End Date
2018-02-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDBK11C
Project Descr
Hurricane Sandy Brooklyn 11 Conduit Replacement
Seq Number
2
Task Description
PRELIMINARY DESIGN
Orig Start Date
2018-02-01T00:00:00.000
Orig End Date
2018-04-01T00:00:00.000
Task Start Date
2018-02-01T00:00:00.000
Task End Date
2018-04-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDBK11C
Project Descr
Hurricane Sandy Brooklyn 11 Conduit Replacement
Seq Number
3
Task Description
FINAL DESIGN
Orig Start Date
2018-04-01T00:00:00.000
Orig End Date
2018-06-01T00:00:00.000
Task Start Date
2018-04-01T00:00:00.000
Task End Date
2018-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDBK11C
Project Descr
Hurricane Sandy Brooklyn 11 Conduit Replacement
Seq Number
4
Task Description
BID AWARD AND REGISTER CONTRCT
Orig Start Date
2018-06-01T00:00:00.000
Orig End Date
2018-09-01T00:00:00.000
Task Start Date
2018-06-01T00:00:00.000
Task End Date
2018-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDBK11C
Project Descr
Hurricane Sandy Brooklyn 11 Conduit Replacement
Seq Number
5
Task Description
CONSTRUCTION TO 25%
Orig Start Date
2018-09-01T00:00:00.000
Orig End Date
2019-03-01T00:00:00.000
Task Start Date
2018-09-01T00:00:00.000
Task End Date
2019-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDBK11C
Project Descr
Hurricane Sandy Brooklyn 11 Conduit Replacement
Seq Number
6
Task Description
CONSTRUCTION TO 50%
Orig Start Date
2019-03-01T00:00:00.000
Orig End Date
2019-10-01T00:00:00.000
Task Start Date
2019-03-01T00:00:00.000
Task End Date
2019-10-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDBK11C
Project Descr
Hurricane Sandy Brooklyn 11 Conduit Replacement
Seq Number
7
Task Description
CONSTRUCTION TO 75%
Orig Start Date
2019-10-01T00:00:00.000
Orig End Date
2020-04-01T00:00:00.000
Task Start Date
2019-10-01T00:00:00.000
Task End Date
2020-04-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDBK11C
Project Descr
Hurricane Sandy Brooklyn 11 Conduit Replacement
Seq Number
8
Task Description
SUBSTANTIAL COMPLETION
Orig Start Date
2020-04-01T00:00:00.000
Orig End Date
2021-09-01T00:00:00.000
Task Start Date
2020-04-01T00:00:00.000
Task End Date
2021-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDBK11C
Project Descr
Hurricane Sandy Brooklyn 11 Conduit Replacement
Seq Number
9
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2021-09-01T00:00:00.000
Orig End Date
2024-06-01T00:00:00.000
Task Start Date
2021-09-01T00:00:00.000
Task End Date
2024-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDBK11G
Project Descr
Hurricane Sandy Brooklyn 11 R/R & Haz Mitigation
Seq Number
1
Task Description
DEVELOP SCOPE
Orig Start Date
2015-08-01T00:00:00.000
Orig End Date
2018-02-01T00:00:00.000
Task Start Date
2015-08-01T00:00:00.000
Task End Date
2018-02-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDBK11G
Project Descr
Hurricane Sandy Brooklyn 11 R/R & Haz Mitigation
Seq Number
2
Task Description
PRELIMINARY DESIGN
Orig Start Date
2018-02-01T00:00:00.000
Orig End Date
2018-04-01T00:00:00.000
Task Start Date
2018-02-01T00:00:00.000
Task End Date
2018-04-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDBK11G
Project Descr
Hurricane Sandy Brooklyn 11 R/R & Haz Mitigation
Seq Number
3
Task Description
FINAL DESIGN
Orig Start Date
2018-04-01T00:00:00.000
Orig End Date
2018-06-01T00:00:00.000
Task Start Date
2018-04-01T00:00:00.000
Task End Date
2018-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDBK11G
Project Descr
Hurricane Sandy Brooklyn 11 R/R & Haz Mitigation
Seq Number
4
Task Description
BID AWARD AND REGISTER CONTRCT
Orig Start Date
2018-06-01T00:00:00.000
Orig End Date
2018-09-01T00:00:00.000
Task Start Date
2018-06-01T00:00:00.000
Task End Date
2018-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDBK11G
Project Descr
Hurricane Sandy Brooklyn 11 R/R & Haz Mitigation
Seq Number
5
Task Description
CONSTRUCTION TO 25%
Orig Start Date
2018-09-01T00:00:00.000
Orig End Date
2019-03-01T00:00:00.000
Task Start Date
2018-09-01T00:00:00.000
Task End Date
2019-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDBK11G
Project Descr
Hurricane Sandy Brooklyn 11 R/R & Haz Mitigation
Seq Number
6
Task Description
CONSTRUCTION TO 50%
Orig Start Date
2019-03-01T00:00:00.000
Orig End Date
2019-10-01T00:00:00.000
Task Start Date
2019-03-01T00:00:00.000
Task End Date
2019-10-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDBK11G
Project Descr
Hurricane Sandy Brooklyn 11 R/R & Haz Mitigation
Seq Number
7
Task Description
CONSTRUCTION TO 75%
Orig Start Date
2019-10-01T00:00:00.000
Orig End Date
2020-04-01T00:00:00.000
Task Start Date
2019-10-01T00:00:00.000
Task End Date
2020-04-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDBK11G
Project Descr
Hurricane Sandy Brooklyn 11 R/R & Haz Mitigation
Seq Number
8
Task Description
SUBSTANTIAL COMPLETION
Orig Start Date
2020-04-01T00:00:00.000
Orig End Date
2021-09-01T00:00:00.000
Task Start Date
2020-04-01T00:00:00.000
Task End Date
2021-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDBK11G
Project Descr
Hurricane Sandy Brooklyn 11 R/R & Haz Mitigation
Seq Number
9
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2021-09-01T00:00:00.000
Orig End Date
2024-06-01T00:00:00.000
Task Start Date
2021-09-01T00:00:00.000
Task End Date
2024-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDBK4FA
Project Descr
Hurricane Sandy Brooklyn 1/4 Fire Alarm Replacement
Seq Number
1
Task Description
DEVELOP SCOPE
Orig Start Date
2015-08-01T00:00:00.000
Orig End Date
2016-02-01T00:00:00.000
Task Start Date
2015-08-01T00:00:00.000
Task End Date
2016-02-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDBK4FA
Project Descr
Hurricane Sandy Brooklyn 1/4 Fire Alarm Replacement
Seq Number
2
Task Description
PRELIMINARY DESIGN
Orig Start Date
2016-02-01T00:00:00.000
Orig End Date
2016-08-01T00:00:00.000
Task Start Date
2016-02-01T00:00:00.000
Task End Date
2016-08-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDBK4FA
Project Descr
Hurricane Sandy Brooklyn 1/4 Fire Alarm Replacement
Seq Number
3
Task Description
FINAL DESIGN
Orig Start Date
2016-08-01T00:00:00.000
Orig End Date
2017-08-01T00:00:00.000
Task Start Date
2016-08-01T00:00:00.000
Task End Date
2017-08-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDBK4FA
Project Descr
Hurricane Sandy Brooklyn 1/4 Fire Alarm Replacement
Seq Number
4
Task Description
BID AWARD AND REGISTER CONTRCT
Orig Start Date
2017-08-01T00:00:00.000
Orig End Date
2018-08-01T00:00:00.000
Task Start Date
2017-08-01T00:00:00.000
Task End Date
2018-08-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDBK4FA
Project Descr
Hurricane Sandy Brooklyn 1/4 Fire Alarm Replacement
Seq Number
5
Task Description
CONSTRUCTION TO 25%
Orig Start Date
2018-08-01T00:00:00.000
Orig End Date
2019-08-01T00:00:00.000
Task Start Date
2018-08-01T00:00:00.000
Task End Date
2019-08-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDBK4FA
Project Descr
Hurricane Sandy Brooklyn 1/4 Fire Alarm Replacement
Seq Number
6
Task Description
CONSTRUCTION TO 50%
Orig Start Date
2019-08-01T00:00:00.000
Orig End Date
2020-08-01T00:00:00.000
Task Start Date
2019-08-01T00:00:00.000
Task End Date
2020-08-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDBK4FA
Project Descr
Hurricane Sandy Brooklyn 1/4 Fire Alarm Replacement
Seq Number
7
Task Description
CONSTRUCTION TO 75%
Orig Start Date
2020-08-01T00:00:00.000
Orig End Date
2021-08-01T00:00:00.000
Task Start Date
2020-08-01T00:00:00.000
Task End Date
2021-08-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDBK4FA
Project Descr
Hurricane Sandy Brooklyn 1/4 Fire Alarm Replacement
Seq Number
8
Task Description
SUBSTANTIAL COMPLETION
Orig Start Date
2021-08-01T00:00:00.000
Orig End Date
2024-05-01T00:00:00.000
Task Start Date
2021-08-01T00:00:00.000
Task End Date
2024-05-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDBK4FA
Project Descr
Hurricane Sandy Brooklyn 1/4 Fire Alarm Replacement
Seq Number
9
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2021-12-01T00:00:00.000
Orig End Date
2024-09-01T00:00:00.000
Task Start Date
2021-12-01T00:00:00.000
Task End Date
2024-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDGPTWH
Project Descr
Hurricane Sandy GRNPT Warehouse R/R & Haz Mitigation
Seq Number
1
Task Description
DEVELOP SCOPE
Orig Start Date
2015-08-01T00:00:00.000
Orig End Date
2015-12-01T00:00:00.000
Task Start Date
2015-08-01T00:00:00.000
Task End Date
2015-12-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDGPTWH
Project Descr
Hurricane Sandy GRNPT Warehouse R/R & Haz Mitigation
Seq Number
2
Task Description
PRELIMINARY DESIGN
Orig Start Date
2015-12-01T00:00:00.000
Orig End Date
2016-06-01T00:00:00.000
Task Start Date
2015-12-01T00:00:00.000
Task End Date
2016-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDGPTWH
Project Descr
Hurricane Sandy GRNPT Warehouse R/R & Haz Mitigation
Seq Number
3
Task Description
FINAL DESIGN
Orig Start Date
2016-06-01T00:00:00.000
Orig End Date
2017-06-01T00:00:00.000
Task Start Date
2016-06-01T00:00:00.000
Task End Date
2017-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDGPTWH
Project Descr
Hurricane Sandy GRNPT Warehouse R/R & Haz Mitigation
Seq Number
4
Task Description
BID AWARD AND REGISTER CONTRCT
Orig Start Date
2017-06-01T00:00:00.000
Orig End Date
2018-06-01T00:00:00.000
Task Start Date
2017-06-01T00:00:00.000
Task End Date
2018-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDGPTWH
Project Descr
Hurricane Sandy GRNPT Warehouse R/R & Haz Mitigation
Seq Number
5
Task Description
CONSTRUCTION TO 25%
Orig Start Date
2018-06-01T00:00:00.000
Orig End Date
2019-06-01T00:00:00.000
Task Start Date
2018-06-01T00:00:00.000
Task End Date
2019-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDGPTWH
Project Descr
Hurricane Sandy GRNPT Warehouse R/R & Haz Mitigation
Seq Number
6
Task Description
CONSTRUCTION TO 50%
Orig Start Date
2019-06-01T00:00:00.000
Orig End Date
2020-06-01T00:00:00.000
Task Start Date
2019-06-01T00:00:00.000
Task End Date
2020-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDGPTWH
Project Descr
Hurricane Sandy GRNPT Warehouse R/R & Haz Mitigation
Seq Number
7
Task Description
CONSTRUCTION TO 75%
Orig Start Date
2020-06-01T00:00:00.000
Orig End Date
2023-03-01T00:00:00.000
Task Start Date
2020-06-01T00:00:00.000
Task End Date
2023-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDGPTWH
Project Descr
Hurricane Sandy GRNPT Warehouse R/R & Haz Mitigation
Seq Number
8
Task Description
SUBSTANTIAL COMPLETION
Orig Start Date
2023-03-01T00:00:00.000
Orig End Date
2025-12-01T00:00:00.000
Task Start Date
2023-03-01T00:00:00.000
Task End Date
2025-12-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDGPTWH
Project Descr
Hurricane Sandy GRNPT Warehouse R/R & Haz Mitigation
Seq Number
9
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2023-07-01T00:00:00.000
Orig End Date
2026-04-01T00:00:00.000
Task Start Date
2023-07-01T00:00:00.000
Task End Date
2026-04-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDGPWHC
Project Descr
Hurricane Sandy GRNPT Warehouse Conduit Replacement
Seq Number
1
Task Description
DEVELOP SCOPE
Orig Start Date
2017-08-01T00:00:00.000
Orig End Date
2018-05-01T00:00:00.000
Task Start Date
2017-08-01T00:00:00.000
Task End Date
2018-05-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDGPWHC
Project Descr
Hurricane Sandy GRNPT Warehouse Conduit Replacement
Seq Number
2
Task Description
PRELIMINARY DESIGN
Orig Start Date
2018-06-01T00:00:00.000
Orig End Date
2019-03-01T00:00:00.000
Task Start Date
2018-06-01T00:00:00.000
Task End Date
2019-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDGPWHC
Project Descr
Hurricane Sandy GRNPT Warehouse Conduit Replacement
Seq Number
3
Task Description
FINAL DESIGN
Orig Start Date
2019-03-01T00:00:00.000
Orig End Date
2019-12-01T00:00:00.000
Task Start Date
2019-03-01T00:00:00.000
Task End Date
2019-12-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDGPWHC
Project Descr
Hurricane Sandy GRNPT Warehouse Conduit Replacement
Seq Number
4
Task Description
BID AWARD AND REGISTER CONTRCT
Orig Start Date
2019-12-01T00:00:00.000
Orig End Date
2020-09-01T00:00:00.000
Task Start Date
2019-12-01T00:00:00.000
Task End Date
2020-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDGPWHC
Project Descr
Hurricane Sandy GRNPT Warehouse Conduit Replacement
Seq Number
5
Task Description
CONSTRUCTION TO 25%
Orig Start Date
2020-09-01T00:00:00.000
Orig End Date
2021-06-01T00:00:00.000
Task Start Date
2020-09-01T00:00:00.000
Task End Date
2021-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDGPWHC
Project Descr
Hurricane Sandy GRNPT Warehouse Conduit Replacement
Seq Number
6
Task Description
CONSTRUCTION TO 50%
Orig Start Date
2021-06-01T00:00:00.000
Orig End Date
2022-03-01T00:00:00.000
Task Start Date
2021-06-01T00:00:00.000
Task End Date
2022-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDGPWHC
Project Descr
Hurricane Sandy GRNPT Warehouse Conduit Replacement
Seq Number
7
Task Description
CONSTRUCTION TO 75%
Orig Start Date
2022-04-01T00:00:00.000
Orig End Date
2023-01-01T00:00:00.000
Task Start Date
2022-04-01T00:00:00.000
Task End Date
2023-01-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDGPWHC
Project Descr
Hurricane Sandy GRNPT Warehouse Conduit Replacement
Seq Number
8
Task Description
SUBSTANTIAL COMPLETION
Orig Start Date
2023-01-01T00:00:00.000
Orig End Date
2025-06-01T00:00:00.000
Task Start Date
2023-01-01T00:00:00.000
Task End Date
2025-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 827
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
827
Managing Agcy
DEPARTMENT OF SANITATION
Project Id
SANDGPWHC
Project Descr
Hurricane Sandy GRNPT Warehouse Conduit Replacement
Seq Number
9
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2025-06-01T00:00:00.000
Orig End Date
2027-12-01T00:00:00.000
Task Start Date
2025-06-01T00:00:00.000
Task End Date
2027-12-01T00:00:00.000