Capital Project Detail Data - Milestones

This dataset contains capital commitment plan data by managing agency, project identification number and project schedules. The dataset was updated three times a year during the Preliminary, Executive and Adopted Capital Commitment Plans. Starting in January 2024, OMB will no longer update this dataset. It is being replaced by the Capital Projects Dashboard administered by the Mayor's Office of Operations.

City Government Mayor’s Office of Management and Budget (OMB) Dataset s7yh-frbm 12 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BARRYP
Project Descr
Berry Playground B154
Seq Number
2
Task Description
DESIGN
Orig Start Date
2021-12-01T00:00:00.000
Orig End Date
2022-12-01T00:00:00.000
Task Start Date
2021-12-01T00:00:00.000
Task End Date
2022-12-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BARRYP
Project Descr
Berry Playground B154
Seq Number
3
Task Description
BID/ REGISTER CONTRACT
Orig Start Date
2022-12-01T00:00:00.000
Orig End Date
2023-09-01T00:00:00.000
Task Start Date
2022-12-01T00:00:00.000
Task End Date
2023-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BARRYP
Project Descr
Berry Playground B154
Seq Number
4
Task Description
CONSTRUCTION
Orig Start Date
2023-09-01T00:00:00.000
Orig End Date
2024-09-01T00:00:00.000
Task Start Date
2023-09-01T00:00:00.000
Task End Date
2024-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BARRYP
Project Descr
Berry Playground B154
Seq Number
5
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2024-09-01T00:00:00.000
Orig End Date
2025-09-01T00:00:00.000
Task Start Date
2024-09-01T00:00:00.000
Task End Date
2025-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BELTPA
Project Descr
Belt Pkwy Lndscp Restoration & Tree Planting Ph2 B166-113M
Seq Number
1
Task Description
DEVELOP SCOPE
Orig Start Date
2012-07-01T00:00:00.000
Orig End Date
2012-09-01T00:00:00.000
Task Start Date
2012-07-01T00:00:00.000
Task End Date
2015-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BELTPA
Project Descr
Belt Pkwy Lndscp Restoration & Tree Planting Ph2 B166-113M
Seq Number
2
Task Description
DESIGN
Orig Start Date
2012-09-01T00:00:00.000
Orig End Date
2012-12-01T00:00:00.000
Task Start Date
2015-07-01T00:00:00.000
Task End Date
2016-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BELTPA
Project Descr
Belt Pkwy Lndscp Restoration & Tree Planting Ph2 B166-113M
Seq Number
3
Task Description
BID/ REGISTER CONTRACT
Orig Start Date
2012-12-01T00:00:00.000
Orig End Date
2013-03-01T00:00:00.000
Task Start Date
2016-06-01T00:00:00.000
Task End Date
2016-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BELTPA
Project Descr
Belt Pkwy Lndscp Restoration & Tree Planting Ph2 B166-113M
Seq Number
4
Task Description
CONSTRUCTION
Orig Start Date
2013-03-01T00:00:00.000
Orig End Date
2014-03-01T00:00:00.000
Task Start Date
2016-09-01T00:00:00.000
Task End Date
2017-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BELTPA
Project Descr
Belt Pkwy Lndscp Restoration & Tree Planting Ph2 B166-113M
Seq Number
5
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2014-03-01T00:00:00.000
Orig End Date
2015-03-01T00:00:00.000
Task Start Date
2017-09-01T00:00:00.000
Task End Date
2025-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BELTPC
Project Descr
FY14 Belt Parkway Street Trees
Seq Number
1
Task Description
DEVELOP SCOPE
Orig Start Date
2013-07-01T00:00:00.000
Orig End Date
2013-09-01T00:00:00.000
Task Start Date
2013-07-01T00:00:00.000
Task End Date
2013-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BELTPC
Project Descr
FY14 Belt Parkway Street Trees
Seq Number
2
Task Description
DESIGN
Orig Start Date
2013-09-01T00:00:00.000
Orig End Date
2013-12-01T00:00:00.000
Task Start Date
2013-09-01T00:00:00.000
Task End Date
2013-12-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BELTPC
Project Descr
FY14 Belt Parkway Street Trees
Seq Number
3
Task Description
BID/ REGISTER CONTRACT
Orig Start Date
2013-12-01T00:00:00.000
Orig End Date
2014-03-01T00:00:00.000
Task Start Date
2013-12-01T00:00:00.000
Task End Date
2014-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BELTPC
Project Descr
FY14 Belt Parkway Street Trees
Seq Number
4
Task Description
CONSTRUCTION
Orig Start Date
2014-03-01T00:00:00.000
Orig End Date
2015-03-01T00:00:00.000
Task Start Date
2014-03-01T00:00:00.000
Task End Date
2015-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BELTPC
Project Descr
FY14 Belt Parkway Street Trees
Seq Number
5
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2015-03-01T00:00:00.000
Orig End Date
2016-03-01T00:00:00.000
Task Start Date
2015-03-01T00:00:00.000
Task End Date
2026-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BELTPD
Project Descr
CON - BIKE PATH THRU CANARSIE PARK WEST
Seq Number
1
Task Description
DEVELOP SCOPE
Orig Start Date
2013-03-01T00:00:00.000
Orig End Date
2013-05-01T00:00:00.000
Task Start Date
2013-03-01T00:00:00.000
Task End Date
2013-05-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BELTPD
Project Descr
CON - BIKE PATH THRU CANARSIE PARK WEST
Seq Number
2
Task Description
DESIGN
Orig Start Date
2013-05-01T00:00:00.000
Orig End Date
2013-08-01T00:00:00.000
Task Start Date
2013-05-01T00:00:00.000
Task End Date
2013-08-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BELTPD
Project Descr
CON - BIKE PATH THRU CANARSIE PARK WEST
Seq Number
3
Task Description
BID/ REGISTER CONTRACT
Orig Start Date
2013-08-01T00:00:00.000
Orig End Date
2013-11-01T00:00:00.000
Task Start Date
2013-08-01T00:00:00.000
Task End Date
2014-11-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BELTPD
Project Descr
CON - BIKE PATH THRU CANARSIE PARK WEST
Seq Number
4
Task Description
CONSTRUCTION
Orig Start Date
2013-11-01T00:00:00.000
Orig End Date
2014-11-01T00:00:00.000
Task Start Date
2014-11-01T00:00:00.000
Task End Date
2015-11-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BELTPD
Project Descr
CON - BIKE PATH THRU CANARSIE PARK WEST
Seq Number
5
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2014-11-01T00:00:00.000
Orig End Date
2015-11-01T00:00:00.000
Task Start Date
2015-11-01T00:00:00.000
Task End Date
2026-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BELTPE
Project Descr
Mill Basin Bridge Trees
Seq Number
1
Task Description
DEVELOP SCOPE
Orig Start Date
2016-07-01T00:00:00.000
Orig End Date
2016-12-01T00:00:00.000
Task Start Date
2016-07-01T00:00:00.000
Task End Date
2016-12-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BELTPE
Project Descr
Mill Basin Bridge Trees
Seq Number
2
Task Description
DESIGN
Orig Start Date
2016-12-01T00:00:00.000
Orig End Date
2018-12-01T00:00:00.000
Task Start Date
2016-12-01T00:00:00.000
Task End Date
2018-12-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BELTPE
Project Descr
Mill Basin Bridge Trees
Seq Number
3
Task Description
BID/ REGISTER CONTRACT
Orig Start Date
2018-12-01T00:00:00.000
Orig End Date
2019-09-01T00:00:00.000
Task Start Date
2018-12-01T00:00:00.000
Task End Date
2019-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BELTPE
Project Descr
Mill Basin Bridge Trees
Seq Number
4
Task Description
CONSTRUCTION
Orig Start Date
2019-09-01T00:00:00.000
Orig End Date
2022-09-01T00:00:00.000
Task Start Date
2019-09-01T00:00:00.000
Task End Date
2022-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BELTPE
Project Descr
Mill Basin Bridge Trees
Seq Number
5
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2022-09-01T00:00:00.000
Orig End Date
2024-09-01T00:00:00.000
Task Start Date
2022-09-01T00:00:00.000
Task End Date
2024-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BKPAV1
Project Descr
Brooklyn Multisite Pavement Reconstruction
Seq Number
1
Task Description
DEVELOP SCOPE
Orig Start Date
2018-07-01T00:00:00.000
Orig End Date
2018-12-01T00:00:00.000
Task Start Date
2018-07-01T00:00:00.000
Task End Date
2018-12-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BKPAV1
Project Descr
Brooklyn Multisite Pavement Reconstruction
Seq Number
2
Task Description
DESIGN
Orig Start Date
2018-12-01T00:00:00.000
Orig End Date
2019-12-01T00:00:00.000
Task Start Date
2018-12-01T00:00:00.000
Task End Date
2019-12-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BKPAV1
Project Descr
Brooklyn Multisite Pavement Reconstruction
Seq Number
3
Task Description
BID/ REGISTER CONTRACT
Orig Start Date
2019-12-01T00:00:00.000
Orig End Date
2020-09-01T00:00:00.000
Task Start Date
2019-12-01T00:00:00.000
Task End Date
2020-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BKPAV1
Project Descr
Brooklyn Multisite Pavement Reconstruction
Seq Number
4
Task Description
CONSTRUCTION
Orig Start Date
2020-09-01T00:00:00.000
Orig End Date
2021-09-01T00:00:00.000
Task Start Date
2020-09-01T00:00:00.000
Task End Date
2021-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BKPAV1
Project Descr
Brooklyn Multisite Pavement Reconstruction
Seq Number
5
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2021-09-01T00:00:00.000
Orig End Date
2022-09-01T00:00:00.000
Task Start Date
2021-09-01T00:00:00.000
Task End Date
2025-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BKPLG1
Project Descr
Brooklyn MPPA SOGR Reconstruction BG-220M
Seq Number
1
Task Description
DEVELOP SCOPE
Orig Start Date
2019-07-01T00:00:00.000
Orig End Date
2019-12-01T00:00:00.000
Task Start Date
2019-07-01T00:00:00.000
Task End Date
2019-12-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BKPLG1
Project Descr
Brooklyn MPPA SOGR Reconstruction BG-220M
Seq Number
2
Task Description
DESIGN
Orig Start Date
2019-12-01T00:00:00.000
Orig End Date
2021-06-01T00:00:00.000
Task Start Date
2019-12-01T00:00:00.000
Task End Date
2021-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BKPLG1
Project Descr
Brooklyn MPPA SOGR Reconstruction BG-220M
Seq Number
3
Task Description
BID/ REGISTER CONTRACT
Orig Start Date
2021-06-01T00:00:00.000
Orig End Date
2022-03-01T00:00:00.000
Task Start Date
2021-06-01T00:00:00.000
Task End Date
2022-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BKPLG1
Project Descr
Brooklyn MPPA SOGR Reconstruction BG-220M
Seq Number
4
Task Description
CONSTRUCTION
Orig Start Date
2022-03-01T00:00:00.000
Orig End Date
2023-09-01T00:00:00.000
Task Start Date
2022-03-01T00:00:00.000
Task End Date
2023-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BKPLG1
Project Descr
Brooklyn MPPA SOGR Reconstruction BG-220M
Seq Number
5
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2023-09-01T00:00:00.000
Orig End Date
2024-09-01T00:00:00.000
Task Start Date
2023-09-01T00:00:00.000
Task End Date
2024-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BQGRN
Project Descr
BQ GREEN
Seq Number
1
Task Description
DEVELOP SCOPE
Orig Start Date
2017-07-01T00:00:00.000
Orig End Date
2017-12-01T00:00:00.000
Task Start Date
2017-07-01T00:00:00.000
Task End Date
2017-12-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BQGRN
Project Descr
BQ GREEN
Seq Number
2
Task Description
DESIGN
Orig Start Date
2017-12-01T00:00:00.000
Orig End Date
2019-06-01T00:00:00.000
Task Start Date
2017-12-01T00:00:00.000
Task End Date
2019-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BQGRN
Project Descr
BQ GREEN
Seq Number
3
Task Description
BID/ REGISTER CONTRACT
Orig Start Date
2019-06-01T00:00:00.000
Orig End Date
2020-03-01T00:00:00.000
Task Start Date
2019-06-01T00:00:00.000
Task End Date
2020-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BQGRN
Project Descr
BQ GREEN
Seq Number
4
Task Description
CONSTRUCTION
Orig Start Date
2020-03-01T00:00:00.000
Orig End Date
2021-09-01T00:00:00.000
Task Start Date
2020-03-01T00:00:00.000
Task End Date
2021-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BQGRN
Project Descr
BQ GREEN
Seq Number
5
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2021-09-01T00:00:00.000
Orig End Date
2022-09-01T00:00:00.000
Task Start Date
2021-09-01T00:00:00.000
Task End Date
2025-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BRIGHM
Project Descr
Brigham Park - plgd & passive area B057-212M/512M
Seq Number
1
Task Description
DEVELOP SCOPE
Orig Start Date
2009-07-01T00:00:00.000
Orig End Date
2009-09-01T00:00:00.000
Task Start Date
2009-07-01T00:00:00.000
Task End Date
2009-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BRIGHM
Project Descr
Brigham Park - plgd & passive area B057-212M/512M
Seq Number
2
Task Description
DESIGN
Orig Start Date
2009-09-01T00:00:00.000
Orig End Date
2009-12-01T00:00:00.000
Task Start Date
2009-09-01T00:00:00.000
Task End Date
2009-12-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BRIGHM
Project Descr
Brigham Park - plgd & passive area B057-212M/512M
Seq Number
3
Task Description
BID/ REGISTER CONTRACT
Orig Start Date
2009-12-01T00:00:00.000
Orig End Date
2010-03-01T00:00:00.000
Task Start Date
2009-12-01T00:00:00.000
Task End Date
2010-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BRIGHM
Project Descr
Brigham Park - plgd & passive area B057-212M/512M
Seq Number
4
Task Description
CONSTRUCTION
Orig Start Date
2010-03-01T00:00:00.000
Orig End Date
2011-03-01T00:00:00.000
Task Start Date
2010-03-01T00:00:00.000
Task End Date
2011-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BRIGHM
Project Descr
Brigham Park - plgd & passive area B057-212M/512M
Seq Number
5
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2011-03-01T00:00:00.000
Orig End Date
2012-03-01T00:00:00.000
Task Start Date
2011-03-01T00:00:00.000
Task End Date
2027-07-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BSKBL1
Project Descr
Brooklyn Basketball Courts Reconstruction (SoGR) BG-320M
Seq Number
1
Task Description
DEVELOP SCOPE
Orig Start Date
2019-07-01T00:00:00.000
Orig End Date
2019-12-01T00:00:00.000
Task Start Date
2019-07-01T00:00:00.000
Task End Date
2019-12-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BSKBL1
Project Descr
Brooklyn Basketball Courts Reconstruction (SoGR) BG-320M
Seq Number
2
Task Description
DESIGN
Orig Start Date
2019-12-01T00:00:00.000
Orig End Date
2021-06-01T00:00:00.000
Task Start Date
2019-12-01T00:00:00.000
Task End Date
2021-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BSKBL1
Project Descr
Brooklyn Basketball Courts Reconstruction (SoGR) BG-320M
Seq Number
3
Task Description
BID/ REGISTER CONTRACT
Orig Start Date
2021-06-01T00:00:00.000
Orig End Date
2022-03-01T00:00:00.000
Task Start Date
2021-06-01T00:00:00.000
Task End Date
2022-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BSKBL1
Project Descr
Brooklyn Basketball Courts Reconstruction (SoGR) BG-320M
Seq Number
4
Task Description
CONSTRUCTION
Orig Start Date
2022-03-01T00:00:00.000
Orig End Date
2023-09-01T00:00:00.000
Task Start Date
2022-03-01T00:00:00.000
Task End Date
2023-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BSKBL1
Project Descr
Brooklyn Basketball Courts Reconstruction (SoGR) BG-320M
Seq Number
5
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2023-09-01T00:00:00.000
Orig End Date
2024-09-01T00:00:00.000
Task Start Date
2023-09-01T00:00:00.000
Task End Date
2024-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: BROOKLYN • Managing Agcy Cd: 846
Pub Date
20220517
Boro
BROOKLYN
Managing Agcy Cd
846
Managing Agcy
DEPT OF PARKS AND RECREATION
Project Id
P-2BTSYEL
Project Descr
Betsy Head Pool Tunnel Electrical Reconstruction
Seq Number
1
Task Description
DEVELOP SCOPE
Orig Start Date
2021-07-01T00:00:00.000
Orig End Date
2021-12-01T00:00:00.000
Task Start Date
2021-07-01T00:00:00.000
Task End Date
2021-12-01T00:00:00.000