Capital Project Detail Data - Milestones

This dataset contains capital commitment plan data by managing agency, project identification number and project schedules. The dataset was updated three times a year during the Preliminary, Executive and Adopted Capital Commitment Plans. Starting in January 2024, OMB will no longer update this dataset. It is being replaced by the Capital Projects Dashboard administered by the Mayor's Office of Operations.

City Government Mayor’s Office of Management and Budget (OMB) Dataset s7yh-frbm 12 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CAT-OPTIM
Project Descr
To Increase the Capacity of Upper Catskill Aqueduct
Seq Number
10
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2015-09-01T00:00:00.000
Orig End Date
2015-12-01T00:00:00.000
Task Start Date
2027-02-01T00:00:00.000
Task End Date
2027-05-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CFP-PMCS
Project Descr
Croton Filtration Process Monitoring & Control System
Seq Number
1
Task Description
DEVELOP SCOPE
Orig Start Date
2022-12-01T00:00:00.000
Orig End Date
2023-02-01T00:00:00.000
Task Start Date
2022-12-01T00:00:00.000
Task End Date
2023-02-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CFP-PMCS
Project Descr
Croton Filtration Process Monitoring & Control System
Seq Number
2
Task Description
PRELIMINARY DESIGN
Orig Start Date
2023-03-01T00:00:00.000
Orig End Date
2023-06-01T00:00:00.000
Task Start Date
2023-03-01T00:00:00.000
Task End Date
2023-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CFP-PMCS
Project Descr
Croton Filtration Process Monitoring & Control System
Seq Number
3
Task Description
FINAL DESIGN
Orig Start Date
2023-06-01T00:00:00.000
Orig End Date
2023-12-01T00:00:00.000
Task Start Date
2023-06-01T00:00:00.000
Task End Date
2023-12-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CFP-PMCS
Project Descr
Croton Filtration Process Monitoring & Control System
Seq Number
4
Task Description
BID AWARD AND REGISTER CONTRCT
Orig Start Date
2023-12-01T00:00:00.000
Orig End Date
2024-03-01T00:00:00.000
Task Start Date
2023-12-01T00:00:00.000
Task End Date
2024-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CFP-PMCS
Project Descr
Croton Filtration Process Monitoring & Control System
Seq Number
5
Task Description
CONSTRUCTION TO 25%
Orig Start Date
2024-03-01T00:00:00.000
Orig End Date
2024-07-01T00:00:00.000
Task Start Date
2024-03-01T00:00:00.000
Task End Date
2024-07-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CFP-PMCS
Project Descr
Croton Filtration Process Monitoring & Control System
Seq Number
6
Task Description
CONSTRUCTION TO 50%
Orig Start Date
2024-07-01T00:00:00.000
Orig End Date
2024-11-01T00:00:00.000
Task Start Date
2024-07-01T00:00:00.000
Task End Date
2024-11-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CFP-PMCS
Project Descr
Croton Filtration Process Monitoring & Control System
Seq Number
7
Task Description
CONSTRUCTION TO 75%
Orig Start Date
2024-11-01T00:00:00.000
Orig End Date
2025-03-01T00:00:00.000
Task Start Date
2024-11-01T00:00:00.000
Task End Date
2025-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CFP-PMCS
Project Descr
Croton Filtration Process Monitoring & Control System
Seq Number
8
Task Description
ORIGINAL EQUIP & FURNISHING
Orig Start Date
2025-03-01T00:00:00.000
Orig End Date
2025-06-01T00:00:00.000
Task Start Date
2025-03-01T00:00:00.000
Task End Date
2025-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CFP-PMCS
Project Descr
Croton Filtration Process Monitoring & Control System
Seq Number
9
Task Description
SUBSTANTIAL COMPLETION
Orig Start Date
2025-06-01T00:00:00.000
Orig End Date
2025-08-01T00:00:00.000
Task Start Date
2025-06-01T00:00:00.000
Task End Date
2025-08-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CFP-PMCS
Project Descr
Croton Filtration Process Monitoring & Control System
Seq Number
10
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2025-08-01T00:00:00.000
Orig End Date
2025-09-01T00:00:00.000
Task Start Date
2025-08-01T00:00:00.000
Task End Date
2025-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CLBRSTROW
Project Descr
CONSTRUCTION OF RIGHT-OF-WAY CLOUDBURST NEIGHBORHOODS
Seq Number
1
Task Description
DEVELOP SCOPE
Orig Start Date
2022-06-01T00:00:00.000
Orig End Date
2022-08-01T00:00:00.000
Task Start Date
2022-06-01T00:00:00.000
Task End Date
2022-08-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CLBRSTROW
Project Descr
CONSTRUCTION OF RIGHT-OF-WAY CLOUDBURST NEIGHBORHOODS
Seq Number
2
Task Description
PRELIMINARY DESIGN
Orig Start Date
2022-08-01T00:00:00.000
Orig End Date
2022-12-01T00:00:00.000
Task Start Date
2022-08-01T00:00:00.000
Task End Date
2022-12-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CLBRSTROW
Project Descr
CONSTRUCTION OF RIGHT-OF-WAY CLOUDBURST NEIGHBORHOODS
Seq Number
3
Task Description
FINAL DESIGN
Orig Start Date
2022-12-01T00:00:00.000
Orig End Date
2023-06-01T00:00:00.000
Task Start Date
2022-12-01T00:00:00.000
Task End Date
2023-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CLBRSTROW
Project Descr
CONSTRUCTION OF RIGHT-OF-WAY CLOUDBURST NEIGHBORHOODS
Seq Number
4
Task Description
BID AWARD AND REGISTER CONTRCT
Orig Start Date
2023-06-01T00:00:00.000
Orig End Date
2023-09-01T00:00:00.000
Task Start Date
2023-06-01T00:00:00.000
Task End Date
2023-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CLBRSTROW
Project Descr
CONSTRUCTION OF RIGHT-OF-WAY CLOUDBURST NEIGHBORHOODS
Seq Number
5
Task Description
CONSTRUCTION TO 25%
Orig Start Date
2023-09-01T00:00:00.000
Orig End Date
2024-01-01T00:00:00.000
Task Start Date
2023-09-01T00:00:00.000
Task End Date
2024-01-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CLBRSTROW
Project Descr
CONSTRUCTION OF RIGHT-OF-WAY CLOUDBURST NEIGHBORHOODS
Seq Number
6
Task Description
CONSTRUCTION TO 50%
Orig Start Date
2024-01-01T00:00:00.000
Orig End Date
2024-05-01T00:00:00.000
Task Start Date
2024-01-01T00:00:00.000
Task End Date
2024-05-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CLBRSTROW
Project Descr
CONSTRUCTION OF RIGHT-OF-WAY CLOUDBURST NEIGHBORHOODS
Seq Number
7
Task Description
CONSTRUCTION TO 75%
Orig Start Date
2024-05-01T00:00:00.000
Orig End Date
2024-09-01T00:00:00.000
Task Start Date
2024-05-01T00:00:00.000
Task End Date
2024-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CLBRSTROW
Project Descr
CONSTRUCTION OF RIGHT-OF-WAY CLOUDBURST NEIGHBORHOODS
Seq Number
8
Task Description
ORIGINAL EQUIP & FURNISHING
Orig Start Date
2024-09-01T00:00:00.000
Orig End Date
2024-12-01T00:00:00.000
Task Start Date
2024-09-01T00:00:00.000
Task End Date
2024-12-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CLBRSTROW
Project Descr
CONSTRUCTION OF RIGHT-OF-WAY CLOUDBURST NEIGHBORHOODS
Seq Number
9
Task Description
SUBSTANTIAL COMPLETION
Orig Start Date
2024-12-01T00:00:00.000
Orig End Date
2025-02-01T00:00:00.000
Task Start Date
2024-12-01T00:00:00.000
Task End Date
2025-02-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CLBRSTROW
Project Descr
CONSTRUCTION OF RIGHT-OF-WAY CLOUDBURST NEIGHBORHOODS
Seq Number
10
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2025-02-01T00:00:00.000
Orig End Date
2025-03-01T00:00:00.000
Task Start Date
2025-02-01T00:00:00.000
Task End Date
2025-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CLBRSTROW
Project Descr
CONSTRUCTION OF RIGHT-OF-WAY CLOUDBURST NEIGHBORHOODS
Seq Number
11
Task Description
DEVELOP SCOPE
Orig Start Date
2025-02-01T00:00:00.000
Orig End Date
2025-03-01T00:00:00.000
Task Start Date
2025-03-01T00:00:00.000
Task End Date
2025-12-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CLBRSTROW
Project Descr
CONSTRUCTION OF RIGHT-OF-WAY CLOUDBURST NEIGHBORHOODS
Seq Number
12
Task Description
PRELIMINARY DESIGN
Orig Start Date
2025-02-01T00:00:00.000
Orig End Date
2025-03-01T00:00:00.000
Task Start Date
2025-12-01T00:00:00.000
Task End Date
2026-12-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CLBRSTROW
Project Descr
CONSTRUCTION OF RIGHT-OF-WAY CLOUDBURST NEIGHBORHOODS
Seq Number
13
Task Description
FINAL DESIGN
Orig Start Date
2025-02-01T00:00:00.000
Orig End Date
2025-03-01T00:00:00.000
Task Start Date
2026-12-01T00:00:00.000
Task End Date
2028-05-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CLBRSTROW
Project Descr
CONSTRUCTION OF RIGHT-OF-WAY CLOUDBURST NEIGHBORHOODS
Seq Number
14
Task Description
BID AWARD AND REGISTER CONTRCT
Orig Start Date
2025-02-01T00:00:00.000
Orig End Date
2025-03-01T00:00:00.000
Task Start Date
2028-05-01T00:00:00.000
Task End Date
2029-02-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CLBRSTROW
Project Descr
CONSTRUCTION OF RIGHT-OF-WAY CLOUDBURST NEIGHBORHOODS
Seq Number
15
Task Description
CONSTRUCTION TO 25%
Orig Start Date
2025-02-01T00:00:00.000
Orig End Date
2025-03-01T00:00:00.000
Task Start Date
2029-02-01T00:00:00.000
Task End Date
2030-02-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CLBRSTROW
Project Descr
CONSTRUCTION OF RIGHT-OF-WAY CLOUDBURST NEIGHBORHOODS
Seq Number
16
Task Description
CONSTRUCTION TO 50%
Orig Start Date
2025-02-01T00:00:00.000
Orig End Date
2025-03-01T00:00:00.000
Task Start Date
2030-02-01T00:00:00.000
Task End Date
2031-02-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CLBRSTROW
Project Descr
CONSTRUCTION OF RIGHT-OF-WAY CLOUDBURST NEIGHBORHOODS
Seq Number
17
Task Description
CONSTRUCTION TO 75%
Orig Start Date
2025-02-01T00:00:00.000
Orig End Date
2025-03-01T00:00:00.000
Task Start Date
2031-02-01T00:00:00.000
Task End Date
2032-02-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CLBRSTROW
Project Descr
CONSTRUCTION OF RIGHT-OF-WAY CLOUDBURST NEIGHBORHOODS
Seq Number
18
Task Description
ORIGINAL EQUIP & FURNISHING
Orig Start Date
2025-02-01T00:00:00.000
Orig End Date
2025-03-01T00:00:00.000
Task Start Date
2032-02-01T00:00:00.000
Task End Date
2032-11-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CLBRSTROW
Project Descr
CONSTRUCTION OF RIGHT-OF-WAY CLOUDBURST NEIGHBORHOODS
Seq Number
19
Task Description
SUBSTANTIAL COMPLETION
Orig Start Date
2025-02-01T00:00:00.000
Orig End Date
2025-03-01T00:00:00.000
Task Start Date
2032-11-01T00:00:00.000
Task End Date
2033-05-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CLBRSTROW
Project Descr
CONSTRUCTION OF RIGHT-OF-WAY CLOUDBURST NEIGHBORHOODS
Seq Number
20
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2025-02-01T00:00:00.000
Orig End Date
2025-03-01T00:00:00.000
Task Start Date
2033-05-01T00:00:00.000
Task End Date
2033-08-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CRO-208B
Project Descr
NEW CROTON DAM RECONSTRUCTION
Seq Number
1
Task Description
DEVELOP SCOPE
Orig Start Date
2016-07-01T00:00:00.000
Orig End Date
2016-09-01T00:00:00.000
Task Start Date
2016-07-01T00:00:00.000
Task End Date
2017-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CRO-208B
Project Descr
NEW CROTON DAM RECONSTRUCTION
Seq Number
2
Task Description
PRELIMINARY DESIGN
Orig Start Date
2016-09-01T00:00:00.000
Orig End Date
2017-01-01T00:00:00.000
Task Start Date
2017-03-01T00:00:00.000
Task End Date
2018-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CRO-208B
Project Descr
NEW CROTON DAM RECONSTRUCTION
Seq Number
3
Task Description
FINAL DESIGN
Orig Start Date
2017-01-01T00:00:00.000
Orig End Date
2017-07-01T00:00:00.000
Task Start Date
2018-03-01T00:00:00.000
Task End Date
2019-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CRO-208B
Project Descr
NEW CROTON DAM RECONSTRUCTION
Seq Number
4
Task Description
BID AWARD AND REGISTER CONTRCT
Orig Start Date
2017-07-01T00:00:00.000
Orig End Date
2017-10-01T00:00:00.000
Task Start Date
2019-09-01T00:00:00.000
Task End Date
2020-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CRO-208B
Project Descr
NEW CROTON DAM RECONSTRUCTION
Seq Number
5
Task Description
CONSTRUCTION TO 25%
Orig Start Date
2017-10-01T00:00:00.000
Orig End Date
2018-02-01T00:00:00.000
Task Start Date
2020-06-01T00:00:00.000
Task End Date
2021-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CRO-208B
Project Descr
NEW CROTON DAM RECONSTRUCTION
Seq Number
6
Task Description
CONSTRUCTION TO 50%
Orig Start Date
2018-02-01T00:00:00.000
Orig End Date
2018-06-01T00:00:00.000
Task Start Date
2021-06-01T00:00:00.000
Task End Date
2022-05-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CRO-208B
Project Descr
NEW CROTON DAM RECONSTRUCTION
Seq Number
7
Task Description
CONSTRUCTION TO 75%
Orig Start Date
2018-06-01T00:00:00.000
Orig End Date
2018-10-01T00:00:00.000
Task Start Date
2022-05-01T00:00:00.000
Task End Date
2023-05-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CRO-208B
Project Descr
NEW CROTON DAM RECONSTRUCTION
Seq Number
8
Task Description
ORIGINAL EQUIP & FURNISHING
Orig Start Date
2018-10-01T00:00:00.000
Orig End Date
2019-01-01T00:00:00.000
Task Start Date
2023-05-01T00:00:00.000
Task End Date
2024-02-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CRO-208B
Project Descr
NEW CROTON DAM RECONSTRUCTION
Seq Number
9
Task Description
SUBSTANTIAL COMPLETION
Orig Start Date
2019-01-01T00:00:00.000
Orig End Date
2019-03-01T00:00:00.000
Task Start Date
2024-02-01T00:00:00.000
Task End Date
2028-08-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CRO-208B
Project Descr
NEW CROTON DAM RECONSTRUCTION
Seq Number
10
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2019-03-01T00:00:00.000
Orig End Date
2019-04-01T00:00:00.000
Task Start Date
2028-08-01T00:00:00.000
Task End Date
2028-11-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CRO-366
Project Descr
REPLACE DOORS, EAST-OF-HUDSON DISTRICT
Seq Number
1
Task Description
DEVELOP SCOPE
Orig Start Date
2007-03-01T00:00:00.000
Orig End Date
2007-05-01T00:00:00.000
Task Start Date
2005-08-01T00:00:00.000
Task End Date
2006-04-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CRO-366
Project Descr
REPLACE DOORS, EAST-OF-HUDSON DISTRICT
Seq Number
2
Task Description
PRELIMINARY DESIGN
Orig Start Date
2007-05-01T00:00:00.000
Orig End Date
2007-09-01T00:00:00.000
Task Start Date
2006-04-01T00:00:00.000
Task End Date
2007-04-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CRO-366
Project Descr
REPLACE DOORS, EAST-OF-HUDSON DISTRICT
Seq Number
3
Task Description
FINAL DESIGN
Orig Start Date
2007-09-01T00:00:00.000
Orig End Date
2008-03-01T00:00:00.000
Task Start Date
2007-04-01T00:00:00.000
Task End Date
2008-10-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CRO-366
Project Descr
REPLACE DOORS, EAST-OF-HUDSON DISTRICT
Seq Number
4
Task Description
BID AWARD AND REGISTER CONTRCT
Orig Start Date
2008-03-01T00:00:00.000
Orig End Date
2008-06-01T00:00:00.000
Task Start Date
2008-10-01T00:00:00.000
Task End Date
2009-07-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CRO-366
Project Descr
REPLACE DOORS, EAST-OF-HUDSON DISTRICT
Seq Number
5
Task Description
CONSTRUCTION TO 25%
Orig Start Date
2008-06-01T00:00:00.000
Orig End Date
2008-10-01T00:00:00.000
Task Start Date
2009-07-01T00:00:00.000
Task End Date
2010-07-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CRO-366
Project Descr
REPLACE DOORS, EAST-OF-HUDSON DISTRICT
Seq Number
6
Task Description
CONSTRUCTION TO 50%
Orig Start Date
2008-10-01T00:00:00.000
Orig End Date
2009-02-01T00:00:00.000
Task Start Date
2010-07-01T00:00:00.000
Task End Date
2011-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CRO-366
Project Descr
REPLACE DOORS, EAST-OF-HUDSON DISTRICT
Seq Number
7
Task Description
CONSTRUCTION TO 75%
Orig Start Date
2009-02-01T00:00:00.000
Orig End Date
2009-06-01T00:00:00.000
Task Start Date
2011-07-01T00:00:00.000
Task End Date
2012-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CRO-366
Project Descr
REPLACE DOORS, EAST-OF-HUDSON DISTRICT
Seq Number
8
Task Description
ORIGINAL EQUIP & FURNISHING
Orig Start Date
2009-06-01T00:00:00.000
Orig End Date
2009-09-01T00:00:00.000
Task Start Date
2012-06-01T00:00:00.000
Task End Date
2013-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 826
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
826
Managing Agcy
DEPT ENVIRONMENTAL PROTECTION
Project Id
CRO-366
Project Descr
REPLACE DOORS, EAST-OF-HUDSON DISTRICT
Seq Number
9
Task Description
SUBSTANTIAL COMPLETION
Orig Start Date
2009-09-01T00:00:00.000
Orig End Date
2009-11-01T00:00:00.000
Task Start Date
2013-03-01T00:00:00.000
Task End Date
2021-09-01T00:00:00.000