Capital Project Detail Data - Milestones

This dataset contains capital commitment plan data by managing agency, project identification number and project schedules. The dataset was updated three times a year during the Preliminary, Executive and Adopted Capital Commitment Plans. Starting in January 2024, OMB will no longer update this dataset. It is being replaced by the Capital Projects Dashboard administered by the Mayor's Office of Operations.

City Government Mayor’s Office of Management and Budget (OMB) Dataset s7yh-frbm 12 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW200IFA1
Project Descr
In-House Pedestrian Ramp Rehabilitation - Crews
Seq Number
4
Task Description
BID AWARD AND REGISTER CONTRCT
Orig Start Date
2017-07-01T00:00:00.000
Orig End Date
2017-10-01T00:00:00.000
Task Start Date
2029-07-01T00:00:00.000
Task End Date
2029-10-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW200IFA1
Project Descr
In-House Pedestrian Ramp Rehabilitation - Crews
Seq Number
5
Task Description
CONSTRUCTION TO 25%
Orig Start Date
2017-10-01T00:00:00.000
Orig End Date
2018-02-01T00:00:00.000
Task Start Date
2029-10-01T00:00:00.000
Task End Date
2030-02-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW200IFA1
Project Descr
In-House Pedestrian Ramp Rehabilitation - Crews
Seq Number
6
Task Description
CONSTRUCTION TO 50%
Orig Start Date
2018-02-01T00:00:00.000
Orig End Date
2018-06-01T00:00:00.000
Task Start Date
2030-02-01T00:00:00.000
Task End Date
2030-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW200IFA1
Project Descr
In-House Pedestrian Ramp Rehabilitation - Crews
Seq Number
7
Task Description
CONSTRUCTION TO 75%
Orig Start Date
2018-06-01T00:00:00.000
Orig End Date
2018-10-01T00:00:00.000
Task Start Date
2030-06-01T00:00:00.000
Task End Date
2030-10-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW200IFA1
Project Descr
In-House Pedestrian Ramp Rehabilitation - Crews
Seq Number
8
Task Description
ORIGINAL EQUIP & FURNISHING
Orig Start Date
2018-10-01T00:00:00.000
Orig End Date
2019-01-01T00:00:00.000
Task Start Date
2030-10-01T00:00:00.000
Task End Date
2031-01-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW200IFA1
Project Descr
In-House Pedestrian Ramp Rehabilitation - Crews
Seq Number
9
Task Description
SUBSTANTIAL COMPLETION
Orig Start Date
2019-01-01T00:00:00.000
Orig End Date
2019-03-01T00:00:00.000
Task Start Date
2031-01-01T00:00:00.000
Task End Date
2031-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW200IFA1
Project Descr
In-House Pedestrian Ramp Rehabilitation - Crews
Seq Number
10
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2019-03-01T00:00:00.000
Orig End Date
2019-04-01T00:00:00.000
Task Start Date
2031-03-01T00:00:00.000
Task End Date
2031-04-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW200IFA2
Project Descr
In-House Pedestrian Ramp Rehabilitation - OTPS
Seq Number
1
Task Description
DEVELOP SCOPE
Orig Start Date
2016-07-01T00:00:00.000
Orig End Date
2016-09-01T00:00:00.000
Task Start Date
2017-07-01T00:00:00.000
Task End Date
2028-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW200IFA2
Project Descr
In-House Pedestrian Ramp Rehabilitation - OTPS
Seq Number
2
Task Description
PRELIMINARY DESIGN
Orig Start Date
2016-09-01T00:00:00.000
Orig End Date
2017-01-01T00:00:00.000
Task Start Date
2028-09-01T00:00:00.000
Task End Date
2029-01-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW200IFA2
Project Descr
In-House Pedestrian Ramp Rehabilitation - OTPS
Seq Number
3
Task Description
FINAL DESIGN
Orig Start Date
2017-01-01T00:00:00.000
Orig End Date
2017-07-01T00:00:00.000
Task Start Date
2029-01-01T00:00:00.000
Task End Date
2029-07-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW200IFA2
Project Descr
In-House Pedestrian Ramp Rehabilitation - OTPS
Seq Number
4
Task Description
BID AWARD AND REGISTER CONTRCT
Orig Start Date
2017-07-01T00:00:00.000
Orig End Date
2017-10-01T00:00:00.000
Task Start Date
2029-07-01T00:00:00.000
Task End Date
2029-10-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW200IFA2
Project Descr
In-House Pedestrian Ramp Rehabilitation - OTPS
Seq Number
5
Task Description
CONSTRUCTION TO 25%
Orig Start Date
2017-10-01T00:00:00.000
Orig End Date
2018-02-01T00:00:00.000
Task Start Date
2029-10-01T00:00:00.000
Task End Date
2030-02-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW200IFA2
Project Descr
In-House Pedestrian Ramp Rehabilitation - OTPS
Seq Number
6
Task Description
CONSTRUCTION TO 50%
Orig Start Date
2018-02-01T00:00:00.000
Orig End Date
2018-06-01T00:00:00.000
Task Start Date
2030-02-01T00:00:00.000
Task End Date
2030-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW200IFA2
Project Descr
In-House Pedestrian Ramp Rehabilitation - OTPS
Seq Number
7
Task Description
CONSTRUCTION TO 75%
Orig Start Date
2018-06-01T00:00:00.000
Orig End Date
2018-10-01T00:00:00.000
Task Start Date
2030-06-01T00:00:00.000
Task End Date
2030-10-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW200IFA2
Project Descr
In-House Pedestrian Ramp Rehabilitation - OTPS
Seq Number
8
Task Description
ORIGINAL EQUIP & FURNISHING
Orig Start Date
2018-10-01T00:00:00.000
Orig End Date
2019-01-01T00:00:00.000
Task Start Date
2030-10-01T00:00:00.000
Task End Date
2031-01-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW200IFA2
Project Descr
In-House Pedestrian Ramp Rehabilitation - OTPS
Seq Number
9
Task Description
SUBSTANTIAL COMPLETION
Orig Start Date
2019-01-01T00:00:00.000
Orig End Date
2019-03-01T00:00:00.000
Task Start Date
2031-01-01T00:00:00.000
Task End Date
2031-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW200IFA2
Project Descr
In-House Pedestrian Ramp Rehabilitation - OTPS
Seq Number
10
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2019-03-01T00:00:00.000
Orig End Date
2019-04-01T00:00:00.000
Task Start Date
2031-03-01T00:00:00.000
Task End Date
2031-04-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW2CR06
Project Descr
CITYWIDE MILLING
Seq Number
1
Task Description
DEVELOP SCOPE
Orig Start Date
2011-05-01T00:00:00.000
Orig End Date
2011-08-01T00:00:00.000
Task Start Date
2027-05-01T00:00:00.000
Task End Date
2028-08-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW2CR06
Project Descr
CITYWIDE MILLING
Seq Number
2
Task Description
PRELIMINARY DESIGN
Orig Start Date
2011-08-01T00:00:00.000
Orig End Date
2011-12-01T00:00:00.000
Task Start Date
2028-08-01T00:00:00.000
Task End Date
2028-12-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW2CR06
Project Descr
CITYWIDE MILLING
Seq Number
3
Task Description
FINAL DESIGN
Orig Start Date
2011-12-01T00:00:00.000
Orig End Date
2012-06-01T00:00:00.000
Task Start Date
2028-12-01T00:00:00.000
Task End Date
2029-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW2CR06
Project Descr
CITYWIDE MILLING
Seq Number
4
Task Description
BID AWARD AND REGISTER CONTRCT
Orig Start Date
2012-06-01T00:00:00.000
Orig End Date
2012-09-01T00:00:00.000
Task Start Date
2029-06-01T00:00:00.000
Task End Date
2029-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW2CR06
Project Descr
CITYWIDE MILLING
Seq Number
5
Task Description
CONSTRUCTION TO 25%
Orig Start Date
2012-09-01T00:00:00.000
Orig End Date
2013-01-01T00:00:00.000
Task Start Date
2029-09-01T00:00:00.000
Task End Date
2030-01-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW2CR06
Project Descr
CITYWIDE MILLING
Seq Number
6
Task Description
CONSTRUCTION TO 50%
Orig Start Date
2013-01-01T00:00:00.000
Orig End Date
2013-05-01T00:00:00.000
Task Start Date
2030-01-01T00:00:00.000
Task End Date
2030-05-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW2CR06
Project Descr
CITYWIDE MILLING
Seq Number
7
Task Description
CONSTRUCTION TO 75%
Orig Start Date
2013-05-01T00:00:00.000
Orig End Date
2013-09-01T00:00:00.000
Task Start Date
2030-05-01T00:00:00.000
Task End Date
2030-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW2CR06
Project Descr
CITYWIDE MILLING
Seq Number
8
Task Description
ORIGINAL EQUIP & FURNISHING
Orig Start Date
2013-09-01T00:00:00.000
Orig End Date
2013-12-01T00:00:00.000
Task Start Date
2030-09-01T00:00:00.000
Task End Date
2030-12-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW2CR06
Project Descr
CITYWIDE MILLING
Seq Number
9
Task Description
SUBSTANTIAL COMPLETION
Orig Start Date
2013-12-01T00:00:00.000
Orig End Date
2014-02-01T00:00:00.000
Task Start Date
2030-12-01T00:00:00.000
Task End Date
2031-02-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW2CR06
Project Descr
CITYWIDE MILLING
Seq Number
10
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2014-02-01T00:00:00.000
Orig End Date
2014-03-01T00:00:00.000
Task Start Date
2031-02-01T00:00:00.000
Task End Date
2031-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW2CR18D
Project Descr
Citywide Milling - Bronx, Manhattan and Queens
Seq Number
1
Task Description
DEVELOP SCOPE
Orig Start Date
2018-06-01T00:00:00.000
Orig End Date
2018-09-01T00:00:00.000
Task Start Date
2018-06-01T00:00:00.000
Task End Date
2018-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW2CR18D
Project Descr
Citywide Milling - Bronx, Manhattan and Queens
Seq Number
2
Task Description
PRELIMINARY DESIGN
Orig Start Date
2018-09-01T00:00:00.000
Orig End Date
2019-01-01T00:00:00.000
Task Start Date
2018-09-01T00:00:00.000
Task End Date
2019-01-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW2CR18D
Project Descr
Citywide Milling - Bronx, Manhattan and Queens
Seq Number
3
Task Description
FINAL DESIGN
Orig Start Date
2019-01-01T00:00:00.000
Orig End Date
2019-07-01T00:00:00.000
Task Start Date
2019-01-01T00:00:00.000
Task End Date
2019-07-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW2CR18D
Project Descr
Citywide Milling - Bronx, Manhattan and Queens
Seq Number
4
Task Description
BID AWARD AND REGISTER CONTRCT
Orig Start Date
2019-07-01T00:00:00.000
Orig End Date
2019-10-01T00:00:00.000
Task Start Date
2019-07-01T00:00:00.000
Task End Date
2019-10-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW2CR18D
Project Descr
Citywide Milling - Bronx, Manhattan and Queens
Seq Number
5
Task Description
CONSTRUCTION TO 25%
Orig Start Date
2019-10-01T00:00:00.000
Orig End Date
2020-02-01T00:00:00.000
Task Start Date
2019-10-01T00:00:00.000
Task End Date
2020-02-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW2CR18D
Project Descr
Citywide Milling - Bronx, Manhattan and Queens
Seq Number
6
Task Description
CONSTRUCTION TO 50%
Orig Start Date
2020-02-01T00:00:00.000
Orig End Date
2020-06-01T00:00:00.000
Task Start Date
2020-02-01T00:00:00.000
Task End Date
2020-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW2CR18D
Project Descr
Citywide Milling - Bronx, Manhattan and Queens
Seq Number
7
Task Description
CONSTRUCTION TO 75%
Orig Start Date
2020-06-01T00:00:00.000
Orig End Date
2020-10-01T00:00:00.000
Task Start Date
2020-06-01T00:00:00.000
Task End Date
2020-10-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW2CR18D
Project Descr
Citywide Milling - Bronx, Manhattan and Queens
Seq Number
8
Task Description
ORIGINAL EQUIP & FURNISHING
Orig Start Date
2020-10-01T00:00:00.000
Orig End Date
2021-01-01T00:00:00.000
Task Start Date
2020-10-01T00:00:00.000
Task End Date
2021-01-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW2CR18D
Project Descr
Citywide Milling - Bronx, Manhattan and Queens
Seq Number
9
Task Description
SUBSTANTIAL COMPLETION
Orig Start Date
2021-01-01T00:00:00.000
Orig End Date
2021-03-01T00:00:00.000
Task Start Date
2021-01-01T00:00:00.000
Task End Date
2021-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW2CR18D
Project Descr
Citywide Milling - Bronx, Manhattan and Queens
Seq Number
10
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2021-03-01T00:00:00.000
Orig End Date
2021-04-01T00:00:00.000
Task Start Date
2021-03-01T00:00:00.000
Task End Date
2021-04-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW2CR19F
Project Descr
Citywide Milling - Brooklyn and Queens
Seq Number
1
Task Description
DEVELOP SCOPE
Orig Start Date
2017-06-01T00:00:00.000
Orig End Date
2017-09-01T00:00:00.000
Task Start Date
2019-06-01T00:00:00.000
Task End Date
2019-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW2CR19F
Project Descr
Citywide Milling - Brooklyn and Queens
Seq Number
2
Task Description
PRELIMINARY DESIGN
Orig Start Date
2017-09-01T00:00:00.000
Orig End Date
2018-01-01T00:00:00.000
Task Start Date
2019-09-01T00:00:00.000
Task End Date
2020-01-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW2CR19F
Project Descr
Citywide Milling - Brooklyn and Queens
Seq Number
3
Task Description
FINAL DESIGN
Orig Start Date
2018-01-01T00:00:00.000
Orig End Date
2018-07-01T00:00:00.000
Task Start Date
2020-01-01T00:00:00.000
Task End Date
2020-07-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW2CR19F
Project Descr
Citywide Milling - Brooklyn and Queens
Seq Number
4
Task Description
BID AWARD AND REGISTER CONTRCT
Orig Start Date
2018-07-01T00:00:00.000
Orig End Date
2018-10-01T00:00:00.000
Task Start Date
2020-07-01T00:00:00.000
Task End Date
2020-10-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW2CR19F
Project Descr
Citywide Milling - Brooklyn and Queens
Seq Number
5
Task Description
CONSTRUCTION TO 25%
Orig Start Date
2018-10-01T00:00:00.000
Orig End Date
2019-02-01T00:00:00.000
Task Start Date
2020-10-01T00:00:00.000
Task End Date
2021-02-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW2CR19F
Project Descr
Citywide Milling - Brooklyn and Queens
Seq Number
6
Task Description
CONSTRUCTION TO 50%
Orig Start Date
2019-02-01T00:00:00.000
Orig End Date
2019-06-01T00:00:00.000
Task Start Date
2021-02-01T00:00:00.000
Task End Date
2021-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW2CR19F
Project Descr
Citywide Milling - Brooklyn and Queens
Seq Number
7
Task Description
CONSTRUCTION TO 75%
Orig Start Date
2019-06-01T00:00:00.000
Orig End Date
2019-10-01T00:00:00.000
Task Start Date
2021-06-01T00:00:00.000
Task End Date
2021-10-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW2CR19F
Project Descr
Citywide Milling - Brooklyn and Queens
Seq Number
8
Task Description
ORIGINAL EQUIP & FURNISHING
Orig Start Date
2019-10-01T00:00:00.000
Orig End Date
2020-01-01T00:00:00.000
Task Start Date
2021-10-01T00:00:00.000
Task End Date
2022-01-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW2CR19F
Project Descr
Citywide Milling - Brooklyn and Queens
Seq Number
9
Task Description
SUBSTANTIAL COMPLETION
Orig Start Date
2020-01-01T00:00:00.000
Orig End Date
2020-03-01T00:00:00.000
Task Start Date
2022-01-01T00:00:00.000
Task End Date
2022-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW2CR19F
Project Descr
Citywide Milling - Brooklyn and Queens
Seq Number
10
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2020-03-01T00:00:00.000
Orig End Date
2020-04-01T00:00:00.000
Task Start Date
2022-03-01T00:00:00.000
Task End Date
2022-04-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW2CR21C
Project Descr
Citywide Milling - Brooklyn and Staten Island
Seq Number
1
Task Description
DEVELOP SCOPE
Orig Start Date
2021-06-01T00:00:00.000
Orig End Date
2021-09-01T00:00:00.000
Task Start Date
2021-06-01T00:00:00.000
Task End Date
2021-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW2CR21C
Project Descr
Citywide Milling - Brooklyn and Staten Island
Seq Number
2
Task Description
PRELIMINARY DESIGN
Orig Start Date
2021-09-01T00:00:00.000
Orig End Date
2022-01-01T00:00:00.000
Task Start Date
2021-09-01T00:00:00.000
Task End Date
2022-01-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HW2CR21C
Project Descr
Citywide Milling - Brooklyn and Staten Island
Seq Number
3
Task Description
FINAL DESIGN
Orig Start Date
2022-01-01T00:00:00.000
Orig End Date
2022-07-01T00:00:00.000
Task Start Date
2022-01-01T00:00:00.000
Task End Date
2022-07-01T00:00:00.000