Capital Project Detail Data - Milestones

This dataset contains capital commitment plan data by managing agency, project identification number and project schedules. The dataset was updated three times a year during the Preliminary, Executive and Adopted Capital Commitment Plans. Starting in January 2024, OMB will no longer update this dataset. It is being replaced by the Capital Projects Dashboard administered by the Mayor's Office of Operations.

City Government Mayor’s Office of Management and Budget (OMB) Dataset s7yh-frbm 12 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
F204FTBLD
Project Descr
Fort Totten Buildings 322 and 323
Seq Number
2
Task Description
CONSTRUCTION
Orig Start Date
2022-12-01T00:00:00.000
Orig End Date
2023-12-01T00:00:00.000
Task Start Date
2022-12-01T00:00:00.000
Task End Date
2023-12-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
F204FTBLD
Project Descr
Fort Totten Buildings 322 and 323
Seq Number
3
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2023-12-01T00:00:00.000
Orig End Date
2024-03-01T00:00:00.000
Task Start Date
2023-12-01T00:00:00.000
Task End Date
2024-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
F204HZTAC
Project Descr
HazTac Trailer Replacement
Seq Number
1
Task Description
CONSTRUCTION
Orig Start Date
2022-05-01T00:00:00.000
Orig End Date
2023-05-01T00:00:00.000
Task Start Date
2022-05-01T00:00:00.000
Task End Date
2023-05-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
F204HZTAC
Project Descr
HazTac Trailer Replacement
Seq Number
2
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2023-05-01T00:00:00.000
Orig End Date
2023-08-01T00:00:00.000
Task Start Date
2023-05-01T00:00:00.000
Task End Date
2023-08-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
F204MR634
Project Descr
Fort Totten Building #634 Renovation for Marine Operations
Seq Number
2
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2022-05-01T00:00:00.000
Orig End Date
2022-08-01T00:00:00.000
Task Start Date
2022-05-01T00:00:00.000
Task End Date
2022-08-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
F204RDWSH
Project Descr
Randall's Bunker Gear Laundry
Seq Number
1
Task Description
DESIGN
Orig Start Date
2021-08-01T00:00:00.000
Orig End Date
2022-02-01T00:00:00.000
Task Start Date
2021-08-01T00:00:00.000
Task End Date
2022-02-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
F204RDWSH
Project Descr
Randall's Bunker Gear Laundry
Seq Number
2
Task Description
CONSTRUCTION
Orig Start Date
2022-02-01T00:00:00.000
Orig End Date
2023-02-01T00:00:00.000
Task Start Date
2022-02-01T00:00:00.000
Task End Date
2023-02-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
F204RDWSH
Project Descr
Randall's Bunker Gear Laundry
Seq Number
3
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2023-02-01T00:00:00.000
Orig End Date
2023-05-01T00:00:00.000
Task Start Date
2023-02-01T00:00:00.000
Task End Date
2023-05-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
F204RF333
Project Descr
Roofing replacement at Fort Totten Building # 333
Seq Number
1
Task Description
CONSTRUCTION
Orig Start Date
2022-04-01T00:00:00.000
Orig End Date
2023-04-01T00:00:00.000
Task Start Date
2022-04-01T00:00:00.000
Task End Date
2023-04-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
F204RF333
Project Descr
Roofing replacement at Fort Totten Building # 333
Seq Number
2
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2023-04-01T00:00:00.000
Orig End Date
2023-07-01T00:00:00.000
Task Start Date
2023-04-01T00:00:00.000
Task End Date
2023-07-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
F204SHADE
Project Descr
Randall's Island Shade Structure
Seq Number
1
Task Description
DESIGN
Orig Start Date
2022-09-01T00:00:00.000
Orig End Date
2023-03-01T00:00:00.000
Task Start Date
2022-09-01T00:00:00.000
Task End Date
2023-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
F204SHADE
Project Descr
Randall's Island Shade Structure
Seq Number
2
Task Description
CONSTRUCTION
Orig Start Date
2023-03-01T00:00:00.000
Orig End Date
2024-03-01T00:00:00.000
Task Start Date
2023-03-01T00:00:00.000
Task End Date
2024-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
F204SHADE
Project Descr
Randall's Island Shade Structure
Seq Number
3
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2024-03-01T00:00:00.000
Orig End Date
2024-06-01T00:00:00.000
Task Start Date
2024-03-01T00:00:00.000
Task End Date
2024-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
F204WATER
Project Descr
Randall's Island Water Tank Replacement
Seq Number
1
Task Description
DESIGN
Orig Start Date
2018-03-01T00:00:00.000
Orig End Date
2018-09-01T00:00:00.000
Task Start Date
2020-04-01T00:00:00.000
Task End Date
2020-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
F204WATER
Project Descr
Randall's Island Water Tank Replacement
Seq Number
2
Task Description
CONSTRUCTION
Orig Start Date
2018-09-01T00:00:00.000
Orig End Date
2019-09-01T00:00:00.000
Task Start Date
2020-09-01T00:00:00.000
Task End Date
2021-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
F204WATER
Project Descr
Randall's Island Water Tank Replacement
Seq Number
3
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2019-09-01T00:00:00.000
Orig End Date
2019-12-01T00:00:00.000
Task Start Date
2021-09-01T00:00:00.000
Task End Date
2021-12-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
F212-COOL
Project Descr
Power and Cooling for Data Center 11 MetroTech
Seq Number
1
Task Description
CONSTRUCTION
Orig Start Date
2020-06-01T00:00:00.000
Orig End Date
2021-06-01T00:00:00.000
Task Start Date
2020-06-01T00:00:00.000
Task End Date
2021-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
F212-COOL
Project Descr
Power and Cooling for Data Center 11 MetroTech
Seq Number
2
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2021-06-01T00:00:00.000
Orig End Date
2021-09-01T00:00:00.000
Task Start Date
2021-06-01T00:00:00.000
Task End Date
2024-10-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
FD175D155
Project Descr
Door Replacement - EC155
Seq Number
1
Task Description
CONSTRUCTION
Orig Start Date
2022-02-01T00:00:00.000
Orig End Date
2023-02-01T00:00:00.000
Task Start Date
2022-02-01T00:00:00.000
Task End Date
2023-02-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
FD175D155
Project Descr
Door Replacement - EC155
Seq Number
2
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2023-02-01T00:00:00.000
Orig End Date
2023-05-01T00:00:00.000
Task Start Date
2023-02-01T00:00:00.000
Task End Date
2023-05-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
FD175D158
Project Descr
Door Replacement - EC158
Seq Number
1
Task Description
CONSTRUCTION
Orig Start Date
2022-02-01T00:00:00.000
Orig End Date
2023-02-01T00:00:00.000
Task Start Date
2022-02-01T00:00:00.000
Task End Date
2023-02-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
FD175D158
Project Descr
Door Replacement - EC158
Seq Number
2
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2023-02-01T00:00:00.000
Orig End Date
2023-05-01T00:00:00.000
Task Start Date
2023-02-01T00:00:00.000
Task End Date
2023-05-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
FD175D161
Project Descr
Door Replacement - EC161
Seq Number
1
Task Description
CONSTRUCTION
Orig Start Date
2022-02-01T00:00:00.000
Orig End Date
2023-02-01T00:00:00.000
Task Start Date
2022-02-01T00:00:00.000
Task End Date
2023-02-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
FD175D161
Project Descr
Door Replacement - EC161
Seq Number
2
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2023-02-01T00:00:00.000
Orig End Date
2023-05-01T00:00:00.000
Task Start Date
2023-02-01T00:00:00.000
Task End Date
2023-05-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
FD175D255
Project Descr
Door Replacement - EC255
Seq Number
1
Task Description
CONSTRUCTION
Orig Start Date
2022-02-01T00:00:00.000
Orig End Date
2023-02-01T00:00:00.000
Task Start Date
2022-02-01T00:00:00.000
Task End Date
2023-02-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
FD175D255
Project Descr
Door Replacement - EC255
Seq Number
2
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2023-02-01T00:00:00.000
Orig End Date
2023-05-01T00:00:00.000
Task Start Date
2023-02-01T00:00:00.000
Task End Date
2023-05-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
FD175DES8
Project Descr
Door Replacement - EMS 8
Seq Number
1
Task Description
CONSTRUCTION
Orig Start Date
2022-02-01T00:00:00.000
Orig End Date
2023-02-01T00:00:00.000
Task Start Date
2022-02-01T00:00:00.000
Task End Date
2023-02-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
FD175DES8
Project Descr
Door Replacement - EMS 8
Seq Number
2
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2023-02-01T00:00:00.000
Orig End Date
2023-05-01T00:00:00.000
Task Start Date
2023-02-01T00:00:00.000
Task End Date
2023-05-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
FD175DR44
Project Descr
DOOR REPLACEMENT - EC44
Seq Number
2
Task Description
CONSTRUCTION
Orig Start Date
2022-04-01T00:00:00.000
Orig End Date
2023-04-01T00:00:00.000
Task Start Date
2021-06-01T00:00:00.000
Task End Date
2022-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
FD175DR44
Project Descr
DOOR REPLACEMENT - EC44
Seq Number
3
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2023-04-01T00:00:00.000
Orig End Date
2023-07-01T00:00:00.000
Task Start Date
2022-06-01T00:00:00.000
Task End Date
2022-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
FD175E287
Project Descr
Door Replacement - EC287
Seq Number
1
Task Description
CONSTRUCTION
Orig Start Date
2022-06-01T00:00:00.000
Orig End Date
2023-06-01T00:00:00.000
Task Start Date
2022-06-01T00:00:00.000
Task End Date
2023-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
FD175E287
Project Descr
Door Replacement - EC287
Seq Number
2
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2023-06-01T00:00:00.000
Orig End Date
2023-09-01T00:00:00.000
Task Start Date
2023-06-01T00:00:00.000
Task End Date
2023-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
FD175G157
Project Descr
Generator - EC157
Seq Number
1
Task Description
DESIGN
Orig Start Date
2020-11-01T00:00:00.000
Orig End Date
2021-05-01T00:00:00.000
Task Start Date
2020-11-01T00:00:00.000
Task End Date
2021-05-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
FD175G157
Project Descr
Generator - EC157
Seq Number
2
Task Description
CONSTRUCTION
Orig Start Date
2021-05-01T00:00:00.000
Orig End Date
2022-05-01T00:00:00.000
Task Start Date
2021-05-01T00:00:00.000
Task End Date
2022-05-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
FD175G157
Project Descr
Generator - EC157
Seq Number
3
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2022-05-01T00:00:00.000
Orig End Date
2023-11-01T00:00:00.000
Task Start Date
2022-05-01T00:00:00.000
Task End Date
2023-11-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
FD175G158
Project Descr
Generator - EC158
Seq Number
1
Task Description
DESIGN
Orig Start Date
2020-12-01T00:00:00.000
Orig End Date
2021-06-01T00:00:00.000
Task Start Date
2020-12-01T00:00:00.000
Task End Date
2021-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
FD175G158
Project Descr
Generator - EC158
Seq Number
2
Task Description
CONSTRUCTION
Orig Start Date
2021-06-01T00:00:00.000
Orig End Date
2022-06-01T00:00:00.000
Task Start Date
2021-06-01T00:00:00.000
Task End Date
2022-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
FD175G158
Project Descr
Generator - EC158
Seq Number
3
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2022-06-01T00:00:00.000
Orig End Date
2022-09-01T00:00:00.000
Task Start Date
2022-06-01T00:00:00.000
Task End Date
2022-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
FD175KT96
Project Descr
KITCHEN - EC96
Seq Number
1
Task Description
DESIGN
Orig Start Date
2021-10-01T00:00:00.000
Orig End Date
2022-04-01T00:00:00.000
Task Start Date
2021-10-01T00:00:00.000
Task End Date
2022-04-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
FD175KT96
Project Descr
KITCHEN - EC96
Seq Number
2
Task Description
CONSTRUCTION
Orig Start Date
2022-04-01T00:00:00.000
Orig End Date
2023-04-01T00:00:00.000
Task Start Date
2022-04-01T00:00:00.000
Task End Date
2023-04-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
FD175KT96
Project Descr
KITCHEN - EC96
Seq Number
3
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2023-04-01T00:00:00.000
Orig End Date
2023-07-01T00:00:00.000
Task Start Date
2023-04-01T00:00:00.000
Task End Date
2023-07-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
FD175MLFT
Project Descr
Mobile Fire Trainer- Mobile Live Fire Training Simulator
Seq Number
1
Task Description
CONSTRUCTION
Orig Start Date
2021-09-01T00:00:00.000
Orig End Date
2022-09-01T00:00:00.000
Task Start Date
2021-09-01T00:00:00.000
Task End Date
2022-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
FD175MLFT
Project Descr
Mobile Fire Trainer- Mobile Live Fire Training Simulator
Seq Number
2
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2022-09-01T00:00:00.000
Orig End Date
2022-12-01T00:00:00.000
Task Start Date
2022-09-01T00:00:00.000
Task End Date
2022-12-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
SANDHM265
Project Descr
HURRICANE SANDY HAZMAT MITIGATION-EC265
Seq Number
1
Task Description
DESIGN
Orig Start Date
2016-04-01T00:00:00.000
Orig End Date
2016-10-01T00:00:00.000
Task Start Date
2017-04-01T00:00:00.000
Task End Date
2017-10-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
SANDHM265
Project Descr
HURRICANE SANDY HAZMAT MITIGATION-EC265
Seq Number
2
Task Description
CONSTRUCTION
Orig Start Date
2016-10-01T00:00:00.000
Orig End Date
2017-10-01T00:00:00.000
Task Start Date
2017-10-01T00:00:00.000
Task End Date
2018-10-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
SANDHM265
Project Descr
HURRICANE SANDY HAZMAT MITIGATION-EC265
Seq Number
3
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2017-10-01T00:00:00.000
Orig End Date
2018-01-01T00:00:00.000
Task Start Date
2018-10-01T00:00:00.000
Task End Date
2023-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
SANDHM266
Project Descr
HURRICANE SANDY HAZMAT MITIGATION - EC266
Seq Number
1
Task Description
DESIGN
Orig Start Date
2016-03-01T00:00:00.000
Orig End Date
2016-09-01T00:00:00.000
Task Start Date
2017-03-01T00:00:00.000
Task End Date
2017-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
SANDHM266
Project Descr
HURRICANE SANDY HAZMAT MITIGATION - EC266
Seq Number
2
Task Description
CONSTRUCTION
Orig Start Date
2016-09-01T00:00:00.000
Orig End Date
2017-09-01T00:00:00.000
Task Start Date
2017-09-01T00:00:00.000
Task End Date
2018-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 057
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
057
Managing Agcy
FIRE DEPARTMENT
Project Id
SANDHM266
Project Descr
HURRICANE SANDY HAZMAT MITIGATION - EC266
Seq Number
3
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2017-09-01T00:00:00.000
Orig End Date
2017-12-01T00:00:00.000
Task Start Date
2018-09-01T00:00:00.000
Task End Date
2025-10-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 068
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
068
Managing Agcy
ADMIN FOR CHILDREN'S SERVICES
Project Id
ACSPDF
Project Descr
Renovation projects for field offices
Seq Number
1
Task Description
DEVELOP SCOPE
Orig Start Date
2018-06-01T00:00:00.000
Orig End Date
2018-09-01T00:00:00.000
Task Start Date
2020-06-01T00:00:00.000
Task End Date
2020-09-01T00:00:00.000