Capital Project Detail Data - Milestones

This dataset contains capital commitment plan data by managing agency, project identification number and project schedules. The dataset was updated three times a year during the Preliminary, Executive and Adopted Capital Commitment Plans. Starting in January 2024, OMB will no longer update this dataset. It is being replaced by the Capital Projects Dashboard administered by the Mayor's Office of Operations.

City Government Mayor’s Office of Management and Budget (OMB) Dataset s7yh-frbm 12 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HWSTEP04
Project Descr
STEP STREET REHABILITATION
Seq Number
8
Task Description
ORIGINAL EQUIP & FURNISHING
Orig Start Date
2005-09-01T00:00:00.000
Orig End Date
2005-12-01T00:00:00.000
Task Start Date
2025-09-01T00:00:00.000
Task End Date
2025-12-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HWSTEP04
Project Descr
STEP STREET REHABILITATION
Seq Number
9
Task Description
SUBSTANTIAL COMPLETION
Orig Start Date
2005-12-01T00:00:00.000
Orig End Date
2006-02-01T00:00:00.000
Task Start Date
2025-12-01T00:00:00.000
Task End Date
2026-02-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HWSTEP04
Project Descr
STEP STREET REHABILITATION
Seq Number
10
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2006-02-01T00:00:00.000
Orig End Date
2006-03-01T00:00:00.000
Task Start Date
2026-02-01T00:00:00.000
Task End Date
2030-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HWTSQI
Project Descr
Public Plaza Improvements
Seq Number
1
Task Description
DEVELOP SCOPE
Orig Start Date
2008-06-01T00:00:00.000
Orig End Date
2008-10-01T00:00:00.000
Task Start Date
1997-07-01T00:00:00.000
Task End Date
1997-10-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HWTSQI
Project Descr
Public Plaza Improvements
Seq Number
2
Task Description
DESIGN START
Orig Start Date
2008-10-01T00:00:00.000
Orig End Date
2010-04-01T00:00:00.000
Task Start Date
1997-10-01T00:00:00.000
Task End Date
1999-04-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
HWTSQI
Project Descr
Public Plaza Improvements
Seq Number
3
Task Description
CONSTRUCTION START
Orig Start Date
2010-04-01T00:00:00.000
Orig End Date
2012-04-01T00:00:00.000
Task Start Date
2025-04-01T00:00:00.000
Task End Date
2031-07-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
ITSBELTPK
Project Descr
Intelligent Transportation Systems on Belt Parkway X501.62
Seq Number
1
Task Description
BID AWARD AND REGISTER CONTRCT
Orig Start Date
2020-06-01T00:00:00.000
Orig End Date
2020-06-01T00:00:00.000
Task Start Date
2020-06-01T00:00:00.000
Task End Date
2025-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
ITSBELTPK
Project Descr
Intelligent Transportation Systems on Belt Parkway X501.62
Seq Number
2
Task Description
CONSTRUCTION START
Orig Start Date
2020-07-01T00:00:00.000
Orig End Date
2020-08-01T00:00:00.000
Task Start Date
2025-07-01T00:00:00.000
Task End Date
2025-08-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
ITSBELTPK
Project Descr
Intelligent Transportation Systems on Belt Parkway X501.62
Seq Number
3
Task Description
CONSTRUCTION COMPLETION
Orig Start Date
2020-08-01T00:00:00.000
Orig End Date
2022-03-01T00:00:00.000
Task Start Date
2025-08-01T00:00:00.000
Task End Date
2027-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
ITSJACKPK
Project Descr
Intelligent Transportation Syston Jackie Robinson Pk X501.60
Seq Number
1
Task Description
BID AWARD AND REGISTER CONTRCT
Orig Start Date
2021-06-01T00:00:00.000
Orig End Date
2021-06-01T00:00:00.000
Task Start Date
2021-06-01T00:00:00.000
Task End Date
2021-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
ITSJACKPK
Project Descr
Intelligent Transportation Syston Jackie Robinson Pk X501.60
Seq Number
2
Task Description
CONSTRUCTION START
Orig Start Date
2021-07-01T00:00:00.000
Orig End Date
2021-08-01T00:00:00.000
Task Start Date
2021-07-01T00:00:00.000
Task End Date
2021-08-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
ITSJACKPK
Project Descr
Intelligent Transportation Syston Jackie Robinson Pk X501.60
Seq Number
3
Task Description
CONSTRUCTION COMPLETION
Orig Start Date
2021-08-01T00:00:00.000
Orig End Date
2023-03-01T00:00:00.000
Task Start Date
2021-08-01T00:00:00.000
Task End Date
2023-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
MOLRETROF
Project Descr
MOLINARI CLASS UPGRADES-RETRO FIT
Seq Number
1
Task Description
DEVELOP SCOPE
Orig Start Date
2015-06-01T00:00:00.000
Orig End Date
2016-06-01T00:00:00.000
Task Start Date
2018-06-01T00:00:00.000
Task End Date
2019-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
MOLRETROF
Project Descr
MOLINARI CLASS UPGRADES-RETRO FIT
Seq Number
2
Task Description
DESIGN START
Orig Start Date
2016-06-01T00:00:00.000
Orig End Date
2018-06-01T00:00:00.000
Task Start Date
2019-06-01T00:00:00.000
Task End Date
2021-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
MOLRETROF
Project Descr
MOLINARI CLASS UPGRADES-RETRO FIT
Seq Number
3
Task Description
CONSTRUCTION START
Orig Start Date
2018-06-01T00:00:00.000
Orig End Date
2020-06-01T00:00:00.000
Task Start Date
2021-06-01T00:00:00.000
Task End Date
2023-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
NYCWINRPL
Project Descr
NYCWIN Replacement
Seq Number
1
Task Description
BID AWARD AND REGISTER CONTRCT
Orig Start Date
2018-06-01T00:00:00.000
Orig End Date
2018-06-01T00:00:00.000
Task Start Date
2019-08-01T00:00:00.000
Task End Date
2019-08-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
NYCWINRPL
Project Descr
NYCWIN Replacement
Seq Number
2
Task Description
CONSTRUCTION START
Orig Start Date
2018-07-01T00:00:00.000
Orig End Date
2018-08-01T00:00:00.000
Task Start Date
2019-10-01T00:00:00.000
Task End Date
2020-10-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
NYCWINRPL
Project Descr
NYCWIN Replacement
Seq Number
3
Task Description
CONSTRUCTION COMPLETION
Orig Start Date
2018-08-01T00:00:00.000
Orig End Date
2020-03-01T00:00:00.000
Task Start Date
2021-06-01T00:00:00.000
Task End Date
2029-07-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
PLANTRANS
Project Descr
TRANSIT SIGNAL PRIORITY-2030
Seq Number
1
Task Description
BID AWARD AND REGISTER CONTRCT
Orig Start Date
2008-06-01T00:00:00.000
Orig End Date
2008-06-01T00:00:00.000
Task Start Date
2022-06-01T00:00:00.000
Task End Date
2022-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
PLANTRANS
Project Descr
TRANSIT SIGNAL PRIORITY-2030
Seq Number
2
Task Description
CONSTRUCTION START
Orig Start Date
2008-07-01T00:00:00.000
Orig End Date
2008-08-01T00:00:00.000
Task Start Date
2022-07-01T00:00:00.000
Task End Date
2022-08-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
PLANTRANS
Project Descr
TRANSIT SIGNAL PRIORITY-2030
Seq Number
3
Task Description
CONSTRUCTION COMPLETION
Orig Start Date
2008-08-01T00:00:00.000
Orig End Date
2010-03-01T00:00:00.000
Task Start Date
2022-08-01T00:00:00.000
Task End Date
2024-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
RTPIFY19
Project Descr
REAL TIME PASSENGER INFO SIGNS - FY19
Seq Number
1
Task Description
BID AWARD AND REGISTER CONTRCT
Orig Start Date
2018-06-01T00:00:00.000
Orig End Date
2018-06-01T00:00:00.000
Task Start Date
2019-06-01T00:00:00.000
Task End Date
2019-07-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
RTPIFY19
Project Descr
REAL TIME PASSENGER INFO SIGNS - FY19
Seq Number
2
Task Description
CONSTRUCTION START
Orig Start Date
2018-07-01T00:00:00.000
Orig End Date
2018-08-01T00:00:00.000
Task Start Date
2020-06-01T00:00:00.000
Task End Date
2020-07-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
RTPIFY19
Project Descr
REAL TIME PASSENGER INFO SIGNS - FY19
Seq Number
3
Task Description
CONSTRUCTION COMPLETION
Orig Start Date
2018-08-01T00:00:00.000
Orig End Date
2020-03-01T00:00:00.000
Task Start Date
2021-06-01T00:00:00.000
Task End Date
2031-07-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
RTPIFY20
Project Descr
Real Time Passenger Info Signs FY20ADOP
Seq Number
1
Task Description
BID AWARD AND REGISTER CONTRCT
Orig Start Date
2019-06-01T00:00:00.000
Orig End Date
2019-06-01T00:00:00.000
Task Start Date
2021-06-01T00:00:00.000
Task End Date
2021-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
RTPIFY20
Project Descr
Real Time Passenger Info Signs FY20ADOP
Seq Number
2
Task Description
CONSTRUCTION START
Orig Start Date
2019-07-01T00:00:00.000
Orig End Date
2019-08-01T00:00:00.000
Task Start Date
2021-07-01T00:00:00.000
Task End Date
2021-08-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
RTPIFY20
Project Descr
Real Time Passenger Info Signs FY20ADOP
Seq Number
3
Task Description
CONSTRUCTION COMPLETION
Orig Start Date
2019-08-01T00:00:00.000
Orig End Date
2021-03-01T00:00:00.000
Task Start Date
2021-08-01T00:00:00.000
Task End Date
2023-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
SANDCONDU
Project Descr
SANDY CONDUIT ADDITIONAL CITY-WIDE WORK
Seq Number
1
Task Description
BID AWARD AND REGISTER CONTRCT
Orig Start Date
2015-06-01T00:00:00.000
Orig End Date
2015-06-01T00:00:00.000
Task Start Date
2023-06-01T00:00:00.000
Task End Date
2023-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
SANDCONDU
Project Descr
SANDY CONDUIT ADDITIONAL CITY-WIDE WORK
Seq Number
2
Task Description
CONSTRUCTION START
Orig Start Date
2015-07-01T00:00:00.000
Orig End Date
2015-08-01T00:00:00.000
Task Start Date
2023-07-01T00:00:00.000
Task End Date
2023-08-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
SANDCONDU
Project Descr
SANDY CONDUIT ADDITIONAL CITY-WIDE WORK
Seq Number
3
Task Description
CONSTRUCTION COMPLETION
Orig Start Date
2015-08-01T00:00:00.000
Orig End Date
2017-03-01T00:00:00.000
Task Start Date
2023-08-01T00:00:00.000
Task End Date
2025-03-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
SANDRF05
Project Descr
Construction of New Ferryboats
Seq Number
1
Task Description
DEVELOP SCOPE
Orig Start Date
2016-07-01T00:00:00.000
Orig End Date
2016-09-01T00:00:00.000
Task Start Date
2011-05-01T00:00:00.000
Task End Date
2014-07-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
SANDRF05
Project Descr
Construction of New Ferryboats
Seq Number
2
Task Description
PRELIMINARY DESIGN
Orig Start Date
2016-09-01T00:00:00.000
Orig End Date
2017-01-01T00:00:00.000
Task Start Date
2014-10-01T00:00:00.000
Task End Date
2015-02-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
SANDRF05
Project Descr
Construction of New Ferryboats
Seq Number
3
Task Description
FINAL DESIGN
Orig Start Date
2017-01-01T00:00:00.000
Orig End Date
2017-07-01T00:00:00.000
Task Start Date
2015-08-01T00:00:00.000
Task End Date
2015-11-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
SANDRF05
Project Descr
Construction of New Ferryboats
Seq Number
4
Task Description
BID AWARD AND REGISTER CONTRCT
Orig Start Date
2017-07-01T00:00:00.000
Orig End Date
2017-10-01T00:00:00.000
Task Start Date
2016-05-01T00:00:00.000
Task End Date
2021-02-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
SANDRF05
Project Descr
Construction of New Ferryboats
Seq Number
5
Task Description
CONSTRUCTION TO 25%
Orig Start Date
2017-10-01T00:00:00.000
Orig End Date
2018-02-01T00:00:00.000
Task Start Date
2017-03-01T00:00:00.000
Task End Date
2018-01-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
SANDRF05
Project Descr
Construction of New Ferryboats
Seq Number
6
Task Description
CONSTRUCTION TO 50%
Orig Start Date
2018-02-01T00:00:00.000
Orig End Date
2018-06-01T00:00:00.000
Task Start Date
2018-01-01T00:00:00.000
Task End Date
2019-02-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
SANDRF05
Project Descr
Construction of New Ferryboats
Seq Number
7
Task Description
CONSTRUCTION TO 75%
Orig Start Date
2018-06-01T00:00:00.000
Orig End Date
2018-10-01T00:00:00.000
Task Start Date
2019-02-01T00:00:00.000
Task End Date
2020-01-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
SANDRF05
Project Descr
Construction of New Ferryboats
Seq Number
8
Task Description
ORIGINAL EQUIP & FURNISHING
Orig Start Date
2018-10-01T00:00:00.000
Orig End Date
2019-01-01T00:00:00.000
Task Start Date
2020-01-01T00:00:00.000
Task End Date
2020-04-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
SANDRF05
Project Descr
Construction of New Ferryboats
Seq Number
9
Task Description
SUBSTANTIAL COMPLETION
Orig Start Date
2019-01-01T00:00:00.000
Orig End Date
2019-03-01T00:00:00.000
Task Start Date
2021-08-01T00:00:00.000
Task End Date
2022-08-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
SANDRF05
Project Descr
Construction of New Ferryboats
Seq Number
10
Task Description
PUNCHLIST COMPLETE, JOB CLOSED
Orig Start Date
2019-03-01T00:00:00.000
Orig End Date
2019-04-01T00:00:00.000
Task Start Date
2025-02-01T00:00:00.000
Task End Date
2025-02-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
SANDRF07
Project Descr
STATEN ISLAND FERRY HEAVY WEATHER MOORING
Seq Number
1
Task Description
DEVELOP SCOPE
Orig Start Date
2017-06-01T00:00:00.000
Orig End Date
2018-06-01T00:00:00.000
Task Start Date
2019-06-01T00:00:00.000
Task End Date
2020-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
SANDRF07
Project Descr
STATEN ISLAND FERRY HEAVY WEATHER MOORING
Seq Number
2
Task Description
DESIGN START
Orig Start Date
2018-06-01T00:00:00.000
Orig End Date
2020-06-01T00:00:00.000
Task Start Date
2020-06-01T00:00:00.000
Task End Date
2022-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
SANDRF07
Project Descr
STATEN ISLAND FERRY HEAVY WEATHER MOORING
Seq Number
3
Task Description
CONSTRUCTION START
Orig Start Date
2020-06-01T00:00:00.000
Orig End Date
2022-06-01T00:00:00.000
Task Start Date
2022-06-01T00:00:00.000
Task End Date
2024-06-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
SANDRF11
Project Descr
Ferry Terminal Floodproofing
Seq Number
1
Task Description
DEVELOP SCOPE
Orig Start Date
2016-07-01T00:00:00.000
Orig End Date
2016-09-01T00:00:00.000
Task Start Date
2018-11-01T00:00:00.000
Task End Date
2020-05-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
SANDRF11
Project Descr
Ferry Terminal Floodproofing
Seq Number
2
Task Description
PRELIMINARY DESIGN
Orig Start Date
2016-09-01T00:00:00.000
Orig End Date
2017-01-01T00:00:00.000
Task Start Date
2020-05-01T00:00:00.000
Task End Date
2020-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
SANDRF11
Project Descr
Ferry Terminal Floodproofing
Seq Number
3
Task Description
FINAL DESIGN
Orig Start Date
2017-01-01T00:00:00.000
Orig End Date
2017-07-01T00:00:00.000
Task Start Date
2020-09-01T00:00:00.000
Task End Date
2021-02-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
SANDRF11
Project Descr
Ferry Terminal Floodproofing
Seq Number
4
Task Description
BID AWARD AND REGISTER CONTRCT
Orig Start Date
2017-07-01T00:00:00.000
Orig End Date
2017-10-01T00:00:00.000
Task Start Date
2021-03-01T00:00:00.000
Task End Date
2021-05-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
SANDRF11
Project Descr
Ferry Terminal Floodproofing
Seq Number
5
Task Description
CONSTRUCTION TO 25%
Orig Start Date
2017-10-01T00:00:00.000
Orig End Date
2018-02-01T00:00:00.000
Task Start Date
2021-05-01T00:00:00.000
Task End Date
2021-09-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
SANDRF11
Project Descr
Ferry Terminal Floodproofing
Seq Number
6
Task Description
CONSTRUCTION TO 50%
Orig Start Date
2018-02-01T00:00:00.000
Orig End Date
2018-06-01T00:00:00.000
Task Start Date
2021-09-01T00:00:00.000
Task End Date
2022-01-01T00:00:00.000
20220517
Pub Date: 20220517 • Boro: CITYWIDE • Managing Agcy Cd: 841
Pub Date
20220517
Boro
CITYWIDE
Managing Agcy Cd
841
Managing Agcy
DEPARTMENT OF TRANSPORTATION
Project Id
SANDRF11
Project Descr
Ferry Terminal Floodproofing
Seq Number
7
Task Description
CONSTRUCTION TO 75%
Orig Start Date
2018-06-01T00:00:00.000
Orig End Date
2018-10-01T00:00:00.000
Task Start Date
2022-01-01T00:00:00.000
Task End Date
2022-05-01T00:00:00.000